HomeMy WebLinkAbout20120119 Ver 1_Inspection_20130426April 26, 2013
Mr. J. J. Swain, Jr., P.E.
Division 13 Engineer
N.C. Department of Transportation
Post Office Box 3279
Asheville, North Carolina 28802
Natural Resources
Subject: Inspection
TIP No. B -5178
Bridge Nos. 235 and 238
Interstate 26 at Pond Road
Buncombe County
Dear Mr. Swain:
tz- OII c
John E. Skvarla, III
Secretary
On April 22, 2013, I inspected the construction work on TIP Project No. B -5178, Bridge Nos. 235 and 238,
over Hominy Creek, on Interstate.26,.in Buncombe County. The inspection included a review of the
construction and compliance with the 401 Water Quality Certification.
Please ensure that all sediment and erosion control structures are maintained and seeding and mulching are
performed as required to protect State surface waters. Also, please refer to the attached inspection report for
any specific items noted during the inspection.
If you have questions, please call me at 828 - 296 -4500.
Sincerely,
�-
Michael R. Parker
Environmental Senior Specialist
Attachment
cc: Cole Hood, PE
Roger Bryan, Division 13, DEO
Ben DeWit, Roadside Environmental
Transportation Permitting Unit
Mike Parker, Asheville Regional Office
B -5178 Bridge Nos. 235 and 238 April 2013 Inspection Letter
SURFACE WATER PROTECTION SECTION — Asheville Regional Office
2090 US 70 Highway, Swannanoa, NC 28778 -8211
Phone: 828- 296-45001 FAX: 828 - 299 -7043 One
Internet: www.ncwaterguality.org NorthCarolina
An Equal Opportunity Affirmative Action Employer ,/ atura"y
Wetland Inspection Deport
Project Num: 20120119 Version: 1 Status: Issued
Project Name: NCDOT- Bridges No. 235 & 238 on SR 3431 (B -5178) Project Type: Replace bridge with bridge
County: Buncombe Region: Asheville
Location: NCDOT- Bridges No 235 & 238 on SR 3431 (B -5178)
Latitude: +35 °32'44'1 Longitude: -82 °36'1711
SW Plan Location:
Site Owner Name: NC DOT PDEA
Inspection Date: 04/22/2013
Reason for Inspection: Routine
Inspection Type: Site Inspection (DOT)
Inspection Contact Person:
On -Site Representative(s):
Primary Inspector: Michael R Parker
Secondary Inspector(s):
Facility compliance Status: ® Compliant
Program Area: 401 (includes isolated /non -404)
Question Areas:
Permit (401 WQC)
Title:
n Not Compliant
Phone:
Phone: 828 -296 -4500
Inspection Summary:
Inspected site with NCDOT staff.
Contractor continues to work on piers for the new bridge. Also, -grading is taking place for the new MSE wall and new lane for 1 -26.
Please ensure that sediment and erosion control structures are maintained to protect Hominy Creek.
Seed and mulch all bare as required.
Permit (401 WQC)
Does the impact(s) match what was approved in the 401 WQC or non 404 permit?
Are the culverts and /or filled areas installed properly?
Is the site compliant with additional conditions of the 401 WQC or non 404 permit?
V__ K1_ AIA AIC
®nnn
®nnn
®nnn
Page: 1