Loading...
HomeMy WebLinkAboutNC0024333_15 MGD EQ Basin Construction_20210518Strickland, Bev From: Russell Colbath <rcolbath@monroenc.org> Sent: Tuesday, May 18, 2021 10:30 AM To: Basinger, Corey Cc: Scheller, Roberto; Kyle Ketchum; 'Struve, James N.' Subject: [External] City of Monroe NOV - 2021-LV-0287 Attachments: Engineer Report WWTP Flow Equalization Improvements 7-17-20.pdf CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to Report Spam. Good afternoon Corey, I wanted to touch base on the above NOV dated April 27, 2021. Proactively addressing I&I in our collections system and the negative impact it has at our WWTP has been a priority for many years. We recently assembled a PER (attached) and sent it to Christyn Fertenbaugh on 7-21-20. It outlined plans to construct additional 15 MG EQ storage at our WWTP to improve storm/wet weather resiliency. We are preparing to submit permit applications/construction drawings, and then bid this $4 million project with anticipated completion in spring 2022. Anything you can do to help expedite permitting for dam safety, erosion control , and A to C would be appreciated. In the PER we also outlined our aggressive I&I control program made up of the following: • Sewer main replacement by City Water Resources crews using pipe bursting technology. • Sewer main replacement using cured in place (CIPP) lining. The current project approach is to bid annual "find and fix" contracts where CCTV is utilized to find high priority repairs which are then rehabilitated using CIPP. • Manhole rehabilitation using spray on cemetatious liners (calcium aluminate for high corrosion areas). • Smoke testing of sewer collection system basins, with current goal of 20% of the system per year. Top of ground repairs, such as sewer cleanouts, etc., are completed when found. • Sewer main and lateral point repairs, either by City crews or by CIPP contractors. • Regular sewer outfall inspections after all 2-inch or greater rainfall events. All in all we are spending close to $1.0 million annually on collection system renewal and replacements. This on top of the noted investment in added EQ storage. Based on all factors, we are not planning to pursue an SOC at this time (as noted in your letter and NOV). I wanted to share this information to ensure you that we are working very hard to keep our collection system and WWTP in full compliance with their respective permits. Thank you. R wlyse).2. C d th-ci th', P.E. i City of Monroe Water Resources Director 704-282-4624 rcolbath@monroenc. orq P nro North Carolina E-mail correspondence to and from this address may be subject to North Carolina's public records laws and if so, may be disclosed. 2 \r1'l0nroe North Carolina City of Monroe Water Resources WWTP Flow Equalization Basin Expansion Preliminary Engineering Report July 20, 2020 R�(i. Co-lbat-h; PE rcolbath@monroenc.org 704-282-4624 Project Background The City of Monroe Water Resources Department operates a wastewater treatment plant (WWTP) located at 775 Treeway Drive in Monroe, North Carolina. The plant meets the wastewater treatment needs of the City of Monroe and the Union County East Side Sewer System. The WWTP has a current capacity of 10.4 MGD, with 2.65 MGD allocated to Union County via interlocal agreement. The WWTP also has a 10 MG earthen flow equalization (EQ) basin to divert high influent flows during wet weather events. The WWTP Master Plan, completed in 2008 by Hazen and Sawyer, identified the future need for an additional 10 MG of flow EQ storage (Attachment 1), generally to be timed with the next WWTP expansion. The Plan does indicate that this added EQ storage could be beneficial prior to the WWTP expansion based on need and available funding. The WWTP expansion, potentially to 15.0 MGD in partnership with Union County, is projected to occur in the early 2030’s. During high intensity and extended duration rainfall events, the WWTP has experienced flows exceeding the hydraulic capacity and EQ storage volume of the plant. This has resulted in the bypass of some treatment processes. All bypass events have been reported to the North Carolina Department of Environmental Quality (NCDEQ) per state standards and pursuant to the City’s NPDES permit. Based on all considerations, the City believes it is prudent to move forward with the design, permitting, and construction of expanded EQ storage basin volume to improve WWTP operations, permit compliance, and prepare for the future WWTP expansion. Sewer Collection System Asset Management WWTP hydraulic overloading during heavy wet weather events is an indication of sanitary sewer collection system inflow and infiltration (I&I) and system rehabilitation needs. The City has a comprehensive sewer asset management program and is committed to collection system upgrades and repairs. The City sewer system asset management plan includes the following: Sewer main replacement by City Water Resources crews using pipe bursting technology. Sewer main replacement using cured in place (CIPP) lining. The current project approach is to bid annual “find and fix” contracts where CCTV is utilized to find high priority repairs which are then rehabilitated using CIPP. Manhole rehabilitation using spray on cemetatious liners (calcium aluminate for high corrosion areas). Smoke testing of sewer collection system basins, with current goal of 20% of the system per year. Top of ground repairs, such as sewer cleanouts, etc., are completed when found. Sewer main and lateral point repairs, either by City crews or by CIPP contractors. Regular sewer outfall inspections after all 2-inch or greater rainfall events. In 2014, the City established a goal to replace or rehabilitate 1% of the collections system sewer main footage annually. Attachment 2 shows the historical performan ce toward meeting this goal. Attachment 3 shows the financial commitment to sewer asset management, totaling $6.1 million since FY2010. The City will continue to aggressively identify, assess, and rehabilitate/replace aging sewer collection system infrastructure to limit rainfall I&I into the system. WWTP Wet Weather Flow Analysis The City’s sewer collection system response to rainfall events, and the associated high flow impact to the WWTP, varies greatly with the type, intensity, spacial distribution, and duration of the rainfall event. It is also significantly influenced by antecede nt moisture conditions, and ground water levels. Table 1 shows the historical storm events for the past 5 years that resulted in hydraulic overloading and subsequent WWTP process bypass. Table 1. Date(s) Rainfall (In.) Reported WWTP Bypass (Gal.) March 7-8, 2014 2.0” 2,221,965 April 19-20, 2014 2.75” 3,562,960 October 3-7, 2015 8.75” 1,022,021 November 2-3, 2015 4.5” 2,441,280 2016 None 2017 None September 15-17, 2018 10.9” 10,803,690 (Hurricane Florence = Design Storm) 2019 None February 7, 2020 3.4” 4,223,750 May 20-21, 2020 7.0” 12,146,000 (note 1) May 28, 2020 2.5” 531,000 (note 1) Note 1. Post storm collection system inspection found 2 manholes with covers off. Bypass volume likely not representative of historical performance. Based on all data and considerations, the September 2018 storm event (Hurricane Florence) was selected as the design storm event for additional EQ storage analysis. The following data is relevant to the analysis: Recurrence frequency – based on NOAA Atlas 14, approximately 200-year event. WWTP maximum hydraulic capacity (flow throughput) = 22 MGD. Peak WWTP influent flow rate during Hurricane Florence = 46 MGD. Total WWTP process bypass volume reported to NCDEQ = 10.8 MG. The 200-year recurrence frequency of this storm is greater than required design standards. However, using this storm for EQ storage volume planning provides a safety factor for climate change uncertainty where future storms may be more frequent and intense, future flow growth from economic development, plus added storage to protect the WWTP until the planned future expansion. Table 2 shows the analysis of WWTP flow and EQ volume needed to eliminate WWTP flow bypass during the design storm. The current 10.4 MGD WWTP is capable of sustained hydraulic throughput of approximately 22 MGD for the extended periods of time typical of most large rain events. The table Table 2. WWTP Influent Flow Data Rain US Climate Data.com Hurricane Florence 9/15/2018 0.81 9/16/2018 5.81 9/17/2018 4.3 10.92 Inches Date Time Total City Influent Total County Influent Total WWTP Influent WWTP Hydraulic Rate Flow to EQ Volume to EQ 1:00 MGD MGD MGD MGD MGD MG 9/16/2018 3:25 AM 15.0 7.0 22.0 22 0.0 0.00 4:25 AM 18.9 8.1 27.0 22 5.0 0.21 5:25 AM 22.3 8.3 30.6 22 8.6 0.36 6:25 AM 25.2 8.3 33.5 22 11.5 0.48 7:25 AM 30.1 8.9 39.0 22 17.0 0.71 8:25 AM 31.0 7.3 38.3 22 16.3 0.68 9:25 AM 31.7 9.1 40.8 22 18.8 0.78 10:25 AM 32.4 10.0 42.4 22 20.4 0.85 11:25 AM 33.1 10.0 43.1 22 21.1 0.88 12:25 PM 34.1 10.0 44.1 22 22.1 0.92 1:25 PM 35.5 10.0 45.5 22 23.5 0.98 2:25 PM 35.8 10.0 45.8 22 23.8 0.99 3:25 PM 36.1 10.0 46.1 22 24.1 1.00 4:25 PM 36.1 10.0 46.1 22 24.1 1.00 5:25 PM 36.3 10.0 46.3 22 24.3 1.01 6:25 PM 35.9 10.0 45.9 22 23.9 1.00 7:25 PM 36.0 9.8 45.8 22 23.8 0.99 8:25 PM 35.9 9.7 45.6 22 23.6 0.98 9:25 PM 35.7 9.6 45.3 22 23.3 0.97 10:25 PM 35.1 9.4 44.5 22 22.5 0.94 11:25 PM 34.9 8.4 43.3 22 21.3 0.89 9/17/2018 12:25 AM 34.2 9.3 43.5 22 21.5 0.90 1:25 AM 33.7 7.7 41.4 22 19.4 0.81 2:25 AM 33.6 8.2 41.8 22 19.8 0.83 3:25 AM 32.9 7.3 40.2 22 18.2 0.76 4:25 AM 32.1 6.9 39.0 22 17.0 0.71 5:25 AM 31.8 6.6 38.4 22 16.4 0.68 6:25 AM 19.8 5.2 25.0 22 3.0 0.13 6:38 AM 17.4 4.6 22 22 0.0 0.00 7:38 AM Time WWTP reached 22 MGD Total EQ Volume (MG)21.42 EQ Reserve for Filter Backwash (MG)1.5 Total Needed EQ Volume (MG) 22.92 shows only those hours where the total WWTP influent flow exceeded 22 MGD. Based on the design storm, including an EQ reserve for filter backwash, 23 MG of total EQ storage is needed. Therefore, 13 MG of added EQ storage is needed to supplement the existing 10 MG EQ basin. Proposed EQ Basin Expansion Figure 1 shows the preliminary concept for a proposed EQ basin expansion. The land parcel was purchased by the City in 2009 and contains 23.75 acres. It is zoned General Industrial which will support the intended project land use. The parcel is wooded with topography generally sloping to the north toward Richardson Creek. While a minimum of 13 MGD is indicated by the design storm, the city believes it is prudent to maximize the EQ volume on the property. The incremental cost of adding 2 MGD, to create a 15 MG basin, will likely be low. The EQ basin project will be funded by the City’s Water and Sewer Enterprise fund and with f unding from Union County consistent with the interlocal agreement. No state or federal funding will be used. The following factors and considerations will form the basis of detailed design, permitting, and construction. Geotechnical Evaluation – Attachment 4 provides the results of the preliminary geotechnical evaluation conducted by GTA and Associates. Additional geotechnical testing will be completed during design and construction as needed. Generally, the evaluation shows the site is suita ble for the intended purpose. NCDEQ Dam Safety – Preliminary communications with NCDEQ Dam Safety staff have occurred concerning the new EQ basin. The City will submit a Jurisdictional Determination/Hazard Classification Request as part of the design phase of the project. It is the City’s intent to limit the EQ basin embankment height to less than 25-feet and less than 50 ac-ft (16MG+/-) of storage to meet the exemption requirements of high hazard dam classification. The City’s existing EQ basin constructed in 2004 did not require such permitting due to the earthen berm dimensions and EQ basin volume. Wetlands and Endangered Species – A preliminary investigation of the site for wetlands and endangered species was conducted by a Hazen and Sawyer environmental scientist on June 19, 2020. Attachment 5 shows the preliminary findings. There were no areas of concern identified. Any additional evaluations of these items will be conducted during project design, and in coordination with NCDEQ. Earthen EQ Basin Design Concept – The proposed earthen EQ basin will use similar design concepts as the existing 10 MG EQ basin. The basin will be lined with a geosynthetic clay liner (GCL) to achieve the required low permeability and hydraulic barrier. Operational cover (typically 18 inches) will protect the GCL from erosion or damage. Preliminary analysis indicates that the effective operating range could be from 504 to 511 feet elevation +/-, with typical berm cross slopes of approximately 1:3. The force main discharge inlet will be designed to protect the basin floor and liner using large rip-rap, concrete, or other energy dissipating features to be determined during design. An NCDEQ Erosion and Sedimentation Control permit will be obtained for the entire project. The entire basin will be fenced per NCDEQ requirements. Proposed 15 MG EQ Basin Operating Elevation 504' to 511' +/- tFIGURE 1 Proposed EQ Basin Expansion (Cont.) Inlet Force Main Hydraulic Analysis – The inlet force main for the new EQ basin will be a combination of 24 and 30 inch piping, flow control valve (motorized eccentric plug valve), flow meter, and appropriately placed isolation valves. The force main will be connected to the existing 24-inch discharge header for WWTP influent pump stations (IPS) #1 and #2 that have the following characteristics: IPS #1 Four (4) identical pumps (Fairbanks Morse 8” 54x6 pump curve (Attachment 6). Individual capacity 3440 GPM at 80-feet TDH. All pumps replaced/new in 2018. IPS #2 Two (2) identical pumps (Fairbanks Morse 10” M5440 pump curve (Attachment 7). Individual capacity 5800 GPM at 80-feet TDH. All pumps replaced/new in 2018. Note: Union County system flows are pumped to the WWTP screenings building by separate pump stations. During heavy rainfall events, after the WWTP total influent flow reaches 22 MGD, operations staff activate flow diversion to EQ basin storage to maintain steady flow rates through the plant. With a new/second EQ basin available, it is anticipated that in the early stages of a rainfall event the existing EQ basin will be activated first as has been done in the past. As a storm event evolves, and flows increase, flow diversion will be shifted to the new EQ basin. The anticipated design flow range for the new EQ basin will be 3 to 20 MGD. A system head curve was developed for the proposed EQ basin force main using this flow range and the following: Pipe lengths: 24 Inch = 85LF, 30 Inch = 675LF. Elevations: Existing Influent pumps 453’, wet well operating level 458’, new EQ basin max 511’. Hazen Williams Roughness Coefficient for DIP = 120. Total of minor head losses at maximum flow = 20’. The system curve indicates that the proposed EQ basin force main will require 77 -feet of total dynamic head (TDH) to deliver the desired 20 MGD flow rate to the basin, at the maximum basin level of 511-feet. Review of the attached pump curves and operational data indicate the existing influent pump stations can meet this flow and TDH while delivering the balance of the influent flow to the WWTP headworks and screening building. It is important to note that the existing WWTP EQ basin has an operating range of 509-516’ elevation, compared to the proposed elevation of 504- 511’ for the new EQ basin. This, in addition to the demonstrated flow diversion capacity of the existing EQ basin and force mains, provides added confirmation that the proposed force main system will deliver the desired 20 MGD flow rate to the new basin. The existing filter backwash waste pit pumps that currently discharge to the existing 10 MG EQ basin will be connected to the new force main with appropriate valving to allow discharge to either EQ basin (See Figure 1.). This will allow operational flexibility, promote odor control, and limit anaerobic conditions in the stored wastewater. Given that the new EQ basin operating range will be 5 feet +/- lower than the existing EQ basin, the performance characteristics of the existing backwash waste pit pumps will function properly with the new EQ basin. Outlet Piping/ Return Flow to WWTP After each rainfall event, historical records show that the WWTP influent flow drops quickly as the sewer collection system I&I dissipates. As the total WWTP flow drops under 22 MGD, operations staff initiate returning stored wastewater back into the plant at the appropriate timing and flow rate so as not to overload WWTP processes. The exisiting EQ basin pumps return flow to the WWTP process at a maximum flow rate of 4.0 MGD. This allows dewatering of the 10 MG basin in 48 to 72 hours. The new EQ basin will be dewatered using a flow control valve, outlet meter, and 20-inch pipe. The return flow to the WWTP will utilize the exising 30-inch sewer collection system interceptor as shown on Figure 1. As-built drawings for the 30-inch pipe show a slope of 0.0014 from manhole 6 to the termination at the WWTP influent pump stations. Using Mannings equation with n=0.013 and as-built slope data, the full pipe capacity is 9.97 MGD. Field measurments of this 30-inch interceptor after rainfall events subside indicate a normal flow depth of 5-inches. This is because the exisitng 54-inch 40 45 50 55 60 65 70 75 80 0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0 18.0 20.0 22.0Total Dynamic Head (FT)Flow Rate (MGD) Proposed WWTP EQ Basin System Head-Discharge Curve EQ Forcemain sewer interceptor on the opposite (north) side of Richardson Creek carries the majority of flow to the WWTP. The 30-inch interceptor acts as a high flow relief main. This allows the 30-inch pipe to quickly return to normal base flow levels after a rain event. The proposed return flow rates from the new EQ basin will range from 1 to 5 MGD. Therefore the 30-inch interceptor has sufficient capacity to receive this flow without surcharging. EQ Basin Operations, Instrumentation The new EQ basin will be operated by WWTP staff as described above and in coordination with the existing EQ basin. The following instrumentation will be available to operators via SCADA telemetry: Force main influent flow rate EQ basin level EQ basin effluent flow rate SCADA and localized alarm annunciators will be installed to alert operators of high or low operational values for flow, level, etc. Control of Odors, Anaerobic Conditions, and limiting WWTP Adverse Impacts The WWTP staff have successfully operated the existing EQ basin for many years. The key to avoiding odors and anaerobic condition is to dewater the basin immediately after high flow events when the WWTP influent flow rate (wet weather flows) drops below 22 MGD. The discharge of filter backwash water to the EQ basins also plays an important role, bringing in tertiary effluent that contains dissolved oxygen and a chlorine residual of 1.0 mg/l +/-. Operations data shows that the WWTP will be able to return flow from both EQ basins after major rain events, with capacity to dewater the basins on an average of 96 hours +/-. This combined with the backwash water additions will help avoid odors, septic conditions, and any adverse impacts to the WWTP process. For the existing EQ basin, removal of any accumulated solids is managed by contracting a floating dredge to pump solids to a dewatering belt press, with the dewatered solids sent to the Anson County Landfill after appropriate sampling. This has only been needed on an interval of approximately 5 years. Solids accumulations in the new EQ basin will be managed and removed using the same approach. Summary The City of Monroe Water Resources Department is committed to operating and maintain their wastewater collection and treatment system in an effective, efficient, and environmentally responsible way. This report provides the framework and direction to move forward with the design, permitting, and construction of expanded WWTP EQ storage capacity. This expansion will improve WWTP operations, permit compliance, and prepare the city for the future WWTP expansion planned for the early 2030’s. List of Attachments 1.Hazen and Sawyer Engineering – WWTP 2008 Master Plan Layout with New EQ Storage 2.Sewer Infrastructure Renewal/Replacement Data 3.Sewer Asset Management Program History 4.Preliminary Geo Technical Report 5.Preliminary Investigation for Wetlands and Endangered Species 6.Existing WWTP Influent Pump Station #1 Pump Curve (Typ. Of 4) 7.Existing WWTP Influent Pump Station #2 Pump Curve (Typ. Of 2) Attachment 1 Attachment 2 0.00% 0.20% 0.40% 0.60% 0.80% 1.00% 1.20% 0 2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 11 12 13 14 15 16 17 18 19 20 S Y S T E M R E N E W A L % L I N E A R F O O T A G E FISCAL YEAR SEWER INFRASTRUCTURE RENEWAL SLIP LINING LF PIPE BURSTING LF OPEN CUT LF RENEWAL %TARGET % Attachment 3City of Monroe Water ResourcesSanitary Sewer SystemRehabilitation and Inflow-Infiltration ControlFY 2010FY 2011FY 2012FY 2013FY 2014FY 2015FY 2016FY 2017FY 2018FY 2019FY 2020TotalSewer Main Pipebursting RehabilitationTotal Feet Complete4,0143,1882,0982,9881,9282,7361,1948,4994,7096,7795,60443,737Total Cost (equivalent)$139,650.00$115,793.20$77,483.39$112,403.53$74,163.25$105,123.40$46,239.15$334,072.09$190,107.56$276,757.52$228,027.20$1,699,820.30Sewer Main Lining RehabilitationTotal Feet Complete3,9417,3155,3683,7907,6694,4358,2046,8696,2026,7847,40067,977Total Cost$142,516.00$248,402.90$184,320.30$190,069.10$272,404.29$286,480.03$146,488.35$294,486.93$295,917.22$427,661.60$468,168.69$2,956,915.41Sewer Manhole RehabilitationTotal Manholes311837304504601630142512Total Cost$19,849.50$69,181.90$25,209.90$27,678.40$47,961.40$0.00$52,273.88$0.00$169,393.82$0.00$164,533.59$576,082.39Sewer Main Smoke TestingTotal Feet Complete32,80100000431,199370,003313,323254,929268,0021,670,257Total Cost (Est.)$5,576.17$0.00$0.00$0.00$0.00$0.00$81,108.09$70,641.27$61,438.96$50,551.49$52,967.25$322,283.23Sewer Point Repairs Total Repairs85542472936262634327333Total Cost (equivalent)$9,019.04$75,892.99$47,349.96$64,694.93$32,694.02$56,073.70$87,651.77$52,222.22$56,828.30$1,215.00$71,747.00$555,388.93Note 2FY Total Cost$316,610.71$509,270.99$334,363.55$394,845.96$427,222.96$447,677.13$413,761.24$751,422.51$773,685.87$756,185.61$985,443.74$6,110,490.25Note - FY20 Projection of Actual REPORT OF PRELIMINARY GEOTECHNICAL SUBSURFACE EXPLORATION 15 MB EQUIALIZATION BASIN City of Monroe WWTP Monroe, Union County, North Carolina July 10, 2020 Prepared For: City of Monroe 300 W. Crowell Street Monroe, North Carolina 28112 Attn: Mr. Russ Colbath Prepared By: GTA ASSOCIATES, INC. Geotechnical and Environmental Consultants 710 Peninsula Lane, Suite B Charlotte, N.C. 28273 (704) 553-2300 – Office (704) 553-2400 - Facsimile GTA Job No: 35200850 ATTACHMENT 4 GTA ASSOCIATES, INC. GEOTECHNICAL AND ENVIRONMENTAL CONSULTANTS A Practicing Geoprofessional Business Association Member Firm 710 Peninsula Lane, Suite B, Charlotte, NC 28273 Phone: (704) 553-2300 Fax: (704) 553-2400  Abingdon, MD  Baltimore, MD  Laurel, MD  Frederick, MD  Waldorf, MD  Sterling, VA  Malvern, OH  Somerset, NJ  NYC Metro  New Castle, DE  Georgetown, DE  York, PA  Quakertown, PA  Charlotte, NC  Raleigh, NC Visit us on the web at www.gtaeng.com July 10, 2020 City of Monroe 300 W. Crowell Street Monroe, North Carolina 28112 Attn: Mr. Russell Colbath, P.E. Water Resources Director Re: Report of Preliminary Geotechnical Subsurface Exploration Proposed 15MG Equalization Basin City of Monroe Wastewater Treatment Plant Industrial Drive - +25 Acres Monroe, Union County, North Carolina Dear Mr. Colbath: In accordance with our agreement executed on May 29, 2020, GTA Associates, Inc. (GTA) has performed a preliminary geotechnical subsurface exploration for a 15-million-gallon equalization basin located to the west of the existing Wastewater Treatment Plant in Monroe, North Carolina. The results of the field testing and our preliminary recommendations regarding design and construction of the proposed equalization basin are included in this report. Unless other arrangements are made by the City of Monroe, GTA will discard the soil samples within sixty days from the date of this report. GTA appreciates the opportunity to assist you with this project. Should you have questions or require additional information, please contact at our office at (704) 553-2300. Sincerely, GTA ASSOCIATES, INC. Andrew Beaty Staff Professional John P. Wille, P.E. Vice President Z:\Project\2020\City of Monroe\WWTP\Report of Preliminary Geotechnical Subsurface Exploration.doc Job No. 7-10-20 TABLE OF CONTENTS PAGE INTRODUCTION .......................................................................................................................... 1 SITE CONDITIONS ....................................................................................................................... 1 PROPOSED CONSTRUCTION .................................................................................................... 2 SITE GEOLOGY ............................................................................................................................ 2 SUBSURFACE EXPLORATION .................................................................................................. 3 SUBSURFACE CONDITIONS ..................................................................................................... 4 LABORATORY TESTING............................................................................................................ 6 PRELIMINARY CONCLUSIONS AND RECOMMENDATIONS ............................................. 7 Preliminary Foundation Support ................................................................................................. 8 Site Grading for Embankments ................................................................................................... 9 Difficult Excavation .................................................................................................................. 10 Subsurface Utilities ................................................................................................................... 11 Surface and Subsurface Drainage ............................................................................................. 12 ADDITIONAL SERVICES .......................................................................................................... 13 LIMITATIONS ............................................................................................................................. 13 ASFE—Important Information About Your Geotechnical Engineering Report Appendix A – Figures Figure No. 1 – Site Location Plan Figure No. 2 – Exploration Location Plan Figure No. 3 – Site Topography Plan Appendix B – Soil Boring Logs Notes for Exploration Logs (1 Sheet) Summary of Subsurface Exploration (1 Sheet) Soil Boring Logs (15 Sheets) Appendix C – Laboratory Results (1 Sheet) 1  REPORT OF PRELIMINARY GEOTECHNICAL SUBSURFACE EXPLORATION 15 MG EQUALIZATION BASIN – CITY OF MONROE WWTP MONROE, UNION COUNTY, NORTH CAROLINA INTRODUCTION The City of Monroe (Client) is planning to construct a 15 million-gallon equalization basin located to the west of the existing City of Monroe Wastewater Treatment Plant. The site encompasses approximately 25 acres of undeveloped wooded land located north of Industrial Drive and west of the Waste Water Treatment Plant in Monroe, Union County, North Carolina. Detailed information regarding the design plans and site grading information has not been provided to us at this time. Please refer the Site Location Plan included as Figure 1 in Appendix A for the approximate location of the site. GTA was retained to perform a preliminary geotechnical subsurface exploration of the project site to characterize the general near-surface subsurface conditions in the proposed equalization basin area. The scope of this study included a field exploration as well as an engineering and laboratory analysis. Included in our field exploration were eighteen (15) Standard Penetration Test borings to depths ranging from approximately 6.1 to 14 feet below the existing ground surface. Preliminary conclusions and recommendations regarding general site development were derived from the engineering analysis of the field and laboratory data. SITE CONDITIONS The site is located at the north end of Industrial drive and west of the existing waste water treatment plant in Monroe, Union County, North Carolina. The site encompasses approximately 25 acres of undeveloped land and is designated as Parcel Identification Number (PIN) 09111008. At the time of our investigation, the subject site is moderately to heavily wooded. The site is bordered to the west by the waste water treatment plant and Joes Branch Creek, to the north by Richardson Creek, and to the south by a manufacturing facility and associated parking. Report of Preliminary Exploration – 15 MG Equalization Basin City of Monroe July 10, 2020 GTA Project No. 35200584 2  Based on the topographic information provided on the Union County GIS, the ground surface elevations across the site range from a high of approximate Elevation 515 feet above mean sea level (AMSL), near the central portion of the subject property, to a low of approximate Elevation 495 feet AMSL, along the western portion of the subject property. Please refer to the attached Topographic Map presented as Figure 3 in Appendix A for more detailed information. PROPOSED CONSTRUCTION GTA was provided with a copy of a “Preliminary Site Plan” of the Equalization Basin provided by the City of Monroe. The Plan indicates that the subject property is proposed to be developed with an equalization basin in the center of the property that will be approximately 550 feet in length by 550 feet in width and approximately 6 feet deep. In addition, the Plan indicates that 2 utility lines will be constructed; a 36-inch force main extending approximately 600 linear feet along the western portion of the subject property to the WWTP, and a 24-inch return line extending approximately 250 linear feet along the northern portion of the property to Richardson Creek. Detailed information regarding the site grading, slope embankment details, as well as inlet and outlet structure information has not been provided to us at this time. However, based on our site reconnaissance, we anticipate that general site grading may consist of cut depths on the order of 6 feet and fill depths up to approximately 10 feet to establish final design grades for the embankment. SITE GEOLOGY The site is located in the Charlotte Belt of the Piedmont Plateau Geologic Province. According to the Geologic Map of North Carolina (1985), the site is underlain by metamudstone and meta argillite (CZmd2) also known as the “Cid Formation”. Ground surface elevations within the Piedmont Plateau vary from approximately 400 feet above sea level (AMSL) in the east to 2,000 feet (AMSL) in the west. Report of Preliminary Exploration – 15 MG Equalization Basin City of Monroe July 10, 2020 GTA Project No. 35200584 3  The typical residual soil profile associated with the Charlotte Belt consists of fine-grained soils (clays/silts) near the surface, where soil weathering is more advanced, underlain by more coarse-grained soils (sandy silts/silty sands) with depth. The boundary between the soil and rock is not sharply defined. This transitional zone, termed weathered rock, is normally found overlying the parent bedrock. The degree of weathering is influenced by fractures, joints, and by the presence of less resistant rock types. Therefore, the profile of the weathered rock and hard rock is quite irregular and erratic, even over short horizontal distances. Lenses, boulders, hard rock, and zones of weathered rock are often encountered within the soil mantle, well above the general unweathered bedrock level. The topography of the Piedmont Plateau consists of well-rounded hills and long rolling ridges with a northeast-southwest trend. This rolling topography is the result of streams flowing across and acting on rocks of unequal hardness. The Piedmont Plateau region is underlain by older crystalline (metamorphic and igneous) rock formations that trend northeast-southwest and vary greatly in their resistance to weathering and erosion. The major streams generally flow across the rock structures that are more highly fractured and more prone to weathering. Please refer to the publications for a more detailed description of the geologic units. SUBSURFACE EXPLORATION The field exploration consisted of drilling Standard Penetration Test (SPT) borings at fifteen (15) locations, designated as B-1 through B-15, across the property. The soil test borings were selected and field located by GTA using the existing topography and aerial photographs by visual estimation. The approximate location of the soil test borings is shown on the attached Exploration Location Plan presented as Figure 2 in Appendix A. Elevations provided on the boring logs were interpolated from site topography provided by Union County GIS. Please note that the boring locations have not been instrument surveyed and thus, all locations and elevations should be considered approximate. Report of Preliminary Exploration – 15 MG Equalization Basin City of Monroe July 10, 2020 GTA Project No. 35200584 4  The borings were drilled on June 17 and 18, 2020 to depths ranging from approximately 6.1 to 14 feet below the existing ground surface using an ATV-mounted CME 550X and ATV- mounted D-50 drill rig provided by HPC. A dozer was required to clear a path to gain access to the boring locations. Therefore, some topsoil was partially/completely removed in the vicinity of the borings during the clearing process. Standard Penetration Testing was performed in the boreholes, with soil samples obtained at approximately 2½-foot intervals in the upper 10 feet and at 5-foot intervals thereafter. Standard Penetration Testing involves driving a 2-inch O.D., 1 ⅜ -inch I.D. split-spoon sampler with a 140- pound hammer free-falling 30 inches. The SPT N-value, given as blows per foot (bpf), is defined as the total number of blows required to drive the sampler from 6 to 18 inches. Samples retrieved from the borings were returned to GTA's laboratory for visual classification by laboratory personnel. Descriptions as provided on the logs are visual. Boring logs were prepared using the observations made in the field during drilling, as well as the visual – manual classification in the laboratory. A geotechnical staff professional classified each soil sample on the basis of color, texture, and plasticity characteristics in general accordance with the USCS classification system. The geotechnical staff professional grouped the various soil types into the major zones noted on the boring logs. The stratification lines designating the interface between each material on the boring logs is approximate; the transition between the strata may be gradual in both the vertical and horizontal directions. SUBSURFACE CONDITIONS The borings confirm the underlying geologic formation as metamudstone and meta argillite (CZmd2). The test borings typically encountered native residual soils underlain by soft/hard weathered rock. Beneath the topsoil layer in the borings, residual soils were encountered. The residual soils generally consist of sandy silt. SPT N-values in the residual soils ranged from 7 to 77 blows per foot (bpf), averaging 38 bpf, indicating these soils are generally stiff to very hard in consistency. Report of Preliminary Exploration – 15 MG Equalization Basin City of Monroe July 10, 2020 GTA Project No. 35200584 5  Beneath the residual soils at Borings B-1 through B-15, soft weathered rock (SWR) was encountered at depths ranging from approximately 1 to 13.5 feet below the existing ground surface. In addition, a lens of SWR was encountered at Borings B-9 and B-14 at depths ranging from approximately 3.5 to 5 feet. Based on the North Carolina Building Code, soft weathered rock is defined as “broken and partially weathered rock with standard penetration resistance (ASTM D 1586) between 50 blows per 6 inches and 50 blows per inch.” SWR is a decomposed rock that serves as the transitional zone between soil and rock. SWR is most commonly delineated from residual soil when SPT values of 100 bpf are exhibited by the SPT sampler. While SWR is a rock- like material, it is often visually classified as a sandy silt as the SPT sampler pulverizes the material as it is driven. Underlying the residual soils and/or SWR at Borings B-2 and B-3, hard weathered rock (HWR) was encountered at a depth of approximately 6 feet below the existing ground surface. Based on the North Carolina Building Code, hard weathered rock is defined as “broken and partially weathered rock of sufficient hardness to refuse soils sampling tools; normally has standard penetration resistance (ASTM D 1586) in excess of 50 blows per 1 inch.” Borings B-1 through B-15 were terminated in the SWR/HWR upon auger refusal at depths ranging from approximately 6.1 to 14 feet below the existing ground surface. Auger refusal is defined as material that could not be penetrated with the drill rig equipment used on the project. Auger refusal may be due to large boulders, rock ledges, lenses, seams, or the top of parent bedrock. Core drilling techniques would be required to evaluate the character and continuity of the refusal material. However, core drilling was beyond the scope of this study. Groundwater was not encountered in the borings at the termination of drilling. Boring cave-in depths ranged from approximately 4.7 to 12.1 feet below the existing ground surface. The boring cave-in depths can be an indication of the groundwater level or may result from the soil falling in as the augers are removed from the borehole upon completion. Please be advised that groundwater levels are expected to fluctuate with changes in precipitation, drainage, and other factors. Report of Preliminary Exploration – 15 MG Equalization Basin City of Monroe July 10, 2020 GTA Project No. 35200584 6  LABORATORY TESTING Recovered soil samples were transported to our laboratory where they were subjected to visual - manual classification by a geotechnical staff professional. Boring Logs were prepared using the observations made in the field during drilling, as well as the visual – manual classification in the laboratory, supplemented by laboratory testing. A sample obtained from Boring B-10 at a depth of 1 to 2.5 feet was tested in our laboratory for Grain-Size Analysis, Atterberg Limits and natural moisture content. The Grain-Size Analysis and Atterberg Limits testing were performed to determine the Unified Soil Classification System (USCS) designation for the soil. The USCS classifications provide information regarding soil engineering behavior. The results are below in Table 1 as well as in Appendix C: TABLE 1: SUMMARY OF LABORATORY TESTING Boring No. Depth (ft) USCS Classification LL PI Moisture Content (%) B-10 1.0 - 2.5 ML 45 13 15.3 Selected samples from the borings were tested in our laboratory for natural (in-situ) moisture content. The tested samples from Borings B-1, B-3, B-5, B-8, B-11, and B-12 indicated natural moisture contents ranging from 12.8 to 25.3 percent, with an average moisture content of approximately 18 percent. One bulk near-surface sample from Boring B-10 was tested for moisture-density relationships in accordance with the Standard Proctor. The results of these tests are summarized in Table 2. Please refer to the laboratory test data provided in Appendix C for further information. Report of Preliminary Exploration – 15 MG Equalization Basin City of Monroe July 10, 2020 GTA Project No. 35200584 7  TABLE 2: SUMMARY OF COMPACTION DATA Standard Proctor (ASTM D698) Boring No. Depth (ft) Maximum Dry Density (pcf) Optimum Moisture (%) Natural Moisture (%) B-10 1 – 2.5 104.7 20.5 15.5 PRELIMINARY CONCLUSIONS AND RECOMMENDATIONS Based upon the results of this study, it is our opinion that the proposed construction is feasible, given that the geotechnical recommendations are followed, and that the standard level of care is maintained during construction. Please note that the presence of weathered and/or unweathered rock as well as moisture-sensitive soils wet of optimum for compaction will impact the design and construction of the proposed development and associated costs. Please note, depending upon the final grading and utility design, costs associated from the removal of weathered and/or unweathered rock could be significant. A discussion of GTA's preliminary assessment and conclusions with respect to the proposed construction is presented in the following paragraphs. As discussed, only conceptual plans have been provided at this time. This report is intended to assist the client with preliminary feasibility and planning. When final mass grading/development plans become available, it is recommended that additional explorations be performed to further identify the limits and characteristics of the near-surface soils and soft/hard weathered rock. Depending on final design grades and building layouts, geotechnical recommendations should be developed for the design and construction of foundations and parking/drive areas. Report of Preliminary Exploration – 15 MG Equalization Basin City of Monroe July 10, 2020 GTA Project No. 35200584 8  1.Preliminary Foundation Support In general, the proposed cast-in-place concrete structures including inlet and outlet structures can be supported on shallow spread footings. The medium stiff to very hard and medium dense to very dense native non-plastic soils are generally considered suitable for support of foundations using an allowable bearing pressure of 2,500 pounds per square foot (psf). Please note that higher allowable bearing pressures may be available if the foundations are bearing on or near the soft/hard weathered rock. This should be further evaluated in the field during final design of the foundations. Exterior footings should be founded a minimum of 12 inches below final exterior grade to provide protection from frost action. Depending upon the foundation bearing elevation, some undercutting and/or recompaction of any soft or very loose near-surface soils should be anticipated. Footings should be supported on stable medium stiff non-plastic natural soils, or properly compacted structural fill as outlined in this report. New fill for support of foundations should be placed in accordance with GTA’s site grading recommendations. Any soft, disturbed, or unstable soil present at the footing subgrade elevation should be excavated to a stable stratum. In addition, if rock is encountered at the foundation bearing elevation, a minimum of 6-inches of #57 washed stone should be placed between the top of the rock and the bottom of the foundation bearing elevation to provide a uniform transition and prevent a “point load” condition on the footings. Over-excavation and replacement, if required, should be performed under the observation of the project geotechnical engineer or their qualified representative based on actual conditions encountered in the field at the time of construction. Bearing capacity evaluations should be performed using a combination of visual observation, hand-auger probing, and Dynamic Cone Penetrometer (DCP) testing. Concrete placement should be performed the same day the footings are excavated to prevent exposure and potential weakening of the foundation subgrade. Report of Preliminary Exploration – 15 MG Equalization Basin City of Monroe July 10, 2020 GTA Project No. 35200584 9  2.Site Grading for Embankments Prior to the placement of fill, where required, the existing subgrade surface should be stripped and grubbed to remove all existing trees, surface vegetation, topsoil/rootmat and other deleterious matter. The stripping thickness will be dependent on a variety of factors, including the soil moisture, construction traffic disturbance, weather during construction, and contractor care. As previously indicated, moisture contents from the various soil test borings ranged from 15.3 to 25.3 percent, with an average moisture content of approximately 18 percent. In addition, the natural moisture content of the Proctor sample obtained at B-10 was 15.5 percent. Therefore, if plans are to reuse the excavation materials for structural fill, some moisture conditioning of the soils should be anticipated, especially for moisture contents greater than 23 percent. To minimize the economic impact associated with poor workability and/or trafficability of wet subgrade soils due to moisture sensitive soils, GTA recommends construction during the dry season (summer/fall) to reduce the effort and cost required for drying of the wet soils. GTA recommends that a contingency be established for drying and/or over-excavating, chemical treatment, and replacing unsuitable soils. After stripping, the fill subgrade should be proof-rolled with a loaded, 10-wheel tandem- axle dump truck. The proof-rolling should be observed by a geotechnical engineer or their qualified representative. Any soft or otherwise unsuitable soils should be dried and re- compacted or removed prior to placement of fill. No fill should be placed until the subgrade is approved by the geotechnical engineer. Off-site borrow, if required, should meet Unified Soil Classification System (USCS) designation SM, SP, SW, GP, GM, or GW and be approved by the Geotechnical Engineer. All fills should be constructed in maximum 8-inch thick loose lifts and be compacted to the following specifications: Report of Preliminary Exploration – 15 MG Equalization Basin City of Monroe July 10, 2020 GTA Project No. 35200584 10  COMPACTION SPECIFICATIONS Structure / Fill Location Compaction / Moisture Specification Below foundations, retaining walls, inlet/outlet structures, and within wall backfill or slopes steeper than 5H:1V 95% of ASTM D-698 Moisture: ± 3% of optimum All compactive effort should be verified by in-place density testing. New fills constructed on slopes steeper than 5H:1V (horizontal to vertical) should be keyed into existing slopes for stability considerations. All fill slopes steeper than 5H:1V should generally be placed as structural fill and be controlled and compacted to minimum densities as specified above. Fill for slopes in non-structural areas, such as landscape berms, can be constructed as steep as 3H:1V up to a height of ten feet. Detailed information regarding the height and slope of the new embankments have not been provided to us at this time. Depending on the height of the new embankment slopes, a slope stability analysis should be performed prior to construction. 3.Difficult Excavation As previously indicated, detailed information regarding the site grading and final design grades have not been provided to us at this time. Based on the results of the field exploration, it is GTA’s opinion that the majority of the excavations less than 5 feet below the existing grades can be made by conventional means, i.e. scraping. However, results of the borings indicate that soft/hard weathered rock (SWR/HWR) was encountered in Borings B-1 through B-15 at depths ranging from approximately 1 to 13.5 feet below the existing ground surface. Report of Preliminary Exploration – 15 MG Equalization Basin City of Monroe July 10, 2020 GTA Project No. 35200584 11  The depth to, and thickness of the soft/hard weathered rock, rock lenses, seams, or bedrock, can vary dramatically in short distances, especially between the boring locations. Therefore, soft/hard weathered rock and/or bedrock should be anticipated during excavation in these areas. It has been our past experience in this geologic area, that materials having SPT ‘N’ values of less than 50 blows per 4 inches can generally be excavated using pans and scrapers by first loosening with a single tooth ripper attached to a suitable size dozer, such as a Caterpillar D- 8 or D-9. It should be noted that ripping is dependent on the equipment and techniques used as well as the operator’s skill and experience. The success of the ripping operation is dependent on finding the proper combination for the conditions encountered. Excavation of the weathered rock is typically much more difficult in confined excavations, such as utility excavations. Jack hammering or blasting should be anticipated for materials having SPT ‘N’ values in excess of 50 blows per 2 inches, or at or near the level that auger refusal is encountered. Test pits should be performed prior to construction to determine whether these materials can be excavated. On projects requiring ripping or jack hammering, a controversy sometimes develops as to whether the material can be removed by ripping or whether blasting is required. The project specifications and contract should be carefully prepared to reduce the potential for disputes and claims relating to excavation of very dense weathered or unweathered rock. 4.Subsurface Utilities The natural soils are considered suitable for support of below grade utilities; however, GTA recommends a minimum 6-inch-thick granular bedding to provide uniform support as dictated by site conditions or as required by local code. Based upon the results of the borings, GTA anticipates that the excavations may be accomplished using standard utility construction equipment to a depth of up to approximately 5 feet below existing grades throughout the majority of the site depending upon the excavator utilized. However, auger refusal material was encountered in Borings B-1 through B-15 at depths ranging from Report of Preliminary Exploration – 15 MG Equalization Basin City of Monroe July 10, 2020 GTA Project No. 35200584 12  approximately 6.1 to 14 feet below the existing ground surface. Jacking or blasting should be anticipated below these depths. After the utility alignments and elevations are designed and prior to construction, test pits should be performed to determine if invert elevations can be achieved. Due to the potential for collapse of unsupported excavations, the utility contractor should be prepared to provide adequate earth support systems during utility construction. Compaction of the soils to the degree specified in the Site Grading section of this report may require that the soils be moisture conditioned prior to placement and compaction within the trench. If the excavated materials are wet of the optimum moisture content, they should be spread in thin layers and aerated by discing to within 2 to 4 percentage points of the optimum moisture. If soils are not dried, suitable borrow material will need to be imported from other areas of the site for utility trench backfill. 5. Surface and Subsurface Drainage As previously indicated, detailed information regarding the site grading and final design grades have not been provided to us at this time. However, final grades should be carefully established to provide adequate surface drainage away from the foundations. A minimum grade of 3 percent in landscape areas is recommended to direct surface water away from the proposed structures. Groundwater was not encountered in the borings at the termination of drilling. The boreholes were backfilled at the termination of drilling for safety reasons. Please note that groundwater levels are likely to fluctuate due to variation in rainfall and other factors. It is GTA’s opinion that excavations to depths of 10 feet or less should not be impacted by groundwater. However, groundwater may be encountered in excavations at greater depths, especially along any low-lying portions of the site. There is also a potential for perched or trapped groundwater to be encountered at shallow depths in localized portions of the site, particularly within granular soil seams underlain by less permeable material or at Report of Preliminary Exploration – 15 MG Equalization Basin City of Monroe July 10, 2020 GTA Project No. 35200584 13  fill/natural ground interfaces. In the event that localized perched water is encountered, the contractor should be prepared to dewater the excavations. ADDITIONAL SERVICES We recommended that during construction of the subject project, a geotechnical engineer be retained to provide observation and testing services for the following items. Review final site and structural plans to evaluate if they conform with the intent of this report. If necessary, perform a design phase geotechnical exploration consisting of additional borings and/or test pits to further evaluate the weathered and/or unweathered rock on-site. Observe and test the preparation of the equalization basin area. Provide observation and testing during fill placement to evaluate if the work is being performed in accordance with the project specifications and intent of this report. Observe the proof-rolling of fill subgrade in the embankment areas prior to placing fill to evaluate stability. LIMITATIONS This report has been prepared for the exclusive use of the City of Monroe in accordance with generally accepted geotechnical engineering practice. No warranty, express or implied, is made. The analysis and recommendations contained in this report are based on the data obtained from limited observation and testing of the surface materials. The borings indicate soil conditions only at specific locations and times, and only to the depths penetrated. They do not necessarily reflect strata variations that may exist between boring locations. Consequently, the analysis and recommendations must be considered preliminary until the subsurface conditions can be verified by direct observation at the time of construction. If variations in subsurface conditions from those Report of Preliminary Exploration – 15 MG Equalization Basin City of Monroe July 10, 2020 GTA Project No. 35200584 14  described are noted during construction, recommendations in this report may need to be re- evaluated. In the event that any changes in the nature, design, or location of the facilities are planned, the conclusions and recommendations contained in this report should not be considered valid unless the changes are reviewed and conclusions of this report are verified in writing. GTA Associates, Inc. is not responsible for any claims, damages, or liability associated with interpretation of subsurface data or reuse of the subsurface data or engineering analysis without the express written authorization of GTA Associates, Inc. In accordance with the guidelines of Geoprofessional Business Association (GBA), it is recommended that GTA Associates, Inc. be retained to provide continuous soils engineering services for this project. Participation of GTA will facilitate compliance with GTA's recommendations, and allow changes to be made in these recommendations, in the event that subsurface conditions are found to vary from those anticipated prior to the start of construction. This report and the attached logs are instruments of service. If certain conditions or items are noted during our investigation, GTA Associates, Inc. may be required by prevailing statutes to notify and provide information to regulatory or enforcement agencies. GTA Associates, Inc. will notify our Client should a required disclosure condition exist. This report was prepared by GTA Associates, Inc. (GTA) for the sole and exclusive use of GTA Associates, Inc. and the City of Monroe. Use and reproduction of this report by any other person without the expressed written permission of GTA or the City of Monroe is unauthorized and such use is at the sole risk of the user. 35200584 GTA ASSOCIATES, INC. Important lntormation about Your Geotechnical-Engineering Report Geotechnical Services Are Performed tor Specific Purposes, Persons, and Projects Geotechnical engineers structure their services to meet the specific needs of their clients. A geotechnical-engineering study conducted for a civil engi­neer may not fulfill the needs of a construction contractor or even another civil engineer. Because each geotechnical-engineering study is unique, each geotechnical-engineering report is unique, prepared solely for the client. No one except you should rely on your geotechnical engineering report without first conferring with the geotechnical engineer who prepared it. And no one-not even you -should apply the report for any purpose or projectexcept the one originally contemplated.Read the Full Report Serious problems have occurred because those relying on a geotechnical­engineering report did not read it all. Do not rely on an executive summary. Do not read selected elements only. A Geotechnical-Engineering Report Is Based on a Unique Set ol Project-Specific Factors Geotechnical engineers consider many unique, project-specific factors when establishing the scope of a study. Typical factors include: the client's goals, objectives, and risk-management preferences; the general nature of the structure involved, its size, and configuration; the location of the struc­ture on the site; and other planned or existing site improvements, such as access roads, parking lots, and underground utilities. Unless the geotech­nical engineer who conducted the study specifically indicates otherwise, do not rely on a geotechnical engineering report that was: •not prepared for you,•not prepared for your project,•not prepared for the specific site explored, or•completed before important project changes were made.Typical changes that can erode the reliability of an existing geotechnical­engineering report include those that affect: •the function of the proposed structure, as when it's changed from aparking garage to an office building, or from a light-industrial plantto a refrigerated warehouse,•elevation, configuration, location, orientation, or weight of theproposed structure,•composition of the design team, or•project ownership.As a general rule, always inform your geotechnical engineer of project changes--even minor ones-and request an assessment of their impact. Geotechnical engineers cannot accept responsibility or liability for problems that occur because their reports do not consider developments of which they were not informed. Subsurface Conditions Can Change A geotechnical-engineering report is based on conditions that existed at the time the study was performed. Do not rely on a geotechnica/-engineer­ing reportwhose adequacy may have been affected by: the passage of time; by man-made events, such as construction on or adjacent to the site; or by natural events, such as floods, droughts, earthquakes, or groundwa­ter fluctuations. Always contact the geotechnical engineer before applying the report to determine if it is still reliable. A minor amount of additional testing or analysis could prevent major problems. Most Geotechnical Findings Are Professional Opinions Site exploration identifies subsurface conditions only at those points where subsurface tests are conducted or samples are taken. Geotechnical engi­neers review field and laboratory data and then apply their professional judgment to render an opinion about subsurface conditions throughout the site. Actual subsurface conditions may differ-sometimes significantly­from those indicated in your report. Retaining the geotechnical engineer who developed your report to provide construction observation is the most effective method of managing the risks associated with unanticipated conditions. A Report's Recommendations Are Not Final Do not overrely on the construction recommendations included in your report. Those recommendations are not final, because geotechnical engi­neers develop them principally from judgment and opinion. Geotechnical engineers can finalize their recommendations only by observing actual subsurface conditions revealed during construction. The geotechnicalengineer who developed your report cannot assume responsibility or liability for the report's recommendations if that engineer does not perform construction observation. A Geotechnical Engineering Report Is Subject to Misinterpretation Other design team members' misinterpretation of geotechnical-engineering reports has resulted in costly problems. Lower that risk by having your geo­technical engineer confer with appropriate members of the design team alter submitting the report. Also retain your geotechnical engineer to review perti­nent elements of the design team's plans and specifications. Contractors can also misinterpret a geotechnical-engineering report. Reduce that risk by having your geotechnical engineer participate in prebid and preconstruction conferences, and by providing construction observation. Do Not Redraw the Engineer's Logs Geotechnical engineers prepare final boring and testing logs based upon their interpretation of field logs and laboratory data. To prevent errors or omissions, the logs included in a geotechnical engineering report should never be redrawn for inclusion in architectural or other design drawings. Only photographic or electronic reproduction is acceptable, but recognizethat separating logs f ram the report can elevate risk. Give Contractors a Complete Report and Guidance Some owners and design professionals mistakenly believe they can make contractors liable for unanticipated subsurface conditions by limiting what they provide for bid preparation. To help prevent costly problems, give con­tractors the complete geotechnical-engineering report, but preface it with a clearly written letter of transmittal. In that letter, advise contractors that the report was not prepared for purposes of bid development and that the report's accuracy is limited; encourage them to confer with the geotechnical engineer who prepared the report (a modest fee may be required) and/or to conduct additional study to obtain the specific types of information they need or prefer. A prebid conference can also be valuable. Be sure contrac­tors have sufficient time to perform additional study. Only then might you be in a position to give contractors the best information available to you, while requiring them to at least share some of the financial responsibilities stemming from unanticipated conditions. Read Responsibility Provisions Closely Some clients, design professionals, and contractors do not recognize that geotechnical engineering is far less exact than other engineering disci­plines. This lack of understanding has created unrealistic expectations that have led to disappointments, claims, and disputes. To help reduce the risk of such outcomes, geotechnical engineers commonly include a variety of explanatory provisions in their reports. Sometimes labeled "limitations," many of these provisions indicate where geotechnical engineers' responsi­bilities begin and end, to help others recognize their own responsibilities and risks. Read these provisions closely Ask questions. Your geotechnical engineer should respond fully and frankly. Geoenvironmental Concerns Are Not Covered The equipment, techniques, and personnel used to perform a geoenviron­mental study differ significantly from those used to perform a geotechnicalstudy. For that reason, a geotechnical-engineering report does not usually relate any geoenvironmental findings, conclusions, or recommendations; e.g., about the likelihood of encountering underground storage tanks orregulated contaminants. Unanticipated environmental problems have led tonumerous project failures. It you have not yet obtained your own geoenvi­ronmental information, ask your geotechnical consultant for risk manage­ment guidance. Do not rely on an environmental report prepared for some­one else.Obtain Professional Assistance To Deal with Mold Diverse strategies can be applied during building design, construction, operation, and maintenance to prevent significant amounts of mold from growing on indoor surfaces. To be effective, all such strategies should be devised for the express purpose of mold prevention, integrated into a com­prehensive plan, and executed with diligent oversight by a professional mold-prevention consultant. Because just a small amount of water or moisture can lead to the development of severe mold infestations, many mold-prevention strategies focus on keeping building surfaces dry. While groundwater, water infiltration, and similar issues may have been addressed as part of the geotechnical-engineering study whose findings are conveyed in this report, the geotechnical engineer in charge of this project is not a mold-prevention consultant; none of the services per­ formed in connection with the geotechnica/ engineer's study were designed or conducted for the purpose of mold preven­ tion. Proper implementation of the recommendations conveyed in this report will not of itself be sufficient to prevent mold from growing in or on the structure involved. Relyt. on Your GBA-Member Geotechncial Engineer for 11dditiona1 Assistance Membership in the GEOPROFESSIONAL BUSINESS AssOCIATION exposes geotech­nical engineers to a wide array of risk confrontaton techniques that can be of genuine benefit for everyone involved with a construction project. Confer with your GSA-member geotechnical engineer for more information. GEOPROFESSIONAL BUSINESS -ASSOCIATION 8811 Colesville Road/Suite G106, Silver Spring, MD 20910 Telephone: 301/565-2733 Facsimile: 301/589-2017 e-mail: info@geoprofessional.org www.geoprofessional.or g Copyright 2014 by Geoprofessional Business Association, lnc.(GBA). Duplication. reproduction, or copying of this document, in whole or in part, by any means whatsoever. is strictly prohibited, except with GBA's specific written permission. Excerpting, quoting, or otherwise extracting wording from this document is permitted only with the express written permission of GBA, and only for purposes of scholarly research or book review. Only members of GBA may use this document as a complement to or as an element of a geotechnical-engineering report. Any other firm, individual, or other entity that so uses this document without being a GBA member could be commiting negligent or intentional (fraudulent) misrepresentation. IIGEA 0914/5.0MRP APPENDIX A FIGURES Base map obtained from Google Maps Monroe, Union County, North Carolina 2020 GTA ASSOCIATES, INC. GEOTECHNICAL AND ENVIRONMENTAL CONSULTANTS 710 Peninsula Lane, Suite B Charlotte, North Carolina 28273 Ph. (704) 553-2300 Fax (704) 553-2400 CITY OF MONROE WWTP EQ BASIN SITE LOCATION PLAN MONROE, NORTH CAROLINA JOB NO: DATE: SCALE: DRAWN BY: REVIEWED BY: FIGURE NO: 35200770 JUNE 11, 2020 NTS GTA JPW 1 NAPPROXIMATE SITE LOCATION EXPLORATION LOCATION PLAN INDUSTRIAL DRIVE, MONROE, NC GTA ASSOCIATES 710 PENINSULA LANE, SUITE B CHARLOTTE, NC 28273 (704) 553-2300 O(704) 553-2400 FDATE: June 11, 2020 FIGURE NO. 2 LEGEND: SOIL TEST BORING LOCATIONS TOPOGRAPHIC PLAN MONROE WWTP EQ BASIN - INDUSTRIAL DRIVE, MONROE, NC GTA ASSOCIATES 710 PENINSULA LANE, SUITE B CHARLOTTE, NC 28273 (704) 553-2300 O(704) 553-2400 FDATE: June 11, 2020 FIGURE NO. 2 LEGEND: SOIL TEST BORING LOCATIONS APPENDIX B BORING LOGS Approximate Depth Approximate Approximate Boring Boring Depth of of Soft / Hard Depth of Level of Cave-in Moisture No. Boring Weathered Rock Auger Refusal Groundwater Depths Content (ft.)(ft.) (ft.) Depth (ft) (ft.) (%) / (Depth) B-1 7.4 6 7.4 Dry 4.7 16.1 (1-2.5') B-2 6.1 1 6.1 Dry 5 B-3 6.1 6 6.1 Dry 5.2 15.3 (1-2.5') B-4 6.4 4 6.4 Dry 5.1 B-5 9.9 9.5 9.9 Dry 6.9 21.5 (1-2.5') B-6 6.2 4 6.2 Dry 4.7 B-7 6.4 4.5 6.4 Dry 4.8 B-8 9.3 9 9.3 Dry 6.8 12.8 (3.5-5') B-9 9.9 4 9.9 Dry 6.8 B-10 14 13.5 14 Dry 12.1 B-11 9.8 9.5 9.8 Dry 6.8 17.2 (3.5-5') B-12 6.7 6.5 6.7 Dry 5.6 25.3 (3.5-5') B-13 6.8 4.5 6.8 Dry 4.8 B-14 9.8 4.5 9.8 Dry 7.8 B-15 7 4.5 7 Dry 4.6 TABLE 1 SUBSURFACE EXPLORATION SUMMARY CITY OF MOROE WWTP EQUALIZATION BASIN GTA JOB NO. 35200850 Page 1 of 1 NOTES FOR EXPLORATION LOGS KEY TO uses TERMINOLOGY AND GRAPHIC SYMBOLS COARSE-GRAINED SOILS (GRAVEL AND SAND) COARSE­GRAINED SOILS MORE THAN 50% OF MATERIAL IS LARGER THAN NO. 200 SIEVE SIZE FINE­GRAINED SOILS MAJOR DIVISIONS SYMBOLS (BASED UPON ASTM D 2488) GRAPHIC LETTER GRAVEL AND GRAVELLY SOILS )'-' \_J 0 CLEAN o[Y 00 GW GRAVELS 1,-,b ___ D <2:jrr_�-c------1.... w. (LESS THAN 15% PASSING THE NO. 200 SIEVE) ; I•�. '. MORE THAN 50% • • 1 .. t •OF COARSE GRAVELS WITH • I • , • GP GM FRACTION FINES • � ◄ I�. RETAINED ON NO. baP'l)lll .. ,.r,,,,:;,1------. 4 SIEVE (MORE THAN 15% PASSING THE NO. 200 SIEVE) � SAND AND SANDY SOILS MORE THAN 50% OF COARSE FRACTION PASSING ON NO. 4SIEVE CLEAN SANDS ...... . . . . . ....... ............ ............ ....... . . . . . (LESS THAN 15% PASSING THE NO. 200 SIEVE) :'..\';;::: :'( .. :.:.. .. ::·.-.::•:" SANDS WITH FINES ···· .. ·.:� �., .. : ':··· -� · /\.; I •;• 7/27//2 (MORE THAN 15% PASSING THE NO. 200 SIEVE) � SILTS AND LEAN CLAYS SILT OR CLAY • ------ GC SW SP SM SC ML CL (<15% RETAINED ON THE NO. 200 SIEVE) LIQUID LIMIT LESS THAN50 ---OL ---SILT OR CLAY WITH SAND OR GRAVEL f-------��-r+------1 MORE THAN 50% o o OF MATERIAL IS (151/o TO 301/o RETAINED ON THE NO. 200 SIEVE)MH SMALLER THAN SANDY OR GRAVELLY SILT OR CLAY ELASTIC SILTSNO. 200 SIEVE AND ��..»:M,:;t-------t S (>30% RETAINED ON THE NO. 200 SIEVE) CH IZE FAT CLAYS LIQUID LIMIT ////"..'/ HIGHLY ORGANIC SOILS GREATER THAN 50 f./f}.f.1/} '{f ///.1/f./. / ·//. OH PT BLOWS PER DESIGNATION FOOT(BPF) "N" VERY LOOSE 0-4 LOOSE 5 -10 MEDIUM DENSE 11 -30 DENSE 31 -50 VERY DENSE >50 NOTE: "N" VALUE DETERMINED AS PER ASTM D 1586 FINE-GRAINED SOILS (SILT AND CLAY) CONSISTENCY BPF "N" VERY SOFT <2 SOFT 2-4 MEDIUM STIFF 5-8 STIFF 9-15 VERY STIFF 16-30 HARD >30 NOTE: ADDITIONAL DESIGNATIONS TO ADVANCE SAMPLER INDICATED IN BLOW COUNT COLUMN: WOH = WEIGHT OF HAMMER WOR = WEIGHT OF ROD(S) SAMPLE TYPE DESIGNATION SYMBOL NOTE: DUAL SYMBOLS ARE USED TO INDICATE COARSE-GRAINED SOILS WHICH CONTAIN AN ESTIMATED 5 TO 15% FINES BASED ON VISUAL CLASSIFICATION OR BETWEEN 5 AND 12% FINES BASED ON LABORATORY TESTING; AND FINE-GRAINED SOILS WHEN THE PLOT OF LIQUID LIMIT & PLASTICITY INDEX VALUES FALLS IN THE PLASTICITY CHART'S CROSS-HATCHED AREA. FINE-GRAINED SOILS ARE CLASSIFIED AS ORGANIC (OL OR OH) WHEN ENOUGH ORGANIC PARTICLES ARE PRESENT TO INFLUENCE ITS PROPERTIES. LABORATORY TEST RESULTS ARE USED TO SUPPLEMENT SOIL CLASSIFICATION BY THE VISUAL-MANUAL PROCEDURES OF ASTM D 2488. SOIL SAMPLE SHELBY TUBE S- U-ADDITIONAL TERMINOLOGY AND GRAPHIC SYMBOLS DESCRIPTION TOPSOIL ADDITIONAL DESIGNATIONS MAN MADE FILL GLACIAL TILL COBBLES AND BOULDERS DESCRIPTION "N"VALUE RESIDUAL SOIL HIGHLY WEATHERED ROCK 50 TO 50/1" DESIGNATIONS MORE THAN 50 BLOWS FOR 1" PARTIALLY WEA THE RED ROCK OF PENETRATION OR LESS, AUGER PENETRABLE GRAPHIC SYMBOLS � ... \f�-.-3:,,:.:,\·i;: ·, ;_ 1:r:��r:/(0 X X X )( XXX X �f -£ xA )<, )<, )(.}<, XJV' -· � .:.i. 00 .oo .oo .oo ,! 0 ! 0 ! 0 ! � �:;:4/{f;,;:;4,i\�: 1iI!f:�l�� � b. b. b. b. b. b. b. b. /j IA A A A A ROCK CORE R- WATER DESIGNATION DESCRIPTION SYMBOL ENCOUNTERED DURING DRILLING � UPON COMPLETION OF DRILLING � 24 HOURS AFTER COMPLETION y NOTE: WATER OBSERVATIONS WERE MADE AT THE TIME INDICATED. POROSITY OF SOIL STRATA, WEATHER CONDITIONS, SITE TOPOGRAPHY, ETC. MAY CAUSE WATER LEVEL CHANGES. REVISED JUNE 2009 0 5 10 15 20 25 30 S-1 S-2 S-3 0.4 3.5 6.0 16 16 14 4-7-17 7-15-22 17-22-50/5 24 37 100+ 506.0 505.6 500.0 498.6 ML SWR Topsoil (5") Brown, moist, very stiff, sandy SILT same, hard Brown, dry, hard, Soft Weathered Rock BORING TERMINATED AT 7.4 FEET UPON AUGER REFUSAL LOG OF BORING NO. B-1 PROJECT:City of Monroe WWTP WATER LEVEL (ft):DRY DATE:6-18-20PROJECT NO.: 35200850 PROJECT LOCATION: Industrial Drive, Monroe, N.C.CAVED (ft):4.7 DATE STARTED:6-18-20 WATER ENCOUNTERED DURING DRILLING (ft)DRY DATE COMPLETED:6-18-20 GROUND SURFACE ELEVATION:506 DRILLING CONTRACTOR:HPC DATUM:AMSL DRILLER:Zack Kiker EQUIPMENT:CME 550X DRILLING METHOD:Hollow Stem Auger LOGGED BY:A.B. SAMPLING METHOD:Standard Penetration Testing CHECKED BY:J.P.W. NOTES:GROUND SURFACE ELEVATIONS ARE APPROXIMATE BASED ON TOPOGRAPHIC SURVEY LOG OF BORING NO. B-1SAMPLENUMBERSAMPLEDEPTH (ft.)SAMPLERECOVERY (in.)SAMPLEBLOWS/6 inchesN (blows/ft.)ELEVATION (ft.)DEPTH (ft.)USCSGRAPHICSYMBOLDESCRIPTION REMARKS Sheet 1 of 1 Sheet 1 of 1 M.C.=16.1% 0 5 10 15 20 25 30 S-1 S-2 S-3 0.5 3.5 6.0 8 2 .5 28-50/6 50/3 50/1 100+ 100+ 100+ 500.0 499.5 494.0 493.9 SWR HWR Topsoil (6") Gray, dry, hard, Soft Weathered Rock same Gray, dry, hard, Hard Weathered Rock BORING TERMINATED AT 6.1 FEET UPON AUGER REFUSAL LOG OF BORING NO. B-2 PROJECT:City of Monroe WWTP WATER LEVEL (ft):DRY DATE:6-18-20PROJECT NO.: 35200850 PROJECT LOCATION: Industrial Drive, Monroe, N.C.CAVED (ft):5.0 DATE STARTED:6-18-20 WATER ENCOUNTERED DURING DRILLING (ft)DRY DATE COMPLETED:6-18-20 GROUND SURFACE ELEVATION:500 DRILLING CONTRACTOR:HPC DATUM:AMSL DRILLER:Zack Kiker EQUIPMENT:CME 550X DRILLING METHOD:Hollow Stem Auger LOGGED BY:A.B. SAMPLING METHOD:Standard Penetration Testing CHECKED BY:J.P.W. NOTES:GROUND SURFACE ELEVATIONS ARE APPROXIMATE BASED ON TOPOGRAPHIC SURVEY LOG OF BORING NO. B-2SAMPLENUMBERSAMPLEDEPTH (ft.)SAMPLERECOVERY (in.)SAMPLEBLOWS/6 inchesN (blows/ft.)ELEVATION (ft.)DEPTH (ft.)USCSGRAPHICSYMBOLDESCRIPTION REMARKS Sheet 1 of 1 Sheet 1 of 1 0 5 10 15 20 25 30 S-1 S-2 S-3 0.8 3.5 6.0 16 16 1 6-7-8 6-13-22 50/1 15 35 100+ 498.0 497.2 492.0 491.9 ML HWR Topsoil (8") Brown, moist, stiff, sandy SILT same, hard Brown, dry, hard, Hard Weathered Rock BORING TERMINATED AT 6.1 FEET UPON AUGER REFUSAL LOG OF BORING NO. B-3 PROJECT:City of Monroe WWTP WATER LEVEL (ft):DRY DATE:6-18-20PROJECT NO.: 35200850 PROJECT LOCATION: Industrial Drive, Monroe, N.C.CAVED (ft):5.2 DATE STARTED:6-18-20 WATER ENCOUNTERED DURING DRILLING (ft)DRY DATE COMPLETED:6-18-20 GROUND SURFACE ELEVATION:498 DRILLING CONTRACTOR:HPC DATUM:AMSL DRILLER:Zack Kiker EQUIPMENT:CME 550X DRILLING METHOD:Hollow Stem Auger LOGGED BY:A.B. SAMPLING METHOD:Standard Penetration Testing CHECKED BY:J.P.W. NOTES:GROUND SURFACE ELEVATIONS ARE APPROXIMATE BASED ON TOPOGRAPHIC SURVEY LOG OF BORING NO. B-3SAMPLENUMBERSAMPLEDEPTH (ft.)SAMPLERECOVERY (in.)SAMPLEBLOWS/6 inchesN (blows/ft.)ELEVATION (ft.)DEPTH (ft.)USCSGRAPHICSYMBOLDESCRIPTION REMARKS Sheet 1 of 1 Sheet 1 of 1 M.C.=15.3% 0 5 10 15 20 25 30 S-1 S-2 S-3 0.6 3.5 6.0 16 5 .5 6-8-18 28-50/5 50/4 26 100+ 100+ 495.0 494.4 491.5 488.6 ML SWR Topsoil (7") Brown, moist, very stiff, sandy SILT Brow, dry, hard, Soft Weathered Rock same BORING TERMINATED AT 6.4 FEET UPON AUGER REFUSAL LOG OF BORING NO. B-4 PROJECT:City of Monroe WWTP WATER LEVEL (ft):DRY DATE:6-18-20PROJECT NO.: 35200850 PROJECT LOCATION: Industrial Drive, Monroe, N.C.CAVED (ft):5.1 DATE STARTED:6-18-20 WATER ENCOUNTERED DURING DRILLING (ft)DRY DATE COMPLETED:6-18-20 GROUND SURFACE ELEVATION:495 DRILLING CONTRACTOR:HPC DATUM:AMSL DRILLER:Zack Kiker EQUIPMENT:CME 550X DRILLING METHOD:Hollow Stem Auger LOGGED BY:A.B. SAMPLING METHOD:Standard Penetration Testing CHECKED BY:J.P.W. NOTES:GROUND SURFACE ELEVATIONS ARE APPROXIMATE BASED ON TOPOGRAPHIC SURVEY LOG OF BORING NO. B-4SAMPLENUMBERSAMPLEDEPTH (ft.)SAMPLERECOVERY (in.)SAMPLEBLOWS/6 inchesN (blows/ft.)ELEVATION (ft.)DEPTH (ft.)USCSGRAPHICSYMBOLDESCRIPTION REMARKS Sheet 1 of 1 Sheet 1 of 1 0 5 10 15 20 25 30 S-1 S-2 S-3 S-4 0.2 3.5 6.0 8.5 13 16 16 16 6-8-14 13-23-34 30-36-38 22-31-50/5 22 57 74 100+ 514.0 513.8 505.5 504.1 ML SWR Topsoil (2") Brown, moist, very stiff, sandy SILT same, hard same Brown, dry, hard, Soft Weathered Rock BORING TERMINATED AT 9.9 FEET UPON AUGER REFUSAL LOG OF BORING NO. B-5 PROJECT:City of Monroe WWTP WATER LEVEL (ft):DRY DATE:6-18-20PROJECT NO.: 35200850 PROJECT LOCATION: Industrial Drive, Monroe, N.C.CAVED (ft):6.9 DATE STARTED:6-18-20 WATER ENCOUNTERED DURING DRILLING (ft)DRY DATE COMPLETED:6-18-20 GROUND SURFACE ELEVATION:514 DRILLING CONTRACTOR:HPC DATUM:AMSL DRILLER:Zack Kiker EQUIPMENT:CME 550X DRILLING METHOD:Hollow Stem Auger LOGGED BY:A.B. SAMPLING METHOD:Standard Penetration Testing CHECKED BY:J.P.W. NOTES:GROUND SURFACE ELEVATIONS ARE APPROXIMATE BASED ON TOPOGRAPHIC SURVEY LOG OF BORING NO. B-5SAMPLENUMBERSAMPLEDEPTH (ft.)SAMPLERECOVERY (in.)SAMPLEBLOWS/6 inchesN (blows/ft.)ELEVATION (ft.)DEPTH (ft.)USCSGRAPHICSYMBOLDESCRIPTION REMARKS Sheet 1 of 1 Sheet 1 of 1 M.C.=21.5% 0 5 10 15 20 25 30 S-1 S-2 S-3 0.5 3.5 6.0 10 6 2 4-4-27 21-50/4 50/2 31 100+ 100+ 504.0 503.5 500.5 497.8 ML SWR Topsoil (5") Brown, moist, hard, sandy SILT Brown, dry, hard, Soft Weathered Rock same BORING TERMINATED AT 6.2 FEET UPON AUGER REFUSAL LOG OF BORING NO. B-6 PROJECT:City of Monroe WWTP WATER LEVEL (ft):DRY DATE:6-18-20PROJECT NO.: 35200850 PROJECT LOCATION: Industrial Drive, Monroe, N.C.CAVED (ft):4.7 DATE STARTED:6-18-20 WATER ENCOUNTERED DURING DRILLING (ft)DRY DATE COMPLETED:6-18-20 GROUND SURFACE ELEVATION:504 DRILLING CONTRACTOR:HPC DATUM:AMSL DRILLER:Zack Kiker EQUIPMENT:CME 550X DRILLING METHOD:Hollow Stem Auger LOGGED BY:A.B. SAMPLING METHOD:Standard Penetration Testing CHECKED BY:J.P.W. NOTES:GROUND SURFACE ELEVATIONS ARE APPROXIMATE BASED ON TOPOGRAPHIC SURVEY LOG OF BORING NO. B-6SAMPLENUMBERSAMPLEDEPTH (ft.)SAMPLERECOVERY (in.)SAMPLEBLOWS/6 inchesN (blows/ft.)ELEVATION (ft.)DEPTH (ft.)USCSGRAPHICSYMBOLDESCRIPTION REMARKS Sheet 1 of 1 Sheet 1 of 1 0 5 10 15 20 25 30 S-1 S-2 S-3 0.5 3.5 6.0 15 16 3 9-11-10 35-27-50/5 50/5.5 21 100+ 100+ 512.0 511.5 508.5 505.6 ML SWR Topsoil (6") Tan, moist, very stiff, sandy SILT Tan, dry, hard, Soft Weathered Rock same BORING TERMINATED AT 6.4 FEET UPON AUGER REFUSAL LOG OF BORING NO. B-7 PROJECT:City of Monroe WWTP WATER LEVEL (ft):DRY DATE:6-18-20PROJECT NO.: 35200850 PROJECT LOCATION: Industrial Drive, Monroe, N.C.CAVED (ft):4.8 DATE STARTED:6-18-20 WATER ENCOUNTERED DURING DRILLING (ft)DRY DATE COMPLETED:6-18-20 GROUND SURFACE ELEVATION:512 DRILLING CONTRACTOR:HPC DATUM:AMSL DRILLER:Zack Kiker EQUIPMENT:CME 550X DRILLING METHOD:Hollow Stem Auger LOGGED BY:A.B. SAMPLING METHOD:Standard Penetration Testing CHECKED BY:J.P.W. NOTES:GROUND SURFACE ELEVATIONS ARE APPROXIMATE BASED ON TOPOGRAPHIC SURVEY LOG OF BORING NO. B-7SAMPLENUMBERSAMPLEDEPTH (ft.)SAMPLERECOVERY (in.)SAMPLEBLOWS/6 inchesN (blows/ft.)ELEVATION (ft.)DEPTH (ft.)USCSGRAPHICSYMBOLDESCRIPTION REMARKS Sheet 1 of 1 Sheet 1 of 1 0 5 10 15 20 25 30 S-1 S-2 S-3 S-4 0.0 3.5 6.0 8.5 16 14 16 3 7-9-11 16-22-43 17-33-44 27-50/3 20 65 77 100+ 511.0 502.5 501.7 ML SWR Tan, moist, very stiff, sandy SILT same, hard same Tan, dry, hard, Soft Weathered Rock BORING TERMINATED AT 9.3 FEET UPON AUGER REFUSAL LOG OF BORING NO. B-8 PROJECT:City of Monroe WWTP WATER LEVEL (ft):DRY DATE:6-18-20PROJECT NO.: 35200850 PROJECT LOCATION: Industrial Drive, Monroe, N.C.CAVED (ft):6.8 DATE STARTED:6-18-20 WATER ENCOUNTERED DURING DRILLING (ft)DRY DATE COMPLETED:6-18-20 GROUND SURFACE ELEVATION:511 DRILLING CONTRACTOR:HPC DATUM:AMSL DRILLER:Zack Kiker EQUIPMENT:CME 550X DRILLING METHOD:Hollow Stem Auger LOGGED BY:A.B. SAMPLING METHOD:Standard Penetration Testing CHECKED BY:J.P.W. NOTES:GROUND SURFACE ELEVATIONS ARE APPROXIMATE BASED ON TOPOGRAPHIC SURVEY LOG OF BORING NO. B-8SAMPLENUMBERSAMPLEDEPTH (ft.)SAMPLERECOVERY (in.)SAMPLEBLOWS/6 inchesN (blows/ft.)ELEVATION (ft.)DEPTH (ft.)USCSGRAPHICSYMBOLDESCRIPTION REMARKS Sheet 1 of 1 Sheet 1 of 1 M.C.=12.8% 0 5 10 15 20 25 30 S-1 S-2 S-3 S-4 0.3 3.5 6.0 8.5 16 9 5 13 3-4-3 19-50/5 20-33-29 7-30-50/5 7 100+ 62 100+ 509.0 508.7 505.5 503.0 500.5 499.1 ML SWR ML SWR Topsoil (3") Red, moist, medium stiff, sandy SILT Red, dry, hard, Soft Weathered Rock Brown, moist, hard, sandy SILT Brown, dry, hard, Soft Weathered Rock BORING TERMINATED AT 9.9 FEET UPON AUGER REFUSAL LOG OF BORING NO. B-9 PROJECT:City of Monroe WWTP WATER LEVEL (ft):DRY DATE:6-17-20PROJECT NO.: 35200850 PROJECT LOCATION: Industrial Drive, Monroe, N.C.CAVED (ft):6.8 DATE STARTED:6-17-20 WATER ENCOUNTERED DURING DRILLING (ft)DRY DATE COMPLETED:6-17-20 GROUND SURFACE ELEVATION:509 DRILLING CONTRACTOR:HPC DATUM:AMSL DRILLER:Zack Kiker EQUIPMENT:D-50T DRILLING METHOD:Hollow Stem Auger LOGGED BY:A.B. SAMPLING METHOD:Standard Penetration Testing CHECKED BY:J.P.W. NOTES:GROUND SURFACE ELEVATIONS ARE APPROXIMATE BASED ON TOPOGRAPHIC SURVEY LOG OF BORING NO. B-9SAMPLENUMBERSAMPLEDEPTH (ft.)SAMPLERECOVERY (in.)SAMPLEBLOWS/6 inchesN (blows/ft.)ELEVATION (ft.)DEPTH (ft.)USCSGRAPHICSYMBOLDESCRIPTION REMARKS Sheet 1 of 1 Sheet 1 of 1 0 5 10 15 20 25 30 S-1 S-2 S-3 S-4 S-5 0.3 3.5 6.0 8.5 13.5 18 16 18 17 4 6-9-11 16-27-26 12-21-29 18-22-30 50/6 20 53 50 52 100+ 512.0 511.7 498.5 498.0 ML SWR Topsoil (3") Brown, moist, very stiff, sandy SILT same, hard same same Brown, dry, hard, Soft Weathered Rock BORING TERMINATED AT 14.0 FEET UPON AUGER REFUSAL LOG OF BORING NO. B-10 PROJECT:City of Monroe WWTP WATER LEVEL (ft):DRY DATE:6-17-20PROJECT NO.: 35200850 PROJECT LOCATION: Industrial Drive, Monroe, N.C.CAVED (ft):12.1 DATE STARTED:6-17-20 WATER ENCOUNTERED DURING DRILLING (ft)DRY DATE COMPLETED:6-17-20 GROUND SURFACE ELEVATION:512 DRILLING CONTRACTOR:HPC DATUM:AMSL DRILLER:Zack Kiker EQUIPMENT:D-50T DRILLING METHOD:Hollow Stem Auger LOGGED BY:A.B. SAMPLING METHOD:Standard Penetration Testing CHECKED BY:J.P.W. NOTES:GROUND SURFACE ELEVATIONS ARE APPROXIMATE BASED ON TOPOGRAPHIC SURVEY LOG OF BORING NO. B-10SAMPLENUMBERSAMPLEDEPTH (ft.)SAMPLERECOVERY (in.)SAMPLEBLOWS/6 inchesN (blows/ft.)ELEVATION (ft.)DEPTH (ft.)USCSGRAPHICSYMBOLDESCRIPTION REMARKS Sheet 1 of 1 Sheet 1 of 1 0 5 10 15 20 25 30 S-1 S-2 S-3 S-4 0.3 3.5 6.0 8.5 16 16 18 13 8-11-23 16-23-36 32-31-39 18-34-50/4 34 59 70 100+ 512.0 511.7 503.5 502.2 ML SWR Topsoil (3") Brown, moist, hard, sandy SILT same same Brown, dry, hard, Soft Weathered Rock BORING TERMINATED AT 9.8 FEET UPON AUGER REFUSAL LOG OF BORING NO. B-11 PROJECT:City of Monroe WWTP WATER LEVEL (ft):DRY DATE:6-17-20PROJECT NO.: 35200850 PROJECT LOCATION: Industrial Drive, Monroe, N.C.CAVED (ft):6.8 DATE STARTED:6-17-20 WATER ENCOUNTERED DURING DRILLING (ft)DRY DATE COMPLETED:6-17-20 GROUND SURFACE ELEVATION:512 DRILLING CONTRACTOR:HPC DATUM:AMSL DRILLER:Zack Kiker EQUIPMENT:D-50T DRILLING METHOD:Hollow Stem Auger LOGGED BY:A.B. SAMPLING METHOD:Standard Penetration Testing CHECKED BY:J.P.W. NOTES:GROUND SURFACE ELEVATIONS ARE APPROXIMATE BASED ON TOPOGRAPHIC SURVEY LOG OF BORING NO. B-11SAMPLENUMBERSAMPLEDEPTH (ft.)SAMPLERECOVERY (in.)SAMPLEBLOWS/6 inchesN (blows/ft.)ELEVATION (ft.)DEPTH (ft.)USCSGRAPHICSYMBOLDESCRIPTION REMARKS Sheet 1 of 1 Sheet 1 of 1 M.C.=17.2% 0 5 10 15 20 25 30 S-1 S-2 S-3 0.6 3.5 6.0 10 10 6 4-4-5 4-6-9 45-50/3 9 15 100+ 512.0 511.4 506.0 505.3 ML SWR Topsoil (7") Brown, moist, stiff, sandy SILT same Brown, dry, hard, Soft Weathered Rock BORING TERMINATED AT 6.7 FEET UPON AUGER REFUSAL LOG OF BORING NO. B-12 PROJECT:City of Monroe WWTP WATER LEVEL (ft):DRY DATE:6-18-20PROJECT NO.: 35200850 PROJECT LOCATION: Industrial Drive, Monroe, N.C.CAVED (ft):5.6 DATE STARTED:6-18-20 WATER ENCOUNTERED DURING DRILLING (ft)DRY DATE COMPLETED:6-18-20 GROUND SURFACE ELEVATION:512 DRILLING CONTRACTOR:HPC DATUM:AMSL DRILLER:Zack Kiker EQUIPMENT:CME550X DRILLING METHOD:Hollow Stem Auger LOGGED BY:A.B. SAMPLING METHOD:Standard Penetration Testing CHECKED BY:J.P.W. NOTES:GROUND SURFACE ELEVATIONS ARE APPROXIMATE BASED ON TOPOGRAPHIC SURVEY LOG OF BORING NO. B-12SAMPLENUMBERSAMPLEDEPTH (ft.)SAMPLERECOVERY (in.)SAMPLEBLOWS/6 inchesN (blows/ft.)ELEVATION (ft.)DEPTH (ft.)USCSGRAPHICSYMBOLDESCRIPTION REMARKS Sheet 1 of 1 Sheet 1 of 1 M.C.=25.3% 0 5 10 15 20 25 30 S-1 S-2 S-3 0.5 3.5 6.0 16 14 8 11-14-28 13-45-50/3 50/4 42 100+ 100+ 510.0 509.5 506.5 503.2 ML SWR Topsoil (5") Brown, moist, hard, sandy SILT Brown, dry, hard, Soft Weathered Rock same BORING TERMINATED AT 6.8 FEET UPON AUGER REFUSAL LOG OF BORING NO. B-13 PROJECT:City of Monroe WWTP WATER LEVEL (ft):DRY DATE:6-18-20PROJECT NO.: 35200850 PROJECT LOCATION: Industrial Drive, Monroe, N.C.CAVED (ft):4.8 DATE STARTED:6-18-20 WATER ENCOUNTERED DURING DRILLING (ft)DRY DATE COMPLETED:6-18-20 GROUND SURFACE ELEVATION:510 DRILLING CONTRACTOR:HPC DATUM:AMSL DRILLER:Zack Kiker EQUIPMENT:CME550X DRILLING METHOD:Hollow Stem Auger LOGGED BY:A.B. SAMPLING METHOD:Standard Penetration Testing CHECKED BY:J.P.W. NOTES:GROUND SURFACE ELEVATIONS ARE APPROXIMATE BASED ON TOPOGRAPHIC SURVEY LOG OF BORING NO. B-13SAMPLENUMBERSAMPLEDEPTH (ft.)SAMPLERECOVERY (in.)SAMPLEBLOWS/6 inchesN (blows/ft.)ELEVATION (ft.)DEPTH (ft.)USCSGRAPHICSYMBOLDESCRIPTION REMARKS Sheet 1 of 1 Sheet 1 of 1 0 5 10 15 20 25 30 S-1 S-2 S-3 S-4 0.5 3.5 6.0 8.5 18 15 17 12 7-11-19 18-34-50/6 28-45 14-20-50/4 30 100+ 45 100+ 506.0 505.5 502.5 500.0 497.5 496.2 ML SWR ML SWR Topsoil (5") Brown, moist, very stiff, sandy SILT Brown, dry, hard, Soft Weathered Rock Brown, moist, hard, sandy SILT Brown, dry, hard, Soft Weathered Rock BORING TERMINATED AT 9.8 FEET UPON AUGER REFUSAL LOG OF BORING NO. B-14 PROJECT:City of Monroe WWTP WATER LEVEL (ft):DRY DATE:6-18-20PROJECT NO.: 35200850 PROJECT LOCATION: Industrial Drive, Monroe, N.C.CAVED (ft):7.8 DATE STARTED:6-18-20 WATER ENCOUNTERED DURING DRILLING (ft)DRY DATE COMPLETED:6-18-20 GROUND SURFACE ELEVATION:506 DRILLING CONTRACTOR:HPC DATUM:AMSL DRILLER:Zack Kiker EQUIPMENT:CME550X DRILLING METHOD:Hollow Stem Auger LOGGED BY:A.B. SAMPLING METHOD:Standard Penetration Testing CHECKED BY:J.P.W. NOTES:GROUND SURFACE ELEVATIONS ARE APPROXIMATE BASED ON TOPOGRAPHIC SURVEY LOG OF BORING NO. B-14SAMPLENUMBERSAMPLEDEPTH (ft.)SAMPLERECOVERY (in.)SAMPLEBLOWS/6 inchesN (blows/ft.)ELEVATION (ft.)DEPTH (ft.)USCSGRAPHICSYMBOLDESCRIPTION REMARKS Sheet 1 of 1 Sheet 1 of 1 0 5 10 15 20 25 30 S-1 S-2 S-3 0.3 3.5 6.0 4 16 10 2-3-4 15-42-50/6 34-50/5 7 100+ 100+ 506.0 505.7 502.5 499.0 ML SWR Topsoil (4") Brown, moist, medium stiff, sandy SILT Brown, dry, hard, Soft Weathered Rock same BORING TERMINATED AT 7.0 FEET UPON AUGER REFUSAL LOG OF BORING NO. B-15 PROJECT:City of Monroe WWTP WATER LEVEL (ft):DRY DATE:6-18-20PROJECT NO.: 35200850 PROJECT LOCATION: Industrial Drive, Monroe, N.C.CAVED (ft):4.6 DATE STARTED:6-18-20 WATER ENCOUNTERED DURING DRILLING (ft)DRY DATE COMPLETED:6-18-20 GROUND SURFACE ELEVATION:506 DRILLING CONTRACTOR:HPC DATUM:AMSL DRILLER:Zack Kiker EQUIPMENT:CME550X DRILLING METHOD:Hollow Stem Auger LOGGED BY:A.B. SAMPLING METHOD:Standard Penetration Testing CHECKED BY:J.P.W. NOTES:GROUND SURFACE ELEVATIONS ARE APPROXIMATE BASED ON TOPOGRAPHIC SURVEY LOG OF BORING NO. B-15SAMPLENUMBERSAMPLEDEPTH (ft.)SAMPLERECOVERY (in.)SAMPLEBLOWS/6 inchesN (blows/ft.)ELEVATION (ft.)DEPTH (ft.)USCSGRAPHICSYMBOLDESCRIPTION REMARKS Sheet 1 of 1 Sheet 1 of 1 APPENDIX C LABORAOTRY RESULTS ASTM Specifications performed may include: D421, D422, D2216, D2217, and D4318.Tested By: SC Checked By: MOISTURE DENSITY RELATIONSHIP TEST REPORT Dry density, pcf89 94 99 104 109 114 Water content, % 7 12 17 22 27 32 37 20.5%, 104.7 pcf ZAV for Sp.G. = 2.68 Test specification:ASTM D 698-91 Procedure B Standard S-1 ML 15.5 2.68 45 13 1 60 (ML) Red Orange SANDY SILT. 35200850 City of Monroe 7/9/20 Elev/Classification Nat.Sp.G. LL PI % > % < Depth USCS AASHTO Moist.3/8 in. No.200 TEST RESULTS MATERIAL DESCRIPTION Project No.Client:Remarks: Project: Date: Location: B-10 Sample Number: 1 Figure Maximum dry density = 104.7 pcf Optimum moisture = 20.5 % Monroe WWTP Hazen and Sawyer • 9101 Southern Pine Blvd, Suite 250 • Charlotte, NC 28273 • 704.357.3150 Technical Memorandum 32138-012July 2, 2020 To: Russell Colbath, Director of Water Resources From: Jarrod Karl, Senior Principal Scientist Jim Struve, Vice President Re: Natural Resources Technical Memorandum Monroe WWTP Flow Equalization Basin Monroe, Union County, North Carolina The purpose of this technical memorandum is to document potential Waters of the United States, Waters of the State and federally-protected threatened or endangered species at the location of the proposed Flow Equalization (EQ) Basin adjacent to the Monroe Wastewater Treatment Plant (WWTP). The location of the proposed basin is immediately adjacent to the WWTP site, separated by a small perennial stream (Joes Branch). Hazen Staff (Jim Struve and Jarrod Karl) met with Kyle Ketchum on June 25, 2020 to review the proposed project area in the field prior to walking the site and conducting field investigation of potential waters, habitats and species. The following sections summarize the methods and results for the desktop and field investigations. Preliminary Desktop Assessment Methods Hazen performed a preliminary desktop assessment to collect background information related to wetlands, waters and protected species prior to conducting the on-site field investigation. To determine the potential presence of streams, wetlands and open waters in the proposed project area, Hazen consulted the United States Geological Survey National Map (TNM)1, the United States Fish and Wildlife Service National Wetlands Inventory (NWI) Wetlands Mapper2 and United States Department of Agriculture - Natural Resources Conservation Service Web Soil Survey (WSS)3 maps pertaining to the proposed project area. To determine the potential presence of protected species or critical habitat in the proposed project area, Hazen consulted the United States Fish and Wildlife Service (USFWS) Endangered and Threatened Species and Species of Concern by County for North Carolina4 online database for Union County and Natural Heritage Element Occurrence (NHEO) Geographic Information System (GIS) shapefiles5. To determine the presence of historic or cultural resources, Hazen consulted the North Carolina State Historic Preservation Office’s HPOWEB 2.0 web application6. 1 United States Geological Survey, The National Map. https://viewer.nationalmap.gov/basic/. 2 United States Fish and Wildlife Service, Wetlands Mapper. https://www.fws.gov/wetlands/Data/Mapper.html. 3 United States Department of Agriculture, Natural Resources Conservation Service, Web Soil Survey. https://websoilsurvey.nrcs.usda.gov/. 4 United States Fish and Wildlife Service, Raleigh Field Office. Endangered and Threatened Species and Species of Concern by County for North Carolina. https://www.fws.gov/raleigh/species/cntylist/union.html. 5 North Carolina Natural Heritage Program, Natural Heritage Element Occurrence Shapefiles. Updated April, 2020. 6 North Carolina Historic Preservation Office, HPOWEB 2.0. https://nc.maps.arcgis.com/home/item.html?id=d2d04d8d7e03403f889419526e682529. ATTACHMENT 5 July 2, 2020 Monroe WWTP Flow Equalization Basin Page 2 of 2 Results Maps reviewed for the presence of potential wetlands and waters indicated the presence of two streams, Richardson Creek and Joes Branch, that border the proposed project area to the north and east, respectively. A potential stream channel was identified on the western border of the proposed project area. No hydric soils or wetlands were indicated. The list of protected species for Union County indicates the potential presence of one endangered mussel species (Carolina heelsplitter (Lasmigona decorata)) and two endangered plant species (Michaux’s sumac (Rhus michauxii) and Schweinitz’s sunflower (Helianthus schweinitzii)). Based on a review of the GIS shapefiles for protected species, there are no records of federally protected species in the project area. One state-listed significantly rare mussel (eastern creekshell (Villosa delumbis)) may be present in Richardson Creek. No historic or cultural resources were identified. On-Site Field Investigation Methods Hazen Staff walked upland areas, drainageways, and floodplains within and adjacent to the project area to determine the presence of wetlands, streams and suitable habitat for protected species. Photographs of the site were taken to document existing conditions at the time of the investigation. Results Two perennial streams (Richardson Creek and Joes Branch) border the proposed project area. No other streams, open waters or wetlands were identified in or adjacent to the proposed project area. Habitat within the proposed project area includes forested upland areas with dense tree canopy and floodplain areas that are frequently flooded. Photographs of the site are located in Appendix A. Conclusions The proposed project is expected to result in impacts to one perennial stream (Joes Branch) due to construction of a force main connecting the proposed EQ basin to the existing WWTP. Impacts to Richardson Creek are not anticipated. No Michaux’s sumac or Schweinitz’s sunflower plants or suitable habitats are present in proposed project area. These two species typically occupy disturbed areas or open woods with an abundance of sunlight. The forested upland areas present in the proposed project area do not provide the sunlight required to support the two species due to the dense tree canopy. The floodplain areas do not support the two species due dense tree canopy and frequent flooding. Richardson Creek is not expected to be impacted by the proposed project, therefore direct impacts to the eastern creekshell should not occur. Indirect impacts to Richardson Creek resulting from downstream sedimentation during construction are possible. Therefore, Hazen recommends consultation with the United States Army Corps of Engineers prior to construction to determine potential requirements. Qualifications of the Investigator Jarrod Karl is a Senior Principal Scientist in Hazen’s Charlotte Office. He has a Bachelor of Science in Environmental Studies from the University of North Carolina at Asheville and has 23 years of experience conducting natural resources assessments, including stream and wetland delineations and endangered species evaluations. Prior to joining Hazen in 2015, Mr. Karl spent 13 years working for Charlotte-Mecklenburg Storm Water Services where he oversaw the City’s Section 401-404 permitting program and stream and wetland mitigation bank. July 2, 2020 Monroe WWTP Flow Equalization Basin A-1 Appendix A: Photographs hazenandsawyer.com PHOTOGRAPHS Monroe WWTP Flow Equalization Basin Monroe, Union County, North Carolina Photo 1. Typical view of upland forested areas with dense tree canopy. Photo 2. View of recent clearing to conduct geotechnical explorations. 1 2 hazenandsawyer.com PHOTOGRAPHS Monroe WWTP Flow Equalization Basin Monroe, Union County, North Carolina Photo 3. Upstream view of Joes Branch, a perennial tributary to Richardson Creek. Joes Branch and adjacent areas near the confluence with Richardson Creek are inundated by flooding during large storm events. Photo 4. View of narrow floodplain area and sanitary sewer right-of-way adjacent to Richardson Creek. A steep slope is present at the edge of the right-of-way. The floodplain is shaded by tree canopy and frequently floods. 3 4 1 Attachment 6 Attachment 7