HomeMy WebLinkAbout20121147 Ver 1_Approval Letter_20130206rMENR
North Carolina Department of Environment and Natural Resources
Division of Water Quality
Pat McCrory Charles Wakild, P E, John E. Skvarla, III
Governor Director Secretary
February 6, 2013
DWQ # 12 -1147
Wake County
Town of Cary
Attn: Joe Godfrey, Parks, Recreation & Cultural Resources
PO Box 8005
Cary, NC 27512
Subject Property: Authorization Certificate per the Neuse Riparian Buffer Rules
Town of Cary — Greenway (Symphony Lake)
Dear Mr. Godfrey:
You have our approval, in accordance with 15A NCAC 02B .0233 and any conditions listed
below, to permanently impact 4,496 square feet of Zone 1 Neuse protected riparian buffer and
2,361 square feet of Zone 2 Neuse protected riparian buffer, and to temporarily impact 389
square feet of Zone 1 Neuse protected riparian buffer, as described within your'application,
received by the N.C. Division of Water Quality (Division) on December 27, 2013. No other
impacts are approved including incidental impacts. In addition, you should obtain or otherwise
comply with any other required federal, state or local permits before you go ahead with your
project including (but not limited to) Erosion and Sediment Control, Non - discharge, and other
regulations. This Authorization Certificate shall expire five (5) years from the date of this
letter.
This authorization certification is for the purpose and design that you described in your
application. If you change your project, you must notify us and you may be required to send us
a new application. If the property is sold, the new owner must be given a copy of this
authorization letter and is thereby responsible for complying with all conditions. This
authorization requires you to follow the conditions listed below.
Conditions of Certification:
1. Impacts Approved
The following impacts are hereby approved as long as all of the other specific and general
conditions of this Certification (or Isolated Wetland Permit) are met. No other impacts are
approved including incidental impacts:
V, etlan„.. Buffers, Stomtwstcr - Cvmphance and Permitting (Webscape) Unit One
1650 Mail S. vic,� center, Raie,,,r, Nowi ^ ? -ohna 2�6y9 -'650 NorthCarolina
Location 512 N Sanst. -v 6l Fate !n "lorlh Carolina 2'604
?hone :'910i- 63CO,F c,94 CtGu,r 3ervict '-F 7V? -674e i
h'61 e! v .w mats'q -1.1,; my
Town of Cary — Greenway (Symphony Lake)
Page 2 of 3
February 6, 2013
2. Protective Fencing
The outside buffer, wetland or water boundary and along the construction corridor within
these boundaries approved under this authorization shall be clearly marked with orange
warning fencing (or similar high visibility material) for the areas that have been approved to
infringe within the buffer, wetland or water prior to any land disturbing activities to ensure
compliance with 15 NCAC 02H .0500.
3. You must revegetate all temporarily disturbed areas within the buffers. If you need
additional information on plantings, see Guidelines for Buffer Restoration available at:
http: / /portal.ncdenr.orpJc /document library /get file ?uuid= e46ec613- 90f8- 4e22 -973c-
57c863afc737 &groupld= 38364.
4. Diffuse Flow Approval by the DWQ for Greenways
All stormwater shall be directed and maintained as diffuse flow at non - erosive velocities
through the protected stream buffers such that it will not re- concentrate before discharging
into a stream. If this is not possible, it may be necessary to provide an engineered level
spreader or stormwater facilities to remove nitrogen and phosphorus priori to discharge. If
deemed necessary, these facilities will require additional approval from the Division of
Water Quality.
5. No Waste, Spoil, Solids, or Fill of Any Kind
No waste, spoil, solids, or fill of any kind shall occur in wetlands, waters, or riparian areas
beyond the footprint of the impacts depicted in the Pre - Construction Notification. All
construction activities, including the design, installation, operation, and maintenance of
sediment and erosion control Best Management Practices, shall be performed so that no
violations of state water quality standards, statutes, or rules occur.
6. Certificate of Completion
The applicant and /or authorized agent shall provide a completed Certificate of Completion
Form to the DWQ Webscape Unit within ten days of project completion (available at:
http: / /porta1.ncden r.org /web /wq /swp /ws /401 /certsand permits /apply /forms).
This Certification can be contested as provided in Articles 3 and 4 of General Statute 150B by
filing a written petition for an administrative hearing to the Office of Administrative Hearings.
You may obtain a petition form from the Office of Administrative Hearings at
http: / /www ncoah.com/ or call (919) 431 -3000 for information.
Within sixty (60) calendar days of receipt of this Certification, you must file the petition with the
Office of Administrative Hearings. A petition is considered filed when the original and one (1)
copy is received in the Office of Administrative Hearings during normal office hours (Monday
through Friday between 8:OOam and S:OOpm, excluding official state holidays).
Type of Impact
Amount Approved (Units)
Plan Location or Reference
Zone 1- permanent
4,496
(square ft.)
PCN pg 7 of 11
Zone 2 - permanent
2,361
(square ft.)
PCN pg 7 of 11
Zone 1- temporary
389
(square ft.)
PCN pg 7 of 11
2. Protective Fencing
The outside buffer, wetland or water boundary and along the construction corridor within
these boundaries approved under this authorization shall be clearly marked with orange
warning fencing (or similar high visibility material) for the areas that have been approved to
infringe within the buffer, wetland or water prior to any land disturbing activities to ensure
compliance with 15 NCAC 02H .0500.
3. You must revegetate all temporarily disturbed areas within the buffers. If you need
additional information on plantings, see Guidelines for Buffer Restoration available at:
http: / /portal.ncdenr.orpJc /document library /get file ?uuid= e46ec613- 90f8- 4e22 -973c-
57c863afc737 &groupld= 38364.
4. Diffuse Flow Approval by the DWQ for Greenways
All stormwater shall be directed and maintained as diffuse flow at non - erosive velocities
through the protected stream buffers such that it will not re- concentrate before discharging
into a stream. If this is not possible, it may be necessary to provide an engineered level
spreader or stormwater facilities to remove nitrogen and phosphorus priori to discharge. If
deemed necessary, these facilities will require additional approval from the Division of
Water Quality.
5. No Waste, Spoil, Solids, or Fill of Any Kind
No waste, spoil, solids, or fill of any kind shall occur in wetlands, waters, or riparian areas
beyond the footprint of the impacts depicted in the Pre - Construction Notification. All
construction activities, including the design, installation, operation, and maintenance of
sediment and erosion control Best Management Practices, shall be performed so that no
violations of state water quality standards, statutes, or rules occur.
6. Certificate of Completion
The applicant and /or authorized agent shall provide a completed Certificate of Completion
Form to the DWQ Webscape Unit within ten days of project completion (available at:
http: / /porta1.ncden r.org /web /wq /swp /ws /401 /certsand permits /apply /forms).
This Certification can be contested as provided in Articles 3 and 4 of General Statute 150B by
filing a written petition for an administrative hearing to the Office of Administrative Hearings.
You may obtain a petition form from the Office of Administrative Hearings at
http: / /www ncoah.com/ or call (919) 431 -3000 for information.
Within sixty (60) calendar days of receipt of this Certification, you must file the petition with the
Office of Administrative Hearings. A petition is considered filed when the original and one (1)
copy is received in the Office of Administrative Hearings during normal office hours (Monday
through Friday between 8:OOam and S:OOpm, excluding official state holidays).
Town of Cary — Greenway (Symphony Lake)
Page 3 of 3
February 6, 2013
The petition may be faxed to the Office of Administrative Hearings at (919) 431 -3100, provided
the original and one copy of the petition is received by the Office of Administrative Hearings
within five (5) business days following the faxed transmission.
Mailing address for the Office of Administrative Hearings:
Office of Administrative Hearings
6714 Mail Service Center
Raleigh, NC 27699 -6714
One (1) copy of the petition must also be served to DENR:
Lacy Presnell, General Counsel
Department of Environment and Natural Resources
1601 Mail Service Center
Raleigh, NC 27699 -1601
Unless such a petition is filed, this Certification shall be final and binding.
Sincerely,
&Xfl�
Karen Higgins, V 1
Wetlands, Buffers, Stormwater —
Compliance & Permitting Unit
cc: DWQ RRO 401 files
Kevin Yates, EcoEngineering, 2905 Meridian Parkway, Durham, NC 27713
File Copy
Filename: 121147TOCaryGreenwaySymphonyLake (Wake) NBR.docx