HomeMy WebLinkAbout20121077 Ver 1_Application_201211271�
L
LV
STATE OF NORTH CAROLINA
DEPARTMENT OF TRANSPORTATION
BEVERLY EAVES PERDUE
GovERNOR
November 15 2012
U S Army Corps of Engineers
Regulatory Field Office
151 Patton Avenue Room 208
Asheville NC 28801 -5006
ATTN Ms Lori Beckwith
NCDOT Coordinator
/�D4,
2�
EUGENE A CONTI'/JR
SECRETARY
a Q 1 2 1 0 7 7
Subject Application for Section 404 Regional General Permit 198200031 and
Section 401 Water Quality Certification for the proposed replacement of
Bridge No 27 over Rock Creek on US 64 in Transylvania County, Federal
Aid Project No BRSTP 0064(99) Division 14 TIP No B 5010 $240 00
Debit Work Order WBS Element 41536 1 1
Dear Madam
The North Carolina Department of Transportation ( NCDOT) proposes to replace Bridge No
27 over Rock Creek on US 64 with a 90 foot reinforced concrete box culvert There will be
140 linear feet of permanent impacts to surface waters which includes 50 feet of bank
stabilization In addition 197 feet of temporary impacts to surface waters will result from
dewatering during culvert installation and fill from the construction of the onsite detour
Please see enclosed copies of the Pre Construction Notification (PCN) North Carolina
Wildlife Resource Commission Letter and email correspondence, EEP Acceptance Letter
stormwater management plan, permit drawings, and design plans for the above referenced
project The Categorical Exclusion (CE) was completed in February 2012 and was
distributed shortly thereafter Additional copies are available upon request
MAILING ADDRESS
NC DEPARTMENT OF TRANSPORTATION
PROJECT DEVELOPMENT AND ENVIRONMENTAL ANALYSIS
1598 MAIL SERVICE CENTER
RALEIGH NC 27699 1598
TELEPHONE 919 707 6100
FAX 919 -212 5785
WEBSITE WWW NCDOT ORG
LOCATION
1020 BIRCH RIDGE DRIVE
RALEIGH NC 27610 -4328
t 11
Correspondence from the North Carolina Wildlife Resources Commission ( NCWRC) dated
February 11 2008 states that a trout moratorium extending from October 15 to April 15 will
be instituted for the project By copy of this letter and attachment NCDOT herby requests
NCWRC review and forward for any updated comments for this project to the Army Corps
of Engineers and the NCDOT within 30 calendar days of receipt of this application This
project calls for a letting date of April 16, 2013 and a review date of February 26 2013
however the let date may advance as additional funding becomes available
A copy of this permit application and its distribution list will be posted on the NCDOT
website at http / /www ncdot org /doh/preconstruct/pe /neu/permrt html If you have any
questions or need additional information, please a mail Jeff Hemphill at
jhemphill @ncdot gov
Sincerely
flt Gregory J Thorpe PhD, Manager
Project Development & Environmental Analysis Unit
Cc NCDOT Permit Application Standard Distribution List
File
4
Oao� W A TF9QG
�? r
O �
Office Use Only
Corps action ID no
DWQ project no
Form Version 1 3 Dec 10 2008
Pre - Construction Notification (PCN) Form
A
Applicant Information
1
Processing
la
Type(s) of approval sought from the
Corps
®Section 404 Permit El Section 10 Permit
lb Specify Nationwide Permit (NWP) number or General Permit (GP) number 198200031
1c
Has the NWP or GP number been verified by the Corpse
❑ Yes
® No
1d
Type(s) of approval sought from the DWQ (check all that apply)
® 401 Water Quality Certification — Regular ❑ Non 404 Jurisdictional General Permit
❑ 401 Water Quality Certification — Express ❑ Riparian Buffer Authorization
1 e
Is this notification solely for the record
because written approval is not required?
For the record only for DWQ 401
Certification
❑ Yes ® No
For the record only for Corps Permit
❑ Yes ® No
1f
Is payment into a mitigation bank or in lieu fee program proposed for mitigation
of impacts'? If so attach the acceptance letter from mitigation bank or in lieu
fee program
® Yes
❑ No
1g
Is the project located in any of NC s twenty coastal counties If yes answer 1 h
below
❑ Yes
® No
1h
Is the project located within a NC DCM Area of Environmental Concern (AEC)?
❑ Yes
® No
2
Project Information
2a
Name of project
Replacement of Bridge #27 over Rock Creek on US 64
2b
County
Transylvania
2c
Nearest municipality / town
Sapphire
2d
Subdivision name
not applicable
2e
NCDOT only T I P or state
project no
B 5010
3
Owner Information
3a
Name(s) on Recorded Deed
North Carolina Department of Transportation
3b
Deed Book and Page No
not applicable
3c Responsible Party (for LLC i f
applicable)
not applicable
3d
Street address
1598 Mad Service Center
3e
City state zip
Raleigh NC 27699 1598
3f
Telephone no
(919) 707 6126
3g
Fax no
(919) 212 5785
3h
Email address
lhemphdl @ncdot gov
4 Applicant Information (if different from owner)
4a Applicant is
❑ Agent ❑ Other specify
4b Name
not applicable
4c Business name
(if applicable)
4d Street address
4e City state zip
4f Telephone no
4g Fax no
4h Email address
5 Agent/Consultant Information (if applicable)
5a Name
not applicable
5b Business name
(if applicable)
5c Street address
5d City state zip
5e Telephone no
5f Fax no
5g Email address
B Project Information and Prior Project History
1 Property Identification
1a Property identification no (tax PIN or parcel ID)
not applicable
1 b Site coordinates (in decimal degrees)
Latitude 35 1119 Longitude 82 9898
(DD DDDDDD) ( DD DDDDDD)
1 c Property size
1 13 acres
2 Surface Waters
2a Name of nearest body of water (stream river etc ) to
proposed project
Rock Creek
2b Water Quality Classification of nearest receiving water
C Tr
2c River basin
Savannah
3 Project Description '
3a Describe the existing conditions on the site and the general land use in the vicinity of the project at the time of this
application
Rural residential /Golf Course Community
3b List the total estimated acreage of all existing wetlands on the property
0
3c List the total estimated linear feet of all existing streams (intermittent and perennial) on the property
190
3d Explain the purpose of the proposed project
To replace a structurally deficient (and/ or) functionally obsolete bridge
3e Describe the overall project in detail including the type of equipment to be used
The project involves replacing a 33 foot single span bridge with a 90 foot RCBC on the existing alignment with an on site
detour Standard road budding equipment such as trucks dozers and cranes will be used
4 Jurisdictional Determinations
4a Have jurisdictional wetland or stream determinations by the
Corps or State been requested or obtained for this property /
project (including all prior phases) in the paste
Comments
❑ Yes ® No ❑ Unknown
4b If the Corps made the jurisdictional determination what type
of determination was made?
❑ Preliminary ❑ Final
4c If yes who delineated the jurisdictional areas?
Name (if known)
Agency /Consultant Company
Other
4d If yes list the dates of the Corps jurisdictional determinations or State determinations and attach documentation
5 Project History
5a Have permits or certifications been requested or obtained for
this project (including all prior phases) in the past?
❑ Yes ® No ❑ Unknown
5b If yes explain in detail according to help file instructions
6 Future Project Plans
6a Is this a phased project?
❑ Yes ® No
6b If yes explain
C Proposed Impacts Inventory
1 Impacts Summary
la Which sections were completed below for your project (check all that apply)
❑ Wetlands ® Streams tributaries ❑ Buffers
® Open Waters ❑ Pond Construction
2 Wetland Impacts
If there are wetland impacts proposed on the site then complete this question for each wetland area impacted
2a
2b
2c
2d
2e
2f
Wetland impact
Type of jurisdiction
number —
Type of impact
Type of wetland
Forested
(Corps 404 10
Area of impact
Permanent (P) or
(if known)
DWQ —non 404 other)
(acres)
Temporary T
Site 1 ❑ P ❑ T
❑ Yes
❑ No
❑ Corps
❑ DWQ
Site 2 ❑ P ❑ T
❑ Yes
❑ Corps
❑ No
❑ DWQ
Site 3 ❑ P ❑ T
❑ Yes
❑ Corps
❑ No
❑ DWQ
Site 4 ❑ P ❑ T
❑ Yes
❑ Corps
❑ No
❑ DWQ
Site 5 ❑ P ❑ T
❑ Yes
❑ Corps
❑ No
❑ DWQ
Site 6 ❑ P ❑ T
❑ Yes
❑ Corps
❑ No
❑ DWQ
2g Total wetland impacts
2h Comments
3 Stream Impacts
If there are perennial or intermittent stream impacts (including temporary impacts) proposed on the site then complete this
question for all stream sites impacted
3a
3b
3c
3d
3e
3f
3g
Stream impact
Type of impact
Stream name
Perennial
Type of
Average
Impact length
number
(PER) or
jurisdiction
stream
(linear feet)
Permanent (P) or
intermittent
(Corps 404 10
width
Temporary (T)
(INT)7
DWQ — non 404
(feet)
other)
Site 1 ® P ❑ T
Fill
Rock Creek
® PER
❑ INT
® Corps
❑ DWQ
15
90
Site 2 ® P ❑ T
Bank
Stabilization
Rock Creek
® PER
❑ INT
® Corps
❑ DWQ
15
50
Site 3 ❑ P ® T
Fill /Dewatenng
Rock Creek
® PER
❑ INT
® Corps
❑ DWQ
15
197
Site 4 ❑ P ❑ T
❑ PER
❑ Corps
❑ INT
❑ DWQ
Site 5 ❑ P ❑ T
❑ PER
❑ Corps
❑ INT
❑ DWQ
Site 6 ❑ P ❑ T
❑ PER
❑ Corps
[:11 NT
❑ DWQ
3h Total stream and tributary impacts
140 Perm
197 Temp
31 Comments
4 Open Water Impacts
If there are proposed impacts to lakes ponds estuaries tributaries sounds the Atlantic Ocean or any other open water of
the U S then indiv ually list all open water impacts below
4a
4b
4c
4d
4e
Open water
Name of
impact number —
waterbody
Type of impact
Waterbody type
Area of impact (acres)
Permanent (P) or
(if applicable)
Temporary
01 ❑ P ®T
Fill
Pond
007
02 ❑P ❑T
03 ❑P ❑T
04 ❑P ❑T
0 Total open water impacts
0 Permanent
0 07 Temporary
4g Comments
5 Pond or Lake Construction
If pond or lake construction proposed then complete the chart below
5a
5b
5c
5d
5e
Wetland Impacts (acres)
Stream Impacts (feet)
Upland
Pond ID
Proposed use or
(acres)
number
purpose of pond
Excavat
Flooded
Filled
ed
Flooded
Filled
Excavated
Flooded
P1
P2
5f Total
5g Comments
5h Is a dam high hazard permit required
❑ Yes ❑ No If yes permit ID no
51 Expected pond surface area (acres)
5j Size of pond watershed (acres)
r5k Method of construction
6 Buffer Impacts (for DWQ)
If project will impact a protected riparian buffer
then complete the chart below If yes then individually list all buffer
impacts below If any impacts require mitigation
then you MUST fill out Section D of this form
6a
❑ Neuse
El Tar Pamlico El Other
Project is in which protected basin?
❑ Catawba
❑ Randleman
6b
6c
6d
6e
6f
6g
Buffer impact
number —
Reason for impact
Buffer
Zone 1 impact
Zone 2 impact
Permanent (P) or
Stream name
mitigation
(square feet)
(square feet)
Temporary T
required?
131 ❑P ❑T
El Yes
❑ No
B2 ❑P ❑T
El Yes
❑ No
B3 ❑P ❑T
El Yes
❑ No
6h Total buffer impacts
61 Comments
D
Impact Justification and Mitigation
1
Avoidance and Minimization
1a
Specifically describe measures taken to avoid or minimize the proposed impacts in designing project
Onsite detour routed to the north to minimize project footprint roadway grade maintained to minimize project footprint
and retaining walls utilized to limit cuts and disturbed areas
lb
Specifically describe measures taken to avoid or minimize the proposed impacts through construction techniques
The North Carolina Wildlife Resource Commission (WRC) issued a Trout Moratorium on February 11 2008 for in stream
construction covering the trout spawning period from October 15 to April 15 The North Carolina Division of Water Quality
(NCDWQ) has designated Rock Creek as trout waters therefore Design Standards in Sensitive Watersheds will be
implemented for this project Alternating baffles will be installed inside the culvert to maintain the natural width of the
stream
2
Compensatory Mitigation for Impacts to Waters of the U S or Waters of the State
2a
Does the project require Compensatory Mitigation for
impacts to Waters of the U S or Waters of the State
® Yes ❑ No
If no explain
2b
If yes mitigation is required by (check all that apply)
❑ DWQ ® Corps
2c
If yes which mitigat ion option will be used for this
project?
❑ Mitigation bank
®Payment to in lieu fee program
❑ Permittee Responsible Mitigation
3
Complete if Using a Mitigation Bank
3a
Name of Mitigation Bank not applicable
3b Credits Purchased (attach receipt and letter)
Type
Quantity
3c Comments
4
Complete if Making a Payment to In lieu Fee Program
4a Approval letter from in lieu fee program is attached
❑ Yes
4b
Stream mitigation requested
90 linear feet
4c
If using stream mitigation stream temperature
❑ warm ❑ cool ®cold
4d
Buffer mitigation requested (DWQ only)
square feet
4e
Riparian wetland mitigation requested
acres
4f
Non riparian wetland mitigation requested
acres
4g
Coastal (tidal) wetland mitigation requested
acres
4h
Comments
5
Complete if Using a Permittee Responsible Mitigation Plan
5a
If using a permittee responsible mitigation plan provide a description of the proposed mitigation plan
6 Buffer Mitigation (State Regulated Riparian Buffer Rules) — required by DWQ
6a Will the project result in an impact within a protected riparian buffer that requires
buffer mitigation?
❑ Yes ® No
6b If yes then identify the square feet of impact to each zone of the riparian buffer that requires mitigation Calculate the
amount of mitigation required
Zone
6c
Reason for impact
6d
Total impact
(square feet)
Multiplier
6e
Required mitigation
(square feet)
Zone 1
3 (2 for Catawba)
Zone 2
1 5
6f Total buffer mitigation required
6g If buffer mitigation is required discuss what type of mitigation is proposed (e g payment to private mitigation bank
permittee responsible riparian buffer restoration payment into an approved in lieu fee fund)
6h Comments
E
Stormwater Management and Diffuse Flow Plan (required by DWQ)
1
Diffuse Flow Plan
1a
Does the project include or is it adjacent to protected riparian buffers identified
❑ Yes ® No
within one of the NC Riparian Buffer Protection Rules?
1 b
If yes then is a diffuse flow plan included? If not explain why
❑ Yes ❑ No
Comments If required from 1a see attached buffer permit drawings
2
Stormwater Management Plan
2a
What is the overall percent imperviousness of this project?
N/A
2b
Does this project require a Stormwater Management Plan?
® Yes ❑ No
2c
If this project DOES NOT require a Stormwater Management Plan explain why
2d
If this project DOES require a Stormwater Management Plan then provide a brief narrative
description of the plan
See attached permit drawings
❑ Certified Local Government
2e
Who will be responsible for the review of the Stormwater Management Plan?
❑ DWQ Stormwater Program
® DWQ 401 Unit
3
Certified Local Government Stormwater Review
3a
In which local governments jurisdiction is this project?
not applicable
❑ Phase II
❑ NSW
3b
Which of the following locally implemented stormwater management programs
❑ USMP
apply (check all that apply)
❑ Water Supply Watershed
❑ Other
3c Has the approved Stormwater Management Plan with proof of approval been
❑ Yes ❑ No
attached?
4
DWQ Stormwater Program Review
❑ Coastal counties
4a
Which of the following state implemented stormwater management programs apply
❑ HQW
(check all that apply)
❑ ORW
❑ Session Law 2006 246
❑ Other
4b
Has the approved Stormwater Management Plan with proof of approval been
❑ Yes ❑ No
attached?
5
DWQ 401 Unit Stormwater Review
5a
Does the Stormwater Management Plan meet the appropriate requirements?
❑ Yes ❑ No N/A
5b
Have all of the 401 Unit submittal requirements been met?
❑ Yes ❑ No N/A
F Supplementary Information
1 Environmental Documentation (DWQ Requirement)
la Does the project involve an expenditure of public (federal /state /local) funds or the
® Yes ❑ No
use of public (federal /state) land?
lb If you answered yes to the above does the project require preparation of an
environmental document pursuant to the requirements of the National or State
® Yes ❑ No
(North Carolina) Environmental Policy Act (NEPA/SEPA)*?
1 c If you answered yes to the above has the document review been finalized by the
State Clearing House? (If so attach a copy of the NEPA or SEPA final approval
®Yes ❑ No
letter)
Comments
2 Violations (DWQ Requirement)
2a Is the site in violation of DWQ Wetland Rules (15A NCAC 2H 0500) Isolated
Wetland Rules (15A NCAC 2H 1300) DWQ Surface Water or Wetland Standards
❑ Yes ® No
or Riparian Buffer Rules (15A NCAC 213 0200)?
2b Is this an after the fact permit application'?
❑ Yes ® No
2c If you answered yes to one or both of the above questions provide an explanation of the violation(s)
3 Cumulative Impacts (DWQ Requirement)
3a Will this project (based on past and reasonably anticipated future impacts) result in
❑ Yes
additional development which could impact nearby downstream water quality?
® No
3b If you answered yes to the above submit a qualitative or quantitative cumulative impact analysis in accordance with the
most recent DWQ policy If you answered no provide a short narrative description
Due to the minimal transportation impact resulting from this bridge replacement this project will neither influence nearby
land uses nor stimulate growth Therefore a detailed indirect or cumulative effects study will not be necessary
4 Sewage Disposal (DWQ Requirement)
4a Clearly detail the ultimate treatment methods and disposition (non discharge or discharge) of wastewater generated from
the proposed project or available capacity of the subject facility
not applicable
10
5
Endangered Species and Designated Critical Habitat (Corps Requirement)
5a
Will this project occur in or near an area with federally protected species or
® Yes ❑ No
habitat
5b
Have you checked with the USFWS concerning Endangered Species Act
❑ Yes ® No
impacts?
❑ Raleigh
5c
If yes ind icate the USFWS Field Office you have contacted
❑ Asheville
5d
What data sources did you use to determine whether your site would impact Endangered Species or Designated Critical
Habitat'?
NCDOT field surveys for Virginia spiraea and mountain sweet pitcher plant 6/24/09 & 5/21/12 found no specimens A
survey for small whorled pogonia on 8/14/07 found no specimens (with final design no longer any pogonia habitat in
project footprint) and a review of the North Carolina Natural Heritage database on 9/11/12 determined No Effect
6
Essential Fish Habitat (Corps Requirement)
6a Will this project occur in or near an area designated as essential fish habitats
❑ Yes ® No
6b
What data sources did you use to determine whether your site would impact Essential Fish Habitat?
NMFS County Index
7
Historic or Prehistoric Cultural Resources (Corps Requirement)
7a
Will this project occur in or near an area that the state federal or tribal
governments have designated as having historic or cultural preservation
❑ Yes ® No
status (e g National Historic Trust designation or properties significant in
North Carolina history and archaeology)?
7b
What data sources did you use to determine whether your site would impact historic or archeological resources?
NEPA Documentation
8 Flood Zone Designation (Corps Requirement)
8a Will this project occur in a FEMA designated 100 year floodplain?
® Yes ❑ No
8b
If yes explain how project meets FEMA requirements NCDOT Hydraulics Unit coordination with FEMA
8c
What source(s) did you use to make the floodplain determination? FEMA Maps
� 4ic—
H (G Z
Dr Gregry J Thorpe, PhD
Date
Applicant/Agent s Printed Name
App,licarWAgent s Signature
(Agent s signature is valid only if an authorization letter from the applicant
is provided
11
® North Carolina Wildlife Resources Commission
TO Carla Dagnino, Project Management, Western Region, NEU
Project Development and Environmental Analysis, NCDOT
FROM Marla Chambers Western NCDOT Permit Coordinator
%ajo- eta m&L),
Habitat Conservation Program, NCWRC
DATE February 11 2008
SUBJECT Scoping review of NCDOT s proposed bridge replacement projects in Buncombe,
Clay Henderson, Madison, Mitchell, Surry, Transylvania, Watauga and Yancey
Counties TIP Nos B -4715, B -4733, B -4547, B -4987 B -4988, B -4984 B -4581
B -4820, B 4989, B -5010, B 4668 B -4687, B -4851
North Carolina Department of Transportation ( NCDOT) has requested comments from
the North Carolina Wildlife Resources Commission (NCWRC) regarding impacts to fish and
wildlife resources resulting from the subject projects Staff biologists have reviewed the
information provided The following preliminary comments are provided in accordance with the
provisions of the National Environmental Policy Act (42 U S C 4332(2)(c)) and the Fish and
Wildlife Coordination Act (48 Stat 401, as amended, 16 U S C 661 667d)
Our standard recommendations for bridge replacement projects of this scope are as
follows
We generally prefer spanning structures Spanning structures usually do not require work
within the stream and do not require stream channel realignment The horizontal and
vertical clearances provided by bridges allows for human and wildlife passage beneath
the structure, does not block fish passage and does not block navigation by canoeists and
boaters
2 Bridge deck drains should not discharge directly into the stream
Live concrete should not be allowed to contact the water in or entering into the stream
Mailing Address Division of Inland Fisheries 1721 Mail Service Center Raleigh NC 27699 1721
Telephone (919) 707 -0220 Fax (919) 707 -0028
Budge Scopmgs 2 February 11 2008
4 If possible, bridge supports (bents) should not be placed in the stream
If temporary access roads or detours are constructed they should be removed back to
original ground elevations immediately upon the completion of the project Disturbed
areas should be seeded or mulched to stabilize the soil and native tree species should be
planted with a spacing of not more than 10 x10 If possible, when using temporary
structures the area should be cleared but not grubbed Clearing the area with chain saws
mowers, bush -hogs or other mechanized equipment and leaving the stumps and root mat
intact, allows the area to revegetate naturally and minimizes disturbed soil
6 A clear bank (nprap free) area of at least 10 feet should remain on each side of the stream
underneath the bridge
7 In trout waters the N C Wildlife Resources Commission reviews all U S Army Corps of
Engineers nationwide and general 404 permits We have the option of requesting
additional measures to protect trout and trout habitat and we can recommend that the
project require an individual 404 permit
S In streams that contain threatened or endangered species Mr Logan Williams with the
NCDOT ONE should be notified Special measures to protect these sensitive species
may be required NCDOT should also contact the U S Fish and Wildlife Service for
information on requirements of the Endangered Species Act as it relates to the project
9 In streams that are used by anadromous fish the NCDOT official policy entitled Stream
Crossing Guidelines for Anadromous Fish Passage (May 12, 1997)' should be followed
10 In areas with significant fisheries for sunfish seasonal exclusions may also be
recommended
11 Sedimentation and erosion control measures sufficient to protect aquatic resources must
be implemented prior to any ground disturbing activities Structures should be
maintained regularly especially following rainfall events
12 Temporary or permanent herbaceous vegetation should be planted on all bare soil within
15 days of ground disturbing activities to provide long -term erosion control
13 All work in or adjacent to stream waters should be conducted in a dry work area
Sandbags, rock berms cofferdams, or other diversion structures should be used where
possible to prevent excavation in flowing water
14 Heavy equipment should be operated from the bank rather than in stream channels in
order to minimize sedimentation and reduce the likelihood of introducing other pollutants
into streams
Bndge Scopmgs
February 11 2008
15 Only clean, sediment free rock should be used as temporary fill (causeways), and should
be removed without excessive disturbance of the natural stream bottom when
construction is completed
16 During subsurface investigations, equipment should be inspected dally and maintained to
prevent contamination of surface waters from leaking fuels lubricants, hydraulic fluids
or other toxic materials
17 If culvert installation is being considered, conduct subsurface investigations prior to
structure design to determine design options and constraints and to ensure that wildlife
passage issues are addressed
used
If corrugated metal pipe arches reinforced concrete pipes or concrete box culverts are
The culvert must be designed to allow for aquatic life and fish passage Generally, the
culvert or pipe invert should be burled at least 1 foot below the natural streambed
(measured from the natural thalweg depth) If multiple barrels are required barrels other
than the base flow barrel(s) should be placed on or near stream bankfull or floodplain
bench elevation (similar to Lyonsfield design) These should be reconnected to
floodplaln benches as appropriate This may be accomplished by utilizing sills on the
upstream end to restrict or divert flow to the base flow barrel(s) Silled barrels should be
filled with sediment so as not to cause noxious or mosquito breeding conditions
Sufficient water depth should be provided in the base flow barrel during low flows to
accommodate fish movement If culverts are longer than 40 -50 linear feet, alternating or
notched baffles should be installed in a manner that mimics existing stream pattern This
should enhance aquatic life passage 1) by depositing sediments in the barrel 2) by
maintaining channel depth and flow regimes and 3) by providing resting places for fish
and other aquatic organisms In essence the base flow barrel(s) should provide a
continuum of water depth and channel width without substantial modifications of
velocity
2 If multiple pipes or cells are used at least one pipe or box should be designed to remain
dry during normal flows to allow for wildlife passage
3 Culverts or pipes should be situated along the existing channel alignment whenever
possible to avoid channel realignment Widening the stream channel must be avoided
Stream channel widening at the inlet or outlet end of structures typically decreases water
velocity causing sediment deposition that requires increased maintenance and disrupts
aquatic life passage
4 Rlprap should not be placed in the active thalweg channel or placed In the streambed in a
manner that precludes aquatic life passage Bloengineenng boulders or structures should
be professionally designed, sized and installed
Bndge Scopings
February 11 2008
In most cases, we prefer the replacement of the existing structure at the same location
with road closure If road closure is not feasible a temporary detour should be designed and
located to avoid wetland impacts minimize the need for clearing and to avoid destabilizing
stream banks If the structure will be on a new alignment the old structure should be removed
and the approach fills removed from the 100 year floodplain Approach fills should be removed
down to the natural ground elevation The area should be stabilized with grass and planted with
native tree species Tall fescue should not be used in riparian areas If the area that is reclaimed
was previously wetlands, NCDOT should restore the area to wetlands If successful the site may
be used as wetland mitigation for the subject project or other projects in the watershed
Project specific comments
1 B 4715, Buncombe Co , Bridge No 655 over Broad River on SR 2797 (Rock Creek Rd)
Broad River, Class C Trout waters, is expected to support rainbow trout A moratorium
prohibiting in stream work and land disturbance within the 25 -foot trout buffer is
recommended from January 1 April 15 to protect the egg and fry stages of rainbow trout
Sediment and erosion control measures should adhere to the design standards for sensitive
watersheds
2 B 4733, Clay Co , Bridge No 11 over Chatuge Lake on NC 175 Chatuge Lake Class C
Trout is not expected to have reproducing trout The hellbender (Cryptobranchus
alleganiensts) Federal Species of Concern (FSC) and state Special Concern (SC) has been
observed at the project site Sediment and erosion control should be well maintained No
additional concerns are indicated at this time Standard recommendations should apply
3 B 4547, Henderson Co , Bridge No 45 over Devil Forks Creek on SR 1525 (Dana Rd) No
special concerns are indicated at this time Standard recommendations should apply
4 B 4987 Henderson Co, Bridge No 35 over Clear Creek on SR 1572 (Apple Valley Rd )
Clear Creek is classified B Trout waters, however it is also on the 303(d) list of impaired
waters The stream is designated Hatchery Supported Designated Public Mountain Trout
Water from the subject bridge upstream and the blotched chub (Erimystax insiginis), FSC
and state Significantly Rare (SR) occurs downstream A moratorium prohibiting in -stream
work and land disturbance within the 25 foot trout buffer is recommended from January 1-
April 15 to protect the egg and fry stages of rainbow trout Sediment and erosion control
measures should adhere to the design standards for sensitive watersheds Public access
should be coordinated for this site according to NCDOT guidelines and agreements with
NCWRC
5 B 4988 Henderson Co Bridge No 309 over Featherstone Creek on SR 1528 Featherstone
Creek Class C waters may support rainbow trout however we will not request a moratorium
at this time If trout are confirmed to be in the area prior to project construction the rainbow
trout moratorium may be requested
6 B 4984, Madison Co , Bridge No 138 over Big Pine Creek on SR 1151 (Big Pine Rd ?) Big
Pine Creek, Class C waters, is Hatchery Supported Designated Public Mountain Trout Water,
however significant trout reproduction is not expected this close to the confluence with the
French Broad River Logperch (Percina caprodes), state Threatened (T), have been
observed at this confluence and the olive darter (Percina squamata), FSC and state SC,
mountain madtom (Noturus eleutherus), state SC, and blotched chub FSC and state SR, are
found downstream in the French Broad River Stringent sedimentation and erosion control
Bndge Scopmgs
February 11 2008
must be well maintained Public access should be coordinated for this site according to
NCDOT guidelines and agreements with NCWRC
7 B 4581, Mitchell Co Bridge No 57 over White Oak Creek on SR 1199 White Oak Creek
Class C Trout waters, is not expected to have significant trout reproduction, however it flows
into Cane Creek, which is managed as Delayed Harvest Trout waters by NCWRC and
supports the olive darter (Percina squamata) FSC and state SC The state and federally
Endangered (E) Appalachian elktoe (Alasmcdonta ravenehana) inhabits North Toe River
further downstream Stringent sedimentation and erosion control must be well maintained
8 B 4820 Surry/Yadkin Co , Bridge No 338 over the Yadkin River on SR 1420 and SR 1190
(Gwyn Street) The Yadkin River Class C waters, supports good numbers of spotted bass
and smallmouth bass in the area Stringent sediment and erosion control should be well
maintained No additional concerns are indicated at this time Standard recommendations
should apply
9 B 4989, Transylvania Co Bridge No 148 over Lamance Creek on SR 1326 Lamance
Creek Class C Trout waters is located in the Nantahala National Forest Game Land and is
classified Wild Trout Waters by NCWRC A moratorium prohibiting in stream work and
land disturbance within the 25 foot trout buffer is recommended from October 15 to April
15 Sediment and erosion control measures should adhere to the design standards for
sensitive watersheds Public access should be coordinated for this site according to NCDOT
guidelines and agreements with NCWRC
10 B -5010, Transylvania Co , Bridge No 27 over Rock Creek on US 64 Rock Creek Class C
Trout waters supports brown trout in the project area Oconee stream crayfish (Cambarus
chaugaensis), state SC, bog turtle (Glyptemys muhlenbergn), state T and federal T due to
Similarity of Appearance and green salamander (aneides aeneus), FSC and state E, are
found nearby A moratorium prohibiting in- stream work and land disturbance within the 25-
foot trout buffer is recommended from October 15 to April 15 Sediment and erosion control
measures should adhere to the design standards for sensitive watersheds
11 B 4668, Watauga Co , Bridge No 29 over Cove Creek on US 321 Cove Creek, Class C
waters supports trout in the vicinity and downstream in the Watauga River Class B Trout
HQW waters The green floater (Lasmigona subviridus), FSC and state E and hellbender
(Cryptobranchus alleganiensis) FSC and state SC, have been observed at the confluence A
moratorium prohibiting in stream work and land disturbance within the 25 foot trout buffer is
recommended from October 15 to April 15 Sediment and erosion control measures should
adhere to the design standards for sensitive watersheds
12 B -4687 Yancey Co Bridge No 105 over Little Creek on SR 1411 Little Creek Class C
Trout waters, supports rainbow trout in the project area and flows to the Cane River, also
Class C Trout waters The Appalachian elktoe (Alasmcdonta ravenehana) federal and state
E, sharphead d irtcr (Etheostoma acutcccps), FSC and suite T, and stonecat (Notul us /lac 11s)
state E, occur in Cane River A moratorium prohibiting in stream work and land disturbance
within the 25 foot trout buffer is recommended from January 1 April 15 to protect the egg
and fry stages of rainbow trout Sediment and erosion control measures should adhere to the
design standards for sensitive watersheds
13 B 4851, Yancey Co, Bridge No 31 over Brush Creek on SR 1308 Brush Creek, Class C
Trout waters, is not expected to support reproducing trout in the project area It loins the
North Toe River, Class C Trout waters, dust downstream, which is inhabited by the
Appalachian elktoe (Alasmcdonta ravenehana), federal and state E, and wavy rayed
Brdge Scopmgs
February 11 2008
lampmussel (Lampsilis fasciola), state SC Sediment and erosion control measures should
adhere to the design standards for sensitive watersheds
We request that NCDOT routinely minimize adverse impacts to fish and wildlife
resources in the vicinity of bridge replacements The NCDOT should install and maintain
sedimentation control measures throughout the life of the project and prevent wet concrete from
contacting water in or entering into these streams Replacement of bridges with spanning
structures of some type, as opposed to pipe or box culverts is recommended in most cases
Spanning structures allow wildlife passage along streambanks, reducing habitat fragmentation
and vehicle related mortality at highway crossings
If you need further assistance or information on NCWRC concerns regarding bridge
replacements, please contact me at (704) 984 -1070 Thank you for the opportunity to review and
comment on this project
cc Brian Wrenn NCDWQ
Marella Buncick USFWS
Angie Rodgers, NCNHP
Elizabeth Lusk, NCDOT
September 25 2012
Mr Gregory J Thorpe PhD
Manager Project Development and Environmental Analysis Unit
North Carolina Department of Transportation
1548 Mail Service Center
Raleigh North Carolina 27699 1548
Dear Dr Thorpe
Subject EEP Mitigation Acceptance Letter
B 5010 Replace Bridge Number 27 on US 64 over Rocky Creek Tiansylvania County
The purpose of this letter is to notify you that the Ecosystem Enhancement Program (EEP) will provide the
compensatory stream mitigation for the subject project Based on the infoi mation supplied by you on September 20
2012 the impacts are located in CU 03060101 of the Savannah River basin in the Southern Mountains (SM) Eco
Region and areas follows
Savannah
Stream
Wetlands
Buffer (Sq Ft )
03060101
Non
Coastal
SM
000arm
Cold
Cl
W
Riparian
R
Riparian
Marsh
Zone I
Zone 2
Impacts
90
0
0
0
0
0
0
0
(feet /acres)
This impact and associated mitigation need were under projected by the NCDO r in the 2012 impact data
EEP will commit to implement sufficient compensatory stream mitigation credits to offset the impacts associated
with this project as determined by the regulatory agencies using the delivery timeline listed in Section F 3 c in of the
N C Department of Environment and Natural Resources Ecosystem Enhancement Program In Lieu Fee Instrument
dated July 28 2010 If the above referenced impact amounts are revised then this mitigation acceptance letter will
no longer be valid and a new mitigation acceptance letter will be required from EEP
1929
If you have any questions or need additional information please contact Ms Beth Harmon at 919 715
Sincerely
Suzanne Klimek
EEP Acting Dire or
cc Ms Lori Beckwith USACE — Asheville Regulatory Field Office
Ms Amy Chapman Division of Water Quality Wetlands /401 Unit
File B 5010
kmtoraty Lfitkawagg Note" Our -(tag
e��
NCDETIR
North Carolina Ecosystem Enhancement Program 1652 Mad Service Center Raleigh NC 27699 1652 / 919 715 0476 / www nceep net
STATE OF NORTH CAROLINA
DEPARTMENT OF TRANSPORTATION
MICHAEL F EASLEY
GOVERNOR
MEMORANDUM TO
FROM
A- _ oty
January 13, 2012
File
Paul F Fisher, P E
Hydraulics Unit
Stormwater Management Plan
B -5010 Transylvania County
LYNDO TIPPETT
SECRETARY
This project will replace bridge #27 over Rock Creek in Transylvania County The
following items were incorporated into the Hydraulic design of this project for
stormwater quality considerations
m Do not discharge stormwater directly into surface waters
• On -Site Detour to north to minimize footprint
• Use retaining walls to minimize cuts and disturbed area
e Hold existing Roadway grade to minimize project footprint
PFF
MAILING ADDRESS
NC DEPARTMENT OF TRANSPORTATION
HYDRAULICS UNIT
1590 MAIL SERVICE CENTER
RALEIGH NC 27699 1590
TELEPHONE 919 2504100
FAX 919 2504108
WEBSITE WWW DOH DOT STATE NC US
LOCATION
CENTURY CENTER COMPLEX
BUILDING B
1020 BIRCH RIDGE DRIVE
RALEIGH NC
r
$$$$$$SYSTIME$$$$$
$$$$ $$$$$$$$$$$$DGN$$$$$$$$$$$$$$$$
$$$$USERNAME$$$$III I
(CON' 1 &a �L � kJ A
y m
r �
O�
m
C1 `^ O
m Z
CA
N D�
O
-1 y
? v0
I
m
b
l v o
Z
0
0
3 N
0
vl
vooy�
Z �D
<
W -� v
< u -' m
O r-
O
Z+
Lh
O
o m
N+
o
I
N
o
F
IM
m
n
r
=
O
2MR �
o 0
Z
0
Z
CAP
�
0
°
�
�
!
�
N =
N
0
O
W
O
y m
r �
O�
m
C1 `^ O
m Z
CA
N D�
O
-1 y
? v0
cf)
Z
CD
0
F
ro
sr
a�
�z
z
�c
�ro
r
xz
W
TIP PROJECT: 5010
bo
y
•
N"
0
0
0
O
O
♦ g
�P
all
d6
`
♦ 0 '0
m
4 m
IN—,- ill ,
O i
m '
n �°z
a
a
n
N
r�
n
0
x
Ln
2
Ln
D
0
a
CD
13
A q
L
Ed D
TUl �,,
-
O
o�
Aa a
r
m
b
l v o
Z
A
C
3 N
-N+
vl
vooy�
Z �D
<
W -� v
< u -' m
O r-
Q
II II II
II II II v
C p m
0 N aLh
J a A �a
? IM
y �a°�1.P-
°
jO
�
!
D O
N =
r
W
�
O p
C
o
Z -�
v O
D
In
IM
y
�0
�Oi
--1
N
cf)
Z
CD
0
F
ro
sr
a�
�z
z
�c
�ro
r
xz
W
TIP PROJECT: 5010
bo
y
•
N"
0
0
0
O
O
♦ g
�P
all
d6
`
♦ 0 '0
m
4 m
IN—,- ill ,
O i
m '
n �°z
a
a
n
N
r�
n
0
x
Ln
2
Ln
D
0
a
CD
13
A q
L
Ed D
TUl �,,
-
O
o�
Aa a
r
=
b
IM
C
za
Z
;a
Q
=
v
N
�
m
o
In
b
y
�0
�Oi
--1
O y
? Q p�
x xi
Yy
m
I�
r)
i
�
MI
m
n
�
0
�
O
II
O
�o
W
O
3
1°o
-
W
3
cf)
Z
CD
0
F
ro
sr
a�
�z
z
�c
�ro
r
xz
W
TIP PROJECT: 5010
bo
y
•
N"
0
0
0
O
O
♦ g
�P
all
d6
`
♦ 0 '0
m
4 m
IN—,- ill ,
O i
m '
n �°z
a
a
n
N
r�
n
0
x
Ln
2
Ln
D
0
a
CD
13
A q
L
Ed D
TUl �,,
-
O
o�
Aa a
�
b
C
za
h
Q
p
N
�
m
b
y
�0
�Oi
? Q p�
x xi
Yy
Zi
n
a
m
�
MI
m
cf)
Z
CD
0
F
ro
sr
a�
�z
z
�c
�ro
r
xz
W
TIP PROJECT: 5010
bo
y
•
N"
0
0
0
O
O
♦ g
�P
all
d6
`
♦ 0 '0
m
4 m
IN—,- ill ,
O i
m '
n �°z
a
a
n
N
r�
n
0
x
Ln
2
Ln
D
0
a
CD
13
A q
L
Ed D
TUl �,,
-
O
o�
Aa a
�
b
C
za
h
Q
z
�
cf)
Z
CD
0
F
ro
sr
a�
�z
z
�c
�ro
r
xz
W
TIP PROJECT: 5010
bo
y
•
N"
0
0
0
O
O
♦ g
�P
all
d6
`
♦ 0 '0
m
4 m
IN—,- ill ,
O i
m '
n �°z
a
a
n
N
r�
n
0
x
Ln
2
Ln
D
0
a
CD
13
A q
L
Ed D
TUl �,,
-
O
o�
Aa a
IIt11$iI����"� NUMN$ Isssssssssssss
i J
ry
II
Sr
s3 TZ
°p, 4 ® I I v
Is-
ti
os //
a /
r � �
1 F o
n
IV
01,01-
s
T
N
N O \
a
m \ lS \
I
O � �
Fle
O \
O
O
c ono
vZ AZ
mo
�m nm
Nye MCA
O ,m a=
C a M,
wo z�
mm N
I rn< z
M
M
J w0
G
I
A
n
K
REVISIONS
o�
¢� // /
/ R -
5 /
Ile
J
!4
Z
cn
S
0
D `
/
� 1
� � Q
Z
a
O�
m o
w
z
Z Z
m
A�NO�
M z
z O
O
v+ o
N
O
O
v
Z
z
O
rI
1 I
J
�I
ssssasaasassa
I �p�
\N M 11\� \y,��
.\
i
REVISIONS
=s"
v®r�',
'
A
4�
C s
€ mM
Iv
gee /
Ide
o,
H
m
M"
+ x�
o +
is
y Fa
mm
cin
+ � i
o
I \ �
II
I
I \
°o \
o co
sm ro
z
mums
N
O �y [3
Ni y3>
Cy mD
AO A�
y u,
n�
m� Z
I d
m
I A
8
D
C)
OD Z
-, n
Ammamm—EAC)
�v
N
O
O
J
Nr
yN
'o
+OOOs
1111
I � r
b
m� pl
Af! < s
Z
n
z
. Ne�.......v
\N M 11\� \y,��
.\
i
REVISIONS
=s"
v®r�',
'
A
4�
C s
€ mM
Iv
gee /
Ide
o,
H
m
M"
+ x�
o +
is
y Fa
mm
cin
+ � i
o
I \ �
II
I
I \
°o \
o co
sm ro
z
mums
N
O �y [3
Ni y3>
Cy mD
AO A�
y u,
n�
m� Z
I d
m
I A
8
D
C)
OD Z
-, n
Ammamm—EAC)
�v
N
O
O
J
Nr
yN
'o
+OOOs
1111
I � r
b
m� pl
Af! < s
Z
n
z
n °o
m
O
O
i
' E
1 i
6$OGN U sssS$3S$SSSSS
;c
1 �
I
E I
� I
y0
I I
sr
TL
_ do
m
I cr)
�)� ds
� y o
I
m d _
Pa
i
M C
� O i
n Z M (�
O O ��.ji�
aim Mm E a V
NN mcn i
Zm D3 s
cn K 4 ?//
c -v m D
nO ��
n D V) CD z
C) z o
M .�
z WZ
®NOS
m o
� o
a
X
0
1p
o_
9H
O
fl QCN
s
O
REMOM
st
N
4�
(n
H
\ 4�1
m
N O
C-)
n
r
m
I�
0
0
0
q� a
0
B
o
i �
z i
p m
q� a
0
co "V
:r CD
by
om
isssssscssesssss
III
1111
I
II
III
II
II
III
II
lu
III
III
ill
I
III
IV
I
III
IJ
11
SCgyLL S
3 �
III
eo is ill m
95 qU r
i I� 9f
w
� I
co
0
r II +
N� f
O a g
I °°
II
u I II c
z Ilgm i
u
0
bO�tii
�1wAml _
� � 1
v j1d
n
I I �
,0 �0 (�
ro ;
�mi'v I I ry `Sf sf
m
m \
n
s
op
W-Wil
23 s
39 37,9
m
r
N
N
Z
n
REVISIONS
n
8/17/99
S
O Gif"
C � GjS'
C
0
0
N
!s
co /
S�+ 1+11 1
/ 00 /
/ O /
/ O /
O / /+
/// /
st
� o
� y /
O
g
S
O tl ro
A W
°o mC)
d
O
rn��I�oDb
u II n II Ills
O
D
sr.
o
N
rnQa
N
y
�NL4
�Ct2 W
O
, 2°
m
n°
lti O
+
t` t11VO
n N
z
°
2
\
r
S I rn �
� \
N
oy9
Ln
z
°d4v �n
u it 'I it u to
It
go.
r on J
�mLA
� v I Lc,.
X11 —oD�
n »ads
I °
�7o I
52 N
m ��S
W131No
Cr) ILO
Ln
+
N
+ � I Z
!Zw +pW I n
11�
SJ \
Mp�S
it IIA l Jvp
y
I Is
S
-
O
S II
3p
m �
�2
00
z
°
N
a
�mv C
Nyak'Sry>f
\
r
S I rn �
� \
N
oy9
Z
n r0 tr
v°° °`�s
f+mmmxA
+
N
osr
mnF
I
r on J
�mLA
� v I Lc,.
P � �
n »ads
I °
�7o I
52 N
m ��S
I
Cr) ILO
S
+
N
+ � I Z
!Zw +pW I n
11�
SJ \
in
A
f \
b
O
I Is
S
\
O
S II
3p
B I0�
M �JS.
Sy
c.
I
m
N� cA
II
B °vr �
mun' r
�0,
V
\
A
+
Wa
V
\
co
II
Sp
I
I
\ n
I
V
II
I
� 69
r
II
II
NAD 8y
II
III
II
III
I I
I I
II
II
I
II
I
111
II
II
NSRS 2007
Wp�RO Z
4
4bj
I-1
e< e
Fe F` S �q 9
?g96FT86` O
S
1 -15�
M � �
519
1
�mzc+
mwmx
a
�„nmm
HN ^N
0
Lit
bi
0
1h
S
N
O
O
tr
'O
O
8 4 M
>b
a
ma
NSSS*$$SSSSSSSS$$
0�
CO_�N +
r +
+
0
� i I n4o
-v
I
n If�l off'
I o
1 S 19 + J�p
S
y 11�
od
4
I I �
�mc °n I I s '\—sr Q
sr
cl
� N A
K
a
M
i ice/
Is
bt
o "Z \R
m
"
rm 7b
� � s
• nmo
{, W
r A m �
waN
m �
n
m �
V OO}
f14
V
S 1pP
W ' �
O T
In v
'A Ipq
�
I
g
0)
� N
i
y
y
11
tr
rl
%
OF
"'a
REVISIONS
N Samm �
1
co
N
Ro
i
A
/99
IX
/ m /
4 S+
/ O
/ O /
O /
Z/ O '
O
X / o
m /
DZ
� � I
I
0 I y i
as o
Se
O
No go
:1D oD-
II 11 11 II IWI �
-- XLn V VN
-0 °i m
�a
S
m�- 11-oD�
-- 1 h II II 11 11 11 4
°NIN=°o �I J Pep 0 ° �wm°
o I 9ej rr 0 U) CA Ol L� to
A
rrn � a � a r1a
i N II y \ SAM r A LLA V
to
ms n K N o
3 \ \ \ !
95g946,�c9 T`t
c m S =p m 6 6
O
N a W
I ENV on V � 7
uj
I
W� =r a SfS�JJ �mv \ 4f1
n \
— I
v m SOS
N �.r
7yJ9?r I
'BB y
I �
NNU2
1�I w a
NU,N y
\ s O
A
IIII \
II
I S JOSJ
I \
II
I
NAD I83�
NSRS' 2007
,II
I I
I
I I
\ s
is
S SIAM _
c Ir
Q1
r m
a a�
co
tP
v
z
f'1
i
s
s
5 ��9
4
nm=n
"m �N
rn�y�oD�
p 11 11 11 11 Ln
'O 11 N4IIVNN�
rn d4uv'i�w
0
v
r- LN
�
$� rz
II 11 II 11 II ii
bl rn vVrVOiN
O
In
rn :ID --i v
L4
5 In 4 On r\) 4 tO
r dot -4 LQNl,Lnn
-D m ��
2 ty)Ln�
In y
- Ir-oD�
11 U)
Ln
i„I�No
N
so,-.I+
4V�N
a
N
0
N
In
V
bD
4�
61/
I
t`
N
O
+
O
O
-'I
J_ Cam\
J \
fp
O
w 8z <
m
~ 30 Aa 1
z� z
O
M
r
8�
Z X� A`�
7
'A Ipq
�
\Po
I
O
y
y
11
o
�ln;�N
CK)
mbgAFO�°
R
rN
�. .�•
�p�n
Ln
A 0�1
Pn
GZ
LA `
m
(i
"Si
mzo�o
n°m
Zmq
TZ�
V1 In
O
Q �ln N
rn A�OL,+
O
Nmm
40o°Ou
c
s
O
(,.J
Wj
m 01 � N ND
d iJ
+
O
+
IN
(Q^V
i
O
r
N
V)
:1D oD-
II 11 11 II IWI �
-- XLn V VN
-0 °i m
�a
S
m�- 11-oD�
-- 1 h II II 11 11 11 4
°NIN=°o �I J Pep 0 ° �wm°
o I 9ej rr 0 U) CA Ol L� to
A
rrn � a � a r1a
i N II y \ SAM r A LLA V
to
ms n K N o
3 \ \ \ !
95g946,�c9 T`t
c m S =p m 6 6
O
N a W
I ENV on V � 7
uj
I
W� =r a SfS�JJ �mv \ 4f1
n \
— I
v m SOS
N �.r
7yJ9?r I
'BB y
I �
NNU2
1�I w a
NU,N y
\ s O
A
IIII \
II
I S JOSJ
I \
II
I
NAD I83�
NSRS' 2007
,II
I I
I
I I
\ s
is
S SIAM _
c Ir
Q1
r m
a a�
co
tP
v
z
f'1
i
s
s
5 ��9
4
nm=n
"m �N
rn�y�oD�
p 11 11 11 11 Ln
'O 11 N4IIVNN�
rn d4uv'i�w
0
v
r- LN
�
$� rz
II 11 II 11 II ii
bl rn vVrVOiN
O
In
rn :ID --i v
L4
5 In 4 On r\) 4 tO
r dot -4 LQNl,Lnn
-D m ��
2 ty)Ln�
In y
- Ir-oD�
11 U)
Ln
i„I�No
N
so,-.I+
4V�N
a
N
0
N
In
V
bD
4�
61/
I
t`
N
O
+
O
O
-'I
J_ Cam\
J \
fp
O
w 8z <
m
~ 30 Aa 1
z� z
O
M
r
8�
Z X� A`�
7
$$$$SYSTIME$$$$$ i
$$ $$$$$$$$$$$$DGN$$$$$$$$$$$$$$$$
$$USERNAME$$$$
CONTRACT:
M
0
ul I J.- %.N 40
00
3 Co --. .^
-I W 141:01�
v�
b
�
�
�e
O
A
b
I
y
mX
p
O
N
M
b
X
0
rZ
3 G7
n
=
n
m
`^ o
nX
m Z
CA
a
w
to
y -�
=
z
z
Ov
r V)
� Q
-V
IN
°
`
m 70
00
m
v
n
a a
�
m
IN INO D lb2J
IJ
Z
m 2
w
<-
O<
Itr m
0 r
II II
II
III
II II O Z
C
v m
V
icNi, la
v,
m
C. A y
ILn
z
�—B
=�
m
D
r
I
o X y
r
0D
�
m
v
I
Z
-�
0
O
-i
^r'
z
>
m
r
=
N
m
=
v
g
X
o
o
X
O y
M
0
ul I J.- %.N 40
00
3 Co --. .^
-I W 141:01�
8
3
a^
�>
Z
m
� � y
I
bh �o
y� b�
tr9 0
n U.,
'y +
I V
O O
O
J
TIP -PROJECT.- B -5010 _
C _
m
v�
b
�
�
�e
O
C
y
b
'�►�%
y
A�
0
O
to
a
w
� Q
°
�
C4,
O y
n
m
8
3
a^
�>
Z
m
� � y
I
bh �o
y� b�
tr9 0
n U.,
'y +
I V
O O
O
J
TIP -PROJECT.- B -5010 _
C _
m
v�
b
�
�
�e
O
C
y
b
'�►�%
M
8
3
a^
�>
Z
m
� � y
I
bh �o
y� b�
tr9 0
n U.,
'y +
I V
O O
O
J
TIP -PROJECT.- B -5010 _
C _
m
..■III
i
i
-
� � �b
bl
+
LL
NAD 83/
NSRS 2007
b
�7
0
C
� b
y �
Z I►�
b z
C b
y
O �
C
h
- ,c°
v�
vJ
O
'�►�%
0
O
..■III
i
i
-
� � �b
bl
+
LL
NAD 83/
NSRS 2007
b
�7
0
C
� b
y �
Z I►�
b z
C b
y
O �
C
h
- ,c°
v�
s
'�►�%
H
Y O
� I n
°
CL I D
y
O
O
O
z
F�.V
a
a
C)
0
z
9 �I
Z
W I
Cln �
S
c]
U1
101
1�
orfeei _,C9
—
NOTES --
-
TERbkL 1S_OC
ND -PLACE
C"N-IRC
—
—
LDERS --REr,
BED-
V- SOME - -S
klN , ---T =
-- _ - - -_- _
r-
-
—
N- CUL- VER-T-
S B
F- RAP - --
I -
'
--SILLS
D,- BAfFLE
O -- BE-1
PA RATELY -A h
I D- ATTACHE I
T
! D0W LS
�-
E--ONT- DAY
OFr SURVIE1F -
AS�97 -5-5=
(620120111
—
- -ROAD
AY -FILE SL
PES-ARC?-
ORS TO
ENTERU
�- ,-- -r--�-
P�OJECi'
-CO
LIE
FLOG
PLAN
GENT
T--
- _THIS-
ULATION
_T,
--
I
I
—
— —�T
—
— - -
- --
o� —
SILL--_
— — —
- --
—
2
ti
—
-- ---
_—
I
—
—
—
B.r.AFFLES
—� —
---
r
—
ZD'
'�I
TT
- - - SE -
OIN -AT '
AAAA -NU -_ jF
ES-- `__?_ " -t_ I
d I
- _ - -_' -
FOB
I J—
-r- -- - -- --
- - -- -- -
--
--
-PIUAN -' -VIEW
—
�—
-- -60X-
- - -
CULVER
DETAIL --
(NOT TQ-
- —
'
- -
-
I
orfeei _,C9
Permit Drawing
,|-4 of
7 E &
� CD
z U)
E°°
\kkk{
\
two£®
E
E;§
g
e@
k «
m CL E
o
o
o
r
/3§£ƒ
u
LL
EU)MM
0
2m(
0
0
�
&
«
§
c a
cu 41 ;0
0
0
[�E
°
v
vCL
@
/
c \ ` \
§
w
CL
= #
�/
k�\
\\
§ §
§
\ ;
{
§
3 �
L
4
M
a =2
/ L��
�
Lo
a)
M
b
! E
N
§�
co
-0
\]
\
M
0
\0
L
\
�
\p
]
}
Permit Drawing
,|-4 of
C