HomeMy WebLinkAbout20111116 Ver 1_Approval Letter_20120522NC®ENR
North Carolina Department of Environment and Natural Resources
Division of Water Quality
Beverly Eaves Perdue Charles Waklld PE Dee Freeman
Governor Director Secretary
May 22 2012
DWQ Project # 11 1116
Wake County
Seth Lawless
Town of Knightdale
950 Steeple Square Ct
Knightdale NC 27545
Subject Property Mingo Creek Trail — Hodge Road to Mingo Creek Park
Mingo Creek [030402 27 32 C NSW]
Approval of 401 Water Quality Certification and Authorization Certificate per the Neuse River Buffer
Protection Rules (15A NCAC 2B 0233) with Additional Conditions
Dear Mr Lawless
You have our approval in accordance with the attached conditions and those listed below to fill or otherwise
impact 0 4947 acre of 404 wetland (permanent impacts) 0 1882 acre of 404 wetland (temporary impacts) 138
linear feet of stream channel (permanent impacts) 44 linear feet of stream channel (temporary impacts) 41 533 7
square feet of Zone 1 Neuse River basin protected riparian buffer (permanent impacts) and 34 506 0 square feet
of Zone 2 Neuse River basin protected riparian buffer (permanent impacts) for a greenway protect as described in
your application received by the Division of Water Quality (DWQ) on December 22 2011 (dated December 22
2012) and additional information received on April 19 2012 (dated April 18 2012) May 16 2012 and May 21
2012 After reviewing your application we have decided that the impacts are covered by General Water Quality
Certification Number(s) 3820 (GC3820) The Certification(s) allows you to use Nationwide Permit(s) NW 14
when issued by the US Army Corps of Engineers (USACE) This letter shall also act as your approved
Authorization Certificate for impacts to the protected riparian buffers per 15A NCAC 213 0233 In addition you
should obtain or otherwise comply with any other required federal state or local permits before you go ahead with
your project including (but not limited to) Erosion and Sediment Control and Non discharge regulations Also,
this approval to proceed with your proposed impacts or to conduct impacts to waters as depicted in your
application shall expire upon expiration of the 404 Permit
This approval is for the purpose and design that you described in your application If you change your protect
you must notify us and you may be required to send us a new application If the property is sold the new owner
must be given a copy of this Certification and approval letter and is thereby responsible for complying with all
conditions If total fills for this project (now or to the future) exceed one acre of wetland or 150 linear feet of
stream compensatory mitigation may be required as described in 15A NCAC 2H 0506 (h)
This approval requires you to follow the conditions listed in the attached certification and any additional
conditions listed below
Nor hCarolina
Naturally
North Carolina Division of Water Quality Raleigh Regional Office Surface Water Protection Phone (919) 791 4200 Customer Service
Internet www ncwaterquality org 1628 Mail Service Center Raleigh NC 27699 1628 FAX (919) 788 7159 877 6236748
An Equal Opportunity /Affirmative Action Employer — 50 / Recycled /10 / Post Consumer Paper
Page 2
N
The Additional Conditions of the Certification are
1 Impacts Approved
The following impacts are hereby approved as long as all of the other specific and general conditions of
this Certification (or Isolated Wetland Permit) are met No other impacts are approved including
incidental and/or temporary impacts
Type of Impact
Amount Approved Units
Plan Location or Reference
404 Wetland
0 1882 (acre) temporary impact
PCN page 5 of 14 — revised April 18 2012
404 Wetland
0 4947 (acre) permanent impact
PCN page 5 of 14 — revised April 18 2012
Stream
138 (linear feet) permanent impact
PCN page 6 of 14 — revised April 18 2012
Stream
44 linear feet) temporary impact
PCN page 6 of 14 — revised April 18 2012
Buffers Zone 1
41 533 7 (square ft) perinanent impact
PCN page 8 of 14 — revised April 18 2012
Buffers Zone 2
34 506 0 (square ft) permanent impact
PCN page 8 of 14 — revised April 18 2012
2 No Waste Spoil Solids or Fill of Any Kind
No waste spoil solids or fill of any kind shall occur in wetlands waters or riparian areas beyond the
footprint of the impacts depicted in the Pre Construction Notification All construction activities
including the design installation operation and maintenance of sediment and erosion control Best
Management Practices shall be performed so that no violations of state water quality standards statutes
or rules occur
3 Erosion and sediment control practices must be in full compliance with all specifications governing the proper
design installation and operation and maintenance of such Best Management Practices in order to protect
surface waters standards
a The erosion and sediment control measures for the project must be designed installed operated and
maintained in accordance with the most recent version of the North Carolina Sediment and Erosion
Control Planning and Design Manual
b The design installation operation and maintenance of the sediment and erosion control measures
must be such that they equal or exceed the requirements specified in the most recent version of the
North Carolina Sediment and Erosion Control Manual The devices shall be maintained on all
construction sites borrow sites and waste pile (spoil) projects including contractor owned or leased
borrow pits associated with the project
c Sufficient materials required for stabilization and/or repair of erosion control measures and
stormwater routing and treatment shall be on site at all times
4 Sediment and Erosion Control Measures
Sediment and erosion control measures shall not be placed in wetlands or waters without prior approval
from the Division If placement of sediment and erosion control devices in wetlands and waters is
unavoidable design and placement of temporary erosion control measures shall not be conducted in a
manner that may result in dis equilibrium of wetlands or stream beds or banks adjacent to or upstream
and down stream of the above structures All sediment and erosion control devices shall be removed and
the natural grade restored within two (2) months of the date that the Division of Land Resources or locally
delegated program has released the project
Page 3
5 Diffuse flow
All stormwater shall be directed as diffuse flow at non erosive velocities through the protected stream
buffers and will not re concentrate before discharging into the stream as identified within 15A NCAC 2B
0233(5) or if this is not possible it is necessary to provide stormwater facilities that are considered to
remove nitrogen
In an effort to comply with the diffuse flow provision of the Buffer Rules (15A NCAC 02B 233(5)) you
provided DWQ with two (2) ditch locations which outlet to wetlands It is our understanding that these
are the only two ditches on the entire protect Any additional ditches that outlet into buffers and/or
buffered features should be approved by DWQ prior to construction
6 Protective Fencing
The outside buffer wetland or water boundary and along the construction corridor within these
boundaries approved under this authorization shall be clearly marked with orange warning fencing (or
similar high visibility material) for the areas that have been approved to infringe within the buffer
wetland or water prior to any land disturbing activities to ensure compliance with 15 NCAC 2H Section
0500
7 Notification of Protect Commencement
Please notify DWQ (Lauren Witherspoon at (919) 791 4251 or lauren witherspoon@ncdenr gov) of the
proposed start date of the protect
8 Signed and Sealed Plans
Prior to project commencement please provide two copies of signed and sealed plans to DWQ
9 Certificate of Completion
Upon completion of all work approved within the 401 Water Quality Certification or applicable Buffer
Rules and any subsequent modifications the applicant is required to return the attached certificate of
completion to the Wetlands Buffers Stormwater Compliance and Permitting Unit (WeBSCaPe) North
Carolina Division of Water Quality 1650 Mail Service Center Raleigh NC 27699 1650
Violations of any condition herein set forth may result in revocation of this Certification and may result in
criminal and/or civil penalties The authorization to proceed with your proposed impacts or to conduct impacts to
waters as depicted in your application and as authorized by this Certification shall expire upon expiration of the
404 or CAMA Permit
If you wish to contest any statement in the attached Certification you must file a petition for an administrative
hearing You may obtain the petition form from the Office of Administrative Hearings You must file the
petition with the Office of Administrative Hearings within sixty (60) days of receipt of this notice A petition is
considered filed when it is received in the Office of Administrative Hearings during normal office hours The
Office of Administrative Hearings accepts filings Monday through Friday between the hours of 8 OOam and
5 OOpm except for official state holidays The original and one (1) copy of the petition must be filed with the
Office of Administrative Hearings
Page 4
The petition may be faxed provided the original and one copy of the document is received by the Office of
Administrative Hearings within five (5) business days following the faxed transmission
The mailing address for the Office of Administrative Hearings is
Office of Administrative Hearings
6714 Mail Service Center
Raleigh NC 27699 6714
Telephone (919) 431 3000 Facsimile (919) 431 3100
A copy of the petition must also be served on DENR as follows
Ms Mary Penny Thompson General Counsel
Department of Environment and Natural Resources
1601 Mail Service Center
Raleigh NC 27699 1601
Unless such a petition is filed this Certification shall be final and binding
This letter completes the review of the Division of Water Quality under Section 401 of the Clean Water Act and
the Neuse River basin riparian buffer protection rule as described within 15A NCAC 2B 0233 If you have any
questions please telephone Lauren Witherspoon at 919 791 4251
JrSince ly
i��
Danny Smit
Surface Water Protection Section Supervisor
Raleigh Regional Office
Enclosures GC 3820
Certificate of Completion
cc DWQ Central Office — WeBSCaPe Unit — 1650 Mail Service Center
RRO File Copy
Craig Brown — USACE Raleigh Field Office
Johnathan Hefner— Stewart Engineering 421 Fayetteville Street Suite 400 Raleigh NC 27601
Filename 11 1116_Mingo Creek Trail Hodge Road to Mingo Creek Park_401_NBR_Approval