HomeMy WebLinkAbout20120174 Ver 1_Approval Letter_20120330XLV4
CN
North Carolina Department of Environment and Natural Resources
Division of Water Quality
Beverly Eaves Perdue Charles Wakild P E Dee Freeman
Governor Director Secretary
March 30 2012
DWQ Project # 12 0174
Cumberland County
Public Works Commission Fayetteville
Joseph E Glass — PWC Engineering Manager
965 Old Wilmington Rd
Fayetteville NC 28301
Subject Property Fayetteville Annexation — Phase V, Area 13 Improvements
UT to Beaver Creek [18 31 24 5] C
Approval of 401 Water Quality Certification with Additional Conditions
Dear Mr Glass
You have our approval in accordance with the attached conditions and those listed below to place fill
within or otherwise permanently impact 0 062 acres of wetlands temporarily place fill within or impact
0 072 acres of wetlands and permanently impact 20 linear feet of perennial stream for the purpose of the
sanitary sewer installation and drainage system piping improvements as described within your
application dated February 15 2012 and received by the N C Division of Water Quality (DWQ) on
February 15 2012 After reviewing your application we have decided that the impacts are covered by
General Water Quality Certification Number(s) 3819 (GC3819) The Certification(s) allows you to use
Nationwide Permit(s) NW 12 when issued by the US Army Corps of Engineers (USACE) In addition
you should obtain or otherwise comply with any other required federal state or local permits before you
go ahead with your project including (but not limited to) Erosion and Sediment Control Non discharge
and other regulations Also, this approval to proceed with your proposed impacts or to conduct
impacts to waters as depicted in your application shall expire upon expiration of the 404 or CAMA
Permit
This approval is for the purpose and design that you described in your application If you change your
project you must notify us and you may be required to send us a new application If the property is sold
the new owner must be given a copy of this Certification and approval letter and is thereby responsible for
complying with all conditions If total fills for this project (now or in the future) exceed one acre of
wetland or 150 linear feet of stream compensatory mitigation may be required as described in 15A
NCAC 2H 0506 (h) This approval requires you to follow the conditions listed in the attached
certification and any additional conditions listed below
The Additional Conditions of the Certification are
I Impacts Approved
225 Green St Ste 714
Fayetteville Worth Carolina 28301
Phone 910 -433 3300 \ FAX 910486 0707\ Customer Service 1877-623 6748
Internet www ncwaterquallty org
An Equal Opportunity Affirmat ve Action Employer
NorthCarollna
Public Works Commission Fayetteville
Page 2 of 3
March 30 2012
The following impacts are hereby approved as long as all of the other specific and general conditions of
this Certification (or Isolated Wetland Permit) are met No other impacts are approved including
incidental impacts
2 Erosion & Sediment Control Practices
Erosion and sediment control practices must be in full compliance with all specifications
governing the proper design installation and operation and maintenance of such Best
Management Practices in order to protect surface waters standards
a The erosion and sediment control measures for the project must be designed installed
operated and maintained in accordance with the most recent version of the North Carolina
Sediment and Erosion Control Planning and Design Manual
b The design installation operation and maintenance of the sediment and erosion control
measures must be such that they equal or exceed the requirements specified in the most
recent version of the North Carolina Sediment and Erosion Control Manual The devices
shall be maintained on all construction sites borrow sites and waste pile (spoil) projects
including contractor owned or leased borrow pits associated with the project
C For borrow pit sites the erosion and sediment control measures must be designed installed
operated and maintained in accordance with the most recent version of the North Carolina
Surface Mining Manual
d The reclamation measures and implementation must comply with the reclamation in
accordance with the requirements of the Sedimentation Pollution Control Act
3 No Waste Spoil Solids or Fill of Any Kind
No waste spoil solids or fill of any kind shall occur in wetlands waters or riparian areas beyond
the footprint of the impacts depicted in the Pre Construction Notification All construction
activities including the design installation operation and maintenance of sediment and erosion
control Best Management Practices shall be performed so that no violations of state water quality
standards statutes or rules occur
4 No Sediment & Erosion Control Measures in Wetlands or Waters
Sediment and erosion control measures should not be placed in wetlands or waters without prior
approval by the Division If placement of sediment and erosion control devices in wetlands and
waters is unavoidable design and placement of temporary erosion control measures shall not be
conducted in a manner that may result in dis equilibrium of wetlands or stream beds or banks
adjacent to or upstream and down stream of the above structures All sediment and erosion
control devices shall be removed and the natural grade restored within two (2) months of the date
that the Division of Land Resources or locally delegated program has released the project
5 Certificate of Completion
Amount Approved (Units)
Plan Location or Reference
404 /CAMA Wetlands —
0 062 (acres)
PCN page 5 of 14
impact
-permanent
404 /CAMA Wetlands —
0 072 (acres)
PCN page 5 of 14
impact
-temporary
Perennial Stream —
(linear feet)
PCN page 5 of 14
ermanent impact
2 Erosion & Sediment Control Practices
Erosion and sediment control practices must be in full compliance with all specifications
governing the proper design installation and operation and maintenance of such Best
Management Practices in order to protect surface waters standards
a The erosion and sediment control measures for the project must be designed installed
operated and maintained in accordance with the most recent version of the North Carolina
Sediment and Erosion Control Planning and Design Manual
b The design installation operation and maintenance of the sediment and erosion control
measures must be such that they equal or exceed the requirements specified in the most
recent version of the North Carolina Sediment and Erosion Control Manual The devices
shall be maintained on all construction sites borrow sites and waste pile (spoil) projects
including contractor owned or leased borrow pits associated with the project
C For borrow pit sites the erosion and sediment control measures must be designed installed
operated and maintained in accordance with the most recent version of the North Carolina
Surface Mining Manual
d The reclamation measures and implementation must comply with the reclamation in
accordance with the requirements of the Sedimentation Pollution Control Act
3 No Waste Spoil Solids or Fill of Any Kind
No waste spoil solids or fill of any kind shall occur in wetlands waters or riparian areas beyond
the footprint of the impacts depicted in the Pre Construction Notification All construction
activities including the design installation operation and maintenance of sediment and erosion
control Best Management Practices shall be performed so that no violations of state water quality
standards statutes or rules occur
4 No Sediment & Erosion Control Measures in Wetlands or Waters
Sediment and erosion control measures should not be placed in wetlands or waters without prior
approval by the Division If placement of sediment and erosion control devices in wetlands and
waters is unavoidable design and placement of temporary erosion control measures shall not be
conducted in a manner that may result in dis equilibrium of wetlands or stream beds or banks
adjacent to or upstream and down stream of the above structures All sediment and erosion
control devices shall be removed and the natural grade restored within two (2) months of the date
that the Division of Land Resources or locally delegated program has released the project
5 Certificate of Completion
Public Works Commission Fayetteville
Page 3 of 3
March 30 2012
Upon completion of all work approved within the 401 Water Quality Certification or applicable
Buffer Rules and any subsequent modifications the applicant is required to return the attached
certificate of completion to the DWQ WEBSCAPE Unit at 1650 Mail Service Center Raleigh
North Carolina 27699 1650
Protective Fencing
The outside buffer wetland or water boundary and along the construction corridor within these
boundaries approved under this authorization shall be clearly marked with orange waning fencing
(or similar high visibility material) for the areas that have been approved to infringe within the
buffer wetland or water prior to any land disturbing activities to ensure compliance with 15
NCAC 2H Section 0500
Violations of any condition herein set forth may result in revocation of this Certification and may result in
criminal and/or civil penalties The authorization to proceed with your proposed impacts or to conduct
impacts to waters as depicted in your application and as authorized by this Certification shall expire upon
expiration of the 404 or CAMA Permit
If you do not accept any of the conditions of this Certification (associated with the approved wetland or
stream impacts) you may ask for an adjudicatory hearing You must act within 60 days of the date that
you receive this letter To ask for a hearing send a written petition which conforms to Chapter 150B of
the North Carolina General Statutes to the Office of Administrative Hearings 6714 Mail Service Center
Raleigh N C 27699 6714 This certification and its conditions are final and binding unless you ask for a
hearing
This letter completes the review of the Division of Water Quality under Section 401 of the Clean Water
Act If you have any questions please telephone Chad Turlmgton in the DWQ Fayetteville Regional
Office at 910 433 3320
Sincerely /
-f J �M4�
Charles Wakild
Director
Enclosures GC 3819
Certificate of Completion
cc Karen Higgins — Wetlands Buffers and Stormwater Compliance and Permitting Unit
Crystal Amschler USACE Wilmington Regulatory Field Office
Debbie Edwards Soil &Environmental Consultants P A (via email)
DLR Fayetteville Regional Office
File Copy