LETTER OF APPROVAL WITH MODIFICATIONS
City of Raleigh
ATTN: Robert L. Massengill, Director of Public Works
PO Box 590
Raleigh, NC 27602
RE: Project Name: State Street Basin Water and Sewer Improvements Phase 1
Acres Approved: 21.99
Project 1D: WAKE-2020-056
County: WAKE, City: Raleigh, Address: Multiple streets, linear project
River Basin: Neuse, Stream Classification: Other
Submitted By: CDM Smith
Date Received by LQS: February 5, 2020
Plan Type: New
Dear Mr. Massengill:
This office has reviewed the subject erosion and sedimentation control plan. We find the plan to be
acceptable with modifications and hereby issue this letter of Approval with Modifications. The
Modifications Required for Approval are listed on the attached page. This plan approval shall expire three
(3) years following the date of approval, if no land -disturbing activity has been undertaken, as is required
by Title 15A NCAC 4B .O 129.
As of April 1, 2019, all new construction activities are required to complete and submit an electronic Notice
of Intent (eNOI) form requesting a Certificate of Coverage (COC) under the NCG010000 Construction
General Permit. After the form is reviewed and found to be complete, you will receive a link with payment
instructions for the $100 annual permit fee. After the fee is received, you will receive (lie COC via
email. You MUST obtain the COC prior to commencement of any land disturbing activity. The eNOI
form may be accessed at den.nc.uoviNCG01. Please direct questions about the eNOI form to Annette Lucas
at Annette.Lucas(c_l�,nedennizov or Paul Clark at Paul.Clark a ncdenr.gov. If the ownerr'operator of this
project changes in the future, the new responsible party is required to apply for hislher own COC.
Title I5A NCAC 413.011$(a) and the NCGO1 permit require that the following documentation be kept on
file at the job site:
1. The approved E&SC plan as well as any approved deviation.
2. The NCGO1 permit and the COC, once it is received.
3. Records of inspections made during the previous 12 months.
Nc,rth Carolina C7cpart rient of £naEronmen;al Clu 4itr Division of Cncrgy. Mineral and Land I.esources
•/ Ralci,frItcu-)na101fic.r In78Mail Sesv!LeCvnrcrr11800Bait cttDrive Rat6c)[i, Nurdi Carolina 27W(a
}�h icit,.4'oo
Letter of Approval with Modifications
City of Raleigh
March 5, 2020
Page 2 of 3
Also, this letter gives the notice required by G.S. 113A-61.1(a) of our right of periodic inspection to
insure compliance with the approved plan.
North Carolina's Sedimentation Pollution Control Program is performance -oriented, requiring protection of
existing natural resources and adjoining properties. If, following the commencement of this project, it is
determined that the erosion and sedimentation control plan is inadequate to meet the requirements of the
Sedimentation Pollution Control Act of 1973 (North Carolina General Statute 113A-51 through 66), this
office may require revisions to the plan and implementation of the revisions to ensure compliance with the
Act.
Acceptance and approval of this plan is conditioned upon your compliance with Federal and State water
quality laws, regulations, and rules. In addition, local city or county ordinances or rules may also apply to
this land -disturbing activity. This approval does not supersede any other permit or approval.
Please note that this approval is based in part on the accuracy of the information provided in the Financial
Responsibility Form, which you provided. This permit allows for a land -disturbance, as called for on the
application plan, not to exceed the approved acres. Exceeding the acreage will be a violation of this permit
and would require a revised plan and additional application fee. You are requested to file an amended form
if there is any change in the information included on the form. In addition, it would be helpful if you notify
this office of the proposed starting date for this project. Please notify us if you plan to have a preconstruction
conference.
Your cooperation is appreciated.
Sincerely,
Sally Castle, El
Regional Engineering Associate
Land Quality Section
Enclosures: Certificate of Approval
Modifications Required for Approval
NPDES NCGO1 Fact Sheet
cc: Kelly Boone, PE (BooneKR0mcdmsmith.corn - Electronic Copy
Regional Office file
Letter of Approval with Modifications
City of Raleigh
March 5, 2020
Page 3 of 3
MODIFICATIONS REQUIRED FOR APPROVAL
Project Name: State Street Basin Water and Sewer Improvements Phase 1
Project ID: WAKE-2020-056
County: WAKE
1. Limits of disturbance are to enclose project areas with no open limits. Provide match lines or
enclose the limits of disturbance on Sheet C40. (GS 113A-57(3), 15A NCAC 04B .0105, 15A
NCAC 04B .0106(5))
2. Provide two copies of the plan set (one full-size and one half-size), showing the modifications
required for approval prior to initiating land -disturbing activity. To facilitate DEMLR review,
bubble, highlight, or otherwise identify the changes to your resubmittal. Provide one copy of
additional items (such as design calculations). Provide a cover letter referencing the project name,
project ID, and purpose for submittal. (G.S. I I3A-57(4))
Ref: G.S. 113A-54.1 through G.S. 113A-57
Sections 15A NCAC 04A.0101 through 15A NCAC 04E.0504
General Permit NCG 010000 NPDES for Construction Activities