HomeMy WebLinkAbout20071841 Ver 4_Staff Comments_20110927Strickland, Bev
From: Cranford, Chuck
Sent: Tuesday, September 27, 2011 2:58 PM
To: Mcmillan, Ian; Strickland, Bev
Subject: AVL Airport 07-1841 V 4
Attachments: AROComments.071841 V4.9.27.11. pdf
Hello Y'all -
Here is our comment sheet for the subject project.
Thanks,
Chuck
**********************************************
Chuck Cranford - Chuck.Cranford@ncdenr.gov
North Carolina Dept. of Environment and Natural Resources
Asheville Regional Office
Division of Water Quality - Surface Water Protection Section
2090 U.S. 70 Highway
Swannanoa, NC 28778
Tel: 828-296-4500
Fax: 828-299-7043
Email correspondence to and from this address is subject to
the North Carolina Public Records Law and may be disclosed
to third parties unless the content is exempt by statute or
other regulation.
401 Water Quality Certification
Regional Office Comments
Project number: 07-1841 V4 Region: Asheville Date: 09-27-11
Project name: Asheville Airport Runway Rehab Staff` Chuck Cranford
Regional Office Supervisor:' Keith Haynes
? Issue as submitted
Q Issue with conditions listed below
Requested Action' ` El Request additional information
? Return to applicant
? Den project
1. Stormwater Management
Before any permanent impervious surface (i.e., building, roadway,
taxiway, tarmac or other similar surface) is installed as part of any
phase of the project described in this certification, the applicant must
meet all of the following:
•
The Stormwater Management Plan (SMP) must be approved in
writing by the City of Asheville. A copy of the approval letter
and approved SMP must be submitted to the Division prior to
installation of any impervious surface within the project site. If
the project is phased, then the approved SMP for each phase
must be submitted to the Division prior to installation of any
impervious surfaces associated with that phase.
The approved stormwater best management practices (BMPs)
must be constructed and operational before any permanent
building or other structure is occupied or becomes operational.
If the project is phased, then the approved BMPs for each future
phase must be constructed and operational before any
permanent building or other structure associated with that phase
is occupied or becomes operational.
The approved SMP, phased or otherwise, as well as drainage
patterns must be maintained in perpetuity.
The SMP may not be modified without prior written
authorization from the SMP approval authority.
Also, include any standard IP conditions you see fit.
Version 1
S:\SWP\Buncombe\401s\Non-DO'RAshevilleAirport\AVLAirport 07-1841 V4\RegionalOffice Comments.9.27.1Ldoc