HomeMy WebLinkAbout20110041 Ver 1_Approval Letter_20110225ir&ENR
North Carolina Department of Environment and Natural Resources
Division of Water Quality
Beverly Eaves Perdue Coleen H. Sullins Dee Freeman
Governor Director Secretarv
February 25, 2011
Cox-Edwards Company, Inc.
Mr. Scott Edwards, PE
1205 Parkway Drive
Goldsboro, NC 27534
DWQ Project # 11-0041
Wayne County
Subject Property: Phase XI Annexation Area, Pump Station Access and Force Main
Neuse River Basin, Ut to Little River (NEU 06, 27-57(20.2); NSW, WS-N)
Approval of 401 Water Quality Certification and Authorization Certificate per the Neuse
River Buffer Protection Rules (15A NCAC 2B.0233) with Additional Conditions
Dear Mr. Edwards:
You have our approval, in accordance with the attached conditions and those listed below, to
place fill within or otherwise impact 0.124 acres of wetlands, 117 feet of streams and 10,873
square feet (ft) of protected riparian buffers for the purpose of constructing a 12 foot wide access
road and installation of sewer force main with permanent 10 foot maintenance corridor, at the
subject property, as described within your application dated January 11, 2011 and received by the
N.C. Division of Water Quality (DWQ) on January 12, 2011. This application was placed on
Hold for additional information on February 9, 2011. Your response was received in this Office
on February 15, 2011. After reviewing your application and response letter we have decided that
the impacts are covered by General Water Quality Certification Number(s) 3819 (GC3819). The
Certification(s) allows you to use Nationwide Permit(s) 12 when issued by the US Army Corps of
Engineers (USACE). This letter shall also act as your approved Authorization Certificate for
impacts to the protected riparian buffers per 15A NCAC 2B .0233. In addition, you should obtain
or otherwise comply with any other required federal, state or local permits before you go ahead
with your project including (but not limited to) Erosion and Sediment Control, and Non-discharge
regulations. Also, this approval to proceed with your proposed impacts or to conduct
impacts to waters as depicted in your application shall expire upon expiration of the 404 or
CAMA Permit.
This approval is for the purpose and design that you described in your application. If you change
your project, you must notify us and you may be required to send us a new application. If the
property is sold, the new owner must be given a copy of this Certification and approval letter and
is thereby responsible for complying with all conditions. If total fills for this project (now or in
North Carolina Division of Water Quality Internet: www.ncwaterquality.org
943 Washington Square Mall Phone: 252-946-6481 One
Washington, NC 27889 FAX 252-946-9215 NorthCarohna
An Equal Opportunity/Affirmative Action Employer - 50% Recycled/l0% Post Consumer Paper Aaturally
Page 2 of 4
the future) exceed one acre of wetland or 150 linear feet of stream, compensatory mitigation may
be required as described in 15A NCAC 2H .0506 (h). This approval requires you to follow the
conditions listed in the attached certification and any additional conditions listed below.
The Additional Conditions of the Certification are:
1. Impacts Approved
The following impacts are hereby approved as long as all of the other specific and general
conditions of this Certification (or Isolated Wetland Permit) are met. No other impacts are
approved including incidental impacts:
Amount Approved Units Plan Location or Reference
Stream 117 feet Plan Set 1-13 and Updates
404/CAMA Wetlands 0.124 (acres) "
Waters acres
Buffers 10,873 (square ft.) "
2. Erosion & Sediment Control Practices
Erosion and sediment control practices must be in full compliance with all specifications
governing the proper design, installation and operation and maintenance of such Best
Management Practices in order to protect surface waters standards:
a. The erosion and sediment control measures for the project must be designed,
installed, operated, and maintained in accordance with the most recent version of the
North Carolina Sediment and Erosion Control Planning and Design Manual.
b. The design, installation, operation, and maintenance of the sediment and erosion
control measures must be such that they equal, or exceed, the requirements specified
in the most recent version of the North Carolina Sediment and Erosion Control
Manual. The devices shall be maintained on all construction sites, borrow sites, and
waste pile (spoil) projects, including contractor-owned or leased borrow pits
associated with the project.
c. For borrow pit sites, the erosion and sediment control measures must be designed,
installed, operated, and maintained in accordance with the most recent version of the
North Carolina Surface Mining Manual.
d. The reclamation measures and implementation must comply with the reclamation in
accordance with the requirements of the Sedimentation Pollution Control Act.
3. No Waste, Spoil, Solids, or Fill of Any Kind
No waste, spoil, solids, or fill of any kind shall occur in wetlands, waters, or riparian areas
beyond the footprint of the impacts depicted in the Pre-Construction Notification. All
construction activities, including the design, installation, operation, and maintenance of
sediment and erosion control Best Management Practices, shall be performed so that no
violations of state water quality standards, statutes, or rules occur.
Page 3 of 4
4. No Sediment & Erosion Control Measures w/n Wetlands or Waters
Sediment and erosion control measures shall not be placed in wetlands or waters to the
maximum extent practicable. If placement of sediment and erosion control devices in
wetlands and waters is unavoidable, they shall be removed and the natural grade restored
within six months of the date that the Division of Land Resources has released the project.
5. Certificate of Completion
Upon completion of all work approved within the 401 Water Quality Certification or
applicable Buffer Rules, and any subsequent modifications, the applicant is required to return
the attached certificate of completion to the 401 Oversight/Express Review Permitting Unit,
North Carolina Division of Water Quality, 1650 Mail Service Center, Raleigh, NC, 27699-
1650.
6. Culvert Conditions
Placement of culverts and other structures in waters, streams, and wetlands must be placed
below the elevation of the streambed by one foot for all culverts with a diameter greater than
48 inches, and 20 percent of the culvert diameter for culverts having a diameter less than 48
inches, to allow low flow passage of water and aquatic life. Design and placement of culverts
and other structures including temporary erosion control measures shall not be conducted in a
manner that may result in dis-equilibrium of wetlands or streambeds or banks, adjacent to or
upstream and down stream of the above structures. The applicant is required to provide
evidence that the equilibrium shall be maintained if requested in writing by DWQ.
7. Any rip-rap placed for streambank stabilization should be limited to the streambank below
the high water mark, and vegetation should be used for stabilization above the high water
elevation. Rip-rap should not be placed in stream channels in such a manner that it impedes
aquatic life passage. The rocks placed on the bank should be backed with filter cloth and
should be clean and sediment free.
8. Heavy equipment must be operated from the banks rather than in the stream channel in order to
minimize sedimentation and reduce the likelihood of introducing other pollutants into the
stream.
9. All mechanized equipment operated near surface waters must be regularly inspected and
maintained to prevent contamination of stream waters from fuels, lubricants, hydraulic fluids,
or other toxic materials.
10. Stormwater shall be directed to vegetated buffer areas, grass lined ditches, or other means
appropriate to the site for the purpose of pre-treating stormwater runoff, and must not be routed
directly into streams. Mowing of the existing vegetated buffers is strongly discouraged, so that
they may be utilized for stormwater diffuse flow.
11. No Impacts Beyond those in Application
No waste, spoil, solids, or fill of any kind shall occur in wetlands, waters, or riparian areas
beyond the footprint of the impacts depicted in the Pre-construction Notification. All
construction activities, including the design, installation, operation, and maintenance of
Page 4 of 4
sediment and erosion control Best Management Practices, shall be performed so that no
violations of state water quality standards, statutes, or rules occur.
Violations of any condition herein set forth may result in revocation of this Certification and may
result in criminal and/or civil penalties. The authorization to proceed with your proposed impacts
or to conduct impacts to waters as depicted in your application and as authorized by this
Certification shall expire upon expiration of the 404 or CAMA Permit.
If you do not accept any of the conditions of this Certification (associated with the approved
wetland or stream impacts), you may ask for an adjudicatory hearing. You must act within 60
days of the date that you receive this letter. To ask for a hearing, send a written petition, which
conforms to Chapter 150B of the North Carolina General Statutes to the Office of Administrative
Hearings, 6714 Mail Service Center, Raleigh, N.C. 27699-6714. This certification and its
conditions are final and binding unless you ask for a hearing.
Any disputes over determinations regarding this Authorization Certificate (associated with the
approved buffer impacts) shall be referred in writing to the Director for a decision. The
Director's decision is subject to review as provided in Articles 3 and 4 of G.S. 150B.
This letter completes the review of the Division of Water Quality under Section 401 of the Clean
Water Act and the Neuse riparian buffer protection rule as described within 15A NCAC 2B
.0233. If you have any questions, please telephone Roberto Scheller of the Washington Regional
Office at 252-948-3940 or Ian McMillan of the 401 Oversight/Express Unit at 919-715-4631.
incerel,,
or Teen ullins
Enclosures: Certificate of Completion
GC 3819
cc: City of Goldsboro
William Wescott, Corps of Engineers Washington Field Office
DWQ 401 Oversight/Express Unit
DLR, WaRO
File copy