December 8, 2010
DWQ Project # 08-1832, Ver. 2
Wake County
T. Allen Pipkin
10320-113 Durant Road
Raleigh, NC 27614
Subject Property: SE 40 Centre
Ut to Poplar Branch [030402, 27-34-11-1, C, NSW]
Approval of 401 Water Quality Certification and Authorization Certificate per the Neuse River
Buffer Protection Rules (15A NCAC 2B .0233) with Additional Conditions
Dear Mr. Pipkin:
You have our approval, in accordance with the attached conditions and those listed below, to place fill
within or otherwise impact 0.0989 acres of 404/wetland, 379 linear feet of reportedly ephemeral stream,
and 0.00 square feet of Zone 1 Neuse River basin protected riparian buffers and 0.00 square feet of Zone
2 Neuse River basin protected riparian buffers, as described in your application dated October 15, 2010,
and received by the Division of Water Quality (DWQ) on October 15, 2010, with additional information
received on November 23, 2010, to construct the proposed industrial project at the site. After reviewing
your application, we have decided that the impacts are covered by General Water Quality Certification
Number(s) 3821 (GC3821). The Certification(s) allows you to use Nationwide Permit(s) NW39 when
issued by the US Army Corps of Engineers (USACE). In addition, you should obtain or otherwise
comply with any other required federal, state or local permits before you go ahead with your project
including (but not limited to) Erosion and Sediment Control, and Non-discharge regulations. Also, this
approval to proceed with your proposed impacts or to conduct impacts to waters as depicted in
your application shall expire upon expiration of the 404 or CAMA Permit.
This approval is for the purpose and design that you described in your application. If you change your.
project, you must notify us and you may be required to send us a new application. If the property is sold,
the new owner must be given a copy of this Certification and approval letter and is thereby responsible for
complying with all conditions. If total fills for this project (now or in the future) exceed one acre of
wetland or 150 linear feet of stream, compensatory mitigation may be required as described in 15A
NCAC 2H.0506 (h). This approval requires you to follow the conditions listed in the attached
certification and any additional conditions listed below.
The Additional Conditions of the Certification are:
1. Impacts Approved
The following impacts are hereby approved as long as all of the other specific and general
conditions of this Certification (or Isolated Wetland Permit) are met. No other impacts are
approved including incidental impacts:
401 Oversight/Express Review Permitting Unit
1650 Mail Service Center, Raleigh, North Carolina 27699-1650
Phone: 919-733-17861 FAX: 919-733-6893
Internet: http://portal.ncdenr.org/web/wgtws
An Equal Opportunity 1 Affirmative Action Employer
T. Allen Pipkin
Page 2 of 4
December 8, 2010
Type of Impact Amount Approved nits Plan Location or Reference
404/Wetland 0.0989 (acres) PCN ap plication page 5 of 12
Stream - reportedly ephemeral 379 (linear feet PCN ap plication page 5 of 12
Buffers Zone 13 0.00 (square ft. PCN ap plication page 7 of 12
Buffers Zone 2 0.00 (square ft. PCN ap plication page 7 of 12
2. No Waste, Spoil, Solids, or Fill of Any Kind
No waste, spoil, solids, or fill of any kind shall occur in wetlands, waters, or riparian areas beyond
the footprint of the impacts depicted in the Pre-Construction Notification. All construction
activities, including the design, installation, operation, and maintenance of sediment and erosion
control Best Management Practices, shall be performed so that no violations of state water quality
standards, statutes, or rules occur.
3. Erosion and sediment control practices must be in full compliance with all specifications governing
the proper design, installation and operation and maintenance of such Best Management Practices in
order to protect surface waters standards:
a. The erosion and sediment control measures for the project must be designed, installed,
operated, and maintained in accordance with the most recent version of the North Carolina
Sediment and Erosion Control Planning and Design Manual.
b. The design, installation, operation, and maintenance of the sediment and erosion control
measures must be such that they equal, or exceed, the requirements specified in the most
recent version of the North Carolina Sediment and Erosion Control Manual. The devices
shall be maintained on all construction sites, borrow sites, and waste pile (spoil) projects,
including contractor-owned or leased borrow pits associated with the project.
c. Sufficient materials required for stabilization and/or repair of erosion control measures and
stormwater routing and treatment shall be on site at all times.
4. Sediment and Erosion Control Measures
Sediment and erosion control measures shall not be placed in wetlands or waters without prior
approval from the Division. If placement of sediment and erosion control devices in wetlands and
waters is unavoidable, design and placement of temporary erosion control measures shall not be
conducted in a manner that may result in dis-equilibrium of wetlands or stream beds or banks,
adjacent to or upstream and down stream of the above structures. All sediment and erosion control
devices shall be removed and the natural grade restored within two (2) months of the date that the
Division of Land Resources or locally delegated program has released the project;
5. Protective Fencing
The outside buffer, wetland or water boundary and along the construction corridor within these
boundaries approved under this authorization shall be clearly marked with orange warning fencing
(or similar high visibility material) for the areas that have been approved to infringe within the
buffer, wetland or water prior to any land disturbing activities;
6. Stormwater Management Plan Implementation Procedures (No Further Approval Needed)
• The approved SMP must be constructed and operational before any permanent building or
other structure is occupied at the site. If a development is phased, then the approved SMP for
each future phase must be constructed and operational before any permanent building or other
structure associated with that phase is occupied.
• The approved SMP as well as drainage patterns must be maintained in perpetuity.
T. Allen Pipkin
Page 3 of 4
December 8, 2010
• The SMP may not be modified without prior written authorization from the SMP approval
authority. If the SMP falls under another state stormwater program, then a copy of the
approval letter and the modified SMP must be submitted to the 401 Oversight/Express Unit
prior to the commencement of the modifications.
7. Certificate of Completion
Upon completion of all work approved within the 401 Water Quality Certification or applicable
Buffer Rules, and any subsequent modifications, the applicant is required to return the attached
certificate of completion to the 401 Oversight/Express Review Permitting Unit, North Carolina
Division of Water Quality, 1650 Mail Service Center, Raleigh, NC, 27699-1650.
Violations of any condition herein set forth may result in revocation of this Certification and may result in
criminal and/or civil penalties. The authorization to proceed with your proposed impacts or to conduct
impacts to waters as depicted in your application and as authorized by this Certification, shall expire upon
expiration of the 404 or CAMA Permit.
If you wish to contest any statement in the attached Certification you must file a petition for an
administrative hearing. You may obtain the petition form from the Office of Administrative Hearings.
You must file the petition with the Office of Administrative Hearings within sixty (60) days of receipt of
this notice. A petition is considered filed when it is received in the Office of Administrative Hearings
during normal office hours. The Office of Administrative Hearings accepts filings Monday through
Friday between the hours of 8:00am and 5:00pm, except for official state holidays. The original and one
(1) copy of the petition must be filed with the Office of Administrative Hearings.
The petition may be faxed-provided the original and one copy of the document is received by the Office
of Administrative Hearings within five (5) business days following the faxed transmission.
The mailing address for the Office of Administrative Hearings is:
Office of Administrative Hearings
6714 Mail Service Center
Raleigh, NC 27699-6714
Telephone: (919)-431-3000, Facsimile: (919)-431-3100
A copy of the petition must also be served on DENR as follows:
Ms. Mary Penny Thompson, General Counsel
Department of Environment and Natural Resources
1601 Mail Service Center
Raleigh, NC 27699-1601
Unless such a petition is filed, this Certification shall be final and binding.
T. Allen Pipkin
Page 4 of 4
December 8, 2010
This letter completes the review of the Division of Water Quality under Section 401 of the Clean Water
Act and the Neuse riparian buffer protection rule as described within 15A NCAC 2B .0233. If you have
any questions, please telephone Ian McMillan or Amy Chapman, at 919-733-1786.
Sin erely, I
v
Coleen H. Sullins
CHS/gym
Enclosures: GC 3821
Certificate of Completion
cc: Brenda Menard, Asst. Attorney General, NC Dept. of Justice, P.O. Box 629, Raleigh, NC 27602-0629
Lauren Witherspoon, DWQ Raleigh Regional Office
USACE Raleigh Regulatory Field Office
File Copy
Nicole Thomson, S&EC, P.A., 11010 Raven Ridge Road, Raleigh, NC 27614
DLR Raleigh Regional Office
Filename: 081832Ver2_sE4GCentre(Wake)401 NBR