December 14, 2020
U. S. Army Corps of Engineers
Raleigh Regulatory Field Office
3331 Heritage Trade Drive, Suite 105
Wake Forest, NC 27587
ATTN: Mr. Monte Matthews
NCDOT Coordinator
Subject: Request for Renewal for Section 404 and 401 Individual Permit and Certification for the
Shelby Bypass, Cleveland County, Division 12, Debit $570 from WBS 34497.1.FS6,
TIP R-2707.
Dear Sir:
The purpose of this letter is to request renewal of the United States Army Corps of Engineers (USACE)
Section 404 Individual Permit and NC Division of Water Quality (NCDWR) Certification for the above
referenced project.
The original Phased Individual Permit indicates that construction must be completed before December 31,
2020. The subsequent March 31, 2017 Phased Individual Permit Modification also indicates the original
permit expiration of December 21, 2020 remains applicable.
Major Permitting History
Section 404 Permit
SAW-2009-01449
401 Certification
20120673
R-2707 (overall project), and Sections A & B April 12, 2013 September 18, 2012
R-2707 C March 31, 2017 April 4, 2017
continued
Project Status:
Sect. Location Length Status Details*
AA West of Peachtree Rd to east of
Kimbrell Rd near Mooresboro 2 miles Complete Construction began in July 2013 and
opened to traffic in September 2016.
AB East of Kimbrell Rd to east of Plato
Lee Rd near Lattimore 1.9 miles Complete Construction began in July 2014 and was
completed in April 2018.
B East of Plato Lee Rd to east of NC 226
north of Shelby 2.6 miles Complete Construction began in July 2014 and was
completed in April 2018.
C East of NC 226 to west of NC 150
heading northeast of Shelby 5.3 miles Under
Construction
Construction began in 2017 and should
be completed in the Winter 2023.
D* West of NC 150 to US 74 west of Long
Branch Rd, east of Shelby 4.1 miles Design*
Final designs are underway. Right of way
purchasing is underway with
construction beginning in 2024.
E*
US 74 west of Long Branch Rd to west
to Stony Point Rd at US 74 Business in
Kings Mountain
2.6 miles Design*
Final designs are underway. Right of way
purchasing is underway with
construction beginning in 2024.
*Future dates are preliminary and subject to change
Remaining Impacts:
Sub-
Tip Location Design
Level Wetlands Streams
Permanent Fill
Streams Permanent
Bank Stabilization
C East of NC 226 to west of NC 150 heading
northeast of Shelby Final 0.94 7,644
D West of NC 150 to US 74 west of Long
Branch Rd, east of Shelby Preliminary 0.4 5,840 76
E
US 74 west of Long Branch Rd to west to
Stony Point Rd at US 74 Business in Kings
Mountain
Preliminary 0.66 2,805 39
2.0 16,289
The C section of this project is scheduled for completion in 2023. The remaining two sections, D and E,
are currently in project design, and in the merger process. Both sections are scheduled for construction
beginning in 2024.
Renewal is hereby requested for the USACE 404 permit and the 401 WQC from NCDWR for the C, D
and E Sections with a requested expiration of December 31, 2029. Please debit $570.00 for processing of
the WQC renewal for R-2707, as noted in the subject line of this application.
A copy of this permit application and its distribution list will be posted in the NCDOT website at
http://connect.ncdot.gov/resources/Environmental.
Thank you for your assistance with this project. If you have any questions or need additional
information, please contact Jeff Hemphill jhemphill@ncdot.gov or (919) 707-6126.