Loading...
HomeMy WebLinkAbout20081615 Ver 2_Public Notice_20100831US Army Corps Of Engineers Wilmington District �8- I LP PUBLIC NOTICE Issue Date: August 31, 2010 Comment Deadline: September 30, 2010 Corps Action ID No: SAW -2006-40808 All interested parties are hereby advised that the Wilmington District, Corps of Engineers (Corps) has received a request from the Town of Topsail Beach, North Carolina (Town) seeking to modify its June 15, 2009 Department of the Army (DA) Permit authorizing the Topsail Beach Interim (Emergency) Beach Fill Protection Project. Specifically, the Town has requested to eliminate the open ocean borrow area (Borrow Area "X") as a sand source and include inshore borrow areas within the existing federal navigation channels (Topsail Creek, Topsail Creek Crossing, and Banks Channel) and Corps maintained dredge material placement sites (DA 189 & DA203) located in Topsail Sound inland of the Town of Topsail Beach. Specific plans and location information are described below and shown on the attached plans. This Public Notice and all attached plans are also available on the Wilmington District Web Site at www.saw.usace.armv.mil/wetlands Applicant: Attn: Tim Holloman, Town Manager Town of Topsail Beach 820 S. Anderson Boulevard Topsail Beach, North Carolina 28465 4 5 AGENT (if applicable): Chris Gibson, PE Gahagan and Bryant Associates of NC 295-A North Green Meadows Drive Wilmington, North Carolina 28405 Authority The Corps will evaluate this request and a decide whether to issue, conditionally issue, or deny the proposed modification pursuant to applicable procedures of Section 404 of the Clean Water Act (33 USC 1344) and Section 10 of the River and Harbors Act. Location The project site is located on the southern end of Topsail Island, within the Town Limits of the Town of Topsail Beach. Topsail Island is located in southeast North Carolina and is the central island along Onslow Bay. The Town is bounded to the north by Surf City, the West by Topsail Sound and south by the federal maintained New Topsail Inlet. The island is accessible to the public by highways 50 and 210 with Highway 50 being the only entry road to the Town of Topsail Beach. The geographic coordinates are Latitude 34022'10" N; Longitude 77037'30"W (NAD83). The proposed modified borrow areas are located west of the island. Background The Town of Topsail Beach has experienced substantial shoreline erosion, exacerbated by multiple direct and near direct encounters with tropical storm systems. In order to mitigate loss of property and infrastructure, a Federal Storm Damage Reduction Project was authorized under WRDA 1992. In Nov 1989 the Corps released a Final Environmental Impact Statement (FEIS) detailing the proposed federal beach nourishment project and preferred borrow sources. Federal funds were not secured for the project however, and the project became inactive when the Town withdrew its support in 1994 due to funding limitations. A General Reevaluation report of the federal project was completed by the Wilmington District and the combined GRR/EIS was released for final public review in Aug 2008. Due to the expected timeline associated with Re -Authorization of the federal project, the Town applied for a DA permit to conduct a one-time, privately funded interim beach nourishment project. The Corps released a supplement to the FEIS (SFEIS) detailing the proposed project on April 10, 2009. Several borrow source alternatives were considered during the development of the SFEIS including the existing federal navigation channels (Topsail Creek, Topsail Creek Crossing, and Banks Channel) and existing federal disposal areas. It was determined, based on the information available at the time, that the volume of material that could be removed from within the limits of the authorized navigation channel was not sufficient to meet the interim shore protection needs. It was also determined that the disposal areas along the Atlantic Intracoastal Waterway (AIWW) did not contain enough material meeting the North Carolina sediment criteria to complete the proposed nourishment project. Thus, alternatives involving these options were not carried forward. A Record of Decision (ROD) completing the NEPA process was signed on June 12, 2009. A DA permit was issued to the town on June 15, 2009 to place approximately 1,000,000 cubic yards of beach quality sand along the 24,700 linear feet of developed shoreline on Topsail Island from an ocean borrow area, designated as "Borrow Area X", located immediately southeast of New Topsail Inlet. The unexpectedly high bids received during the contract procurement process in 2009 and delays in project implementation prompted the Town to re -investigate alternative sand sources. As a part of this effort, the Town contracted Gahagan & Bryant Associates, Inc (GBA) to conduct more detailed vibracore surveys of disposal areas along the AIWW as well as some areas within the existing federal channels. GBA also examined recent hydrographic surveys of the existing federal channels. This new information revealed 2 that removal of the material now accumulated in the existing federal channels within Topsail Creek, Topsail Creek Crossing, and Banks Channel combined with removal of suitable material from within two Federal disposal areas along the AIWW would generate adequate volumes of material suitable to complete the beach nourishment project. The town has now proposed to modify its DA permit to eliminate the offshore area, "Borrow Area V as a sand source for the project and instead utilize material from the above mentioned federal channels and disposal areas. The Town has asserted that utilizing these inland borrow sources would result in substantial cost savings with less environmental impacts and would fully meet the Town's interim beach nourishment needs. To minimize environmental impacts, the Town proposes to limit borrow activities to only that material accumulated within the authorized dimensions of the Federal navigation channels and within two active Corps disposal areas, owned by the State of North Carolina, and located within the Corps' AIWW easement. Regularly conducted federal channel maintenance activities are currently authorized to utilize portions of the proposed beach nourishment project area for disposal. Applicant's Stated Purpose According to information provided by the applicant, the purpose of the proposed modification is to minimize project costs and environmental impacts while providing an equal level of shoreline protection as the currently authorized project. The proposed permit modification does not seek to alter the permitted beach nourishment design, but only to modify the location from which the material will be acquired. Project Description Due to an urgent need for a beach nourishment project along the oceanfront of Topsail Beach, beach fill construction is proposed for the fall of 2010. This project will involve a multi -faceted approach, targeting several key borrow areas to achieve the quantity and quality of material necessary to meet and exceed state standards in constructing a viable beach. The proposed plan includes 800,000-975,000 cubic yards (cy) of material to be placed along approximately 25,000 ft of Topsail Beach's oceanfront shoreline. Based on the characteristics of the material found in the borrow areas, approximately 900,000 to 1,050,000 cy of material will be required to build the designed beach template. Borrow Area Locations Each proposed borrow area is situated in the back barrier area or landward of the barrier island atop of which the Town of Topsail Beach resides. These sites include portions of the Corps maintained Disposal Areas DA -189 and DA -203. Other targeted sites include areas within the federally maintained navigation channels of Topsail Creek, Banks Channel, and the Atlantic Intracoastal Waterway (AIWW). Four main segments have been delineated along the oceanfront to receive dredge material during construction phase. To reduce project cost, streamline workflow, and optimize the sediment source budget each segment of the oceanfront will receive material from a specified borrow area. 3 Currently, the proposed oceanfront fill segment boundaries are conditional and subject to change based on the contractor's schedule of work. Borrow Material Characteristics The applicant has submitted to the Corps the findings from the geotechnical investigations conducted by GBA. The borrow areas were divided into four (4) sub- sections for evaluation, DA -189, DA -203, the Atlantic Intracoastal Waterway, and Topsail Creek/Banks Channel. Each sub -section was investigated and analyzed as an independent site as well as part of the entire source. GBA performed the investigation in both DA -203 and DA -189 twice, once as a reconnaissance level study and once utilizing the standards prescribed in by the North Carolina Coastal Resource Commission (CRC) in administrative code 15A NCAC 07H.0312. Both methodologies produced nearly identical results. To ensure beach fill material placed on a beach is compatible with the beach, The North Carolina Coastal Resources Commission (CRC) adopted a state Sediment Criteria Rule for borrow material (15A NCAC 07H .0312). This rule also limits the amount of silt (< 0.0625 mm) to 5% above the native beach material and gravel (>4.76 mm) to 5% above native beach material. Also, the percent of the borrow material by weight between 4.76 mm and 2.0 mm cannot exceed the native by more than 5%. Characterization of each borrow site requires no less than 10 evenly spaced cores or one core per 10 acres, whichever is greater. These technical standards are discussed further in the FSEIS, Section 5.15.7.1. The beaches of Topsail Beach, have an average gravel content of 0.17%, the upper limit of gravel is 5.17%. The silt content of the native material is 0.94% resulting in a maximum allowable silt content from the borrow areas of 5.94%. The material within each borrow area sub -section meets the Sediment Compatibility Criteria defined by the CRC for silt, shell gravel and carbonate content. The material has similar mean and median grain size to that of the currently planned borrow area as shown in the following table. Table 1: Inland Borrow Area Composite Summary Table Topsail 2010 Whrar_erps Borrow Volume Mean Mean Median Median PHI Area (CY) (mm) (phi) (mm) (phi) Sorting Silt Shell AIWW 91,000 0.18 2.48 0.18 2.46 0.33 0.43 7.8 Topsail Creek 107,000 0.24 2.05 0.22 2.17 0.65 0.21 6.8 DA203 1 460,000 0.19 2.42 0.18 2.48 0.50 4.13 4.8 DA189 387,000 0.18 2.50 0.17 2.59 0.52 5.73 4.5 Inland 1.045 Borrow MY 0.19 2.42 0.18 2.49 0.51 4.00 5.2 4 Table 2: Borrow material characteristics compared to native material Borrow Volume Mean Mean Median Median PHI % % Area (CY) (mm) (phi) (mm) (phi) Sorting Silt Shell Topsail N/A 0.24 2.05 0.21 2.23 0.86 0.94 11 Native Inland 1.045 0.19 2.42 0.18 2.49 0.51 4.00 5.2 Sources MY X 1.5 0.20 2.31 0.16 2.63 1.21 2.17 5.0 MY Dredging Logistics The project will involve the use of a hydraulic dredge in the 16"-20" class. Planned pipeline routes will follow corridors used previously during historic dredge and nourishment events in the local area. Pipelines will cross over the island at specific approved use areas previously used by the Corps to access the beach with dredge pipeline. A suitable pipeline route for dredging DA -189 and discharging fill to the oceanfront beach will follow Harvey's Cut and cross over the island at Queen's Grant. Similarly, the pipeline route associated with dredging practices to the south at DA -203 and in the federal navigation channels will follow Topsail Creek and cross over the island at Smith Avenue. Locations of proposed cuts into each DA are based on minimizing environmental impacts on marsh vegetation surrounding these sites and also consider draft depths that dredges of this class require. With the exception of the area designated for cut -in access to a DA, no vegetation that exists currently outside the dikes or surrounding the DA will be impacted by project construction efforts. Established vegetation within the dikes of each DA will be cleared as needed for the dredging activity. Dredge Access to Borrow Areas Access to all borrow areas is via the AIWW. Typically to access and remove material from a confined disposal facility, a contractor will dredge a temporary access channel from the main channel into the site. The material will be removed by normal hydraulic dredging methods. Then, after project completion and dredge is demobilization, the access channel is filled in and the levee restored by mechanical earth moving equipment so that the site is again operational. This method will be utilized for excavation of DA - 203. For DA -189, the perimeter of the island has been identified as a Primary Nursery Area (PNA). The North Carolina use standards, specifically 15A NCAC 07H.208 (b) (1), preclude new dredging in a PNA. Equipment is allowed to be transported over a PNA or marsh so long reasonable and prudent measures are utilized to minimize the disturbance to the areas. Thus, for DA -189, construction equipment (i.e. dredge, induction pump, or other method of slurrying material) will be transported into the DA without excavating any area between the mean high water line and the federal navigation channel. 5 The proposed dredge access method (subject to minor changes) into DA -189 is as follows: 1. A "starter pond" of sufficient length, width, and depth for the dredge to begin operations will be excavated inside the existing perimeter levees. 2. At the access point, the perimeter levee will be graded down to slopes and elevations that would allow skids or mats to be placed over the marsh and levee. 3. Skids or mats will be laid over the marsh and the dredge will be pulled across the skids, over high ground into the starter pond. 4. The dredge will perform dredging operations with slurry water being provided by pumps or siphon. 5. The dredge will be demobilized using steps 3 & 2, with the levees being restored to elevations consistent with the design. This procedure will avoid and minimize to the maximum extent possible the potential impacts to the PNA adjacent to DA -189. Clearing of Disposal Areas With the exception of the areas designated for cut -in or access to a DA, no vegetation that exists currently outside the dikes or surrounding the DA will be impacted by project construction efforts. Established vegetation within the dikes of each DA will be cleared and burned if it resides above proposed dredge material. On, DA -189, vegetation will be cleared and relocated to the northern extent of the disposal site to be burned prior to dredging efforts. On DA -203, little to no clearing of vegetation is expected to be necessary in the proposed area of disturbance. Levee Reconstruction Once dredging operations are completed in these disposal areas, both DA sites will be restored. Material unsuitable for beach fill from the DA's will be used to rebuild the portions of dike affected by this project. Slopes of 2:1 will be constructed for all dikes surrounding the disturbed portion of each DA. An existing outfall pipe and weir box assembly currently exists on DA -189. In order to utilize this existing assembly, a trench will be excavated extending from the weir box and that material then used to rebuild the previously penetrated dike. DA -203 will have a new outfall pipe and weir box assembly constructed to meet USACE and DCM regulations for a CDF. Approximately 250,000-300,000 cy of capacity will be created for the USACE in each DA as a result of dredging these borrow sites for this project. Beach Construction Construction parameters of the beach profile and shoreline extent to be nourished, along the oceanfront fill area of Topsail Beach, will follow the authorized beach plan as on described in the SFEIS and ROD. Beach slope (15:1) and berm elevation (6.0 ft NAVD88) will generally follow the typical construction profile, as authorized. . Project Impacts The material within the proposed borrow areas has similar characteristics to the material found in Borrow Area X and is expected to behave similarly once placed on the beach. Therefore, no new impacts are anticipated within the permitted beachfill area. The proposed modification will totally avoid previously authorized impacts to 127 acres of Essential Fish Habitat (EFH) impacts within Borrow Area X. The proposed modification will result in approximately 0.05 acres of impacts to sandy bottom habitat associated with the dredge cut into DA -203. The proposed method to access DA -189 precludes the necessity to excavate adjacent Primary Nursery Areas (PNA). The proposed project will also include dredging approximately 67 acres of bottom within the regularly maintained federal channel segments. All dredging within the federal channel segments will be restricted to the within the currently authorized channel dimensions. Maintenance dredging of Banks Channel, Topsail Creek, and the AIWW is conducted by the Corps approximately every three to four years. Based on current conditions, the Corps is preparing for maintenance activities in these channels in Fiscal Year (FY) 2011. Other Required Authorizations The Corps will generally not make a final permit decision until the North Carolina Division of Water Quality (NCDWQ) issues, denies, or waives State certification required by Section 401 of the Clean Water Act (PL 92-500). In addition, pursuant to 33 CFR 325.2(b)(2), the Corps cannot issue a permit for the proposed work until the applicant has demonstrated and the North Carolina Division of Coastal Management (NCDCM) has concurred that the proposed activity complies with and will be conducted in a manner that is consistent with the approved North Carolina Coastal Zone Management Program. This consistency determination may come in the form of a Coastal Area Management Act (CAMA) permit. Essential Fish Habitat This notice initiates the Essential Fish Habitat (EFH) consultation requirements of the Magnuson -Stevens Fishery Conservation and Management Act. The Corps has not made a determination if the proposed modification to the project will or will not adversely impact EFH or associated fisheries managed by the South Atlantic or Mid Atlantic Fishery Management Councils or the National Marine Fisheries Service. Based on the applicant's submitted information the proposed modification will result in a substantial (99.5%) reduction in direct impacts to EFH over the currently permitted project. 7 Cultural Resources The Corps has consulted the latest published version of the National Register of Historic Places and is not aware that any registered properties, or properties listed as being eligible for inclusion therein are located within the project area or will be affected by the proposed work. Presently, unknown archeological, scientific, prehistoric, or historical data may be located within the project area and/or could be affected by the proposed work. Endangered Species The Corps has reviewed the project area, examined all information provided by the applicant and consulted the latest North Carolina Natural Heritage Database. Based on available information, the Corps has determined pursuant to the Endangered Species Act of 1973 (ESA), that the proposed project may affect federally listed endangered or threatened species or their formally designated critical habitat. A Biological Assessment (BA) has been prepared and coordinated with the United States Fish and Wildlife Service (USFWS) and the National Marine Fisheries Service (NMFS) pursuant to Section 7 of the Endangered Species Act of 1973, as amended. This assessment determined that the proposed action may affect but will not likely adversely affect the piping plover and the seabeach amaranth. Due to timing of the project and precautions taken during its implementation, other Federally listed endangered or threatened species should not be affected. Consultation under Section 7 of the ESA will be initiated and no permit will be issued until the consultation process is complete. Evaluation The decision whether to modify the existing permit will be based on an evaluation of the probable impacts, including cumulative impacts, of the proposed activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefit which reasonably may be expected to accrue from the proposal must be balanced against its reasonably foreseeable detriments. All factors which may be relevant to the proposal will be considered including the cumulative effects thereof; among those are conservation, economics, aesthetics, general environmental concerns, wetlands, historic properties, fish and wildlife values, flood hazards, flood plain values (in accordance with Executive Order 11988), land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, considerations of property ownership, and, in general, the needs and welfare of the people. For activities involving the discharge of dredged or fill materials in waters of the United States, the evaluation of the impact of the activity on the public interest will include application of the Environmental Protection Agency's 404(b)(1) guidelines. Commenting Information The Corps of Engineers is soliciting comments from the public; Federal, State and local agencies and officials, including any consolidated state viewpoint or written position of the Governor; Indian Tribes and other interested parties in order to consider and evaluate the impacts of this proposed activity. Any comments received will be considered by the Corps of Engineers to determine whether to issue, modify, condition or deny a permit for this proposal. To make this decision, comments are used to assess impacts on endangered species, historic properties, water quality, general environmental effects and the other public interest factors listed above. Comments are used in the preparation of an Environmental Assessment (EA) and/or an Environmental Impact Statement (EIS) pursuant to the National Environmental Policy Act (NEPA). Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity. Any person may request, in writing, within the comment period specified in this notice, that a public hearing be held to consider the application. Requests for public hearings shall state, with particularity, the reasons for holding a public hearing. Requests for a public hearing shall be granted, unless the District Engineer determines that the issues raised are insubstantial or there is otherwise no valid interest to be served by a hearing. Written comments pertinent to the proposed work, as outlined above, will be received by the Corps of Engineers, Wilmington District, until 5pm, September 30, 2010 Comments should be submitted to Dave Timpy, Project Manager , 69 Darlington Avenue, Wilmington, N.C. 28403. 0 ar" c I E }} Xv MO N c 3;. O , C 0 WF— > DD z mm z m m F m> oa r. 1 D= LO ` a mz Im r D r- r' T a a pit p iP1 rq z TOPSAILBEACH . 1 •URISHMENT f._a. �QJ Photo: Pander Count, 2003 LOCATION PROJECT