HomeMy WebLinkAboutNCC203481_ESC Approval Submitted (3)_20200825a. The initial and signed inspection report must be filed with the DSD Site Engineering
Division prior to the commencement of any land disturbing activity.
b. A licensed professional shall conduct weekly inspections for all sites where Hillside,
Steep Slope and/or Mountain Top Protection regulations apply and bi-weekly for all other
sites.
c. All weekly inspections and bi-weekly inspections must be kept on inspection logs and
retained at the site.
5. For constructed slopes with a grade of 50% (2:1) and greater than five feet in height, inspection
and submittal of a Slope Stability Certificate are required by a North Carolina registered
professional engineer with geotechnical expertise sufficient to perform the inspection and
stability analysis.
6. Please note that Temporary Ground Cover must be established, prior to release of grading
approval for issuance of a Temporary Certificate of Occupancy. Permanent Ground Cover must
be established, prior to grading approval for the issuance of a Certificate of Occupancy.
7. Contractor must provide proof of active grading permits for any offsite borrow or waste areas.
8. Inspection request should be called into 828-259-5946, or can be scheduled via web at
www.develop.ashevillenc.gov
9. Grading Permit expires in one (1) year from the date of permit issuance. A one-time, one-year
extension can be granted. Please drop off or mail the extension application form at the Permit
Application Center, 161 S. Charlotte Street, Asheville NC 28801, within 60 days prior to permit
expiration.
See Permit for additional Stormwater, Flood and Grading Conditions.
Please note that this approval is based in part on the accuracy of the information provided in the
Financial Responsibility Form, which you provided. You are requested to file an amended form if there
is any change in the information included on the form. In addition, it would be helpful if you notify this
office of the proposed starting date for this project. Please notify us if you plan to have a
preconstruction conference.
Sincerely,
Ric Ledford, CFM
Senior Plan Reviewer
Development Services Department
Site Development Engineering
3