Date Information Received: 05/27/2020
Project Information
ID#: Version:
20200922 1
Project Name: Rodanthe Bridge Transmission Line, South End
County(ies):
Dare
Contact Emails:
markr@chec.coop
brickrd@booth-assoc.com
garcy.ward@ncdenr.gov
kyle.w.barnes@usace.army.mil
Project Folder Web Access
Click here to log in to see the project information submitted.
Staff Review Documentation
Decision:* Waived Project
Date decision letter written* 7/30/2020
Check all agencies that need to V DCM
receive notification of your decision. r WRC
DMS
Has your decision letter been uploaded into Laserfiche?*
r Yes - Uploaded separately
f Yes - Attaching it to this form
f No - Sent for signature (TPB Unit Only)
r NIA
Staff Comments and Documentation
Staff review documentation: FDForjpgonly
Staff Comments: After consultation with the Corps it was determined that the
impacts requested have already been approved under previous
permits for the bridge and utilities, therefore a separate permit is
not required for this activity. Should the scope of the project
change, please notify this office as a 401 or modification may be
required.