LETTER OF APPROVAL
Caropine Ventures, LLC
2709 Thorngrove Ct.
Fayetteville, NC. 28303
RE: Project Name: Caropines Phases 8 & 12
Acres Approved: 10.96
Project ID: ZP-08-20
County: Moore
City: Southern Pines
Address: Avenue of the Carolinas
River Basin: Cape Fear Stream Classification: WS-III-B-HQW
Submitted By: Matt Lowder, Triangle Site Design, PLLC
Date Received by: Town of Southern Pines, 6/23/2020
Plan Type: Residential
Dear Caropine Ventures, LLC,
This office has reviewed the subject erosion and sedimentation control plan. We find the plan to
be acceptable and hereby issue this Letter of Approval. The enclosed Certificate of Approval
must be posted at the job site. This plan approval shall expire three (3) years following the date
of approval, if no land -disturbing activity has been undertaken, as is required by Title 15A
NCAC 4B .0129.
As of April 1, 2019, all new construction activities are required to complete and submit an
electronic Notice of Intent (NOI) form requesting a Certificate of Coverage (COC) under the
NCGO10000 Construction Stormwater General Permit. This form MUST be submitted prior to
the commencement of any land disturbing activity on the above named project. The NOI form
may be accessed at de .nc.gov/NCGO1. Please direct questions about the NOI form to Annette
Lucas at Annette. lucas@ncdenr.Qcoy or Paul Clark at Paul.clark@ncdenr.gov. After you submit a
complete and correct NOI Form, a COC will be emailed to you within three business days..
Title 15A NCAC 4B .0118(a) and the NCGO1 permit require that the following documentation
be kept on file at the job site:
1. The approved E&SC plan as well as any approved deviation.
2. The NCGO1 permit and the COC, once it is received.
3. Records of inspections made during the previous 30 days.
Letter of Approval
Caropine Ventures, LLC
7/2/2020
Page 2 of 2
Also, this letter gives the notice required by G.S. 113A-61.1(a) of our right of periodic inspection
to insure compliance with the approved plan.
North Carolina's Sedimentation Pollution Control Act is performance -oriented, requiring
protection of existing natural resources and adjoining properties. If, following the
commencement of this project, the erosion and sedimentation control plan is inadequate to meet
the requirements of the Sedimentation Pollution Control Act of 1973 (North Carolina General
Statute 113A-51 through 66), this office may require revisions to the plan and implementation of
the revisions to insure compliance with the Act.
Acceptance and approval of this plan is conditioned upon your compliance with Federal and
State water quality laws, regulations, and rules. In addition, local city or county ordinances or
rules may also apply to this land -disturbing activity. This approval does not supersede any other
permit or approval.
Please note that this approval is based in part on the accuracy of the information provided in the
Financial Responsibility Form, which you provided. You are requested to file an amended form
if there is any change in the information included on the form.
Prior to start of any construction, the NPDES NCGO1 Construction Stormwater permit must be
acquired from NCDEQ and a Preconstruction Conference must be held with Town Staff. The
NCGO1 permit must be obtained prior to scheduling the Preconstruction Conference. Once the
NCGO1 is obtained, please notify Jay Hough, the Town's Construction Inspector, 910-692-1983,
to schedule the Preconstruction Conference.
Your cooperation is appreciated.
Sincerely,
James Michel, PE
Town Engineer
Town of Southern Pines
Enclosures: Certificate of Approval
NCGO1 Fact Sheet
DEMLR Monitoring Form Rev August-8-2019
ec: Matthew E. Lowder, Triangle Site Design, PLLC