Loading...
HomeMy WebLinkAboutWQ0029945_More Information (Received)_20200727July 23, 2020 ON'WASA anwasa.com ATTN: Tessa Monday, PE, Environmental Engineer III 228 Georgetown Rd NCDEQ Division of Water Resources Jacksonville. NC 28540 Non -Discharge Branch 1617 Mail Service Center Raleigh, NC 27699-1617 RE: Permit No. WQ0029945 Onslow Water and Sewer Authority (ONWASA), Onsiow County Summerhouse Wastewater Reclamation WWTP High -Rate Infiltration System Request for Permit Modification Dear Ms. Monday, This letter is sent in response to your letter of June 25, 2020 requesting additional information to support a Request for Permit Modification submitted by ONWASA for the above - referenced facility. As a general comment, the testing conducted by the engineer and hydrogeologist was performed to establish the capacity of the existing basin under site and hydrogeologic conditions as they currently exist. No physical aspects of the basin, either below -ground or aboveground, or pumping characteristics were changed. Rather, this testing was performed to verify and then certify the hydraulic loading rate I capacity of the existing system. The following provides responses to the individual questions raised in your June 251" letter: A. Hydrogeologic Reporf (15A 1VCAC 02T .0704(e)) 1. Provide additional information on the design of the groundwater lowering system, including a map which identifies the extent of the system. A plan drawing and sections of the groundwater lowering system, including the drain system location and pump station, from the original design drawings (by McKim & Creed) are attached. The pumps are started and stopped based on level in the station wet well. Water flows from the infiltration basin to the drain system, then into the pump station and is pumped to Silver take. The lake has an existing surface water outlet. 2. The proposal indicates that three to four piezometers would be installed between the pond and one of the existing drains. Information provided indicates that at least three piezometers were installed, however no information was provided on the location of the existing drain. Please update the site sketch to show the location of the existing drains Three piezometers were installed at the locations shown an the attached original Basin #2 drawing via call -outs. The location of the drain system that surrounds the basin per the original drawings for the system is also labeled. Page 1 of 4 3. Provide information on the installation of the constructed piezometers (materials, methods, drilling lag, etc.). Groundwater Pump and Well Company constructed the piezometers by the washdown method: 1) A hole was excavated with a hand auger to approximately six inches below the water table surface, at which point the sand collapses with deeper excavation. 2) In order to place the PVC slotted pipe, a temporary 2-inch diameter, open end pipe was used to pump water from a 126 gallon fresh water tank into the bottom of the hand-augered hole. 3) This flushing action was used to deepen the hole to the finished depth of each piezometer. 4) The temporary pipe was pulled and the 1-inch diameter pipe was set in the deepened hole and gravel pack (# 2 - Hoffman Well Gravel) placed around the 1- inch pipe The piezometers monitored portions of the sand aquifer at approximately 4.3 feet above mean sea level for P 1, 1.26 feet below mean sea level for P 2, and 0.5 feet above mean sea level for P 3. Information on the piezometers is provided below. Piezometer Total Slot Top Slot Ground Stick- Synoptic Depth Depth Setting Elevation up (121112019) (ft.) Estimate (NA❑ 88) (NAD 88 Ft.) Feet Feet/Elev. Feet ft. m.s.I. ft. M.S.I. P1 7.0' 6.0' to 4.31 ft. 10,31' 0.0' 5.1275.19' 6.5' msl msl P2 13.3' 12.5' to -1.25 ft. 11.261 0.1' 8.30'12.97' 13.0' msl msl P3 11.5' 10.5' to 1.00 ft. 11.00' 0.3' 9.26112.04' 11.0' msl msl 4_ Please show the following (within 500 feet of the facility area): a. All wells and piezometers, including Usage and construction details; b. Ephemeral, intermittent, and perennial streams; c. Springs, lakes, ponds, and other surface drainage features; and d. Review and compliance boundaries. All hydrogeologic information was described in the Hydrogeologic Report 2006 ("Soil & Hydrogeologic Investigation Summerhouse on Everett Bay, Holly Ridge, Onslow, N.C." April 3, 2006). No hydrologic conditions were changed as part of the testing. Review and compliance boundaries are unchanged versus the original permit. Page 2 of 4 5. provide a description of the site hydrogeology, including groundwater discharge features, drainage features, existing and abandoned wells, and other features that may affect the movement of the treated wastewater, including the groundwater lowering system. The information requested was presented in the 2006 study investigation report and has not changed. This report is attached with the requested hydrogeology and drainage features information ("Soil & Hydrogeologic Investigation Summerhouse on Everett Bay, Holly Ridge, Onslow, N.C." April 3, 2006). See response to Item 1 for drawing information on the groundwater lowering system. The testing used the existing system and did not change any aspect of it. 6. Provide a discussion of the current groundwater flow regime of the site and the post modification groundwater flow regime, focusing on the relationship of the system and basin to groundwater receptors, groundwater discharge features, and groundwater flow media. The groundwater flow regime was not changed during the testing versus historical operation of the basin. The actual flow conditions were included in the letter revised March 23, 2020, "Hydrogeolocgic Certification...". No conditions were changed since the approved permit WQ0029945, except well water was added to the treated wastewater effluent to maintain the target loading rates for the testing. The drains provided a pumped line sink surrounding Basin 2 (Figure 6F, Water Level Equipotential Winter, Wet Year). The groundwater from the drain was pumped to Silver Lake as restoration to the hydrologic cycle. 7. Provide modeling results of the mounding analysis to predict the level of the seasonal high-water table after increased wastewater application. This testing performed was a field test and the water levels were measured versus analyzed in a mounding analysis. This test was completed from December 2019 to February 2020 (Seasonal high-water period due to minimal evapotranspiration). Mounding analysis was not performed and was not included or required in the approved pilot fetter plan, Please see answer to Item 13 also. 8. Identify the source of the rainfall data provided in the application. Rainfall data was collected by ONWASA staff at the ONWASA Summerhouse WWTP during the period coinciding with the testing_ 9, Indicate what equipment was utilized to obtain water elevation data_ Data loggers were programed to provide level data for every four-hour interval from November 2019 into January 2020. Data loggers were Eijkelkamp Micro Divers (4 ea.) pressure range up to 10 psi in Basin 2 and each of the piezometers 10. Indicate the depth of Basin #2 relative to mean sea level, or another datum at the site (if known). The original hydrogeologic report recommended that Basin 2 (Pond 6 in the 2006 Report) be excavated to an elevation of 3 feet above mean sea level. Pa6r: 3 0f 4 11, Address if additional measurements were obtained after January 10, 2020 to observe the Groundwater Pump Station Data to equalize. Additional data was not collected after January 10, 2020. 12. Provide the MODELOW modeling results of the increased loading rate during the pilot study. MODFLOW modeling of the increased loading rate during the pilot testing was not proposed nor required as part of the approved testing plan. The testing plan was a straightforward capacity test on an existing infiltration basin that provides a field result versus a modeled result. 13. As indicated in the approved pilot study proposal, provide a comparison of the pilot test results to the original MODFLOW modeling results for the basin. The measured maximum water level was achieved during the test period when the basin was loaded at 145,000 gallons per day during the Month of December, which is typically the time for seasonal high-water table conditions in this area (lowest evapotranspiration). The original MODFLOW model for this basin indicated a capacity of 132,287 gallons per day (note: in the original model Basin 2 was referred to as Pond 6), The predicted water table elevation in the original MODFLOW modeling was 9.89 feet above mean sea level (see attached report) at Day 750 of the model simulation. The load testing performed for certification in this project revealed a stabilized water level at 8.5 feet above mean sea level for a loading rate of 145,000 gallons per day. Thus, Basin 2 is now certified for 145,000 gpd by Ed Andrews as provided in the certification document submitted with the permit modification request, If you have any questions regarding the attached information, please feel free to contact Carl Scharfe, PE with The Wooten Company at (919) 828-0531 or cscharFeC5?tiiewootencompany.coai7. This firm oversaw the work performed and is under contract with ONWASA for that purpose. Encl: Sincerely, David M. Mohr, PE Chief Operations Officer ONWASA Cc� Carl Scharfe, PE, The Wooten Company Page 4 of 4 i;�V! ?4FVWAT�i, i;0IJ,EUW.% ni'3CHARGE 'AAIN Fi±rIq ;WC:R'; IT,"". ON J J 7' 45 EL ' r 8•' LF�'w CCHIf �Inl, �3TEu �, 9' GLR'MEp ,PATER � � b 'I RI.L NE BY OTHERS ___ - f •r 4 �r A H fAppIRCATSgNS {Po 41 0 ell 4r 4 � � �" '� MODIFlCATiOHS [Po EXISTING DRAIN SYSTEM A. 1 _ � 11E Fk�l! IN HASlulr. 5.Y311! ,ps V:ELs. 1 - r S,%mp LU[J.TED INSI M L}DX FDA? G4 LES EXISTING DRAIN SYSTEM L + ' A' r r — `�L 4 fiJ -'L� , 'AH dIGW MET N +AA% WATER L6a ELkv �I ��� ♦ �lNFi TRdTfLlh �,1GI+i !- YY'Fil 4F BER4 ELEf! 11.0' _ 1 l I � � BOTfpM 9F EV.:IN r ELEV. rt 6' I INFILTRATION BASIN #2 j ` �Z � I _ +An:]IFEb EviaH SHAaE f AW, �oim l LABEL3 WETTED AREA - 2.8 AC I P-1 w I J ! RECUJMEO WATER '3X.N SEE • P-2 EXISTING GROUNDWATER I ii I f4grE ON PA1 (T' . 3 PLACES) r —�- P-3 LOWERING PUMP STATION y ! ♦�- , . I II- '13 - �—• - .. �� G� 3 R I --J A PLUPA N _ ■ �CLA: ANTI SEE*' CnLLn^ ♦ ♦ ' .t ITYF b fN Ci7+1TET,'' Tr;'E II C.LEAO (TYP. 2LIL' 014 ENTFP; _ \ �� Trs'E I �'LFAH rr TV t7E INSTALLS 4T ALL 96 9E%ND ANr TECS ALUNCa 1 - f GROUNOWATER OLLECTIOIJ EXISTING DRAIN SYSTEM sA,Ny _ LOCATION OF PIEZOMETERS FOR 11/25/19 � DRTlas oNAYxNc IeAs em. MOOIF[➢ m Af3lICT CNANCiS - t EXISTING DRAIN SYSTEM TO 1/10/20 BASIN 2 PILOT TEST LOADING YAOE NFfNG CUNSira Vpm 9AE0 uro THE INFWmATON FNOYM 9T THE C WACTON AND MI NOT NWN RUJ3 YINVED. mE OvWiE S WEAL 00M Nor Cff Y" A E THE WOOTEN COMPANY, 2020 A ACY OF TKS ORAAWG. THE MOACT WAS eursraucrA IN A4AAL C 'QA,Awx WTH THe pews THE WOOTEN COMPANY, 2020 RS 095{RYID TNAOI YEHOOIC 09SPVATON PE]FO INFO OT nq EHPEEN'S wtHCm= RUTISS ITATM xk �` SUMMERHOUSE 6ATE AUGUST201, SCALE � NNW. A O9a1-O63S _ ��TT}}���� ((fi�� nn WATER RECLAMATION FACILITY oR. ��-IZ-M g Sr"•+ !1\1L►'141,1J 4� REHABIUTATION uftafn mN ``r 17,30 voral[y Drive, Suite SOD �YEo � -��n�A� C3 by RoiaigN. North Corolino 276M CI\4L IN- YIGN. Awe NA ' s4 Phone: (919)233-8091, Fox: (919)233-9031 n.` �, uemnaar F-1222 Onslow Water& Sewer Authority INFILTRATION BASIN #2 # " ° a y PLAN RMED � oomsmcnm -2 www mcMimcreed�cm E1ECTR1cAL coxoun - a cawOLr II L' - I~(WP RB_pTPa_)nA_L_E TJIII TEE WITH cI"AP QUI CK <VEnT *EAaE''ALE 6` MOTORIZED (Tw) CORRECT vTH snarvcE OR cINTO CONRRETEAe"00 BExD -_ 24" MANHOLE aGNERt 6^ wUTCHI uuxSLPE aowME,ER i zcs _r- 6^DI PIPE — --/ L-------——��ur----i —-------- 2L6 —J= �— ---- �� TH L--- >'I V\ i e xa TEE x / xfo / Boo, ( w) , ,/z' SUMP PUMP - _ - FROM VAULT � .. � a DIFCnARGE - L - it " GLIDE BAR L 6 Wx6 Lxsu (IF_, uluExsoNsjT MIx. COUPLING ADAPTER nTE r r (BCH.1 G S .) DDPLINIBLE E 6 w.s L.o'oo(INSIDE DI IIousjT Mlx. Aa KIFr uI �j ADAPTER(TYR) NOTES: ALL PUMP STATION PIPING SHALL BE FLANGED -END TO PLAIN -END D.I.P.. UNLESS (VALVE VAULT ROTATED BO' FLANGEDSUNLESS OT"THEHERWTSEALL NOTEDnNG6 ANO VALVES SHALL BE FLANGED x 2. ALL FITTING$ INSIDE WETWELL AND VALVE VAULT SHALL BE FLANGED AND 1 - PLAN - GROUNDWATER CONTROL PUMP STATION #2 3. a LL PI PE OPENINGS IMINIMUM E�L AIND VALVE VAULT SHALL BE CORED AND )i, = V-0^ FILLED W,LH NEOPRENE RUBBER BOOTS, 4, VALVE VAULT PIPING SHALL BE SUPPORTED WITH MASONRY SUPPORTS AS SHOWN 5, FOR ORIENTATION OF WETWELL AND VALVE VAULT SEE PUMP STATION SITE CRANE LE DAVIT 6. COORDINATE SIZE AND QUANTITYOF ELECTRICAL CONTROL CONDUITS WITH ELECTRICAL DRAWN - ""AST 111' "IN INTO CO 5 AB CONCRETE SLAB, GOD V. SEE ELECTRICADRAWINGS CNAL WETWELL�AND VALOVEINSTRUMENTATION P PING PENELOCATIONS TRAlI0N6 AND OORNLTOCKABLE) CONNECTIONS. e RIERSETRNGAPLAN PROVIDED BY THE APPROVED PUMP MANUFACNRER. TO ACCESS OR (LOCKABLE)ALUMINUM C FRAME INTO CONCRETE SLAB PRE-E WITH 6O 5.5.) LCNCRETA TOP EN (FEE BRAL sPECIFICanONS) IRE -CAST 'AL ELEC caBLE HOLDER IF.S)Ax�\\) PUP UP 5'-O'MIN. CONCRETE EL. 5.O 9.0 TOP OF IONCRETE EL - SO. CONCRETE EL9 CIAC EL 90 11. PRE CIAD r E PE s TIE , o GR a In_ ° D CHECK T owPLING ADAPTER .21 PVC PIPE 1 ,Mp^ P R EPA` IFREASERALL A. DIP TO SPICER LAKE CONTROL VALVE IN,= HIGH WATER ALARM EL = 5.5' - - - - - - - VAULT MODIFlCAlI0N8 INV. EL 10 DWG. C9) LAG PUMP ON EL = 6D' BALL CHECK VALVE LEAD PUMP ON EL = 6.5' A a. LIMP PUMP A vIZED LEVEL CONTROL FL(Typ Sa` 9) SLOVE LO SUMP PIT -RID HOLD ROUT I REPIAC 6 PCA CA IPE LIMP DISCHARGE MAGN TO BOOTNEOPR(TNw)RUBBER ADAD 3 PVC SON_ _ TO �APT(BEHIrvO) FLOW METER LL PUMPS OFF EL. = 1.5' N 6' STONE BASE 5 F. DU FUNBY PUMP MANU EO ARWnD TER L r CABRLE (PROVIDED 6" STONE 845E RE FLOW M PREcnsT EASE. LOW WATER EVE r T A PIP GATE VALVE C.BRA WASTI.ATER PUMPS SIT SPECIFICATIONS FOR DUTY POINTS Gw CODECTOR PIPE - TOP OF SLAB EL�RL LL.5- -OAID CJ F (P ov1DET. 0Bv PUMPDISCHARGEcCURER)TON OICKETE TR BALLAST FT TO SUKIIBA'S1E (0-0 50 OD) r.r �r r lED AR ENDED BaSERECAsi " M2 C CIA l E .IN 6 STONE LHGKNEs INLEGRAL fLDAi COx1RCL tin (' �'ND 2 - SECTION 0 GROUNDWATER CONTROL PUMP STATION #2 SH R.L ♦ D SUMMERHOUSE E w WATER RECLAMATION FACILITY ..w �I"1 REHABILITATION A �C6 1 )30 Varsit, Drive, Suite 500 ; i D mR �EBn'�o nleigx, ND Carolina 27606 CIVIL tyn �Y Ph— (9191)233-6091, Fax: (919)233-8031 - 222 0 low Water @ ScweAwhvriLy GROUNDWATER CONTROL PUMP STATION R�gp carsmucnorre�a B.c #2 PLAN AND SECTION s ump �,~I6 AIR�PP�LL PLAN VIEW Row Arvo PRCPERTr un[s { f DESI—ED WETLANDS " AIR CAR SIN 0 WELL 21-0 a INE MTMREFE"'o GRADE DETES. G PLAIN ) G-RIACT 1— E WE E OTHER LIKES Env. = x6.D sVE 0 FEAR FILTER AL A R, Irvv. ELTv.:3., AGGREGATE ED— OF EASIN INv. E[V. RUFFER FDOT A A FIu FOR F cROIHED ITONE FAZE (aPPRoxIMATELv P<o) MONPC OUTHIc EASE PERFORATIONS DOM NOTE: ASTETE ANTI ITCH caLAR STONE FAST ANCHOR TTE MATERIAL AS ELECTR CAL RKT(INCLUDING CONDUIT SECTION VIEW ENGINEER. MIRAF _ N OR v APPROVED PERFORMED DNDER CONTRACT No. I 50 Ml1I1U1 FRO' MIX WATER SURFACE ELEVATION TO PERFORATED DRAIN PIPE INFILTRATION BASIN #1 INFLUENT STRUCTURE NOT TO SCALE 3x3x12 THICK �PP�SUIRCRTT I 2 �oollcH cSUHE°�I ANICALSEAL Ow�TERMNE AO.NMMMMAX INN.VI.: NEO0N TFTIOe 'FPss EWEIL U, RD S7OWISTCETRB sECLGEK,V L -, PLAN VIEW 6� ROw6AND PROPERTI uNED � � DESIGNATED WETANDS e.D SIN 2 WEIF D_DTED -aLL= EED22ATIONS R- RECLAIM ATER LIKE TRUE10CAnRE ON a `FORDINFILTRATION N' LTW-2D NOTE: CRUSHED STONE EASE (A11ao—A-1 <o') Ru6FER FDGT ALL N' 77 MR, (wc rt 1. PLACE ANCHOR HAD CONCRETE ANTI SEEP COLOR u0N0—I'CI EasE 'ILL DO PERFORMED UNDER C 1 SECTION VIEW ELEVAnON To INFILTRATION BASIN #2 INFLUENT STRUCTURE NOT TO SCALE 2- SRGE LINE E RECLAIMED WATER LINE imo ON BASIN ,IP. WITH CHECKH. 80 VALVEVC AND TRUE UNION IRIISITE DDHTRACTOR SO LINE�OII s"'T II LocKIDLE ALUMINUM I A FILco HATCH WITH FHEDN VAL, AND TRDE _PH ADAPTER C.0 L — OF2)°" REPLACED E%IST. 6 EVALVEw oA ACTUATOR - PIPE wPPPoai TwE E o we WITH uInIT S—OHEIP(Tw OFV) -Dv �_Iy i F - s REPIACE EIM QR AL1VAl0R REPLACED CONTROL VALVE 1=u=1Il 6 SUMP (REFER 10 SPECS) IM C4 ACTUA T-TyI MECHANICAL SEAL - - ACTUATED PLUG VALVE (iYP Of 10) 9JMP PUMP LIMIT SWITCHES (T P Of 2) AND BOAT SNITCHES WH COIRING REPLACED AS REV'D. INTEGRAL FLOAT 1ATc AOAHTER (Tw OF 2) PLAN VIEW SECTION VIEW A.29 INFILTRATION BASIN #1: VALVE VAULT SO—: PLAN VIEW INTEGRAL FLOAT21) NA tlAOrl RI 6• sM' , Fpp SUMP PUMP 6 sumP AND BOAT UE .1 . SWITCH ITISR REPIACEDAS RED'D. S.- SECTION VIEW INFILTRATION BASIN #2: VALVE VAULT SCALE : 1/-V-o- XVVUX4VY `RAM —ECT WAS PVC a BASIN M SUMMERHOUSE E )Nw WATER RECLAMATION FACILITY REHABILITATION A C41)30 Varsit, Drive, Suite 500 AS o mR �Rn �o alaigN, No Carolina 27606 CIVIL tyn �H Ph— (9191)233-6091, Fax: (919)233-8031 - zzz Omlow Wa a & SDwe AMlhonl, A INFILTRATION BASIN DETAILS REVSm AFTER corismucnal � a EWUPWR aCP 2 11 YDROGF.OLOLiY GFOLOGY EDW tN ANDR E, WS & ASSOCIATES, P.C. CONSULTING HYDROGEOLOGISTS P.O. BOX 30653 RALEIGi1, N.C. 27622 - 0653 PHONE: (M) 783 - 9395 FAX: (919) 783 - 015l April 3, 2006 Mr. Timothy T. Baldwin, P.E. McKim & Creed, P.A. 200 MacKenan Court Suite 200 Cary, N.C. 27511 Re: Site Evaluation - Sumnlerliause on Everett Bay Onslow County, North Carolina Dear Mr. Baldwin. FNVMONmEN I ALKIENVFS SOILS Attached is the final report for the two infiltration basins that Dr. Rubin and I evaluated. This report supports your design for the disposal system at Bogue Watch, The loading of 400,000 gallons per clay can be accomplished safely using four infiltration basins comprising at least 8.36 acres.disposal system : • - •,`- a-.; _ sr,7; ,y111;111I111l1��� r If you have any questions please contact my office. ='� ` `t_-`; ti ���-*-\STEIaLfC' Very truly yours, a � ' �° , I-��4 b � o� Edwin Andrews & Associates, P.C.'f _ _ r _. = y`r,' s-ea�ae�^y NN 11110 Edwin E. Andrews III, P.G., N.C.L.S.S. Consulting}r '3 Hydragealogist and Soil Scientist=�t =: :� r ` yr,= `r s 1 .���_ ,-,:�' �JW 1226 Dr. A. R. Rubin, Senior Environmental Scientist McKim & Creed, P.A. encl. Table of Contents 1.0 Introduction: 1-1 1.1 Statement of Purpose 1-1 1.2 Regulatory Requirements 1-2 1.3 Background 1-3 1.4 Project Location 1-4 1.5 Scope of WorluTield Mcthodology 1-5 1.6 Management Considerations 1-6 2.0 Soils and Geology: 2-1 2.1 SCS Soil Description 2-1 2.2 Soil Descriptions 2-2 2.3 Geology 2-3 2.4 Agronomic Analysis 2-4 3.0 Hydrogeology: 3-1 3.1 General Hydrology 3-1 3.2 Water Table Contour 3-2 3.3 Unsaturated Thickness Mapping 3-2 3.4 Aquifer Hydrology 3-3 3.5 Modflow Simulation 3-4 4.0 Conclusions and Recommendations: 4-1 4.1 Conclusions 4-1 4.2 Recommendations 4-2 4.3 Limitations 4-3 LIST OF FIGURES AND TABLES ALL FIGURES - APPENDIX A FIG. I SITE MAP Appendix FIG. 2 SOIL MAP Appendix FIG, 3 UNSATURATED THICKNESS MAP Appendix FIG. 4 WATER TABLE CONTOUR MAP Appendix FIG. 5A-H CALIBRATION FIG, 6 A-E WATER LEVEL MODEL RESULTS Appendix FIG. 7 A-E MODEL MOUNDING RESULTS Appendix FIG, S A-E NITRATE MODEL RESULTS Appendix ALL TABLES - APPENDIX A TABLE 1 - Soil Descriptions Appendix TABLE 2 - Lithology Log Appendix TABLE 3 - Ksat Analyses Appendix TABLE 4 - Water Level Data Appendix TABLE 5 - Aquifer Test Analysis Appendix GEOTECHNICAL DATA APPENDIX COMPLETION REPORTS APPENDIX COMPLETION REPORTS APPDNDIX SUINTMERHOUSE ON EYERETr BAl' ONSLOW COUNTY, NORTH CAROLINA PROJECT EAA wRIII 0106 1.0 - INTRODUCTION: 1.1 Statement of Purpose: The objective of this analysis is to provide design engineers, McKim & Creed Engineering with reconmiendations for land disposal of reclaimed water, based on site characteristics, for the development Summerhouse on Everett Bay, Onslow County, N.0 . This analysis characterizes the soil, geology and aquifer hydrology that influences our recommendations for design. The recommendations utilize options that comply with the requirements of the North Carolina Division of Water Quality, Aquifer Protection Section 15A NCAC ,0200. A preliminary investigation of the site was performed by Dr. A. R. Rubin, McKirn & Creed Engineers, to determine disposal options (see attached report). Dr. Rubin identified areas that were suitable as receiver sites for land application of highly treated effluent with nutrient reduction. The selected method for disposal is the use of two Infiltration Ponds. Two specific sites were selected for detailed soil and hydrogeologic investigation, in conjunction with recommendations by Dr. Rubin. The capacity of the site to accommodate land application of reclaimed water using infiltration Ponds was analyzed at two proposed pond locations. Ponds 4 5, would have a loaded area of 5.59 acres; and Ponds 46, an area of 2.76 acres (design maximum water level). This evaluation recommends the construction of two separate infiltration ponds capable of infiltrating approximately 400,000 gallons per day at a loading rate of 1.1 gallons per day per square foot on 8.36 acres. In order to minimize the mounding, the flow was divided into two hydraulically isolated Ponds. Pond # 5 has a loading rate 1.1 gallons per day per square foot for 267,713 gallons per day. Pond # 6 has a loading rate of 1.1 gallons per day per square foot for 132,287 gallons per day, The field work supporting this evaluation includes soils analyses by Edwin Andrews & Associates, SUMMERHOUSE ON EVERETT BAN' ONSLONV COUNTY, NORTH CAROLINA PROJECT EAA IYRIR 0106 P.C. with a site assessment by Dr. A. R. Rubin, McKin-i & Creed Engineers. Disposal using infiltration is predicated on further nutrient reduction at the reclaimed water facility so that the risk of groundwater contamination at the compliance boundary is eliminated. It is feasible that the infiltration ponds will ultimately act as wet weather storage ponds for water reuse on common areas if future regulations permit use. 1.2 Regulatoiy Requirements: The proposed system will operate under a Non -Discharge Permit issued by the State of North Carolina Department of Environment, Health, and Natural Resources, (Division of Water Quality, Aquifer Protection Section). Applicable regulations governing the infiltration alternative are included in 15 A NCAC 211.0200 - Waste Not Discharged to Surface Waters, effective May 2000, and 15 A NCAC 2L - Ground Water Classifications and Standards. Requirements relating to soil and hydrogeologic characteristics of the site include a hydrogeologic and lithologic description of the site to depth of 20 feet [(5)(e)]. Transmissivity and specific yield were determined for the unconfined aquifer based on tlu•ce withdrawal tests [(5) (f)], 15A A NCAC .0205 also addresses design specifications to be provided by a professional engineer. 15A A NCAC 2H. 0400 addresses aerial limitations and engineering requirements for this type of facility and 15A A NCAC 2L addresses Compliance Boundaries and the maximum allowable concentrations of substances discharged to ground -water from this type of facility. Since there is nutrient reduction in the treatment process, groundwater contamination should not occur at the review or compliance boundaries as regulated in 15A NCAC 2L. 1-2 SUM11ERHOUSE ON EVERETI' IIAY ONSLOW COUNTY, NORTH CAROLINA PROJECI' EAA WHIR 0106 1.3 Background (Dr. A. R. Rubin - full report in Appendix): A total of eight (8) potential areas were examined as potential wastewater receiver areas. Four (4) were ultimately selected as designated receiver areas for the reclaimed water. The proposed receiver areas are located on the map attached. These areas are presently hosting woody vegetation and tine cropping system will be removed to accommodate the reclaimed water through the Ponds system. The agronomic assessment and associated plan are necessary to assure adequate vegetation is present on the banks and in terrace areas in these Ponds to minimize sediment losses and to provide stable areas for infiltration. A second potential use for the reclaimed water is berm landscape irrigation with reuse quality water. Finally, an agronomic assessment is also required to assure liquid generated from pumping site drainage is assimilated on terraces near the site boundary. Beneficial reuse of the treated wastewater on the connmon-lands and residential landscaped areas, and the series of infiltration Pondss to serve as an all season system capable of recharging shallow groundwater all provide excellent potential treatment for domestic and commercial wastewater generated on the site. This type of conjunctive system is serving residential, commercial, industrial, and agricultural operations throughout the southeast very successfully. The site and soil conditions encountered on the designated wastewater receiver sites are well suited for the development of this conjunctive type of wastewater system. There are two purposes to the brief report which follows. Tine first is to describe the results of the soil testing accomplished on the site. The second is to provide recommendations forthe cropping system that serves as stabilizing crops oil berms and otherreceiver areas for this liquid. In addition to requirements imposed by close proximity to sensitive receiver waters, land based wastewater treatment andrenovation systems exhibit a variety of characteristics considered favorable for treatment of wastewater. These include: 1-3 SUMMERHOUSE ON EVERETI' IIAY ONSLOW COUNTY, NORTH CAROLINA PROJECT EAA WRIR 0106 1. Excellent potential to recycle and reuse treated liquid on high value landscaped sites and in aesthetic impoundments incorporated into the local landscape 2. Necessity to provide vegetation to stabilize areas with made -land (berms and embankments, terraces, etc.). 1.3 Project Location: The site is located North of Everett Bay, on the south side of State Route 1534 (Holly Ridge Rd.) from Holly Ridge, Onslow County, N.C. (Figure Number 1 A, Site Location Map). The North Carolina Planar Coordinates for the site [V are approximately 2,455,200 feet East and 271,872 feet North (entrance to the site). The site maintains the geomorphic characteristic of the lower Coastal Plain region of North Carolina. According to the Soils Map of Onslow County the area consists of the interlluvial deposits and associated drainage features to the Intracoastal Waterway (Everett Bay and Spicers Bay) , and Kings Creek influences drainage to the west of the site. The slopes range from nearly level to more than 4 percent on the proposed area to be irrigated. The site has elevations extending to 40 feet above sea level. The site is drained by unnamed tributaries leading to Kings Creek to the west, Spicers Bay to the south and to the Everett Bay to the southeast. 1-4 SUMMERHOUSE ON ENIME•IT RAY O\SLOW COUNTY, NORTH CAROLINA P110JE,CT EAA NVRIR 0106 1.4 Scope of WorlL/Field Methodology: The scope of this project includes the collection of all surficial and subsurface data necessary to characterize the site based on site specific hydrologic and soil functions relative to the proposed use of infiltration ponds. Site specific aqui fer testing was made within the scope of this investigation near Pond # 5, (Aquifer Test Site 1 and 2) and Pond 4 6 (Aquifer Test Site 3). Based on aquifer testing, a detailed aquifer analysis has been developed for water management on the site. Information used to develop aquifer coefficients and values for the underlying sand (water table) aquifer was from the aquifer tests, and generally confirmed by the water table contour. This information was subjectively compared and calibrated with overall site characteristics. A series of MODFLOW simulations compared the measured water table surface to the expected steady state conditions, with average seasonal evapotranspiration, The loading model included in this evaluation contained the same rainfall and evapotranspiration values used in the water balance analysis. A subsequent analysis was performed using evapotranspiration values from the Wilmington area (nearest published values) and evaporation data from Aurora (from infiltration ponds). Field work for this study consisted of the installation of twenty hand borings, completed as temporary piezometers, six test wells, and aquifer testing. The horizontal and vertical controls for the observation points were surveyed and static levels were measured. A soil snap has been prepared with a description of each typical soil (Pedon) for each map unit. Infiltration analyses (k,,,,) were attempted at two sites, using Compact Constant Head PernreametersTI, , however, the data is not included in this report because the soils will be removed from each infiltration pond (in both cases it was difficult to obtain readings because of the very high conductivity response) (Figure No. 1, Site Map). 1_5 SUMMERHOUSE ON EVERETT BAY ONSLOw COUNTY, NORTII CAROLINA PROJECI` EAA WRIB 0106 1.5 Management Considerations: This report analyzes current field data and field conditions observed during the study period and uses information collected to evaluate disposal options. Loading modeling and predictive methodology based on the field data document basic characteristics of the site that may limit loading, based on the soils and proximity to outlet drainage. This evaluation is based on the concept of using tertiary treatment, nutrient reduction and waste water disposal. The concept is to provide additional treatment and load the site at an infiltration rate of 1.1 gallons per day per square foot on 8.36 acres. Two pond sites have been designated as infiltration pond sites. The pond number 5 is surrounded by a drain constructed to 16 feet above mean sea level, and pond number 6 is surrounded by a drain at zero feet mean sea level. Because the ponds are an amenity, water level elevations will need to be maintained, using either a fresh water resource or controlling the outlet drain volume. Even though the loading rate for the sandy soil will be less than 1.5 gallons per day per square foot. soil plugging is anticipated in the infiltration pond. A maintenance plan is recommended for pond management, which should include potential bottom dredging. Maintenance and monitoring will need to be provided by treatment plant personnel to insure that the infiltration capacity remains optimized. This report is divided into segments pertaining to soils, hydrogeology (water table), and aquifer hydrology. Generally figures and tables are included in the text to help visualization, 8.5 by 11 or l l by 17 copies of the figures and larger tables are located in the appendix of this report for detail. 1 - 6 SUMMERHOUSE ON EVERETT RAY ONSLOw COUNTY, NORTH CAROLINA PROJECT LAA WRIR 0106 2.0 - SOILS AND GEOLOGY: 2.1 SCS Soil Description: The soils on this tract were clapped and described based on the classification of soils used in the published soil GIS data front the North Carolina Geographic Clearinghouse. In January 2006, Mr. Edwin Andrews, North Carolina Licensed Soil Scientist, and Dr. A. R. Rubin, McKim & Creed Engineers, analyzed the preliminary soil leap for the site to evaluate potential for reuse. A detailed soil map prepared by Edwin Andrews, N.C.L.S.S. was prepared for the immediate area that contains the disposal sites. The NRCS soil map prepared for the region contained Wando, and Onslow soils, (Figure No.2A, NRCS Soil Map). The site map containing the hifiltratioll Ponds shows these soils grouped, based oil drainage and landscape position, into two soil groups Wando fine sand and Onslow loamy fine sand (Figure No. 213, Soil Map). A series of twenty piezonleters and six test wells were used to form the basis for this analysis (Figure No. 1, Site Map - 11 by 17 inch Wrap attached). Because of limited availability of land, it was determined that Infiltration Ponds with associated drainage can be configured to both fit tile site plan and the drainage requirement. Soil boring locations for the soil descriptions identifying the areas investigated at soil boring profiles at Piezonicters 6, and 7 along with two additional borings (Hand Boring Number 21 and 22) are shown on the Soil Map (Figure No. 213, Soil Map). The attached soil map shows two soil series: Wando fine sand and Onslow loamy finc sand in the areas selected for infiltration Ponds. Basin # 5 area is predominantly Wrapped as Wando with small portions of Basin # 5 in the transition areas between Wando soils and Onslow soils (northern edge). Basin # 6 appears similar to Wando fine sand with a thin Bt horizon oil the southern edge of the site (Onslow loanly fine sand)(Figurc Number 2B, Soil Map - full scale map in appendix). The infiltration bonds were located based Oil preliminary soil mapping by Dr. A. R. Rubin, McKim & Creed Engineer's. The infiltration pond construction will remove the Still soh"n (A, B and upper 2-1 SUAUMERHOUSE oN EVEREIT BAY ONSLONN' COUNTY, NORTH CAROLINA PROJECT EAA WRIII 0106 C horizons) into the underlying sediments; therefore, aquifer hydrology, pond configuration and maintenance will affect the function of the infiltration system. Soil Descriptions: The soil profile description for each unit is based on the soil boring collected at the time of piezometer construction (Table No. 1, Soil Profile Descriptions). Small areas of different soil series Inay be present as inclusions on the project but were not mapped in the soil units for the sake of simplicity. SOIL MAP LEGEND BROWN BRICK NONE MUCKALEE LOAM TAN HATCH LI CPO/FT.' WANDO FINE SAND MAGENTA SLASH 1.1 GPDIFT' ONSLOW LOAMY FINE SAND GRAY EARTH NONE BOKICKET LOAM Soils found on the project range from the excessively well drained Wando tine sand, a thermic Typic Udipsamment, to a very poorly drained Bohicket loam (adjacent to Spiccrs Bay and Everett Bay), a thermic typic Sulfaquent. Soils found in between these two soils are the moderately well drained Onslow fine sandy loan, a thermic Spodic Paleudult; and poorly drained Muckalee loam, Typic Fluvaquent. The soils will be excavated in cacti of the pond areas, therefore there will be no additional treatment of effluent as the waste water migrates through the soils. The proposed disposal option will be to treat the wastewater to tertiary levels and to provide nutrient reduction; therefore, wastewater disposal usingthese infiltration Ponds should not degrade groundwater simulation was made, described later in this report, to further analyze the potential Soil Descriptions: Table No. 1 Soil Profile Description SUMMERIlOUSF ON EVERFI-I'RAY ONSLOW COVNTV, NORTl1 CAROLINA PROJECT EAA WRIB 0106 A — 0-5 inches; grayish brown (10YR 5/2) fine sand, single grain; loose; few fine roots CI — 5-16 inches; Yellowish brown 00YR 5/4) fine sand; single grain; loose; few fine roots C2-16-31 inches; brown (10Y 5/3) fine sand; single grain; loose; few soft nodules of dark yellowish brown (10YR 414), organic -coated sand C3 - 31-38 inches; white (10YR 8/2) fine sand; single grain; loose; C4 - 38-48 inches; very pale brown (10YR 7/4) fine sand loose C5 —48-72 inches; yellowish brown (10 YR 514) fine sand loose. Cg- 72-8480 inches; light gray (10YR 7/2) fine sand Soil Series: Wanda fine sand Landscape: Coastal Plain L.andform: Marine terrace parent Material: Littoral sediments Drainage Class: Well Particle Size Class: fine sand Temperature Regime: thermic Subgroup Classification: Typic Udipsamment Slope: 2% Boring at P-6, similar profiles found in borings near P-7, Ksat Site 5 and Ksat Site 7 (near B33) 2.3 Geolou: Surficial geology has been mapped as the Socastee Formation (Late Pleistocene). "`Tile Socastee Formation ...is composed mostly of interbedded sands and clays of backbarrier and barrier• origin, and contains a relatively immature sand mineral assemblage. The surface is marked by numerous wel I preserved barriers upon which Carolina Bays occur."' I - Chapter 17 entitled "Surficial Geology and Geomorphology" by David R. Soller and Hugh H. Mills in Tile Geology of the Carolinas, 1991, edited by J. Wright Horton, Jr. and Victor A. Zullo, University of Tennessee Press, Knoxville. 2-3 SUMMERHOUSE ON EVERETI' BAY ONSLOW COUNTY, NORTH CAROLtNA PROJECT EAA 1YRIO 0106 Regionally, the area is underlain by the Pleistocene Core Creek Formation, and the Upper Pliocene Bear Bluff and Duplin Formations (which correlates to the Middle Yorktown formation), unnamed sequences of the Eocene Castle Hayne Formation, and the late Cretaceous Pee Dee Formation. The surficial interfluvial terrace on this site is divided into the flood plain deposits, the well drained ridge deposits and the backland terraces associated with sediments deposited in lagoons, swamps and isolated wetlands. The Castle Hayne Aquifer, is a result of secondary permeability in the indurated limestone and sand. The Castle Hayne well yields are moderate to high to the east and southeast of the site supplying an alternative supply to Onslow County, Camp Lejuene, City of Jacksonville and the Town of Holly Ridge (See attached stratigraphic information). Regional well information has been gathered from North Carolina Division of Water Resources database (Hydrogeologic Framework). This conceptual model of the aquifer system combines the Pliestocene to recent sediments as a surficial DWR Hydrogeologic Fiarnewolk Detail foi Holly Ridge Homes 1 Dilta County Onslow Latitude 34.49444- Longitude -7T64166 Location Accuracy hlap gib, , Ivry Quad AA 26C Holly Ridge Home, Name 1 Deplh Land Surface Upper Tediwy CU Upper Tedimy Yorktown CU Yc Iktown Pungo River CU Pungo Rarer Castle Hayne CU Castle Hayne Beaufort CU Beaufort Peedee CU Peedee Black Creek CU Black Creek Upper Cape Fear CU Upper Cape Fear Lower Cape Feat CU Lower Cape Fear Lower Cretaceous CU Loner Crelacoous Basement Urd LP aI-Al ns a,a ah P.,n in table. 4&F {t•r are 1k w.n In prat 46000 65.00 10001 10001 100131 10001 10001 10001 23 1 10000 10000 W003 10003 1011M 10003 10003 10003 10003 kt1003' n:�o:-u�a la.r, e•��t;, t.ul n�f. i- n,.falr to rid etc. al,an. 1�� • I[4rrr1 - un,l dae,-1l , t 10000• ICrU�J und,-not terietraled 10003, In �,a. unillfely 4. Eu{,t r: n,f penetraSs6 Data from 2.6 miles to the west of the site surnr.lal [9 Upp1 It, liary cU F3Upper refllary t] Vorktmsn LU E1 riektonn a Nnyo Blacr cu 0 punyo Blau t] (:a$lle Ila)ne LU 8 Caa tre Ilay nc ® Bcauror t Cu ❑?—utO k r7 Peke CU n Iy,t&e 0 Black creek LU Q Blmk Ucck ® Upper Cape Fear CU ❑ Uppo Cape tear G Loner Cape fear CU Leader Cape Felr A L—cr Crelareoffa CU i Lotacr Creta[ceua U Basement aquiferand aquaclude matrix extending to the Castle Hayne Aquifer from theNorth Carolina Division of Water Resources database (Hydrogeologic Framework) (Fig. No. 2B, Database Download from 2-4 SUMMERHOUSE ON EYERETT BAY ONSLOW COUNTY, NORTH CAROLINA PRO.IECT EAA NVRIB 0106 the North Carolina Division of Water Resources). This modeling evaluation increased the aquifer thickness dimensions and reduced hydraulic conductivity to enable modeling using the same transmisslvity values to maintain modeling consistency (Table No. 2, Boring Logs - Geoteclinical Borings). TABLE NO. 2 LITHOLOGY LOG PW-1 ortli of Pond # 5 0-5 ft. Gray clayey topsoil 5-10 ft. Gray fine to medium well sorted sand 10-15 ft. Gray fine to medium well sorted sand 15-20 ft. Gray fine to mediuni well sorted sand PW-2 (Pond # 5) 0-3 ft. Dark brown clayey sand 3-14 ft. Gray fine to medium well sorted sand PW-3 (Pond # 6) 0-5 ft. Yellow fine to medium well sorted sand 5-10 ft. Gray fine to mediuni well sorted sand 10-16 ft. Gray fine to medium well sorted sail(] 17-15 ft. Gray clayey fine sand 2-5 SUMMERHOUSE ON EVERR'M' IIAY ONSLOw COUNTY, NORTH CAROLINA PROJECT EAA \VRIB 0106 2.4 Agronomic Analysis (This Section Prepared by Dr. A. R. Rubin): Wastewater Remediation: Treated domestic or mlmicipal wastewater will potentially be utilized in several ways. Water will be lost through transpiration by vegetation, evaporation from the vegetation and soils surface, and percolationtllrough the soil profile. Th is water will also enter nearby surface waters in wetlands and streams via lateral flow. Any excess nutrients in the wastewater wi 11 be treated through microbial processes, plant uptake, adsorption to soil solids, and biologically mediated chemical transformations (i.e. denitriflcation). The primary objective ofestablishing a wastewater spray field using vegetation is to effectively renovate the water through plant uptake and evapotranspiration to prevent nutrients and other unwanted constituents from enteringgroundwater. The pre-app I ication wastewater treatment proposed prov ides al I of these reqitirements and the land is to be used as a dispersal mechanism for the reclaimed water. A primary objective of the rapid infiltration portion of the project is to promote recharge ofthe steal low groutldwaterto maintain base flow into adiacent wetlands and to create aesthetically pleasing water vistas for residents of the community. Few vegetative species are well adapted for use in berms and terraces supportingthc Ponds. The plant species selected must be matched to specific sites where they exhibit optimal growth. Tllrfand grasscrops have served as an excellent stabilizing crop on many stmehrres associated with land treatment facilities throughout the southeast. Nutrients promote plant growth and microbiological activity in the soil and the liquid applied onto these areas will contain no essential mltricnts of concern in the receiver• environmcnt because oft}Ie pre-treatment This reclaimed water is basically a source of water for Ponds and common Iandscaped areas. The turf and plant materials established throughout the planned community will benefit fi•om irrigation. The reclaimed wastewater isan excellent irrigation resource forthe Holly Ridge community. Hybrid Bermudagrass and other warm season grasses or turf systems are capable of sequestering 300 lb PAN/ac/yr or higher under ideal management conditions, but the crop will not be managed aggressively and recommended loadings For 2-G SUMMERHOUSE ON EVERETT IBA V ONSLOw COUNTY, NOWHI CAROLINA PROJECT EAA wRIB 0106 the terrace areas alid the berm sideslopes and top are 80 pounds of Nitrogen per acre per year as a crop maintenance amendment. Ideal managenrentdoes include weed control and minimizing equipment traffic on the site especially following rainfall or irrigation events. The recommended liquid load ing onto beret sides avid tops is no more than 1.75 inches per acre per week as requ ired and this liquid loading can be added as required to support plant growth and development or potentially used throughout the planned community where reclaimed water- could be used. The recommendations specify the addition of the following essential Nutrients: A. 60 to 80 pounds of Plant Available Nitrogen (PAN) - Generally this is supplied as Ammonium Nitrate or slow release nitrogen. If the slow release nitrogen is available economically, then this is the reconunended nutrient. A very small portion ofPAN will be supplied through the wastewater irrigation system proposed. Supplemental requirements will be established as additional information is available concerning turf management areas. B. 40 pounds of Phosphorus - This is generally supplied as a phosphate compound. The phosphorus reconmlended is essential for root development. A very small portion of P will be supplied through irrigation, but supplements will be required to establish and maintain vegetation. C. 60 pounds of Potassium - Generally this is supplied as a salt of potassium such as potassium chloride. Potassium is essential for development of root, stem, and leaf tissue. Potassium mast be supplied as a supplement. D. 1.5 to 2 tons of Lime - Soil pH is very low. This low pH influences the availability of essential plant nutrients. The time recommended is required to facilitate the uptake of essential plant nutrients. 2-7 SUMMERHOUSE ON EVEHEYF BAY ONSLOW COUNTY, NORI.1I CAROLINA PROJECT EAA wRIB 0106 These nutrient additions should be supplied in the fall of the year and prior to any reseediIlg With the grass species recoIllmended in the section which follows. The plant nutrient deficiencies noted are severe and must be corrected soon. Maintenance of soil fertility is an important component of any land treatment operation and pond system operation. Without vegetation, the effectiveness of any land application operation is compromised and berm sideslopes are susceptible to erosion. The SAR of any irrigation water mist be determined and monitored. The SAR is calculated as the ratio of sodium (Na) to one halfthe square rootofcalcitini (Ca) and magnesium (Mg) with all concentrations expressed as equivalents. The SAR calculation is: SAR = Na/(Ca/2 + Mg/2) 2 (units in imeq/L) An SAR in excess of 10 is considered as an irrigation hazard and system operators must take special precautions to monitor salt levels of sodium in both irrigation water and soil. An SAR in excess of 7.5 is considered a mild irrigation hazard and operators should consider establishing a similar monitoring program, If the level of sodium in the soil exchange complex increases to a level over 10, then corrective measures such as gypsum addition should be implemented. At present no information is available concerning SAR, but once it is available, plans will be developed to address sodium issues if required (SAR is above 10). Since the Ponds rely on maintaining soil permeability, measures of SAR are important and must be accomplished soon after system operation begins. Soil Sodium: Another measure of sodium, completed for the soil, to determine potential problems with irrigation systems, is called the exchangeable sodium percentage (ESP). ESP is calculated as follows: 2-8 SUMMERHOUSE ON EVEREI"I' BAY ONSLOW COUNTY, NORTH CAROLINA PROJECT EAA WRI110106 ESP = Na/CEC x 100 Where: Na is an index value for sodium (North Carolina Agronomic Division B Soil Testing Indices) This calculation should result in data no greater than 10-15%. Soils with ESP values > 10-I5% can be remediated through under draining and adding soluble sources of Ca such as gypsum (CaSO.), being careful of manganese (Mn) & Mg deficiencies in plants. Ca/Mn and Ca/Mg ratios should be kept in balance. Excessive sodium in the soil system can lead to management problems in the future and affect the overall capacity of the site. Trace Metals The USEPA regulates the levels to which selected metals can accumulate on Rnywaste receiver site. Regulated metals have not been tested in reclaimed water at Holly Ridge, Zinc and Copper levels in the reclaimed wastewater must be tested to make sure that these constituents do not limit the capacity of the site for wastewater treatment. Nutrient Loadings Holly Ridge proposes to spray reclaimed wastewater on small areas of grass and landscaped areas near the proposed wastewater treatment facility and on common lands in the planned community. The sites were determined to have few hydraulic limitations. Nutrient loadings or recommendations necessary to establish and support vegetation on pond berms and sideslope areas, and in areas intended to receive the groundwater from the site drainage network are provided in Table 2. 2-9 SUMMERHOUSE ON EVERE'1'1' 13AY ONSLOW COUNTY, NORTH CAROLI,NA PROJECT FAA NVRn10106 Conclusions: The soil resources at Summerhouse on Everett Bay will be modified dramatically as the development proceeds. The agronomic plan provided is intended to guide the establishment and maintenance of vegetation important is stabilizing areas on the site involved with Table 1, Soil test results (as index values unless indicated), Holly Ridge Parameter Site 1 Site 2 Site 3 Site 4 OM % 0.3 0.5 0.7 1.3 CEC (meclfg) 5.4 5.9 6.3 7.1 pH (SU) 5.5 5.3 5.5 5.2 P 39 44 28 19 K 25 22 19 12 Ca % 44 49 52 55 Mg % 12 12 10 15 Zn 22 25 19 21 Cu 12 15 17 16 Na % 3% 0. 9% 1. 2% 0.7% Table 2, Recommended Nutrient and Lime Additions, a -asses and Agricultural Crops On Banks and Terraces, Holly Ridge Wastewater Receiver Sites (Units as Indicated) Nutrient Site 2 Site 2 Site 3 Site 4 N 60-80 60-80 60-80 60-80 P 20-40 20-40 20-40 20-40 K 40-60 40-60 40-60 40-60 Li is 1.5 1.7 1.5 2.0 wastewater management. Agronomic considerations are most critical where liquid is provided as an irrigation resource. The nutrient and lime recommendations provided are intended to satisfy plant nutrient requirements on those portions of the site important to support the wastewater infrastructure, but not involved in the dispersal of treated liquid. The infiltration Ponds require no nutrient loading or supplements. 2-10 SUMMERHOUSE ON EYERM'r 11AY ONSLOw COUNTY, NORTH CAROLINA PROJECT EAA WRIB 0106 3.0 - HYDROGEOLOGY: 3.1 General Hydrology: The hydrogeology portion of this evaluation focuses on the ability of the treated wastewater to drain into and through the soil, then laterally into the hydrologic cycle in an environmentally appropriate method. The initial downward movement is characterized by infiltration rates (often defined as K,,t), During infiltration, water gravity drains from the infiltration pond through saturated interstices into the water table aquifer. As the water reaches the water table surface, the water table surface will be rising as a result of the new water (mounding). However, the soils tested by using Compact Constant Head Permeameter" for Ksat Analyses will be excavated during the pond construction (Table No. 3A - 3D, Ksat Analyses). All of the soil horizons wi I be excavated, minimizing the influence that restrictive cemented horizons would have on Nvater movement. The Bli horizons associated with the Onslow soils that are near each pond will be excavated. The underlying surficial sand appeared to be uniform beneath both ponds. The saturated flow beneath the surface has been quantified by direct aquifer testing. The determination of the aquifer coefficients of the surficial aquifer were used to develop a modeled simulation of the system. The surficial aquifer is bound by a confining layer that is present below 16 to 21 feet and the ground water surface (Water table surface) at equilibrium with atmospheric pressure. The water level fluctuates as a function of recharge (typically rainfall), and discharge by either evapotranspiration or base flow to surrounding surface water streams. The height and shape of the water table surface is a function of the aquifer coefficients, recharge and outlets, therefore the measured water level elevations provide confirmation of the conceptual made] prior to computer simulation. 3- 1 SUMMERHOUSE ON EVERETT BAY ONSLOw COUNTY, NORTH CAROLINA PROJECT EAA wRIB 0106 3.2 Water Table Contour Surface: The water table surface is generally influenced by heterogeneity in the soil matrix, recharge, water table aquifer characteristics, surface drainage and near surface permeability. The water table synoptic was affected by rainfall and topography (Table # 4, Water Table Data) (Figure No. 3, Water Table Contour Map). The water table contour map shows the influence of Kings Creek to the west and Spicer Bay and Everett Bay to the south. This water table information was used to calibrate the model for non loading conditions. The MODFLOW simulation in this evaluation considers the rainfall and evapotranspiration as dynamic variables. The calibration to the synoptic surface does not reflect all of the drainage and evapotranspiration fluctuations encountered during the winter. Generally, the piezometers used in the preparation of the water table contour map serve as the basis for calibration for the MODFLOW simulation, allowing for seasonal evapotranspiration, average rainfall and estimated drain conductance for the streams. 3.3 Unsaturated Thickness Mapping; After construction of twenty piezometers, the depth to water and the water table contour was determined from a synoptic measurement (February 5, 2006) (Table # 4, Water Table Data). The depth to water (unsaturated thickness) provides an indication that the infiltration pond surface may need additional fresh water to maintain a visually suitable surface elevation. The water levels reflected conditions similar to seasonal high conditions expected in February, (Figure No. 4, Depth to Water Table Map). The depth to water was greater than three feet below land surface at most of the piezometer sites. Actual isopach thickness contours reflect localized surface features such as line sinks or ditches that run through the site. Generally, during the spring, summer, and fall months the depth to water may increase due to regional evapotranspiration (upward). The depth to water during February reflects lateral movement as defined using the Darcy Equation. 3- 2 SUMMERHOUSE ON EVERETT BAY ONSLOw COUNTY, NORTII CAROLINA PROJECT EAA NVR1I1 0106 3.4 Aquifer Hydrology: The surficial aquifer was tested at three sites, with two tests in the vicinity of tile proposed infiltration Pond Number 5 Site and one at Pond Number 6 (February 4-14, 2006). This information was used to define regional conditions for areas around the Infiltration Pond Sites. The first aquifer test was completed north of Basin No. 5 (Figure No. 1, Site Map); the second aquifer test site was completed in Pond Number 5; and the third aquifer test site was completed near Pond Number 6. At the site north of Pond Number 5, the test wells were drilled to a depth of 21 feet with screen settings from 14 to 19 feet (Table No. 5A, Aquifer Test No. 1). The observation well was located 21.5 feet from thepumping well, which was pumped at 4.5 gallons per minute for 1,730 minutes. The transmissivity was calculated to be 274 square feet per day, and the hydraulic conductivity was calculated to be I3.7 feet per day for a 20 foot thick aquifer, and the specific yield was calculated to be 0.07 (dimensionless). These coefficients were selected as initial values for model calibration for the areas mapped as Onslow soils. The second aquifer test was completed on February 6, 2006 in an area mapped as transitional similar to Onslow and Wando soils at Pond 5, Pond # 5 (Figure No. 1, Site Map). The test wells were drilled to a depth of 19 feet with screen settings from 14 to 19 feet (Table No. 5C, Aquifer Test 2). The observation well was located 20 feet from the pumping well, which was pumped at 14.5 gallons per ininute for 1,440 minutes. The transmissivity was calculated to be 279 square feet per day; the Hydraulic conductivity was calculated to be 14.7 feet per day for a 19 foot thick aquifer, and the specific yield was calculated to be 0.244 (dimensionless). These coefficients were selected as initial values for model calibration for the areas mapped as both Wando and Onslow soils. The third aquifer test was completed in an area slapped as Wanda soils at Pond # 6 (Figure No. 1, Site 3- 3 SUMMERHOUSE ON EVERETT BAY ONSLOw COUNTY, NORTH CAROLINA PROJECT EAA WRIB 0106 Map). The test wells were drilled to a depth of21 feet with screen settings fron-i13 to 18 feet (Table No. 5D, Aquifer Test 3). The observation well was located 20 feet from the pumping well, which was pumped at 5.0 gallons per minute for 1400 minutes. The transmissivity was calculated to be 242 square feet per day; the hydraulic conductivity was calculated to be 11.5 feet per day for a 21 foot thick aquifer; and the specific yield was calculated to be 0.168 (dimensionless). These measured coefficients were used to build the conceptual model as the first step in constructing a computer simulation. The process of calibration compares these measured water level elevations to computed water levels using these aquifer coefficients. 3.5 Modlfow Simulation: The disposal of highly treated wastewater using infiltration Ponds has been simulated for this evaluation using Visual Modflow'- comprised of Modflow and MT3D solute transport fora 20 year period. To establish meaningful coefficients for this modeling effort, the model was built using coefficients determined from the aquifer testing, then refined by calibration to the measured water levels collected on February 4, 2006. The model consisted of a three layer grid with a total of 23,368 cells covering a regional area 12,000 feet by 7,500 feet. The Summerhouse on Everett Bay site is generally in the center of the model (Figure No. 5A, Calibration Grid). A steady state simulation was completed using seasonal rainfall and evapotranspiration conditions. The calibration usingthe 20 piezolneters had a root mean squared error 1.527 ft. with a normalized root mean squared error of6.299% (Figure No. 513 - 5F, Calibration Graph and Maps). The calibration was completed with a conductivity of 9 feet per day for the Wando soils, and 8 feet per day for the Onslow soils in the areas containing the Pond 4 5 and Pond # 6 (Figures No. 5D, and 5E, Conductivities) Using the calibrated results a transient state model was prepared for a 20 year operation of the two 3- 4 SLTMMERIlOUSE ON EVERETT BA1' ONSI.Ow COUNTY, NORTH CAROLINA PROJECT FAA 1VRIB 0106 infiltration ponds. For the model, the ponds were loaded at 400,000 gallons per day over an 8.36 acre area (1.1 gallons per day per square foot). Monthly rainfall data from Onslow County, evapotranspiration data from Wilmington, and evaporation data from Aurora were used in the model to simulate water level fluctuations during the 8" in 10 wettest years (years # 3 and 8). A drain system was assigned into the model at an elevation of 16 feet above mean sea level near Infiltration Pond Number 5 and, at zero feet mean sea level around Infiltration Pond Number 6. The water levels calculations for the piezometer locations showed an increase of water level during a wet season (750 days) to: 25.89 feet mean sea level at Infiltration Pond Number 5 (Figure No. 6A, Head vs Time) ; and 9.89 feet for Infiltration Pond Number 6. These modeled levels show the effect of the drains (Figure No. 6E - 6H , Equipotential Surface Map for a wet year). The mounding in the model was determined by subtracting the water levels calculated inthe calibration model from the water levels at each time step. The maximummound was for the time period from 750 to 900 days at less than 3.2 feet at Infiltration Pond Number 5 (Figure No. 7A, Time vs Drawdown). Seasonal mounding maps are shown for the third year to help to estimate the effect of seasonal fluctuations. The seasonal fluctuation was less than one foot, with the maximum drawdown being 2 feet (Figures Numbered 713 through 7E, Mounding Maps). Using the Modflow results, a solute transport model was configured to simulate a loading of 10 mgll of nitrogen for 10 years (Fig. No 8A - 8D, Nitrogen Model Results) . The Nitrogen achieved steady state after 5 years because of the drains. Nitrogen reduction Is important to protect Surrounding surface waters and minimize Algae growth in the Infiltralion Ponds. Zone budgets for this maximum flow period at 750 days were based on two different segments of the drains, Zone Budget 2 was the zone budget for the drain in the vicinity of Infiltration Pond Number 5. Zone (Figure No. 9A,Zone Budget). Zone Budget 3 was the segment extending around Infiltration Pond Number 6. The discharge in the drains of Zone Budget 2 was 49,314 cubic feet per day and the discharge in the drains of Zone Budget 3 was 52,062 cubic feet per day. The zone 3- 5 SUMMERHOUSE ON EVERETT BAV ONSLOW COUNTV, NORTH CAROLINA PROJECT EAA wRIB 0106 budgets include all groundwater flowing into the zone. The control pumps should be able to accommodate this volume temporarily to adjust groundwater levels after a large rain event, therefore, the pump capacity should be able to discharge the volume in a desired time interval (such as a four hour window). 3- 6 SUMMERHOUSE ON LVEIZETT BAY ONSLOw COUNTY, NORTH CAROLINA PROJECT FAA wR1B 0106 4.0 CONCLUSIONS AND RE, COMMENDATIONS: 4.1 CONCLUSIONS: This analysis has evaluated the soils and hydrologic characteristics of the proposed wastewater disposal system for Summerhouse on Everett Bay, Onslow County. After mapping the soils throughout the northern segment ofthe development site, it was determined that an infiltration pond system is the best option for wastewater management for the proposed development plan. The area consisted of soil most like Wando fine sand and Onslow loamy fine sand. Specifically, the Onslow loamy fine sand contains restrictive horizons (Bli). The excavation of Infiltration Pond Number 5 will penetrate these layers by excavating to an elevation of 22 feet above mean sea level (depths from 8 to 10 feet) and excavating Infiltration Pond Number 6 will penetrate these layers by excavating to an elevation of feet above mean sea level (depths 8 to 10 feet). The waste water volume of400,000 gallons per day will infiltrate to the surficial aquifer at a loading rate of 1.1 gallons per day per square foot (8.36 acres of basins). The two basins are isolated from each other by a pumped drainage system to control groundwater levels. Infiltration Pond Number 5 will accommodate 267,713 gallons per day on 5.59 acres. Infiltration Pond Number 6 will accommodate 132,287 gallons per day on 2.76 acres. Groundwater quality will be protected by the addition of nutrient reduction to the waste water treatment. Therefore, the waste water is restored to comply with groundwater standards at the review boundary, without relying on treatment through the soil horizons. The loading has been modeled using an effluent concentration of 10 milligrams per liter for a twenty year operational period. flee modeling shows that the disposal system will function with the controlled drainage at 16 feet above 4- 1 SUMMERHOUSE ON EVERETT BAY ONSLOw COUNTY, NORTH CAROLINA PROJECT EA WRIB 0106 mean sea level at Infiltration Pond Number 5, and zero feet above mean sea level at Infiltration Pond Number 6, so that the maximum mound should be less than two feet and the review and compliance boundary will be protected. 4.2 RECOMMENDATIONS: The recommendations resulting from this analysis are summarized as follows: • The site can accommodate 400,000 gallons per day at 1.1 gpd/ftz on 8.36 acres; • Provide treatment that will insure that the groundwater will not be degraded at the compliance boundary; U Excavate the ponds to an elevation of approximately 22 feet above mean sea level (Infiltration Pond Number 5) and 3 ft (Infiltration Pond Number 6); maintain the bottom of the ponds periodically to insure infiltration potential at 1,1 gallons per day per square foot;. • Add drains so that groundwater levels can be managed to maintain stable levels in the infiltration ponds. The drains should be configured between each pond to isolate each pond so that mounds do not coalesce from one pond to the other. The pumped discharge in the drains of Zone Budget 2 was 49,314 cubic feet per day and the pumped discharge in the drains of Zone Budget 3 was 52,062 cubic feet per day. The control pumps should be able to accommodate this volume temporarily to adjust groundwater levels after a large rain event, therefore, the pump capacity should be able to discharge the volume in a desired time interval (such as a four hour window). A method of controlling the groundwater drains such as using valves will help to manage levels in the infiltration ponds. • Reduce nutrients in the effluent to ground water standards (15ANCAC 2L); 4-2 5L[AI,IICRROUSE ON 1'.YCRI; T Il,w ONSLOW COUNTY, FORTH CAROLINA PROJECT EAA WRI131111;6 -1.3 LIMITS OF TNVESTIGATION: Data presented in this investigative report represent isolated data points. Corlelt'siolls of [his report illclu{litrg maps, CaICuhit ious aad models. are based on extrapolations between data points and on subjective hydrogeologic, soils and geologic interpretation, therefore, may not be completer' 1'epresenllltivc ()fall canuiitions in the study nre;1, Conclusions and recommendations ofthis report are based on hest uvaihlblc data, collected within budgetary constraints of the original proposal. It is the prel"ise of this effort that the information collected and ann1v/ed is representative of a reasonable effort to Ilndti-Valld and solve tl1C eXiSfillg problem. No guarantee 1s C.\presse(l later 01, I1tl]>E1t`{'l�Jj�}t:l�C?ti-5..�]r iiddlt1011R1`t(,.i?7}1�1jU}h� rl'CIUII'Cd at a tine. ,:' _ .,, t_-- _,. 11 C .-+_T"_` Si_..ti'•' ,fs' A '!!/ • CJ`5�..9000�gR �/1 \4 uVU[[yyO/��r 1 � t � ��" ° �1JTCf17 �Aa '�y •'���� 6dll, Stlbin it}}ppt1 06 ii April 3 2 , 0 s :,i_+iimar V J Edwin E. Andrews.P.C., N .V',N.! .L.S.S. �re''y �•_. =t_��M1�ai i�3,`-�i � _o`.a .�.;•�cS;C�..�`�-l's6/// D�1[�A� o-b� i COlI I1511�t111+ I�yCiI'C1�Ct7�C1151 c�ilC�QII 5CIe1111St for.]�� Af (•..fsr}y'. Er»��iN ,�Nnitrl;�vS �� 1�SsociA�i•�s, P.C. P`= }. r.t�• y rL � =r,---•- �- r j d�•-!-iv'� ��t�- IT �'a Dr. A. R. Rubin, j12CIUM & Creed Engineers, P.A. x x E• s 4 0 O+ ®' k_ a . z 0 o � � o u o x < w 3 ti 11C 0' 800, iYtlIA�O[tl 01�I1; ® 11 It ::.:iIII i„ a:w 1.:1 n I::d,ldl I n:,.Ill QI,a1 1, tl ..... :nnd,1 1..:. I.I.I.I6,q .Ji„I::, I LEGEND • GEOTECHNICAL BORING PIEZOMETER LOCATION AQUIFER TEST LOCATION Q Ksat LOCATION T8 SUMMERHOUSE ON EVERETT BAY .. FIGURE NO,2 SOIL MAP <' .'.f�'i 4ti 6'V SCALE V=900' - EAA PROJECT RW IR 0106 W SUMMERHOUSE ON Ed'ERE'!'T F3AY Yii FIG NO.3 SCALE V = SOW WATER TABLE CONTOUR MAP ('c1vti,1;,!'GN(: }S AN ) .SOIL SCIEN" PINTS EAA PROJECTRWI611106 1 P12 0' Soo, t SUMMERHOUSE ON EVERETT BAY FIGURE NO.4 SCALE V - 800' DEPTH TOWATER MAP ..,tl�6. i.::1J1 IX1 : � I.- SO} ;, �;t'rUAAPROJECT KWI6010 n n ti Z17- ni c ae• aa' o N O 3g.0 P17 20 P 5 0 18 c 24.0 26.0 0 0 2 C � b 10O � o N ZZ O P6� 00 �g 6.0 _ O - P4 `6.0 - P4 �a.0 2i- 3 Z O ♦ W 10.0 p •O O 1544 2400 360o 4800 6000 7200 8400 9600 10944 SUMMERHOUSE ON EVERETT BAY FIG. 5B - CALIBRATION EQUIPOTENTIAL MAP U-4 14. b4 24.54 Observed Head (ft) Num. of Data Points: 20 Max. Residual: -2.685 (ft) at P12/A Min. Residual: 0.154 (ft) at P17/A Residual Mean: -0.451 (ft) Abs. Residual Mean : 1.329 (ft) SUMMERHOUSE ON EVERETT BAY FIG. aC - CALIBRATION GRAPH ■ Layer #1 95% confidence interval 95% interval Standard Error of the Estimate : 0.335 (f Root Mean Squared : 1.527 (f Normalized RMS : 6.699 (% Correlation Coefficient : 0.97 0 L ❑ D i � 1 ( c . t I_� 1 m i S > D ti 0 2000 9000 6000 8000 I0000 ROOD SUMMERHOUSE ON EVERETT BAY FIG. 5D - CONDUCTIVITIES LAYER 1 TEAL 8, WHITE 9, BLUE 5, PURPLE 28, AND GREEN 16 FT/DAY 0 0 a � - o N Ga �'� _sue `, ;•lt\1 � � - 0 200b 4000 5000 Bobo looao 12000 SUMMERHOUSE ON EVERETT BAY FIG. 5E - CONDUCTIVITIES LAYER ? TEAL 8, WHITE 4, BLUE 5, AND GREEN 16 FT/DAY 6 Lo ❑ J cim O ` Y o - Q .J 0 2000 gooc 600o soon i0000 Iz000, SUMMERHOUSE ON EVERETT BAY FIG. 5F - CONDUCTIVITIES LAYER 3 WHITE 9, AND RED 40 FT/DAY SUMMERHOURSE ON EVERETT BAY FIG. 5H - X -SECTION - CONDUCTIVITIES COL 55 Head vs. Time Time = 750.0002 ■ POND 51A(Observed) POND 5/A(Calculated) = 25.89921 -•- POND 5/A(Calculated) _ • POND 6/A(Observed) N ;3 �i M+ 1a an E; ■no `_MR_Eon ___ f POND 61A(Calcuiated) r Ia m = co Time = 750.0002 POND 6/A(Calculated) = M88853 ti 50 1050 2050 Time [days] SUMMERBOUSE ON EVERETT BAY FIG. 7A - WATER LEVEL VS TIME SUMMLKHUUSE UN EVERETT BAY FIG. 6B - RECHARGE WITH DRAINS DRAIN AROUND POND 5 AT 14.5 FT./MSL - ZONE 2 DRAIN AROUND POND 6 AT 0.5 FT,/MS. - ZONE 3 r . P9 x 'Pe P4 w j SUMMERHOUSE ON EVERETT BAY FIG. 6C - EQUIPOTENTIAL SPRING WET YEAR n b - P P 0 11 P Pi 22.0 o i =' 20.0 m r a /.•-.aa PB -S- P5 P4 j } SUMMERHOUSE ON EVERETT BAY FIG. 6D - EQUIPOTENTIAL SUMMER WET YEAR \p O P2 _ P3 .\ _ Co O ti -26.0 -za 0 22.0 C- p tib p O.: R2 XP3 z' 1" �4.0 iJ F I 4408 4900 5600 SUMMERHOUSE ON EVERETT BAY FIG. 6E - EQUIPOTENTIAL FALL WET YEAR P ` o P11 0 P _ 24 0 P30 o =' 20.0 ro �. P7 \ P9 ONO 5* r L Y "l b. bn O t PB P2 F-O ry 4 O P3 j 0 .k o # n m .* 4406 4900 5600 6300 7000 7700 6400 9247 SUMMERHOUSE ON EVERETT BAY FIG. 6F - EQUIPOTENTIAL WINTER WET YEAR Drawdown vs. Time ■ POND 5/A(Observed) -0- POND 5/A(Calculated) • POND 6/A(Observed) f POND 6/A(Calculated) a� v ram." Time = 419.9999 POND 6/A(Calculated) = 3.19487 rn N C O 3 a`^ 0 ■nMR r�MA o s■:� ■■ ■ ■ ■■ ■ z M „ ■ ■ a Time = 431.4757 ■ s_, M POND 5/A(Calculated) =-2.157444 r _ -- WE a c-� 0 cri 50 1050 2050 Time [days] SUMMERHOUSE ON EVERETT BAY FIG. 7A - TIME VS DRAWDOWN M" N 0 e - I m o 2.p M P7 M � ' I 0; c - PO 5 CO - PD 0 1 1 coe +s e N N P6 O O/ o \i% 2 N P2 ui 0 m 5616 6000 P3 6400 6600 7200 7600 8000 8216 SUMMERHOUSE ON EVERETT BAY FIG. 7B - DRAWDOWN - SPRING WET YEAR I J r N � _ b � L "1 O 12.0 P7 n 0 m PONO 9 P6 Qy Po �I O \ I 1 I N P8 i O � 6.O.p0 N P2 l m +�• Ir 5616 6000 P3 6400 6800 7200 7600 8000 8216 SUMMERHOUSE ON EVERETT BAY FIG. 7C - DRAWDOWN - SUNIMER WET YEAR m m Y I 0 b m 0r n 13. 0' '-F' r 0 P7 O 0 m O NO 5 + O P6 •� 11.0 -� �o�. to I 'J I�J l.. i I� � � 1 ,. r ..n . PO D l 6 0 9� qQ �0 P N PB e- J� O O b. 0j N P2 m 5616 6000 P3 6400 6800 7200 7600 8000 8216 SUNIMERHOUSE ON EVERETT BAY FIG. 7D - DRAWDOWN - FALL WET YEAR m � m I I f � f .0 m P7 m m o POND 5 I� N � •• \fir 1 1 f \ "'� w O 0 o � - N P,}8, I 0 ry ry M c hx Y. m O m 5616 6000 P3 6400 6800 7200 7600 Bobo 8216 SUMMERHOUSE ON EVERETT BAY FIG. 7E - DRAWDOWN - WINTER WET YEAR ConcO01 [mg/L] - -2.000 0.000 2.000 4.000 6.000 8.000 10.000 12.000 0 m ri ' .. PID n — P7 P9 _P6 r ry o p p !r D N P4 - • P2 ;Y P3 � N P-1 a -� - 0 f # O � � ri r r� O 1 5 �#r n 4251 4900 5600 630D 7D00 7700 6400 9312 SUMMERHOUSE ON EVERETT BAY FIG. 8A - NITROGEN 5 YEARS Conc001 0 O✓ N N p 2 4.867 - 5.714 6.571 7.429 82 e \ P7 pq �P N� --P_1 _—+s a I^ � -- 4561 4800 5400 SUMMERHOUSE ON EVERETT BAY FIG. 8B - NITROGEN 10 YEARS = F 6000-—�6600 ---- 7200 —_ 7800 84 P10 a 0 N Ni rzao �eoo SUMMERHOUSE ON EVERETT BAY FIG. 8C - NITROGEN 20 YEARS Time = 750 Zone Budget: MODFLOW Date: 4/2/2006 Zone3 - - SUMMERHOUSE ON EVERETT BAY FIG. NO. 9, DRAIN BUDGETS SUMMERHOUSE ON EVERETT BAY TABLE NO. 3A, HYDRAULIC CONDUCTIVITY RESULTS TEST BY: Edwin Andrews TEST SITE 1 Soil notes: WEAK Bit Location CM, DTW Hole depth 70 head 15 Ameter Valve A Conver. cm Reference 10 d 65 config. On C111^-2 Factor Initial: 56 D 80 H 1 65 2 2 0.001056 105 Final: 55 dt (min) Res (cm) dR (cm) DTW (cm) H (cm) Conver. factor Q (cm"3/m) Q (cm^31hr) K (Croft) K (in/hr) K (in130 days) DRAINAGE (in130 days) 1 43.9 1.2 56 14 105.0 1 43.3 0.6 55 15 105.0 63.0 3.780.0 4.0 1.6 1131.5 45.3 1 42.7 0.6 55 15 105.0 63.0 3,780.0 4.0 1.6 1131.5 45.3 1 42.1 0.6 55 15 105.0 63.0 3,780.0 4.0 1.6 1131.5 45.3 1 41.5 0.6 55 15 105.0 63.0 3,780.0 4.0 1.6 1 1131.5 45.3 Ksat 4 1.6 45.0 Remarks: TEST SITE 2 Soil notes: Bt Location CM. DTW Hole depth 32 head 15 Ameter Valve A Conver. cm Reference 11 d 27 config. On cm"-2 Factor Initial: 18 D 42 H1 27 2 2 0.001056 105 Final: 17 dt (min) Res (cm) dR (cm) DTW (cm) H {cm} Conver. factor Q (cm^31m) Q (cm^31hr) K (cmlhr) K (inlhr) K in130 da s) DRAINAGE (in130 da s) 1 25.5 0.0 18 14 105.0 1 25.3 0.2 17 15 105.0 21.0 1,260.0 1.3 0.5 377.2 15.1 1 25.2 0.1 17 15 105.0 10.5 630.0 0.7 0.3 188.6 7.5 1 25.1 0.1 17 15 105.0 10.5 630.0 0.7 0.3 188.6 7.5 1 25 0.1 17 15 105.0 10.5 630.0 0.7 0.3 188.6 7.6 1 24.9 0.1 17 15 105.0 10.5 630.0 0.7 0.3 188.6 7.5 Ksat 0.7 0.3 7.5 Remarks! SUMMERHOUSE ON EVERETT BAY TABLE NO. 3B HYDRAULIC CONDUCTIVITY RESULTS TEST BY: Edwin Andrews TEST SITE SITE 3 Soil notes: Bt Location CM, DTW Hole depth 30 head 15 Ameter Valve A Conver. Cm Reference 10 d 25 conflg. On cm^-2 Factor Initial: 16 D 40 H1 25 2 2 0.001056 105 Final: 15 dt (min) Res (cm) dR (cm) DTW (cm) H (cm) Conver, factor Q (cm"31m) Q (cm"31hr) K (cmlhr) K (tnlhr) K (in130 days) DRAINAGE (inl30 da s) 1 43.1 0.0 16 14 105.0 1 42.9 0.2 15 15 105.0 21.0 1,260.0 1.3 0.52 377.2 15.1 1 42.7 0.2 15 15 105.0 21.0 1,260.0 1.3 0.52 377.2 15.1 1 42.5 0.2 15 15 105.0 21.0 1,260.0 1.3 0.52 377.2 15.1 1 42.3 0.2 15 15 106.0 21.D 1,260.0 1.3 0.52 1 377.2 15.1 Ksat 1.3 0.50 300 15.1 Remarks: TEST SITE - SITE 4 Soil dotes: Weak Bt Location CM. DTW Hole depth 40 head 16 Ameter Valve A Conver. cm Reference 11 d 36 config, On crnA-2 Factor Initial: 26 D 51 H1 36 2 2 0.000961 105 Final: 25 dt (min) Res (cm) dR (cm) DTW cm) H (cm) Conver. factor Q (cm^3lm) Q (cm^31hr) K (cmlhr) K (inlhr) K i230 days) DRAINAGE inl30 days) 0 32.1 0.0 26 14 1 D5.0 1 31.8 0.3 25 15 105.0 31.5 1,890.0 2.0 0.8 565.7 56.6 1 31.5 0.3 25 15 105.0 31.5 1.890.0 2.0 0.8 565.7 56.6 1 31.4 0.1 25 15 105.0 10.5 630.0 0.7 0.3 188.6 18.9 1 31.3 0.1 25 15 105.0 10.5 630.0 0.7 0.3 188.6 18.9 1 31.2 0.1 25 15 105.0 10.6 630.0 0.7 Ksat 0.7 0.3 1 188.6 0.3 168 18.9 18.9 Remarks: SUMMERHOUSE ON EVERETT BAY TABLE NO. 3C, HYDRAULIC CONDUCTIVITY RESULTS TEST BY: Edwin Andrews TEST SITE SITE 5 Soil notes: Bh Location CM. DTW Hole depth 34 head 15 Ameter Valve A Conver. Cm Reference 11 d 29 config. On cm^-2 Factor Initial: 20 D 45 H1 29 2 2 0,001056 105 Final: 19 dt (min) Res (cm) dR (cm) DTW (cm) H (cm) Conver. factor Q (cm^31m) Q (cm^31hr) K (cmlhr) K (inlhr) K (in130 days) DRAINAGE (in130 da s) 0 33.8 0.0 20 14 105.0 1 33.2 0.6 19 15 105.0 63.0 3,780.0 4.0 1.57 1131.5 45.3 1 32,7 0.5 19 15 105.0 52.5 3,150.0 3.3 1.31 942.9 37.7 1 32 0.7 19 15 105.0 73.5 4,410.0 1 4.7 1.83 1320.1 52.8 1 31.3 0.7 19 15 105.0 73.5 4,410.0 4.7 1.83 1320.1 62.8 Ksat 4.7 1.80 53.0 Remarks; POND 5 SOIL TO BE EXCAVATED TEST SITE SITE 6 Soil notes: Bli Location CM. DTW Hole depth 23 head 15 Ameter Valve A Conver. cm Reference 11 d 8 conf . On cm^-2 Factor Initial: 9 D 34 H1 8 1 1 0.000961 20 Final: 8 dt (min) Res (cm) dR cm DTW (cm) H (cm) Conver. factor Q (cm"31m) Q (cm^31hr) K cmlhr) K inlhr) K (in130 days) DRAINAGE (in130 days) 0 48.1 0.0 9 14 20.0 1 47.9 0.2 8 15 20.0 4.0 240.0 0.3 0.1 71.8 2.9 1 47.7 0.2 8 15 20.0 4.0 240.0 0.3 0.1 71.8 2.9 1 47.5 0.2 8 15 20.0 4.0 240.0 0.3 0.1 71.8 2.9 1 47.3 0.2 8 15 20.0 4.0 240.0 0.3 0.1 71.8 2.9 1 47.1 0.2 8 15 20.0 4.0 240.0 0.3 0.1 71.8 2.9 Ksat 0.3 0.1 71 2.9 Remarks: POND 5 - SOIL TO BE EXCAVATED SUMMERHOUSE ON EVERETT BAY II TABLE NO. 3D, HYDRAULIC CONDUCTIVITY RESULTS II PEST BY: Ed Andrews PEST SITE -SITE 7 ,foil notes: Bt Location CM. DTW Hole depth 50 head 16 Ametor Valve A Conver. cm Reference 10 d 45 config. On cm^-2 Factor Initial: 36 D 60 H1 45 2 2 0,009610 105 Final 35 dt (min) Res (cm) dR (cm) DTW (cm) H (cm) Conver. factor Q (cm"3/m) Q (ci,03/hr) K (cm/hr) K (in/hr) K (in130 days) DRAINAGE (iW30 days) 0 39.8 0.5 36 15 105.0 1 39.6 0.3 35 16 105.0 31.5 1,890.0 18.2 7.2 5148.5 205.9 1 39.3 0.3 35 16 105.0 31.5 1,890.0 18.2 7.2 5148.5 205.9 1 39.1 0.5 35 16 105.0 52.5 3,150.0 30.3 11.9 8580.9 343.2 1 38.9 0.4 35 16 105.0 42.0 2,520.0 24.2 9.5 6864.7 274.6 Ksat 24 9.0 270.0 Remarks: POND 6 - SOIL TO BE EXCAVATED rEST SITE - SITE 8 moil notes: Btt Location CM. DTW Hole depth 20 head 16 Ameter Valve A Conver. cm Reference 30 d 15 confi . On cm"-2 Factor Initial: 6 D 63 H1 15 1 1 0.000961 20 Final: 5 di (min) Res (cm) dR (cm) DTW (cm) H (cm) Conver. factor Q (cm"3/m) Q (cm^31hr) K (cmlhr) K (inlhr) K (in/30 days) DRAINAGE (in130 da s) 0 31.7 0.0 6 15 20.0 1 31.5 0.2 5 16 20.0 4.0 240.0 2.3 0.9 653.8 26.2 1 31.3 1 0.2 5 16 20.0 4.0 240.0 1 2.3 0.9 653.8 26.2 1 31.1 0.2 5 16 20.0 4.0 240.0 2.3 0.9 653.8 26.2 1 30.9 0.2 5 16 20.0 4.0 240.0 2.3 0.9 653.8 26.2 Ksat 2.3 0.9 0 26.0 Remarks: POND 6 - SOIL TO BE EXCAVATED SUMMERHOUSE ON EVERETT BAY TABLE NO.4, WATER LEVEL DATA - SURVEYED WATER WATER WATER STICK-UP GROUND T.O.C. EAST NORTH ELEVATION DEPTH DEPTH NAD 83 FT. NAD 83 FT FT. M.S.L. FT. FT. T.O.C. FT. FT. M.S.L. FT. M.S.L. 2456094 270253 5.1 4.2 P1 5.0 0.8 9.3 10.1 2456057 270935 7.7 2.6 P2 5.9 3.3 10.3 13.6 2455276 270732 10.4 2.3 P3 5.6 3.3 12.7 16.0 2454517 270855 18.0 7.4 P4 8.4 1.0 25.4 26.4 2454393 271142 22.9 10.7 P5 13.3 2.6 33.6 36.2 2455208 271872 27.8 8.3 P6 12.0 3.8 36.1 39.8 2456219 272265 20.7 7.3 P7 10.7 3.4 28.1 31.5 2454658 271300 26.1 7.1 P8 10.3 3.1 33.2 36.3 2454354 272094 24.8 3.4 P9 7.1 3.7 28.2 31.9 2454262 272547 24.6 3.1 P10 4.4 1.4 27.7 29.0 2453592 272984 24.3 1.3 P11 3.3 2.0 25.6 27.6 2454308 273649 27.9 2.7 P12 5.9 3,2 30.5 33.7 2453059 274001 21.5 3.8 P13 7.8 4.0 25.2 29,2 2453680 274780 27.7 1.9 P14 6.9 5.0 29.6 34.6 2452976 274880 21.8 4.7 P15 8.9 4.2 26.5 30.7 2453349 275940 26.0 1.1 P16 4.0 2.8 27.1 29.9 2451449 274833 25.0 0.4 P17 2.5 2.1 25.4 27.5 2452021 273988 14.4 4.6 P18 8.0 3.3 19.1 22.4 2452318 274393 17.3 4.8 P19 8.8 4.0 22.1 26.1 2451949 274907 23.0 3.3 P20 7.5 4.2 26.2 30.4 Edwi •ews.' ciate: P.O. 6o:r6uti53 Rnje�gh, N,C. Pumping Test No, 4 Well Pond 6 - North of Pond discharge 4,50 U.S.9al/min 10-1 100 101 101 ton m Q 10-' 10-2 10-3 o OW-6 Transmissivity [ft2/d]: 2-74 x 102 Hydraulic conductivity [ftld]: 1 37 x 10l Aquifer thickness [ft]: 20,00 Storativlty: 7.11 x iti-s ping tr Isis Qa 3.200E _ le No. . -gel NEUMAN's method Unconfined aquifer with Project: Summerhours at Everetts Bay delayed watertable response Evaluated by: EEA Test conducted on: 21412006 1fu 101 101 14,- 1n, Hydraulic conductivity vertical [ft/d]: 8.66 x 10-i Specific yield: 711 x t0-2 Edwi ews _ �ciate _ Iping t _ysis �z. _ 3.P0�0 oale�No cn, rage 2 P.O. Box 30653 NEUMAN's method Ralemgh. V.c. Unconfined aquifer with Project: Summerhours at Everetts Bay delayed watertable response I Evaluated by: EEA Pumping Test No 4 Test conducted on: 2W2006 Well Pond 5 - North of Pond OW-6 Discharge 4.50 U.S.gallrnin Distance from the pumping well 19.50 ft Static water level: 0,00 ft below datum Pumping test duration Water level -u-, 0,44 3 0.0069a 0.46 4 4.01042 0.48 5 0.01389 049 6 0.01736 0.49 7 0.02083 0,5 $ 0,02431 0.51 9 0.0277B 0.51 10 0.03125 0.52 11 1 0.03472 0.52 12 0.03819 0.52 13 0,04167 0,53 14 -Ts-- 0.04514 0,53 0.048 11 0.53 16 0.05208 0.54 17 ! 0.05556 0.54 1 a 0.05903 0.54 19 0, 06250 0.55 20 CO6597 0,54 21 0,06944 0.54 22 0.07292 0.55 23 ' 0.07639 0.56 24 0.07986 0.55 25 0.08333 0.56 26 0.08681 0.56 27 0.09028 0.56 28 0.09375 0,56 29 0,09722 0.56 30 0,10069 0.56 31 0,10417 0.56 32 0.10754 0,56 33 0,11 n.57 0.11458 35 0.1180b 0.57 3B 0.12153 0.57 37 0.12500 0.57 39 0,12847 0.57 39 0.13194 0.57 40 0.13542 0.53 41 0,13869 0.58 42 0.14236 0.57 43 0.145$3 0, 57 44 ' 0.14931 0.50 45 0.15278 0 58 46 0.15625 0.58 47 D.15972 0.58 4$ 0.16319 0.53 49 0.1566 7 0.57 50 0.17014 0.58 Orawdown 0.44 0.46 0.48 0.49 0.49 0,50 0,51 0,51 0.64 0.54 0.54 0.55 0.54 0,54 =52 0.55 0.56 a 56 0.56 0.56 0.56 0.56 0.56 0.56 0.56 0.56 0,57 0.57 0,57 0.57 0.57 0.57 0.57 a.5a 0.58 0.57 0.57 0.59 0.58 0.58 0.58 0.58 0.57 Edwi - ' ,ews ' �ciate _ _ aping t� �+sis ❑s 3.2o0E_ ale No. P,O. box auu53 NEUMAN's method Raleigh, N.C. Unconfined aquifer with Project: Summerhours at Everetts Bay delayed watertable response Evaluated by: EEA Pumping Test No. 4 Test conducted on: 2/412006 Well Pond 6- North of Pond OW-6 Discharge 4.50 U.S.gallrnin Distance from the pumping well 19,50 ft Static water level: 0,00 ft below datum Pumping test duration Water level Drewdown a � 1 0.1711611 1 0.59 0.69 521 0.17708 0'S9 0,59 53 0.18056 I 0.69 0.59 TTD.184a3 0.59 0.59 55 D,18750 0.59 0.50 5fi 0.19097 0.59 0.59 57 0.19444 0.60 0.60 58 0.19792 0.60 0.60 59 0.20139 0.60 0.60 60 0.20486 0-60 Q,60 61 a, 20833 0.60 0.60 62 0,21181 0,60 0.60 63 0,21526 0,60 0.60 64 D.2 i 875 0-50 0.60 65 0.2222z ° 60 66 a.22569 ISO 60 0,6 0 67 0.22917 0.50 0.60 68 0.23264 0.61 0.61 69 0.23611 0.60 0.60 70 0.23958 0.61 Q.61 71 0.24306 0.61 0.61 72 n.z4s53 0.61 0.61 TT0.25000 061 0.61 74 0,2534 r 0.61 0,61 75 0.25694 0.62 0.62 76 0.26042 0.62 0.62 4.26389 0.62 0.62 78 0.26736 0.62 0.62 79 0,27083 0.62 0.62 80 0,27431 0.62 4.62 81 0.27778 4.62 0.62 82 0.28125 0, 62 0.62 83 0.28472 0,62 0,62 84 0.28819 0.62 0, 62 85 0.29167 0.62 0.62 86 0.29514 0.63 053 B7 0.29861 0.53 a 0.6., 68 0.30208 0.63 0.63 84 0,30556 I 0,63 0.63 90 0.30903 0.63 0.63 91 0.31250 0,63 0.62 92 D.31597 0.63 0.633 93 0.31944 2 `' 0.63 94 ❑. 32292 -0.63 0.63 95 1 0,32639 Q•63 0.63 96 0.32986 0.63 0.63 97 0.33333 4.63 053 98 0.336B1 p 64 0.64 99 0,34028 0,64 0.64 00 1 0.34375 0.64 0.64 Edw; rews )ciate iping t ysis Ds 3.200t fle No oe a P.C. Box 30653 Raleigh, N.C. NEUMAN's method Unconfined aquifer with delayed watertable response o i_Project: Summerhours at Everetts Bay Evaluated by: EEA Pumping Test No. 4 Test conducted on: 214l2006 Well Pond 6- North of Pond OW-6 Discharge 4-50 U.S.gallmin Distance from the pumping well 19.50 ft Static water level: 0.00 ft below datum Pumping test duration Id] Woter level IftI Drawdown En] 101 0.34722 0,63 0.63 1 C2 0.35069 1 0.63 0.63 10a 0.35417 0.64 0.64 104 0.35784 0.64 0.64 105 0.36111 0.64 0.64 ice 0.36456 0.64 0.54 107 026S06 0.64 0.64 10a 0.37153 0.65 0.65 log 0.37500 0.64 0.54 110 0,37847 0.65 0.65 111 0.38194 0.65 0,65 112 C.38542 0.65 0.65 113 0.36889 0.65 0.65 114 0.39236 0.65 0.65 115 0.39583 0.65 0.65 116 0.39931 0.65 0.65 117 0.40278 0.66 0.66 118 0.40625 0.65 0.65 119 0.40972 0,66 0.66 12C 0.41319 0.66 0.66 121 0.41667 0.66 ! 0.66 122 0.42014 0.66 0.66 123 0,42361 0.66 0.66 124 0.42703 0.66 0.66 125 0.43C56 0.66 0.66 126 0.434C3 0.66 0.66 127 0.43750 0.67 0.67 128 0.44097 0.67 0.67 129 0.44444 a6e 0,66 130 0.44792 0.67 0.67 131 0.45139 0,67 0.67 132 0 4548E 0.67 0.67 133 0,4583a 0.67 0.67 134 046181 0.67 0.67 135 0.46528 0.68 0.ea 135 0.46875 1 0.67 0.67 1371 0.47222 10.6a 0,68 138 0,47562 1 0.68 0.68 139 0.47917 0,68 0.68 140 0.48264 0.67 0.67 141 0,48611 0.68 0.68 142 0.48953 0,68 0.68 143 0.4930E 1 0.68 0.68 144 0.49653 O.EB 0.68 145 0.50000 0.62 0,68 146 0.50347 0.68 0.68 147 0.50694 0.68 0.88 148 0.51042 0.69 0,69 149 0,51389 0.68 0.68 150 1 0,51736 0.68 0.68 Da 3.20DE i� -le c . ge 5 Edwi ews � ciate. _ ping a psis _ P.0_ Soz30653 NEUMAN'S method Ralapgh, N.C. I Unconfined aquifer with Project_ Summerhours at Everetts Bay delayed watertable response Evaluated by: EEA Pumping Test No. 4 Test conducted on: 2X2006 Well Pond 6 - North of Pond OW-6 Discharge 4.50 U.S.gallmin Distance from the pumping well 19.50 ft Static water leve[: 0.00 ft below datum Pumping test duration Water level Drawdewn [d] [ft] [ft] 151 0.52C83 0.69 0.69 152 0.52431 0.6$ 0.69 153 0.52778 0.69 0,63 134 0.53125 0.62 n.69 155 0.53472 0.69 0.69 156 0.53819 0.69 0.69 157 0,54167 0.69 0.69 158 4.54514 0.69 0.69 159 0,54851 0.69 0.65 160 C.55208 D.69 0.65 161 0.55556 0.69 0.69 162 0.55903 0'69 0.69 163 0.56250 D.69 p 0.690.69 164 0.56597 0.fi9 165 0,56944 0.70 0.70 166 0,57292 D.69 0.69 167 0.57639 0.70 0.70 168 0,57966 0.70 0.70 169 0.53333 0.70 0.70 170 0.58661 0.70 0,70 171 0, 59028 0.70 0.70 172 0, 59375 0.71 0.71 173 0, 59722 0.71 0.71 174 0,50069 0.71 0.71 175 0-6D417 0 71 0.71 176 0.50754 0,71 0.71 177 0.61111 D- 71 0.71 175 0.61458 0.71 0.71 179 0.61806 0.71 0.71 I 180 0.62153 0.71 0.71 181 0.62500 I 0.71 0.71 182 0.62847 0.71 0.71 183 0.63194 1 0.71 0.71 184 0.6354.2 1 0.71 0.71 185 0.63889 n.71 0.71 186 0.64236 0.72 0.72 1$7 0.64583 0.72 0.72 188 0.64931 0.71 0, 71 189 { 0.55278 072 0.72 190 0,65625 0.72 0.72 191 0.65972 i 0,72 4.72 192 0 66319 0.72 0.72 193 0.66667 0.72 0,72 194 0,67014 0.72 0.72 195 0,57351 0.72 I D 72 196 0.67708 0.72 0.72 197 0.68056 C.72 0.72 195 0,68403 0.72 0.72 199 0.68750 0.72 D.72 zno 0.69097 0.72 0.72 Edw' news _ tciate__ _ _tying t ysis Da __32004 u2No P.O. BOX 30653 NEUMAN's methcd 0 g Ralocgn, nl.c. Unconfined aquifer with Project: Summetcurs at Everetts Bay delayed watertable response Evaluated by: EEA Pumping Test No. 4 Test conducted on: 2 4/2046 _ Well Pond 6 - North of Pond OW-6 Discharge 4.50 U.S.gallmin Distance from the pumping well 19,50 ft St8tio water level: 0.00 ft below datum Pumping test duration Water level Orawdown 1 0.69444 0.72 0.72 2 0.69792 0.73 0,73 3 0,70139 0.72 0.73 4 0.70486 1 0.74 5 0.70833 0.73 0.74 6 0, 711 11 0.73 0.73 0, 7 0.715 5 0.73 0 73 0 f3 8 0.71875 0 73 0 73 9 0.72222 0.73 0.73 0 0.72569 0.73 ❑.73 0,72917 0,73 0.73 2 0.73264 i 0.73 0.73 3 0,73611 0.74 0,74 4 0.73958 0.74 p,74 5 0_74306 0.74 0.74 6 D.74653 0.74 0,74 7 0.75000 0.74 0.74 9 0.75347 0.74 0.74 9 0,75694 0,74 0.74 D 0,76042 0.74 0.74 1 0.76389 0,74 0.74 p 0.77 075 0.75 3 0.77053 0.7y 0.75 ¢ 0.77431 D,7s 075 5 0,7777$ 0,75 0.75 0.78125 0.75 0.75 r 0.78472 0.75 0, 75 3 0,7$819 D,75 0.75 3 0.79167 0.75 0.75 � 0.79514 0.75 0.75 0,79861 0.75 0.75 � 0.80208 0.75 0.75 3 0.80556 0.75 J 0.75 � 0.80903 0.75 0.75 0.81250 0.75 0.75 } 0,81597 0.75 0.75 0.81944 0.76 0.76 3 0.82292 0.76 0.76 i 0,82539 0.76 0.76 0,52956 0.76 0.76 0.83833 0.76 0.75 0.83681 0.76 0.76 4 0.84028 0.75 0.76 0.84378 0.76 0.76 0.84722 1 0.76 0.75 � 0,85069i 0,77 0.71 0.85417 0.77 0.77 0.85764 0.77 0,77 3 0,86111 0,77 0.77 0.86458 - 0.77 0.77 Edw',- "-trews �clate -- P.O, bun at.053 Rolnugh, N,C Pumping Test No. 4 Well Pond 6 - Nvrth of Pond Discharge 4.50 U,S.gallmin Static water level: 0.00 ft below datum Pumping test duration 266 285 293 1ping t ysis De �3 �v aim ter„ uge 7 NEUMAN's method Unconfined aquifer with Project: Summerhaurs at Everetts Say delayed watertable response Evaluated by: EEA Test conducted on: Z4l2006 Oyv-6 Distance from the pumping well 19.50 ft Water Ievei 0.87153 0.7 0,87500 0.7 0.87847 0.77 6881 44 0.77 O.S8542 0.7a 0.$8889 0.78 0.89236 0,78 0.89583 1 0.78 0.39931 i 0.78 0,90278 0.78 0.90625 0.78 0.90972 0.79 0.91319 0.79 0.91667 0.79 0.92014 0,76 0,92361 0.79 0.92708 0.78 S30 6 -0.79 0,93403 0.79 0.93750 0.79 0.940 77 0.79 094444 1 0.79 0.94792 0.79 0.95139 0 79 0.95486 0.79 0.95833 0.79 0.90131 0,20 0.965 8 -0.80 0,96875 0.80 0.972 22 0,s0 0.97569 0.80 0.97917 0.80 0.98264 0.80 0,80 0.99653 D.80 1.00OOD 0.80 1.00347 0,60 1.00694 0.80 1.01042 O.a0 1.01385 0.80 1.01736 0.80 1.Oz083 0.80 1.02431 0.60 1.027 S CC'SO 1.03125 0 80 1.03472 021 1.03819 I o Drav down tI 0.77 0.77 0,77 0.77 0.77 0.78 0.7^0 0.78 0.7a 0.78 0.78 0.73 0.79 0.79 0.79 0,78 0.79 0.78 0.72 0.79 0.79 0.79 0, 79 0 79 0.79 n �c 0.79 0.80 0.30 0.30 fl.80 0.30 0.80 0.80 0.80 0.80 0.80 0,80 0.80 0.30 0.80 I 0.50 o.ea 0.80 0.80 OM 0.80 0.80 0.81 0,80 Edwi " 'rews )tiate _Iping t psis �r RG. oox.iuo53 NEUMAN's method RalciSn, N c_ I Unconfined aquifer with delayed watertable response Pumping Test No 4 Well Pond 6 - North cf Pond Discharge 4.50 U.S.gallmin Static water level. 0.00 ft below datum Pumping test duration Water level 1.04167 0.80 1.04514 0.80 1.04861 0,80 705208 0.80 1.05556 0.81 1,05903 o.so 1,06250 0 81 1 06597 0.60 1.05944 0 81 1.07292 0.81 1.07639 0.80 1.07986 0.81 1.08333 0.80 1.08681 0.80 1.09028 0.82 1,09375 0 81 1,09722 0.81 L10059 0.60 1,10417 0.80 1.10764 0, 80 ,11 11 0.81 1.11458 0.82 1.118106 0.82 1.12153 0.81 1.12500 0.82 1.12647 0.82 1,13194 0.86 1.13542 OM 1.13889 0 82 1.142 66 0,52 1.14583 0.81 1.14931 0.80 1.15278 0.82 1.156 5 -0.82 1.159 22 0.82 1.16319 0.82 1,16667 0.82 1.17014 j n on I. 1 I J V 1 0,82 1.17708 0.61 1.18056 10.81 1.18403 ❑.81 1.1875p 0.83 1.190 77 0.82 7194 44 0.82 1.19792 0.83 1.20139 0,83 M.3.200c. , -zle Na. ,,.,, � age 8 Project: Summerhours at Everetts Bay Evaluated by: EEA Test conducted on: 2/412006 OW-5 Distance from the pumping well 19.50 ft Drawdown 0.80 0.80 0.80 0.80 0.81 0.80 0.81 0.80 O.s1 0.81 an 0.81 0.80 0.80 0.82 0.81 0.81 0.80 0.80 0.60 0.81 0.82 ❑.82 0.81 0.82 0.82 0.80 0.62 0.82 0.82 0.81 0.80 0.82 0.82 0.82 0.82 0.32 0.80 0-82 0,81 0.81 0.81 0.83 0.82 0.82 .dwin ws & iates. r.0. EoxauU53 Rafe.gh. N.C. Pumping Test No. 5 Well 5 at Pond 5 Discharge 14,50 U.S.gallmin 0 0 _ ng tes s Date 2 CS o. No. 5—, ye 1 NEUMAN's method Unconfined aquifer with Project Summerhouse at Everetts Bay delayed water -table response Evaluated by_ EEA Test conducted on: 310312006 11u 101 10t 10'` 1(13 en< —5 _N o U W-5 Transmissivity [ftVd]: 2.79 x 10'' Hydraulic conductivity [ftld): 1.47 x 101 Aquiferthlckness [ft]: 19.00 Starativfty: 2.44 x 10'-' Hydraulic conductivity vertical ]fUd]; 2.65 x 1 D° Specific yield', 2.44 x 10-1 5dwir -' ?ws & -iates '- iing le, ;is 5Q, -QC,3 NEUMAN's method Raleigh, N.C. Unconfined aquifer with delayed wateRable response Pumping Test No. 5 Well 5 at Pond 5 Discharge 14.50 U.S.9311min Static water level: 0.00 ft below datum Pumping test duration Water level [d) [ttl 1 0 00347 0,00 2 0.00694 0,55 3 0.01042 0.92 4 0.01389 493 I i 5 0.02778 1 0.91 6 0.03125 0.99 7 0.03472 0.99 8 0.03819 0.99 9 0.04167 4.99 10 0,04514 1.00 11 C.08661 0,97 12 0.09028 0.99 13 0.09375 1,00 14 0.09722 1.00 15 0.10069 1.00 i6 D.10417 1.01 17 0.10764 T.02 13 0.11111 1 02 19 0,114 88 1.02 20 18621 12153 1-04 22 1250Q231,04 gO. 12847 1.45 24 0,19194 1,05 25 0.13542 26 0,13889 1.06 7E��E 0.14236 1.07 8 j229 0145831.07 0.1031 1,07 30 0.15278 1, 08 31 U.15625 1.08 0.15972 1.08 J�4 0.16319 1,09 D.16667 1.10 35 0.17173fi1014 1.10 36 0. I 1 11 37 E38 639 240 041 71.12 42 MC.20486 T.13 43 1.13 44 1.14 6 1,14 45 1.15 47 0.21181 1.15 48 0.2152$ 1,i5 49 0.21875 1.16 50 4.2222 16 Dat. .2006 ...,,a No Project: Summerhouse at Everetts Bay Evaluated by: EEA Test conducted on: 3l03I2006 OW-5 Distance from the pumping well 20.00 It Drawd awn 4.00 0.55 0.92 0.93 0.91 0,29 0.99 0.99 0,99 1.00 0.97 0,99 1.00 1-00 1.00 1.01 1.02 1.02 1.02 1.03 1,04 1.04 1.05 1.05 1.06 1.06 07 1 1.07 1,07 1.05 1,08 1.08 1.a9 1.10 1,10 1.11 1=6 Edwil ews F ciateE _ _ _ping tE_ sis P.O. 8bx3o6S3 NEUMAN's method Raleigh, Iv.c. Unconfined aquiferwan delayed watertable response Pumping Test No, 5 Well 5 at Pond 5 0iscn8rge 14,50 U.S.gallmin Static water level: 0.00 ft below datum Pumping test duration Water level 0.22559 1.17 0.22917 g52 53 1,17 0.23264 1,17 54 0.23611 55 0.23958 T.18 56 1.18 0.24306 1,18 57 0.24653 58 1.19 0.25000 1 19 59 0.25247 60 1.19 0.Z5694 61 19 026042 1.20 62 6,26389 63 0.26736 1, 20 54 1.20 0.27083 1.21 BS 0,27431 66 EH 0.27778 1.21 o t 1.21 0, 26125 L21 68 0.25472 89 028319 123 70 1.23 0.29167 1.23 71 0.29514 1.23 72 0.29861 73 23 0,30208 1.24 74 0.30556 12d 75 0,30903 1.24 76 0.31250 1,24 n 0.31597 78 1.24 0.31944 1.24 0.32292 1.25 0.32639 1,25 0.32986 1.25 0.33333 1.26 im 1,26 0.340281 0,343751.27 27 0,34722 127 0.35059 1.27 8 Z 0.35417 .27 1 0.35764 1.27 0 0.36111 � 0.36458 .28 L28 3 0.36805 12$1 0.37153 25 4 0.37500 1.29 5 0.37847 1.29 6 039194 1.30 7 0.38542 8 1 29 0-38889 1.30 y 0.39236 1.30 0 0.39563 1.30 Dat_, . --S.2006 i aide No, nb, Page-3 Project' Summerhouse at Everetts Bay Evaluated dy: EEA Test conducted on: 310312006 OW-5 Distance from the pumping well 20.00 ft orawdown 1.17 1.1 7 1.17 1.18 1.18 1 18 1.19 1.19 1 19 1.19 1,20 12'.. 1.21 1,21 1.21 1.21 1,23 1.23 1.23 1.23 1.23 1.24 1.24 1.24 1.24 1.24 1.24 1.25 1.25 1.25 1.25 1 26 1.27 1.27 1.27 1,27 1.27 1.27 1.28 1.28 1,25 1.28 1.29 .29 1.30 1,29 1.30 1.30 7.30 Edwi' - MS., cifate: P.C. ; ex 4ue53 ping to _ _._.7s s lOatc. [0.o3 fi Tab ' le No. 5B, page 4 NEUMAN's method Raleigh, Iv.c. Unconfined aquifer with Project: Summerhouse at Everetts Bay delayed watertable response Evaluated by EEA Pumping Test No. 5 p Well 5 at Pond 5 Test conducted on: 3/03/2006 D'JV-5 ❑ischarge 14.50 U.S.gallmin Distance from the pumping well 20.00 ft Static water level; 0.00 ft below daium Pumping test duratlon Water level Drawdown 1 ny Idj 102 0.40278 1.30 1.30 1D3 0.40625 1.30 1.30 104 0.40972 1.30 i,�v 0 105 0 41319 i.31 1.31 106 0.41667 1.31 1.31 107 0.42014 1.32 108 0.42261 1.32 1.32 109 0.42708 1, 32 1.32 110 0.4305E 1.32 1.32 111 0.43403 1, 32 1.32 112 0.43750 1,32113 1.32 D.44097 1.32 1.32 114 l 0,44-444 1.32 1.32 115 1.33 1.33 11 D.44702 0.45139 1.33 1.33 117 0.4548E 1.33 1.33 118 0.45833 1.33 1,23 119 0 45181 1.34 1.34 120 0.4652$ 1, 33 1,33 121 0.46875 1-34 1,34 122 0.47222 1,34 1.34 M3 0.47569 1.34 1.34 124 0,47917 1.35 1.35 125 0.482E4 1'34 1.34 1 0.43611 1 34 1.34 1 27 0.48958 1,34 1.34 12' 0,4930E 1.35 1.35 129 0.49653 1.35 1, 35 130 0.50004 1.35 1.35 131 0.50347 1 3E 1.36 0.50694 1. J6 T.36 133, 0 51042 1. E 1,36 1 0.51359 1.3E 1.3E 135 0.5173E 1.37 1.37 135 0.52083 1.37 1.37 137 0.52431 1.37 1.37 138 0152776 1 37 1.37 139 ❑.53125 1,37 44 0.53472 1.37 1,37 141 0.53819 1-38 1.38142 0.54157 1.38 1.38 14 0.54514 1.3E 144 0.54861 1.39 1,39 146 0-55208 1.35 1.39 14E 055556 1.39 1 39 147 0.15903 139 , 1.39 148 0.56250 1.$9 1.39 0.56597 1 39 150 I 0.56944 1.40 1 40 _ i,40 1 40 t Edw rews xiatc P.O. Bos 30653 1--rping t..,, .lysos Ralcrgh, N_c. NEUMAN's method Unconfined aquifer with delayed watertable response Pumping Test No. 5 Well 5 at Pond 5 Discharge 14.50 U.S.gadmin Static water level: 0.00 ft below datum Pumping test duration Water level 160 164 165 156 167 18 196 0.58353 0.58681 0.59026 0.6076� 0.6 1111 0.63889 0.65625 0.65972 0.67014 C57 667 0,70139 070486 0-70833 0.711$1 0.71528 0.71B75 6-72 222 0.72569 072917 0.73264 -7361I 0.73958 Date: 28.03�>. Table Project: Summerhouse at Everetts Bay Evaluated by: FEA Test CgrdLCted on: 3/03/2006 OW-5 Distance from the pumping well 20.00 f! Drawdown 1.40 1.40 1.40 1.40 1.40 1.40 1,41 1,41 1.41 1.41 1,41 1.41 1 41 1-41 7.41 1 7.41 1.41 141 1.41 1.42 1.41 142 1.42 1 42 1.42 1.42 1.42 7.43 1-42 1.43 1.43 1.43 1.43 1.43 1.44 1,44 1.43 1-44 .43 1,44 1.44 1.44 1.44 1 A4 1 .44 1 1.44 ,44 1 A4 1.44 1.44 1.44 1.45 1.45 1 A5 1.45 45 1.45 1,45 1.45 1.45 1.45 1.45 1,46 45 1,46 71.46 i 46 1.46 1.46 46 1.46 1.46 1.45 1.46 1.46 46 1,46 1.46 1.46 1.46 1.46 1.47 1.47 1,46 1.46 1.47 1.47 1.47 147 1.47 I 1,47 1.4E 1.48 1.47 1.47 1.48 1 AB 1,43 1.48 Page Pt Edw' - "rews )ciate ping t - P_0. box ouo53 ysis NEUMAN'S method P.nloigh, N.c Unconfined aquifer with delayed watertatsle response Pumping Test No, 5 Well 5 at Pond 5 Discharge 14.50 U.S.gallmin Static water level: 0.00 ft below datum Pumping test duration Water level [d] [ft] 20t 0.74653 z02 0,75000 1 203 I 0.75347 1 204 0.75694 1 205 0-7 61042 1 206 0.76339 1 207 0.76736 1. 208 0.77083 1 209 0.77431 1, 21C 0.77778 1. 211 0.78125 1. 212 0.78472 1 213 0.78819 1. 214 0.79167 1 215 0.79514 1. 210 0,79661 1 217 0.80208 216 0.80556 1 0.80903 1' 0-8125C 1 =224 0_51597 1., 0_a1944 1 0.62292 1 a,azs39 1.; 225 0.82986 1,! 226 0.83333 1 22r 0.33681 1.: 228 0.84028 229 0.64375 230 0.84722 1 , 0.85069 1 232 0.35417 1 ; 233 0.85764 1.` 234 0.86111 1 1 r 235 0,66455 _ 236 0,86806 1" `'3 7 0.87153 1 239 0,87500 1 E 23S 0:87847 1.5 240 0.88184 J. 5 241 0,88542 1.5 242 ' 0.85899 1.51.5 243 0.89236 244 O.S9583 1.5 245 0.39931 1 5 246 0.90278 1.5 247 0.90625 1, 5 243 0.90972 1.5. 249 0.91319 1.5 z50 0.91667 1 5 1.5; ❑a e. en.03.200b CTable No. 56, Page 6 Project; Summerhouse at Everetts Bay Evaluated by: EEA Test conducted on, 3/03/2006 C W-5 Distance from the pumping well 20,00 ft ❑rawdown [ft� 46 1.46 46 1.46 47 T47 47 1,47 � 48 1,48 48 1,48 -1 4$ 4a -1 49 -49 'i 1.47 17 1.47 1 17 1.47 '6 1,45 19 1.49 1.49 t9 T.49 i0 51.0 50 1.50 50 1 50 i0 -1 S0 io 1.50 0 1.5c ic 1.50 io 1,50 1 1,51 1.51 1.51 51 1 7MZ1 1 1 2 21111 2 1 52 2 152 2 1.52 1.52 i - 1,52 1.52 1.52 1.53 1,53 i 1.53 i 153 I 1.53 1.53 _„zp ...YSIS Edw rews tciate. P.O. Box 30653 NEUMAN's. method Raleigh, N.c Unconfined aquifer with delayed watertadle response Pumping Test No. 5 Well 5 at Pond 5 Discharge 14.50 U.S.gall Static water level: 0.00 ft below datum Pumping test duration Water level o,9z361 0.92708 0.94097 094444 0.94792 0.95139 0.95486 0.95823 0.96181 0.96528 0.96875 0,97222 0.97569 0.99306 1153 1,54 1.54 1.54 1.54 1.54 1.54 I.S4 1,54 1.55 1.55 1.54 55 1.56 1.56 1.56 1.56 1,56 1.56 1.56 1.56 1.56 Dare' [6.03.Z�0015 �. p Table 5B, Page 7 Project: Summerhouse at Everetts Bay Evaluated by: EEA Test conducted on: 3/0312006 OW-5 Distance from the pumping well 20,00 ft D ram down 1.53 1,53 1,54 1.54 1- 1.54 1.54 1.54 1.54 1.54 1,5 1.55 1.55 1.54 1.55 1.56 .56 1 FR Edwi _ _pws i_ date p ng ie urysis P.O. Box30663 NEUMAN's method Rrlmgh, N.0 UrlCDnflned aquifer with delayed watertable response Pumping Test Ne, 5 Test conducted on: 3/06/2006 PW-6 Discharge 5.00 U.S.gallmin 0 0 Da e. 40.u3 2006 Table. No. SC, Page 1 Project: Summerhourse at Everett Bay Evaluated by: EEA IN10 10 107 tn3 In4 5 _F o OW-5 Transmisslvity [ft'Id]: 2.42 x 10z Hydraulic conductivity [ftld]_ 1 15 x 101 Aquiferthickness [ft]: 21.00 Storativity: 1M x 10-5 Hydraulic conductivity vertical [fVd]: 7.62 x 10-1 Specific yield: 1,63 x 1C' 8dw1 mws i a �� i� _.7sis - P.O. Box sugping 53 - Oaic. ...u3.2006 F- able. No. 5C, Page 2 NEUMAN's method G Raleigh. n' Unconfined aquifer with Project Summerhourse at Everett Bay delayed watertable response Pumping Test No. 6 Evaluated by: EEA Test conducted on: 310612006 P W-6 OW-6 Discharge 5,00 U.S.gallmin ❑ft Static water level: 0.00 fl below datum Distance from the pumping well 20.00 Pumping test duration Water level Drawdown 1 [d] [tt] 0,01042 [n] 2 0.48 0.48 0.01369 0.55 0.02431 0.55 0,02773 ° 56 0.56 0.03125 0.56 0.56 0. D3472 0.67057 0.03819 0.56 0.58 0 58 0.04167 0.58 0.04514 0,57 0.57 6.57 0.57 �10,04661 052080505556 0.57 0.59 °.05903 D.59 0.59 0,06250 0 59 0.59 0.60 0.05597 0.60 O.Ofi944 0.60 0.60 0. C7292 0, 60 0.60 0.07639 0,60 ° 6° 0.60 0.07986 0.60 0,05333 0.61 0.61 0,61 0.02681 0,61 0.091028 0.61 0.61 D.09375 0,61 0.61 0.61 C.09722 0.61 0.10069 0 61 0.61 0.10417 0.51 I :;: 0.10764 0.61 0.11111 0.61 0.61 0.114 66 0.61 0.61 0.6Z 0.11 BOB 0.52 0,12153 0,62 0.52 0.12500 0.61 0.61 0,12847 0.61 0.61 D.13194 0.61 0,61 ,73542 R.62 0.62 0.13889 0.62 i 0,62 0.14236 0.62 0.52 0,14563 0,62 0,62 C.14931 0.62 0,62 0.15278 0 63 0, 63 0 15625 0.6y 0 .63 4.15972 0.63 0.63 0.16319 0.63 D.63 0.16667 0.63 CM 0.17014 1 0, 63 0.63 0.173 61 0.63 0,53 0.17708 O.fi4 e4 0.64 0.1 0056 0,64 0.64 4.64 10.64 Edwir ' ews F ciate, -P.O. Bo"o_ _ping tE_ ;sis Dates, : �3 ` I i aole�No. 5C Page oa3 - - NEUMAN's method Ralmgh, N.C. Unconfined aquifer with I Project. 5ummerhourse at Everett Bay Pumping Test No. 6 delayed watertahle response Evaluated by: EEA Test conducted on: 310612006 P W-6 OW-6 Discharge 5,00 U.S.gallmkn Distance from the pumping well 20.00 ft Static water level: O.DO ft below datum pumping test duration Water level Drawdown 0.1S403 L" j 52 0,18750 0.64 D.64 53 419097 0.65 0,65 54 0. f 9444 0.56 0.65 55 0.19792 0.65 0.65 56 0,20139 0.65 0.65 57 0.20486 4,65 0,65 56 0.20a33 0.55 0,65 59 0.21181 0.65 1 0.65 64 0.21520" 0,65 0.65 61 0, 21675 0.66 0.66 62 0.22222 Q.66 0.56 63 0.22569 0,66 0.66 64 0.22997 0.66 0 fi6 0.23264 0.66 0.66 Be66 4.23611 0'6 0.67 67 0.23958 0.66 0.66 68 0.24306 0.67 0.67 69 0.24653 0.67 057 70 0.25000 0,67 0-67 71 0.25347 0.67 0.67 72 0.256 44 D,67 Q.67 73 0.26042 0.65 0.68 74 0.26389 0.66 0.68 75 0.26735 0.59 0.69 76 D.27083 0.69 0. fi9 77 0, 274B1 0.69 0.69 78 0.27775 0.69 0.69 79 0,28125 0.69 0, 69 $0 0.28472 D.69 0.69 81 0.28819 0.69 0.69 82 029167 0.69 0.69 63 0.29514 0.69 0.69 84 0.29861 D 69 0,59 85 0.30208 0.5 0.69 Sfi 0.30556 mg 0.69 87 0.30903 0.70 0.70 88 0.31250 0. 4.69 $9 0 a 1597 070,70 0.70 g0 0.31944 0,70 0 70 91 1 0.32292 0.70 0.70 92 0.32639 0,70 070 93 0 .700.32986 0, 70 94 0.33333 0.70 0.70 95 0.33681 070 0.70 96 0,34025 0.71 0.71 97 0.34375 0'71 0,71 9S 0.34722 0.71 0.71 99 0.35069 0 71 0 71 t 00 0.35417 0,7i 0.71 0.71 0.71 -dwir ,WS 8 :iates JIng te:_ _ ais nat� 2006.No. _ e a P.O, Box 30653 NEUMAN's method tl Raleigh, N.C. Unconfined aquifer with Project: 5urnmerhourse at Everett Bay delayed watertable response Evaluated by: EEA Pumping Test No. 6 Test conducted on: 310612006 PW-6 QW 6 Discharge 5.00 U.S.gallmin Distance from the pumping well 20.00 ft Static water level: 0.DO fl below datum Pumping test duration Water Level Drawdown Id] [ftj Ift] 101 0, 35764 0.71 0.71 102 0,35111 0,72 0,72 103 0,36458 0.72 0.72 104 0.36306 0 72 0.72 105 037153 0.72 0.72 106 0.37500 0,72 4.7_ 2 107 0,37647 0.72 0.722 10E 0.38194 0,72 0.72 109 0.38542 4.72 4.72 110 10,33889 0.72 1 072 111 0.39236 0,72 0,72 112 0.39583 0,72 E 0.72 113 0.39931 0 72 0,72 114 0.4027E 0,72 0,72 115 0.4Q625 0.72 0.72 116 0.40972 0,72 0.72 117 0.41319 0.72 0.72 118 0.41667 0-72 0.72 119 0.42014 0,73 0,73 120 0.42351 0,72 0.72 121 0.427D5 0.72 0.72 12-2 0.43056 0.72 0.72 123 0.43403 0.73 0.73 124 0.43750 0-73 0.73 125 0.44097 0,73 0.73 126 0.44444 0.73 0.73 127 0.44792 0,73 0.73 128 0.45139 0.73 0.73 129 0.4548fi 0.73 0,73 130 0,45833 0.74 0.74 131 0.46181 0.74 C.74 132 0.46528 0,74 0.74 133 0.46875 0.74 0.74 134 0.47222 0.74 0,74 135 0.47569 0.74 0.74 136 0.47917 0.74 0.74 137 0.48264 074 0.74 138 0.48611 0.74 0.74 139 0.48958 0.74 0.74 140 0.49306 0,74 q,74 141 0.49653 0.74 0,74 142 0.50000 0.74 0.74 143 0.50347 0.74 0.74 144 0.50694 0.74 0.74 145 O.51 D42 0.74 D.74 146 D.51389 0.74 0.74 147 0 51736 0.74 D.74 148 052063 0.74 0.74 149 0.52431 0.74 0.74 150 0.52778 0-75 0,75 idwin_ wa & _,sates, - - --wing tea. -Is = ---�� ❑atE 20 No- P.O. Box 30653 NEUMAN's method Amcigh, N,a Unconfined aquifer with Project: Summerhourse at Everest Bay delayed watertable response Evaluated by: EEA Pumping Test No. 5 Test conducted on: 310612006 PW-6 OW-6 Discharge 5,00 U.S.gallmin Distance from the pumping well 20.00 ft Static water level: 0.00 ft below datum Pumping test duration Water level ❑rawdown Id] I [ftl I I 0.75 152 0 53472 0.75 0.75 153 0.53819 0-75 0.75 154 0.54157 0.75 0.75 155 0, 54514 0,75 0.75 156 0.54851 0.74 0.74 157 0, 5520B 075 0.75 158 0, 55556 0.75 0.75 159 0.55903 0.75 0-75 160 0,56250 0,75 0.75 161 0.55597 0.75 0.75 162 0.56944 0.75 0,75 163 164 0,57292 0, 57639 0,75 0.75 0.75 0.75 155 0.57966 0.76 0.76 166 10,53333 0.76 0,76 167 0.58681 0.76 0,76 168 0 59026 0,76 0.76 169 759375 4,76 4.76 170 0.59722 0,77 0.77 171 0,50069 0.77 0 77 172 0.60417 0-77 0.77 173 0, 60764 0.77 0.77 174 0, 61111 0.77 0.77 175 0.61458 0.77 0.77 176 0.61606 0.77 0.77 177 0.82153 0.77 0.77 178 0.62500 0.78 0.78 179 0.62847 0.78 0.78 180 0.63194 0-78 0,7e 181 0.63542 0,77 0.77 182 0.63869 077 0,77 183 0.64236 0,77 0.77 184 0.64583 077 0.77 j 1B5 0,54931 0,77 0.77 186 0,65278 0.77 0,77 187 0.65625 077 0.77 188 0,55972 0.78 0.76 189 O.B6319 0.78 0.78 190 0.5566 7 0.73 0.78 191 0.67014 076 0.78 192 0.57361 0.78 10,78 193 057708 0.7E 0.78 194 0.68055 0-78 0.78 195 0,68403 0.76 0, 78 196 0.68750 0.79 0.79 197 0.69097 0.76 0,78 198 0.69444 0.79 0-79 199 0.69792 0.79 0,79 ," 0.70139 0,79 0.79 =dwin !ws & :iates -� E' ---Inc tee �is i ❑ate _ ._ 2nn8 - ni„ o G P.D. Box 30653 NEUMAN's method Raleigh, N.0 Unconfined aquifer with Project; Summerhourse at Everett Bay delayed watertable response I Evaivated by: EEq Pumping Test No. 6 Test conducted on: 310612006 JPW"6 CW-6 ] Discharge 5.00 U,S.gallmin ❑Istance from the pumping well 20.00 ft Static water level: 0,00 ft below datum 201 202 Pumping test duration [d] 0.70436 0.70833 Water level Crawdown in] Ini 0.78 0.78 0.79 0 79 203 204 0.71181 0.71528 0.79 0.79 0.79 0.79 205 0.71875 0.79 0.79 206 207 0.72222 0.72569 0.79 0.79 0.79 0.79 208 209 210 0.72917 0,73264 0.73611 0.79 0.79 0,79 0.79 0.79 0.79 211 212 0.73958 0.74306 0.79 0.79 0.79 0 79 213 0.74653 0.79 0.79 214 0.75000 0.79 0,79 215 0.75347 079 0.79 215 217 218 0,75694 0.76042 0.76389 0.79 0.80 0.79 0.79 0.80 Q79 219 220 0.76736 0.80 0.77083 0.80 0.80 0.8D 221 0.77431 0,80 0.6D 222 0.77778 0-79 0, 79 223 0.78125 0.79 0.79 224 0.78472 0.79 0.79 225 0.78815 0,79 0.79 225 0,79167 0.79 0.79 227 0.79514 018D 0 8p 228 0.79861 0,80 0.80 229 0,80208 0.80 0.80 230 0,80556 10,50 0.8D 231 0.80903 0,30 0.8D 232 0.81250 0.80 0.80 233 0.81697 0, 80 0.8D 234 0.81944 0.50 0.80 235 0,82292 0.50 0.8D 235 0.32639 0.60 0 60 237 0.82985 0.80 0.80 23S 0.83333 0.80 0.80 239 0.33631 0.80 0,80 j 240 0.84028 0.80 0.80 2 11 j 242 0.84275 0.84722 0.80 0.80 Mac 0.80 243 1 244 0.85069 0.85417 0.80 0.80 0.80 0.80 245 0.35764 0.81 0.81 246 D.86111 0.81 j 0.81 47 2149 0.86458 0.80 0.90 480.86806 080 0.80 0.87153 0.80 0.80 250 0.87500 0.80 0.80 cdwir_ . _ ±ws 8 ;iates,. P.O. Box 80653 NEl1MAN's method Raleigh, N.C. Unconfined aquifer with delayed watertable response Pumping Test No. 6 PW-6 Discharge 6.00 u.S.gallmin Static water level: 0.00 ft below datum Pumping test duration Water level [d] Ift1 0.68194 0.88542 0,88889 0.89236 O39583 039931 0.90278 090625 0, 90972 0.91319 0.91567 0.92014 0.92351 0.93403 0.93750 0.94097 0.94444 0.94792 0,95139 OS5466 0.95833 0.97222 0,81 o-s1 0.81 0,81 O.H1 0,81 0.81 0.81 0.81 0,8C 0.81 0,81 0.81 0.81 0.81 0.81 0.81 0.81 0.81 0.81 0.81 0.81 0.H1 0.83 0.83 0.83 2006 i euie. No. zL,, rage 7 Project: Summerhourse at Everett Bay Evaluated by: EEA Test conducted on: 3/06/2006 C W-6 Distance from the pumping well 20.00 ft ❑rawdown [ft] 0,81 O.H1 0.81 0,81 0.81 0.81 0.81 0.81 0.81 0.80 0.81 0.81 0.81 0.81 0.81 0.81 0.81 OL%oTechnologies, March 15, 2006 Kevin Eberle, P.E. I-VICK NI & CREED, Y.A. 200 Maekenan Court, Suite 200 Cary, NC 27511 Re: Report of Subsurface fnvcstigation Proposed Everet Bay WWTP and Infiltration Basins Holly Ridge, North Carolina GeoTcchnologies Project No, 1-06-0200-EA Gentlemen: 3200 Wellington Court, Suite G Rolelgh, North Carolina 27b15 919-954-1514 Fax 919-954-1428 GeoTechnologies, Inc. has completed the authorized subsurface investigation to evaluate foundation support considerations for a new WWTP and several infiltration ponds to be constricted at the Everet Day development in Holly Ridge, North Carolina. Subsurface conditions at the site were investigated by drilling 35 soil test borings in the approximate locations shown on the attached Figures IA and 1B. These locations were established in the field by the project surveyors, and therefore the locations should be considered accurate. The borings were advanced to a depth of 25 to 50 feet below existing grade utilizing rotary mud drilling techniques. Soils were sampled at selected intervals using standard penetration test procedures designated in ASTM D-1586. Ail exception were borings B-10 and B-25 which could not be accessed with the drill rig and were advanced with hand augering techniques to depths of 4 to T5 feet below grade. This report presents the findings of the investigation and our recommendations for site grading and foundation support. ME AND PROM CT INFORMATION The proposed project will involve construction of a WWTP and several infiltration ponds to service the Everet Bay development proposed for constriction off of Holly Ridge Road in Holly Ridge, North Carolina. The WWTP includes several structures including an equalization basin, digesters, MBR units, an odor control unit, operations building, and the in -plant pump station and reclaimed water pump station. The equalization basin will be supported approximately 2 feet below grade on a 35 x 35 foot slab and will have a 19 foot liquid height. The sludge digester will consist of two units with dimensions of 33 x 33 feet with approximately 12 feel of liquid height, 1-lic MBR units will consist of two pairs with dimensions of 100 x 40 feet. Each MBR unit will have a weight of 427 tons per hair. The odor control units will be supported on 25 x 15 foot stabs with a total equipment weight of 66,000 lbs. The operations building will be an approximately 60 x 15 foot building with the heaviest equipment being a generator weighing approximately 24,000 lbs. There will also be a chemical storage arca in the building with a loading of 5,000 lbs. The proposed pump stations will be frilly embedded; however, the invert depths are unknown at this time. In addition to the WWTP, nine infiltration basins are also proposed as part of the new development. The infiltration basins are expected to be constructed by excavating 6 to 8 feet below existing grade. Geolechnicol and Construction Malorials rosling services McMin & Creed, P.A. Pveret Bay WWTP March 15, 2005 Page: 2 At the time of our investigation the site consisted primarily of undeveloped woodlands and fanii fields. The site appeared to be relatively flat with some drainage ditches extending through the property. SUBSURFACE CONDITIONS Generahzed subsurface profiles prepared from the test boring data are attached to this report as Figures 2 through 6 to graphically illustrate subsurface conditions encountered at this site. Mare detailed descriptions of the conditions enCOLIntered at the individual test boring locations are then presented on the attached test boring records, The subsurface profile in the area of the WW"I'P (13-1 through B-9) was found to consist of a mixture of clean to silty and clayey sands interbedded with sandy and silty clays, Typically, the near surface soils within the upper 2 to 3 feet consisted of silty and clayey sands, with penetration resistances of 3 to 10 blows per foot (bpo, which transition into sandy and silty clays. The clays generally extended to depths of no more than approximately 6 to 8 feet below grade, with penetration resistances of to 10 bpf, where they transition back into slightly silty to silty sands. The sands were generally encountered to depths varying from 16 to 22 feet below grade and exhibited penetration resistances of 2 to 20 bpf. Underlying the sands, the soils transition into sandy and silty clays. 'These deeper clays were typically soft to very soft in consistency with penetration resistances ranging fi•om 0 to 7 blows per foot (bpt). Underlying the clays, the soils transition into clean to silty and clayey sands with penetration resistances varying from 6 to in excess of 50 bpf These materials generally extended to approximately 45 to 47 feet below grade where marl was encountered. The marl was generally sampled as silty sand with shell and limerock fragments, and penetration resistances within these materials varied from 16 to in excess of 100 bpf. Generally, the penetration resistances exceeded 50 bpf within the underlying marl materials. l;xceptions to this profile were encountered at borings 13-1, B-3, B-7, B-8, and B-9 Micro either peat or organic clays were generally encountered between depths of 30 and 35 feet. Peat was not encountered in the remainder of tine borings. Groundwater in the WWTP area was generally about 2.5 to 3 feet below grade. The borings encountered within the ponds were somewhat different. The ponds which were drilled just south of the proposed W WTP encountered similar conditions to the WWTP with near surface sands underlain by clays that extended to depths of 12 to 14 feet before then transitioning back into sands intermixed with peat and clay layers. These materials were encountered to 25 feet, the termination depth within the pond areas. The borings which were completed in ponds oar other portions of the site generally encountered much sandier soils with the majority of the borings encountering slightly silty to silty and clayey sands with occasional clay layers. In general, it appeared that tine borings completed on the southerrunost portions of the site gene;ally encountered much sandier soils. The clayey soils appeared to be predominant in the area near the WWTP and in the pond areas immediately south of the proposed plant site. In general, groundwater was typically encountered at depths of about 2 to 3.5 feet below grade at the time o f boring completion. McKim & Creed, P.A. Cveret Bay W_WTP March 15, 2005 Page: 3 RECOMMENDATIONS The following recommendations are made based upon a review of the attached test boring data, our understanding of the proposed constriction, and past experience with similar projects and subsurface conditions. Should existing plans change significantly from those now under consideration, we would appreciate being provided with that information so that these recommendations may be confirmed, extended, or modified as necessary. Additionally, should subsurface conditions adverse to those indicated by this report be encountered during construction, those differences should be reported to us for review and cotnur►ent. Site Grading Considerations. The first step in site preparation should involve the removal of all vegetation and topsoil from beneath the proposed structure locations. Generally, we anticipate topsoil thicknesses will be less than 6 to 12 inches; however, it is possible that some deeper stripping may be required in areas where tree root bulbs exist. Following stripping operations, it may be necessary to perform some discing, drying, and recompacting in order to stabilize the near surface soils for subsequent building constriction. The need for discing and drying will be largely dependent on climatic conditions at the lime that grading commences. Additionally, groundwater levels were relatively high, and some ditching may be required to temporarily lower groundwater conditions which will facilitate construction operations, The on -site soils, with the exception of topsoil and Highly plastic clays, will be suitable for reuse as structural fill. The highly plastic clays could be utilized in deeper fill sections; however, given the relatively flat nature of the site, we do not anticipate that deep fill areas will exist beneath structural components of the development. All fill material placed beneath structural areas should be compacted to a minimum of 95% of the standard Proctor maximum dry density except in the final foot where this requirement should be increased to 98%. Below Grade Construction. We understand that the pump stations will be fully embedded below grade. Due to the high groundwater conditions and the sandy nature of the subsurface soils, we anticipate that aggressive dewatering will be required in order to permit construction of below ground structures. We recommend that auy below grade construction be dewatered with closely spaced well points to provide a dry area for construction of those structures. We recommend that design of the dewalering system be left as a responsibility of the contractor. Below grade structures should be designed to resist earth pressures assuming a triangular lateral earth pressure distribution computed based on an equivalent fluid pressure of 50 pef above the groundwater table and 95 pcf below the groundwater table. Although groundwater was measured at a depth of about 2 to 3 feet at the time of this investigation, it should be recognized that groundwater could rise to near the ground surface during storm events such as hurricanes. We recommend that all below grade structures be designed to resist hydrostatic uplift pressures which could increase significantly when the structures are emptied for maintenance, Hydrostatic uplift could be resisted by increasing the size of the base slabs to engage additional weight of soil or by installing some type of anchor such as lielical anchors into the underlying soil. 00010 1"nologlo5,Inc. McKim & Creed, Y.A. Everet Bay W V P March 15, 2005 Page: 4 Foundation Support Considerations. GeoTechnologics has evaluated support of the proposed WWTP structures on both mat foundations and driven piles. If mat foundations are utilized, we rcconunend limiting bearing capacities to no more than 1,500 psf due to the softer near surface soils which exist in some areas. Given the relatively large sizes of the mat foundations, our calculations indicate that a 1,500 psf pressure will likely accommodate the majority of the structures, Careful inspection of any mat or shallow spread footing foundations should be conducted to verify that the exposed soils are suitable for support of the contact pressures. The majority of the borings appear to fall out of the actual location of the plant, and some verification through inspection will be necessary. If supported on shallow foundations, the estimated settlements for the structures is expected to be approximately the amount shown in the following table. Structure Total Settlement (Inches) Basin 5.3 —Equalization Digester 3.9 NIBR 2.9 Odor Control Building 1.0 Operations Building <1.0 These total settlements include the estimated secondary consolidation which will likely occur due to the presence of a peat strata between approximately 32 and 36 feet below grade. We anticipate that differential settlements will be approximately one half the magnitude of the total settlement. The total settlements can be reduced by preloading the structures with approximately 10 to 15 feet of soil; however, we anticipate that a 90 day waiting period would be required for the preconsolidation to occur. Settlement monitoring could be performed by placing settlement plates on the subgrade prior to placement of the surcharge load to determine when the preconsolidation settlements have reduced to an acceptable level. If you desire to consider surcharging and use of shallow mat foundations, we would appreciate an opportunity to more accurately calculate the required surcharge heights at each structure where this is being considered. In the event the structural engineer determines that the proposed settlements are excessive for shallow foundations and inadequate time exists for surcharging structure locations, consideration could be given to utilizing driven piles for support of some or all of the structures. The piles will need to be driven to a depth of approximately 40 feet or more to bear below the peat materials which were encountered within many of the borings. Typically, driven timber piles are the most economical method for support of these type structures when peat materials are encountered. However, some dense sands exist above the peat layer in several of the borings, and it is unlikely that timber piles can be driven to the required depth without either jetting or preaugering to depths of as much as 35 feet in sonic locations. If timber piles are utilized, they should be driven with a hammer having a minimum rated energy of 15,000 ft. lbs. and should achieve allowable capacities of 25 tons per pile when driven to depths of 40 feet to bear below the peat strata. Alternately, a steel 12 x 53 H-pile section could be utilized which could be driven to bear at 40 to 50 which would be feet below the peat materials. We do not anticipate that predrilling or jetting would be necessary for the steel piles; however, some difficult driving should be expected. If steel piles are utilized, allowable capacities of up to 40 tons could be utilized without the need for Geo%thnoingi�s, lnc, McKim & Creed, P.A. F.veret Bay W WTP March 15, 2005 Page; 5 performing load testing. If steel piles with an allowable capacity of 40 tons are utilized, it should be anticipated that embedment depths of as much as 45 to 55 feet could be required in some areas of the treatment plant. We recommend that piles be driven to a dynamic driving criteria calculated from a suitable formula such as the ENR formula or the Ailey equation. Pile driving should he monitored to verify that the required capacities have been achieved. We recommend that the slabs be structurally supported on the driven piles to prevent excessive settlement of area slab loads. Alternately, the slab areas could be surcharged with approximately 15 feet of material to preconsolidate the underlying peat. However, it should be understood that surcharging periods could be as long as six months and that the secondary compression of peat materials will be relatively large which could result in some Iarger than desired long-term settlements. As such, we strongly advise that pile foundations be utilized beneath all elements of the WWTP. The attached Figures 7 and 8 present pile capacities vs. depth for both timber piles and steel H-piles. However, as previously discussed, we anticipate that significant difficulty will be encountered when utilizing timber piles due to the deep prcdrilling or jetting depth which would be required to penetrate below the peat strata. Embankment Construction. The first step in embankment construction should be the removal of all vegetation and topsoil from areas where the proposed ponds will be constructed. Following removal of the topsoil, we recorntnend the subgrades be inspected to verify that no repairs are required prior to placement of embankment materials. This can be performed by proofrolling with a partially loaded dump truck. Based on the results of the soil test borings, we do not anticipate that any significant repairs will be required. The on -site soils consist of a mixture of sands and clays. Due to the high groundwater conditions, we anticipate that the majority of the soils will be wet of optimum moisture content. The sands can be stockpiled and allowed to drain and will be relatively easy to reuse as structural Fill. However, the clays will likely require spreading, discing, and drying in order to achieve proper compaction with these materials. We recommend that all nratetials placed within the embankment be compacted to a minimum of 95% of the standard Proctor maximum dry density. Additionally, we recommend that consideration be given to constructing slopes no steeper than 314;1V for long-term stability considerations. It should be noted that the study did not include any evaluation regarding permeability of the on -site soils. However, the sands which exist on the site are expected to have relatively high permeabilities. Grain size distribution tests can be performed on some of the obtained samples if you desire. Alternately, field tests can be conducted to better evaluate infiltration rates. Infiltration Basins. We understand that numerous infiltration basins will be constructed throughout the development. It is desired that the infiltration basins be able to percolate out as much water as possible. Generally, the subsurface profile consists of a thin veneer of near surface sands approximately 2 to 3 feet deep, underlain by clays which generally extend to depths of 6 to 8 feet. If the ponds are excavated to extend below the clay layers, loading of water into the pondd should create some head which will help water seep out of the battorn of the ponds. Groundwater will typically exist at approximately 2 to 3 feet below existing grade, and a head above this level will be required to create the necessary head to force water flow out of the bottom of the ponds. We understand that an exception will he the larger pond located in the central portion of the site which is desired to hold water year around. In this pond area, we suggest that consideration be given to utilizing the pond as a GeoTechnologies, Inc. McKim & Creed, P.A. Everet Bay WWTP March 15, 2005 Page: b borrow pit area and excavating the pond to obtain structural fill required throughout the development for lot and road construction. The sands which will exist within this area will provide excellent structural fill although they will likely be wet of optimum moisture content and will require some stockpiling and drying time in order to achieve compaction with those materials. Additionally, dewateting will be required in order to operate equipment within the base of the pond area. Once the area has been mined out to obtain the desired inatedal, waste soil such as topsoil and wet plastic clays could be placed back within the base of the pond to create a more innpentieable layer which will help retain water during drier months of the year. Seismic Design Considerations. Based on the results of the soil test borings, as well as our review of the North Carolina Building Code, we recommend the site be designed for a site class "D" with regard to soil seismic design classification. GeoTechnologres, Inc, appreciates the opportunity to be of service on this phase of the project. Please contact us if you have any questions concerning this letter or if we may be of additional service on this or other projects. Sincerely, GeoTechnologics, Inc. - t Dav I. Isr el, P.E. NC Registration No. 14319 DLUpr-eblOam Attachments 060200ea.doc CA Q�o��ss�ati� .d SEAL ` 14319 e s • e Nttr Ge*Technole&i ,W. 1 • V I �I' O.S.ECT BASIN .gll,il��y f @D AT -"STORAGEIp I100 80, CAPACVTY} 'I, •1I�' / _ I J 0. At -12 ut . � 1 It .f - � • �! ,C_ PROJECT-: SCALE: Not to Scale JOB Flo: 1 -06-0200-EA Everet Bay %%coTechnologies, Ho,ly Ridge, c- North Carolina �......... FIGURE No: IA , PROJECT: Everet Bay Holly Ridge, North Carolina 'ScaLE: N©'= to Sua1e Depth (Feet) B- 1 B- 2 0 77A 3 4 5 5 I;L•I, 9 10 fI-t: } 5 ,1I1 I ; '• 7 15 I•:II:!•. ;CII 7 I, � �I I:I.I 5 20 2 1 25 71 53 30 54 48 35 21 39 40 21 29 45 35 59 50 5015.5" 5015.5" 55 PROJECT: Everet Bay Holly Ridge, North Carolina GENERALIZED SUBSURFACE PROFILE LEGEND B- 3 B- 4 B- 5 B- 6 B- 7 ■ Topsoil 10 VA IiA 8 4 7 3 6 Clayey Sand 10 7 5 4 10 Moderate Plasticity Clay I•I I Poorly -graded raded Sand with Sift y-g 1. I Paorly-graded Sand ^� Peat 7 6 9 3 g S71ty Sand 2 1 1 4 3 ® Law Plasticity Clay Hlgh Plasticity Clay 2 5 WOH 2 4 ® Marl High Plasticity Organic Silt or Clay 6 10 2 11 5 Shells & Sand i I�1 7 13 9 6 11 8 Standard Penetration Resistance Groundwater at Time of Baring .I I, 42 55 63 11 21 68 72 " . 26 22 III � I 8 5016" 60 16 5015" 7 1 r. JOB i�o:1-06-2C- Depth (Feet) GENERALIZED SUBSURFACE PROFILE B- 8 B- 9 B-10 B-11 B-12 B-13 B-14 7 6 6 -�Z 3 g 5 7 6 5 8 9 10 4 3 .��� & 1 7 4 2 15 1 2 14 9 WOH 20 2 20 ' 13 J j 3 5 6 25 3 3 '1�� 11 2 4 13 3o 7 4 35 10 6 40 21 21 45 64 31 50 50 5011 " 55 PROJECT: SCALE. As Shown Everet Bay Holly Ridge, North Carolina I' Fq JOB No:1-06-0200-EA r :�- LEGEND Topsoil Silty Sand ® Low Plasticity Clay Poorly -graded Sand with Silt ® Clayey Sand ® High Plasticity Clay 99 Peat ElPoorly -graded Sand Marl j/ High Plasticity Organic Silt or Clay UModerate Plasticity Clay Low Plasticity Silt 8 Standard Penetratlon Resistance Groundwater at Time of Boring Depth (Feet) GENERALIZED SUBSURFACE PROFILE B-1 5 B-16 B-25 B-26 B-27 B-28 B-29 0 2 Q 6 5 Q 2 szIl 4 3 4 12 17 16 7 1�� 10 WOH 4 38 12 14 WOH 16 5 13 4 12 20 14 WOH J" fla IJ 11 Ill 9 2 22 f I' j.l {I. 24 _L•L 15 26 5 10 17 2 11� 10 PROJECT: SCALE: As Shown Everet Bay JOB No:1-06-0200-EA Holly Ridge, North Carolina FIGURE No:4 LEGEND ■ Topsoil Silty Sand High Plasticity Clay Poorly -graded Sand with Silt Clayey Sand Poorly -graded Sand Low Plasticity Clay ❑ 8 Standard Penetration Resistance V Groz3ndwator at Time of Boring Depth (Feet) GENERALIZED SUBSURFACE PROFILE LEGEND B-30 B-31 B-32 B-33 B-34 B-35 B-36 Topsoil 7/ Poorly -graded Sand 2 5 f' 7 8 6 5 5 3 Clayey Sand 17 4 Poorly -graded Sand with Slit 4 34 7 8 7 Silty Sand 6 j. High Plasticity Clay 8 ❑ B Standard Penetration Resistance Groundwater at Time of Boring 10 24 5 7 7 2 as 2 12 14 is 8 a 3 5 7 2 16 18 :20 20 3 4 3 12 2 2 22 24 mj, A 9 3 10 34 23 WOH 16 26 --- PROJECT: SCIALE: As S�,,-_vvn V J C B N c: 1 -0 c -,_� 2 3:� - E Everet Bay CjSpTechnologies, Inc. — Holly Ricdo ge, North Carol;ra GENERALIZED SUBSURFACE PROF11LE LEGEND B-37 B-38 B-39 B-40 B-41 B-42 B-43 ■ Topsoil 0 Poorly -graded Sand 2 2 4 5 3 6 I 2 7 Silty Sand rr 4 Clayey Sand 5 5 12 4 Low Plasticity Clay 6 Poorly -graded Sand with Silt High Plasticity Clay ❑ 8 Standard Penetration Resistance 5 3 WOH 11 V Groundwater at Time of Boring 12 14 7 8 16 4 3 16 i'f �,i i. 18 20 18 WOH 5 12 Il s 10 22 24 22 26 WOH 7 15 7 6 PROJECT: SCALE: S�-ovvr, JOB No:1-06-0200-EA Everet Bay OeoTechnerr i- Holly Ridge, North Carolina FIGURE Nc:6 DEPTH (FT.) 0.0 0. 7,i 16.' 21.1 25. LTEST BORING RECORD DESCRIPTION ELEVATION PENETRATION BLOWS PER (Fr.) (BLOWS/FT.) SIX INCHES n to )n to Fn inn To soil Sp_ + q -- 2-2-3 3-3-3 15-14-10 9-7-8 3-9-11 4-4-5 2 Loose Brown Fine SAND 1 - Medium Dense Tan Fine SAND gp - 'Medium Dense Dark Gray Clayey Fine SAND SC Loose Gray Slightly Silty Fine SAPID Sp S'1 I Boring terminated at 25.5' uruttnawater encountered at 3.5' at tinge of boring. JOB NUMBER 1-06-0200-EA BORING NUMBER B-30 DATE 3 -3-06 PAGE t OF i OeoTe(hnologies, Inc, DEPTH (FT.) 0.0 0.5 2.0 7. `- 12-t 25.5 TEST BORING RECORD DESCRIPTION ELEVATION PENETRATION BLOWS PER (FT.) (BLOWS/FT.) SIX INCHES n to in an 6n inn TQ spsl SM 2-4•S 5-6-5 laa 4-5-5 Ve l.uose Black Silty Line SAND tvledium Dense Light Gray Slightly Silty Fine SAND Si' SSuI Very Sall Gray CLAY CHl-0.0 Medium Dense to Loose Slightly Silly Fine Sr1N1) 5P SM f i{ 1 1 � �I Baring terminated at 25.5' kiraunawater encountered at 2' at time of Boring. JOB NUMBER BORING NUMBER DATE PAGE I OF 1 1-06-0200-FA B-26 3-7-06 � . TEST BORIN�RECORW DEPTH DESCRIPTION ELEVATION PENETRATION BLOWS PER (IiT.) (rT.) (BLOWS/FT.) SIX INCHES 0.0 0 10 20 40 60 100 0.5 2.8 6.5 11.0 25.5 To sail S p 2-2-3 5-8-9 2-1-0 4 G-7 5-5-C 7-9-8 Loose Brown & Tan Slightly Silty Fine SAND Medium Dense Gray Silty Fine SAND SM Vety Safi Dark Gray CLAY CH i II �I �I I Medium Dense Gtay Slightly Silty Finc SAND SP SM Baring terminated at 25.5' Groundwater encountered at Tat time of boring, JOB NUMBER 1-06-0200-EA BORING NUINTBER B-27 DATE 3-8-06 PAGE 1 OF 1 25902909— GeoTe nolog=Inc. TEST BORING IZECORD DEPTH DESCRIPTION ELEVATION PENETRATION BLOWS PER (FT.) (FT.) (BLOWSI T.) SIX INCHES 0.0 0 10 20 d0 60 100 Ic Ix 17.0 21.5 25.5 Loose Dark Brown Silty Fine SAND 5Nl 221 2-2-2 2-2-2 3-a-5 l l-1 Q I Medium Dense Tan Slightly Silty Fine SAND SP scut j .� Very Loose Gray Slightly Silty Fine SAND SP S,IM -I- I l Loose Gray Slightly Silty Fine SAND SP SM It� I Very Soft Gray CLAY CH E3oring temilnated at 25.5' Groundwater encountered at Tat time of boring. JOB NUiV11BE1t 1-06-0200-EA BORING NUMBER B-23 DATE 3-7-06 PAGE l OF 1 GeoTechnologies, Inc. v TEST BORING RECORD DEPTH DESCRIPTION ELEVATION PENETRATION BLOWS PER (FT.) (FT.) (BLOWSIFT.) SIX INCHES 0.0 0 10 20 40 60100 0.3 To soil Q. Loose Tan Fine SAND 3-3-3 3 S-3-4 Dense Gray Fine SAND SP 15-18-20 Medium Dense Tan & Gray Clayey Nie SAND SC7. 7-7-3 1 ! 1-14 5-5-5 Very 3ott Dark Gray Fine Sandy CLAY CL I Medium Dense Dark Gray Slightly Silty Fine Sp SAND SN1 Baring terminated at 25.5' t C f f n t is c E l' JOB NUMBER 1-06-0200-FA BORING NUMBER B-29 DA'TH. 3-6-06 PAGE I OF 1 GcoTechnologies, Ir�c. DEPTH (FT.) 0.0 0. 3 3. 7_, tTi 25.' TEST BORING R1+;COItD DESCRIPTION ELEVATION PENETRATION BLOWS PER (FT.) (BLOWS/FT.) SIX INCHES n in )n to Kn inn To soil SP 5M .f. ! - - - 3-3-4 7-7-7 3-3-2 3-3-5 1-2-I 2-1-2 v- i Loose Light Gray Slightly Silty Fine SAND i Medium Dcase Black Silty Fine SAND w/0r9anic Traces SM Loose Tan Fine SAi4D gp Soft Gray Silty CLAY CFI Baring terminated at 25.5' UiuuJ1U%Yater encottnrerea at S.--)' at time of boring. JOB NUMBER 1-06-0200-EA BORING NUMBER B-31 DATE 3-6-06 PAGE 1 OF I GeoTe(hnologies, Inc, DEPTH (FT.) 0.0 0. 3.� 8.1 21.5 25.5 JOB NUMBER BORING NUMBER DATE PAGE 1 OF 1 FITE-�SSTBORING RECORD DESCRIPTION ELEVATION PENETRATION BLOWS PER (FT.) (BLOWS/FT.) SIX INCHES A m -)n in Kn inn 1-06-0200-EA B-32 3-6-06 TEST BORING RECORD DEPTH DESCRIPTION ELEVATION PENETRATION BLOWS PER (rT•) (FT.) (BLOWS/FT.) SIX INCHES 0.0 0 10 20 40 60 100 0.5 '1'o sail Loose Brown & Tan Rue SAND FiSP 3.0 2-3-3 Loose Dark Brown Silty Fine SAND S,M 6.0 Loose sight Brown Fine. SAND SM 2-3-4 n 12.5 3-3-4 Very Loose Gray Clayey Fine SAIND Sc 4-2-1 22.0 Dense Dark Gray Silty Cute to Medium SAND 5M w/l,kne Rock Fragments 25.5 4-12-22 Boring terminated at 25,5' V F C L F L' 0. L' a 2 4 f Groundwater encountered at 7.5' at time of boring. � JOB NUNI 3ER 1-06-0200-EA BORING NUMBER B-33 DATE 3-7-06 PAGE 1 OF i M-GOcoTechnologles,inc DEPTH (FT.) 0.0 Q 7. 12, ! 7.: 25, JOB NUMBER BORING NUMBER DATE PAGE I OF I FFT�E,�TIBI�t-NGECORD DESCRIPTION DESCRIPTION ELEVATION PENETRATION BLOWS PER (FT.) (BLOWS/FT.) SIX INCHES n Yn 7n An 4n inn 1-06-0200-BA B-34 3-7-06 mad f-- TEST BORING REcolm DEPTH DESCRIPTION ELEVATION PENETRATION BLOWS PER (r'T•) (FT-) (BLOWS/FT.) SIX INCHES 0.0 n in In an fn inn 2,8 7.0 12.0 16,5 25.5 Loose Dark Brown Silty Fine SANt D 5lv[ 2-2-3 9.9-9 3-3-d 1-t-E wolf Q c F c c f i t C f Loose ]3rotim Slightly Silty Fine SAND Sp Sf41 Mcdiunt Dense Brown Fine SA -NI D SP Loose Gray Silty Fine SAND SP Very Loose Dark Gray Silty Putt SAND SN' Boring terminated at 25,5' Groundwater encountered at 3' at time of boring. JOB NUMBER 130IUNG NUNMER DATE PAGE I OF I 1-06-0200-FA \ 1�-35 .... 3-3-06 eoTe chnologles, DEPTH (FT.) 0.0 0.5 3.0 7.0 16.0 22.0 25.5 TEST BORING RECORD DESCRIPTION ELEVATION PENETRATION BLOWS PER (FT.) (BLOWSIFT.) SLY INCHES 0 10 20 40 60 100 JOB NUMBER I-06-0200-EA BORING NUMBER B-36 DATE 3-4-06 PAGE 1 OF 1 GooTechnologies, Inc. In DEPTH (FT.) 0.0 0s 25 13.i 16.5 22.0 25.5 l TEST BORING RECORD DESCRIPTION ELEVATION PENETRATION BLOWS PER (FT.) (BLOWS/PT.) SIX INCHES 0 In zn en Tn inn to soil SY m - ---F 2-1-1 2-2-3 3-3-2 3-4-3 2-8-10 7-1 1-31 Loose Brown Silty SAND Loose Brown to Tan Fine SAND Sp Loose Brown Silty Fine SAND 5M Sc Medium Dense Dark Gray Clayey Fine SAND Medium Dense Gray Silty Fine SAND SM Boring tarnrinaied at 25.5' i JOB NUMBER 1-06-0200-EA BORING NUMBER B-37 DATE 3-2-06 PAGE i OF 1 GeoTechnologies, inc. h D DEPTH (FT.) 0.0 0.5 5.` 12,C 16.5 25.5 TEST BORING RECORD DESCRIPTION ELEVATION PENETRATION BLOWS PER (FT.) (BLOWS/FT.) SIX INCHES n in 'n ran Kn Inn To soil � SP 2-2-2 3-2-3 2-2-1 3-3-5 1-WOF1 W014 Loose Tan to Brown Fine SAND Very Loose bight Brawn Fine SA111 5P Loose fight Gray Fine SAND Sp Very Lance Gray Silty Fine SAND SM Boring terminated at 25,5' JOB NUMBER 1-06-0200-EA BORING NUMBER B-38 DATE 3-4-06 PAGE L OF l GeoTechnoIogies, Inc. DEPTH (FT.) 0.0 M 6.5 12.0 16.5 25,5 TEST BORING RECORD DESCRIPTION ELEVATION PENETRATION BLOWS PER (FT.) (BLOWS/FT.) SIX INCHES 0 10 20 40 60 100 JOB NUMBER 1-06-0200-EA BORING NUMBER B-38 DATE 3-4-06 PAGE I OF I 2-2-2 3-2-3 2-2-] 3-3-5 I-wofI WOH I b V WELL CONSTRUCTION RECORD North Carolina -Department of Environntertt and Naltrral ResourcLs -Division of Water Quality - Groundwator Section NY ELL CONTRACTOR (INDtVMAL) NAl4T8 (print}y r t' LtJa sa0 CFRTIFieATIONII 0y 1VELr, CONTRACTOR COMA NY NAM PHONE RTATF WELL CON,%fniJCI"ION pMRhjirN ASSOCIATED FYQ PRLIR7ITlI (rfanpLi ble) (if applicable) 1- WELL USE (Check Applicable Box)-- Rcsidentiai 1] MunicipaflP�_iblic it tntiustrial 12 Agricultural U Monitoring ❑ Recovery Cl Heat Pump Water Injection ® Other 0 If Other, List Use d 2. WELL LOCATION: `IopographiclUnd setting L/ Nearest Town: f� Q - County Orbs ion Midge ©Slope L]Vallcy Mr -at ,SSr s;yltgw-r ! • (gym a �i C -- (Check appropriate boat) (Stn Nam . Numbers, t amnunity, Subdivisioat, Lot a., Zip Code) Latitude/longitude of well loealion 3 OWNER: lLlvy,J�.� (dcgrtralminutlssxonds) Address //tom Ar _rA.A. , .lyl Latitude/longitude soltrce:L1GPS0Topographic reap 5-1�e 2 t) (Street or RoUG NO) (ohzok box) I`l®� arm_- _/�• �� t 6� DEPTH DRILLING LOG City of Town Strte Zip Code From To FgrrmuonDesertption 1�4_ 0*ems Arta cado- Phoar. nurnbcr 4. DATE DRILLED zvoC -- 5- TOTAL DEPTH:.i 6- DOES WELL REPLACE EXISTING WELL? YES Cl NO E" 7 STA- lC WATER LEVEL Below Top of Casing.- (Use'W' irAbuve Top of Coring) — 8- TOP OF CASING IS _ 1 FT. Above Lzrid Surtnce* _ 'Top of c�uiug terminutcd zVor Wan lindAurfrre t-ertulrtsn valiance to sccordRace With 13A NCAC 2C.011& \ 9. YIELD (-gpm): S METHOD OF TEST �- 10. WATER ZONES (depth): LOCATION SKETCH 11. DISINFECTION: Type I7i,' Amount /ram t- Show direction and distance in miles from at 1=1 12- CASING: Wall Thickne s two State Roads or County Roads, Include Ore road Depth Di<�.tneter ar-%VeigUTIL MaterW numbers and common road names. From d To Ft From J To FL From To Ft- 13. (TROUT: Depth Material Method From G To r-- 4 From Tv EI III, SCREEN', Depth Diameter Slot Size Matcrlal � From "Tam Ft '_ ! in- 1� irL From _ To FL in. 15 SAND/GRAVEL PACK Depth Size Material From TO Ft Front To Ft 16. RENLMMS: f DO I{EItEB Y CERTIFY THAT THIS WELL. WAS COI CONS7RUL l t?$ STANDARDS, AND THAT A COPY TURF OF IN ACCORDANCE WT}'H 15A NCAC 2C, NVELL O HAS BEEN PROVIDED TO 711E WELL OWNER THH. WELL DATE Submit the 0riginA to the Ilivisi0tl of Witter ¢ttality, Grottudwater Section,1636 Moil Service Center -Raleigh, NC V69!'-163-6 Phone No. (919) 733-3221, ilhin 30 d€ty& GW-1 1MV. 07/2001 WELL, CONSTRUCTION RECORD North Carolina - Department of Environment and Natural Resources -Division of Water Quality - Groundwater Section WRLL CONTRACTOR (fNDIVIDUAL) NAMIR (print)-E2 r t< INa l" r ! r�sc,Tsa CERTJHCATYON f1 G6' WELL CONTRACTOR COMPANY MOM gG_-(.v���tG�u� � PEIONEft STATE WELL CONSCRUMFLON PERATU Y1 _ A•SSSOUATED WQ PBLtPJ ITH (if applicable) (if applicable) `' 1. WFL USE (Check Applicable Box)-- Residential © Muniaipal/PubieD 1ndwkiW0 Ag[icutural0 Monitoring 0 Recovery El [feat Pump Water Nection 0 01116r 0 If Ochs , List Use_ ?— 47— - � `,,& 2. WELL LOCATIO Nearest Town: f/ ZW A County C. (Strmt Namc,, Numbc'fs, Community, a5ditision�Lai No., p Cede) 3 OWNER44 ljJr# �p:,,e !d ^..1 �1� Address ssrd 7i 11P__/i 4 ,s T-4,4L Al 11_ DISINFEMON: Typed Alnmmt 64t4-,, 12. CASING: Wall Thickmss Depth Diameter orWeight/FL Material From J- 'To lr a- / /1-`C-_-. '" �j L From To Ft - From To FL 13. GROUT: Dep Material Method From d _ To Ft. / /9/•�--- ` Ft _ 14. SCREEN: Depth D9amcicr Slot Size Mate0al From I To Ft r Vy in r in. From To Ft in_ in. 15_ SAND/GRAVEL PACK -- Depth Size Material From J fl To _`Lj T Ft. e Front To Ft 16. REMARKS: Topographic/1--and setting [ARidge 0Slope ❑Valley ❑Flat (check apprapriete box) Latitude/longitude of twll location {deg�etslmi nutcalscwnd9) Latitudeftngitude source, 0GPSCITopogmphic map (SU I or Rnut� No.) (ahmk box) = 2s( DEPTH DRILLING LOG City or Town state ZipC:ode From To Formation Description e7 ! T 6r Y CCU Area endrr Phuno num6cr 4. DATE DR.[LLED 5. TOTAL DEPTH: -- 6. DOES WELL REPLACE EXISTING WELL? YES 0 NO Ur'_- T STATIC WATER LEVEL Delow Top of Casing: — G YT. (u: y ., irAbove lop of OWng) _ S. TOP OF CASING IS FT_ Above Land Surface - 'Top oCeasiap lerminuted PVar 1x &w land surface mquhi-q a Verimce In aecordAncowlth 15A NCAC2C.011& _ 9. YIELD ();pat): / T-_ METHOD OF TEST„ 10. WATER ZONES (depth;): LOCATION SKETCH Show direction and distance in miles front at least two State Roads or County Roads. Include the road numbers and common road names. I DO HEREBY CERTIFY 7til:w R IN ACCORDANCE Wr�,i-I 15A NCAC2C, WELL CONSTRUCT[I �7 STAND7 RECO�AS BEEN PROVIDED TO TtIE WELL OWNER i N COIN UCTING THE WELT, DATE Submit the w igimal to The Division of Water Quality, Grou adwatcr Ss c#ion, 1636 Mvil Service Center-- Raieigb, NC t?699 t636 1Phane No. (919) 7334221, within 30 days, GW-1 REV. 07/2001 WELL CONSTRUCTION RECORD North Carolina - Department of Environn m and Natural Resources - Division of Water Quality - Groundwater Section 1VeLL CONTtIACTU1t (1NDMDUAL) NAM-0 (point)- ra _ %- �AlGt�r3q ��nr CERTIFICATION #l�__qa WELL CONTRACTOR COMPANY nlAr�sa C ix.G�+. �/ p _ .---- --- PIIc7NE n pS.V 5TATi? WP—L.r, CONS RUUCb N VVICU ITY1 — --- A&%0ATHD WQ PRRn7rTM -- - -- (if'apYlicslrle) WELL USE (Check Applicable Box)- Residential © illumiuipaWublic ❑ IndwWol ❑ Agiicultural Q Monitoring © Recovery ❑ Heat Pump Water Injection ® Other 0 If Other, List use_ Te- 2. WELL LOCATION: Topographic/Land setting -, "1fj Nearest Towrr f Colmty tip. l — (Strec in LM is, C inntunity, Subdivision, Ld No., Zip Code) 1 OWNE1,� Address6 (Sheet or Rny�W Hq-) , y _ — AIA1 ___ %E/ � City or Town Stato TT Zip Code Arra cod -Phone: number 4. DATE DRILLHD r✓_ � S- TOTAL DEPTH:r�_ 6- DOES WELL REPLACE EXISTING WELL? YES L1 NO C1 7. STATIC WATER LUVEL Below Tap of Casing: R 7 FT_ (Usa "+" if Abave •ihp WE it ) 9TOP OF CASING I5 0/, FT_ Above I -and Surface* ,Tap orarsing balaY laud serrinre requircA a vartanct la accurda-me wlth 15A NrAC7.0 .01M 9. YIELD (gpm): METHOD orTEST- �, �-- 10. WATER ZONES (depth): s J - — 11. DISINFECTION: Type- - &b� Amount 12. CASWO: WaltThictrness Death na Diae(er orWeight/Ft- Material From_ To// Ft._ i 1"- f r / I Prom To Ft_. From TO FL 13. GROUT: Depth Materiel Method From 49 To FL + From To J Ft _ 14. SCREEN: Depth Diameter slotSizc Material From -fir - - To �S FL_ -( in. r, in- IoVe From _ To Ft_ in. irt- 1S. SAND/GRAVEL PACK - Depth Fro - ---To r i� size Ft r r Material From To F'L 16. REMARKS: I DO HEREBY CERTIFY THAT THIS WELL WAS C01 CON87RUCH 1!7 STANDARDS, AND THAT A COPY / Oct, CTRE OF PE�J ❑Ridge ❑Slope OValley L*Iat (chick appmpriate box) Latitudellongitude of well location (dcgnxs/ndnutasls=M3) ^ Latitudellongitude source:❑0PSI]Topographic imp Colt-nk box) DEPTH DRILLING LOG From TO Fonnation Description LOCNFION_SKkTC1-I Show direction and distance in miles from at least two State Roads or County Roads. Include the road numbers and common road names. TN ACCORDANCE WITH I SA NCAC 2C, WELL ,OFF HAS BEEN PROVIDED TO.1HE WELL OWNER THE WELL DA Snbnait the origittaul to the DivisimoF Water Qu€rtity, GRntwilwaterSeeiloo, 1636 Mail Service Center - Ralcio, NC V699-1636 Phone No. (919) 733-3221,within 30 days, GW-1 REV. 07/2001 SITE INVESTIGATION AND AGRONOMIC PLAN SUMMERHOUSE ON EVERETT BAY WASTEWATER RECEIVER SITE ONSLOW COUNTY, NORTH CAROLINA By A. R. Rubin, Senior Environmental Scientist The proposed Summerhouse on Everett Bay residential/recreational community requires a permitted wastewater reclarnation facility to accommodate the domestic wastewater generated in the community. A community -wide wastewater collection and treatment system is required to accommodate the domestic and commercial wastewater generated within the boundaries of the development and sensitivity of adjacent surface waters necessitates use of a non -point discharge system. The wastewater treatment system proposed consists of an advanced aerobic treatment system consisting of a membrane bioreactor followed by disinfection. These processes are capable of consistently and reliable producing reuse quality water. In addition to this advanced treatment system, a storage system will be provided for upset and a series of bermed, high rate infiltration basins will be developed to facilitate both infiltration of liquid to the site and to create aesthetically pleasing water features on the property. These infiltration galleries are to serve as the ultimate receiver for the reclaimed wastewater. A total of eight (8) potential areas were examined as potential wastewater receiver areas. Four (4) were ultimately selected as designated receiver areas for the reclaimed water. The proposed receiver areas are located on the map attached. These areas are presently hosting woody vegetation and the cropping system will be removed to accommodate the reclaimed water through the basin system. The agronomic assessment and associated plan are necessary to assure adequate vegetation is present on the banks and in terrace areas in these basins to minimize sediment losses and to provide stable areas for infiltration. A second potential use for the reclaimed water is berm landscape irrigation with reuse quality water. Finally, an agronomic assessment is also required to assure liquid generated from pumping site drainage is assimilated on terraces near the site boundary. Beneficial reuse of the treated wastewater on the common -lands and residential landscaped areas, and the series of infiltration basins to serve as an all season system capable of recharging shallow groundwater all provide excellent potential treatment for domestic and commercial wastewater generated on the site. `Phis type of conjunctive system is serving residential, commercial, industrial, and agricultural operations throughout the southeast very successfully. The site and soil conditions encountered on the designated wastewater receiver sites are well suited for the development of this conjunctive type of wastewater system. There are two purposes to the brief report which follows. The first is to describe the results of the soil testing accomplished on the site. The second is to provide recommendations for the cropping system that serves as stabilizing crops on berms and other receiver areas for this liquid. In addition to requirements unposed by close proximity to sensitive receiver waters, land based wastewater treatment and renovation systems exhibit a variety of characteristics considered favorable for treatment of wastewater. These include: 1. Excellent potential to recycle and reuse treated liquid on Nigh value Iandscaped sites and in aesthetic impoundments incorporated into the local landscape 2. Necessity to provide vegetation to stabilize areas with made -land (beans and embankments, terraces, etc.). Site and Soil Conditions Site selection is critical when assessing a wastewater application system, Existing published data such as that contained in the Modern Soil Survey of Dnslow County are useful to determine general site characteristics, but detailed information is necessary for proper design and specification of the system components. Detailed field study provides site specific data regarding variations within the site; existing soil fertility; soil texture, structure and morphology; and water table or restrictive horizon depth. These site specific data are essential to establish proper loading rates, recommendations for plant species selection, operation and maintenance recommendations, and overall site management requirements. The site has been investigated to allow for permitting as a wastewater receiver site and has been examined for that purpose. The site and soil investigation required to obtain the necessary permit was been developed jointly by representatives from Mckun and Creed and Ed Andrews and Associates. The purpose of this brief report is simply to provide criteria for developing a land based wastewater management system and to assess plant nutrient requirements on areas of the site intended to host the components of the infrastructure associated with infiltration. Detailed knowledge of site history and soil characteristics is necessary to establish design and maintenance recommendations of wastewater application systems. Ideally, a permitted wastewater receiver site will contain soil materials at least 24 inches in depth with loam to sandy surface horizons over deep subsurface horizons that allow treatment and renovation to proceed. The soil depth required for treatment depends on treatment system goals and expectations. Sites which do not meet theses recommended criteria can be used as a receiver, but only following extensive wastewater treatment. Soils well suited for high hydraulic loading rates should be rapidly permeable and soil fertility levels suited for crop production become unnecessary on the receiver sites. Soils that contain high levels of clay or sand are somewhat limited for wastewater applications and the hydraulic and nutrient loadings must be adjusted to accommodate these limitations or these restrictive soils are removed to facilitate necessary infiltration. Use of the soil materials on the Holly Ridge— Summerhouse on Everett Bay sites as receiver soils for wastewater require allow loadings at high hydraulic rates because of the depth of soil available, [lie sandy texture of the soil materials present in the treatment/assimilation zone, and the outlets to adjacent drainage. The soil materials on the existing permitted wastewater receiver site are mapped in the Modern Soil Survey of Onslow County as primarily as the Kureb series. Characteristically the Kureb soil resource is excessively well drained and rapid permeable soil with evidence of seasonal saturation encountered at depths of over 48 inches. The site is located along SR 1327 approximately 1.0 miles south of the intersection of Highway 17 and State Road 1327. Currently, The SurrunerHouse/Holly Ridge controls approximately 1200 acres of land and a portion of this is intended to serve as a receive for treated wastewater. A detailed Soil/Site Evaluation was performed by previous consultants for the permitted wastewater receiver sites. More recently, scientists with McKirn and Geed and Edwin Andrews (NCLSS) performed required investigations to confirm soils and site characteristics and to garner required information to obtain necessary permits. A soils investigation was initiated on the proposed land receiver sites. A series of 3.5 inch hand auger borings were advanced to depths of 84 inches (or less if grotumdwater precluded advancing to that depth) across the site. These auger borings were advanced to characterize the depth of each of the horizons, the color of the soil material within each of the soil horizons, and the texture, structure, and consistence of the soil material within each of the horizons. The auger boring was also done to verify the existing snapping units indicated in the USDA soil survey for Onslow County (USDA, 1995). Descriptions of some of the borings are included in the Andrews report. The Andrews report details hydraulic loading and capacity for file sites investigated. The hand auger borings confirmed that soils snapped on the site according to the Onslow County Soil Survey are present. The majority of the soils on the proposed land receiver sites proposed to host the basins consist of Kureb sand. Slopes were measured with a hand held clinometer and they ranged from 0-3% over the sites proposed. The Kureb series is formed in sandy Coastal Plain areas. These soils are excessively well drained, with slow runoff, excellent, rapid permeability im both the upper topsoil and in the lower horizons. Depth to a seasonal high water table is below 4.0 feet in the Kureb Soil. Samples of the soil material were collected randomly from the permitted wastewater receiver site. The samples collected represent areas of approximately 10 to 15 acres. The soil samples collected were subjected to a battery of standard soil fertility tests as performed by the North Carolina Department of Agriculture, Agronomic Services Laboratory. Both the analytical values and the approximate NCDA Index Values are presented in the table. The results of the soil testing are summarized in Table 1, SoiI 'Pest Results, Proposed 1-Iolly Ridge Wastewater receiver sites, attached. These test results indicate that the soil resources encountered over the site are generally low in the traditional soil fertility indicators. These nutrient deficiencies must be corrected for the land application operation to succeed. The recommended nutrient additions are presented in Table 2, Recommended Nutrient and Lime Additions, Proposed Holly Ridge Wastewater receiver site amenities (berms and terrace areas). These results are presented as recommended loadings in pounds per acre or toils per acre. Agricultural supply companies are familiar with these recommended loading units and no difficulties are anticipated in obtaining the required nutrients. The recommended nutrient additions should be supplied prior to the vegetation establishment effort proposed. Wastewater Rennediation Treated domestic or municipal wastewater will potentially be utilized in several ways. Water will be lost through transpiration by vegetation, evaporation from the vegetation and soils surface, and percolation through the soil profile. This water will also enter nearby surface waters in wetlands and streams via lateral flow. Any excess nutrients in the wastewater will be treated through microbial processes, plant uptake, adsorption to soil solids, and biologically mediated chemical transformations (i.e. denitrification), The primary objective of establishing a wastewater spray field using vegetation is to effectively renovate the water through plant Uptake and evapotranspiration to prevent nutrients and other unwanted constituents from entering groundwater. The pre -application wastewater treatment proposed provides all of these requirements and the land is to be used as a dispersal mechanism for the reclairned water. A prinary objective of the rapid infiltration portion of the project is to promote recharge of the shallow groundwater to maintain base flow unto adjacent wetlands and to create aesthetically pleasing water vistas for residents of the connrnunity. Few vegetative species are well adapted for use in berms and terraces supporting the basins. The plant species selected must be snatched to specific sites where they exhibit optimal growth, Turf and grass crops have served as an excellent stabilizing crop on many structures associated with land treatment facilities throughout the southeast. Nutrients promote plant growth and microbiological activity in the soil and the liquid applied onto these areas will contain no essential nutrients of concern in the receiver environment because of the pre-treatment. This reclaimed water is basically a source of water for basins and common landscaped areas. The turf and plant materials established throughout the planned community will benefit from irrigation. The reclairned wastewater is an excellent irrigation resource for the Holly Ridge community. Hybrid Bermudagrass and other warns season grasses or turf systems are capable of sequestering 300 lb PAN/ac/yr or higher under ideal management conditions, but the crop will not be managed aggressively and recommended loadings for the terrace areas and the berm sideslopes and top are 80 pounds of Nitrogen per acre per year as a crop maintenance amendment. Ideal management does include weed control and minimizing equipment traffic on the site especially following rainfall or irrigation events. The recommended liquid loading onto berm sides and tops is no more than 1.75 inches per acre per week as required and this liquid loading can be added as required to support plant growth and development or Potential])' used throughout the planned cornrnunity where reclaimed water could be used. The recommendations specify the addition of the following essential nutrients: A. 60 to 80 pounds of Plant Available Nitrogen (PAN) - Generally this is supplied as Ammonium Nitrate or slow release nitrogen. If the slow release nitrogen is available economically, then this is the recommended nutrient. A very small portion of PAN will be supplied through the wastewater irrigation system proposed. Supplemental requirements will be established as additional information is available concerning turf management areas. B. 40 pounds of Phosphorus - This is generally supplied as a phosphate compound. The phosphorus recommended is essential for root development. A very small portion of P will be supplied through irrigation, but supplements will be required to establish and maintain vegetation. C. 60 pounds of Potassium - Generally this is supplied as a salt of potassium such as potassium chloride. Potassium is essential for development of root, stem, and leaf tissue. Potassium must be supplied as a supplement. D. 1.5 to 2 tons of Lime - Soil pH is very low. This low pI-I influences the availability of essential plant nutrients. The lirne recommended is required to facilitate the uptake of essential plant nutrients, These nutrient additions should be supplied in the fall of the year and prior• to any reseeding With the grass species recommended in the section which follows. The plant nutrient deficiencies noted are severe and must be corrected soon. Maintenance of soil fertility is an important component of any land treatment operation and basin system operation. Without vegetation, the effectiveness of any land application operation is compromised and berm sideslopes are susceptible to erosion. The SAR of any irrigation water must be determined and monitored. The SAR is calculated as the ratio of sodium (Na) to one Half the square root of calcium (Ca) and magnesium (Mg) with all concentrations expressed as equivalents. The SAR calculation is: SAR = Na/(Ca/2 + Mg/2) V, (units in meq/L) An SAR in excess of 10 is considered as an irrigation hazard and system operators must take special precautions to monitor salt levels of sodium in both irrigation water and soil. An SAR in excess of 7.5 is considered a mild irrigation hazard and operators should consider establishing a similar monitoring program. If the level of sodium in the soil exchange complex increases to a level over 10, then corrective measures such as gypsum addition should be implemented. At present no information is available concerning SAR, but once it is available, plans will be developed to address sodium issues if required (SAR is above 10). Since the basins rely on maintaining soil permeability, measures of SAR are important and must be accomplished soon after system operation begins. Soil Sodium; Another measure of sodium, completed for the soil, to determine potential problems with irrigation systems, is called the exchangeable sodium percentage (ESP). ESP is calculated as follows; ESP = Na/CEC * 100 Where: Na is an index value for sodium (North Carolina Agronomic Division — Soil Testing Indices) This calculation should result in data no greater than 10-1.5%. Soils with ESP values > 10-15% can be remediated through under draining and adding soluble sources of Ca such as gypsum (CaSO4), being careful of manganese (Mn) & Mg deficiencies in plants. Ca/Mn and Ca/Mg ratios should be kept in balance, Excessive sodium in the soil system can lead to management problems in the future and affect the overall capacity of the site. Trace Metals The USEPA regulates the levels to which selected metals can accumulate on any waste receiver site. Regulated metals have not been tested in reclaimed water at Holly Ridge. Zinc and Copper levels in the reclaimed wastewater must be tested to make sure that these constituents do not limit the capacity of the site for wastewater treatment. Nutrient Loadings Holly Ridge proposes to spray reclaimed wastewater on small areas of grass and landscaped areas near the proposed wastewater treatment facility and on conunnon Iands in the plaiuned community. The sites were determined to have few hydraulic liinitations. Nutrient loadings or recommendations necessary to establish and support vegetation on basin berms and sideslope areas, and in areas untended to receive the groundwater from the site drainage network are provided in Table 2. Conclusions; The soil resources at Summerhouse on Everette Bay will be modified dramatically as tine development proceeds. The agronomic plan provided is intended to guide the establishment and maintenance of vegetation unportant is stabilizing areas on the site involved with wastewater management. Agronomic considerations are most critical where Iiquid is provided as an irrigation resource. The nutrient and Tune recommendations provided are intended to satisfy plant nutrient requirements on those portions of the site important to support the wastewater infrastructure, but not involved in the dispersal of treated Iiquid. The infiltration basins require no nutrient Ioading or supplements. Table 1, Soil test results (as index values unless indicated). Holly Ridge Parameter Site I Site 2 - o- Site 3 Site 4 OM % 0.3 0.5 0.7 1.3 CEC (meq/g) 5.4 5.9 6.3 7.1 pH (SU) 5.5 5.3 5.5 5.2 P 39 44 28 19 K 25 22 19 12 Ca % 44 49 52 55 Mg % 12 12 10 15 Zn 22 25 19 21 Cu 12 15 17 16 Na % 3% 0.9% 1.2% 0.7% Table 2, Recommended Nutrient and Lime Additions, Grasses and Agricultural Crops On Banks and Terraces, Holly Ridge Wastewater Receiver Sites (Units as indicated) Nutrient Site 2 Site 2 Site 3 Site 4 N 60-80 60-80 60-8) 60-80 P 20-40 20-40 20-40 20-40 K 40-60 40-60 40-60 40-60 Lime 1.5 1.7 1.5 2.0