HomeMy WebLinkAboutSWA000072_YPUB-STORM DRAIN MANUAL-06302020_20200713 30 June 2020 The SITE Group 1111 Oberlin Road 919-832-6658 (o) Raleigh NC 27605 919-839-2255 (f) Table of Contents Stormwater and Erosion Control Calculations Package  Narrative  Bioretention Pond Sizing  Pre-Post Hydrograph Model  Culvert Design  Pipe Sizing  Erosion Control Calculations o Sediment Basin o Outlet Protection o Diversion Ditches  Soil & USGS Maps  Drainage Area Maps 30 June 2020 JOB: YPUB The SITE Group 1111 Oberlin Road 919-832-6658 (o) Raleigh NC 27605 1/3 919-839-2255 (f) Youngsville Public Utility Building South College Street Youngsville, North Carolina Executive Summary General The project site is a 3.04 acre parcel located on the east side of South College Street in Youngsville. The parcel is located in the Neuse River Basin and a 50’ Neuse River Riparian Buffer covers a significant portion of the lot. A utility building with associated parking and a gravel utility yard will be constructed on the northern half of the property. It will be accessed by a driveway that enters the site along the southern property line and crosses the stream. An application has been submitted to North Carolina Division of Water Resources for permits for the stream crossing and buffer impacts. Stormwater runoff from the building rooftop, parking lot, and gravel utility yard will be conveyed to a bioretention pond through a combination of piping and overland flow. Outflow from the bioretention pond will be directed to a non- jurisdictional ditch that outfalls into the riparian buffer. Stormwater Summary Computer simulated reservoir routing using Hydraflow™ modeling software was completed for the 1 year, 2 year and 10 year 24 hour storm events utilizing stage-storage and stage-discharge functions. Stage-storage was determined using the contours of the bioretention pond, and stage-discharge functions were developed using the proposed outlet structure. The outlet structure was designed to attenuate the post-development discharge rates for the 1 and 2 year 24-hour storm events equal to or less than pre-development levels. Hydraflow Storm Sewers modeling software, as incorporated into the AutoCAD Civil 3D computer program, was used to conduct hydrologic analysis of the stormwater pipe network. The rational method was used to compute flow to each storm inlet and routed through the system to calculate flow rates, velocities and hydraulic grade line. This information was used to size the outlet protection where stormwater leaves the site. Hydraflow Express Extention was used to model flow through the temporary diversion ditches so appropriate channel lining could be selected. 30 June 2020 JOB: YPUB The SITE Group 1111 Oberlin Road 919-832-6658 (o) Raleigh NC 27605 2/3 919-839-2255 (f) PEAK STORMWATER RUNOFF SUMMARY PEAK RUNOFF PRE POST DEVELOPMENT DEVELOPMENT 1 YR 24 HR Project Site Peak Flow 0.007 CFS 0.004 CFS ( - 42.9%) 2 YR 24 HR Project Site Peak Flow 0.026 CFS 0.022 CFS ( - 15.4%) 10 YR 24 HR Project Site Peak Flow 1.448 CFS 3.345 CFS (+131.0%) 25 YR 24 HR Project Site Peak Flow 3.459 CFS 5.948 CFS (+ 72.0%) 100 YR 24 HR Project Site Peak Flow 7.599 CFS 10.390 CFS (+ 26.9%) EROSION CONTROL SUMMARY The site drains from northern portion of the property southward into the riparian buffers. Clean water diversion ditches will be constructed along the northern property line to divert offsite water around the site and through silt fence outlets. A skimmer sediment basin will be constructed just to the north of the riparian buffer to treat stormwater runoff resulting from construction. Silt fence will be placed around the construction limits to contain any sedimentation that is not captured in the skimmer basin. The following standard practices will be used on the site. 6.05 Tree Protection Tree protection and combination tree protection / silt fence will be installed around the perimeter of the site to protect trees on adjacent properties from damage due to construction activities. Silt fence outlets will be installed at low points in the fence to allow water to leave the site. 6.06 Gravel Construction Entrance A temporary gravel construction entrance will be installed to reduce removal of sediment from the site by construction equipment. 6.10 Temporary Seeding Temporary seeding will be used to stabilize any disturbed areas that will not be brought to final grade for a period of more than 21 calendar in accordance with NPDES Construction Stormwater General Permit NCG010000. 6.11 Permanent Seeding Permanent seeding will be used to stabilize disturbed areas once the site is brought to final grade. 6.20 Temporary Diversions Temporary diversion ditches will be used around the perimeter of the property to divert clean water around the construction site. Diversion ditches will also be used within the site to direct runoff into the sediment basin. 30 June 2020 JOB: YPUB The SITE Group 1111 Oberlin Road 919-832-6658 (o) Raleigh NC 27605 3/3 919-839-2255 (f) 6.32 Temporary Slope Drains Temporary slope drains will be installed at the end of the diversion ditches to protect the side slopes of the sediment basin from erosion. 6.41 Outlet Stabilization Outlet stabilization will be provided with a rip-rap apron installed at each stormwater outfall point. 6.52 Block and Gravel Inlet Protection Block and gravel inlet protection will be installed around new storm structures to provide detention and sedimentation prior to water entering the storm system. 30 June 2020 The SITE Group 1111 Oberlin Road 919-832-6658 (o) Raleigh NC 27605 919-839-2255 (f) BIORETENTION POND SIZING Project: Children's Lighthouse Childcare Holly Springs Project No.: YPUB Calculated By: Sam Nye, P.E. Bioretention Surface Area Design Description Acres Total Drainage Area 0.58 Impervious Area 0.44 Percent Impervious Area 75.9% 1-Inch Runoff Volume Calculation 1) Volume calculations using the "Simple Method" as described by Schueler (1987) Rv = 0.05 + 0.9(I) Where: Rv = Runoff Coefficient, in/in I = Percent Impervious I= 75.9% Rv = 0.733 V = 3630 x Rainfall Depth x Rv x Drainage Area Design Rainfall =1.0 inch Drainage Area = 0.58 acres V Required= 1,543 cu. ft. 2) Surface Area Required For Bioretention Area V = 1,543 cu. ft. Pond Depth =12.0 inches SA Required =1,543 sq. ft. REQUIRED S.A. =1,543 sq. ft. PROVIDED S.A. = 2,025 sq. ft. Elevation of S.A. =400.5 REQUIRED Volume =1,543 cu. ft. PROVIDED Volume = 1,792 cu. ft. Runoff Volume From Schueler Simple Method Required Surface Area of Bioretention Area Developed Drainage Areas THE SITE GROUP Project: Children's Lighthouse Childcare Holly Springs Project No.: YPUB Calculated By: Sam Nye, P.E. Bioretention Underdrain Design (per Chapter 12 NCDENR Design Manual) Surface Area = 1,425.00 s.f. Depth of Ponding = 12 inches Infiltration rate (Assumed)1 in/hr Fines 9.00%8%-12% Organic Matter (Peat Moss)7.00%3%-5% Sand 84.00% 85%-88% Media Depth 30.00 inches Use 8% fines for 2 in/hr infiltration rate (NCDENR Manual) Phosperus Index of media must be between (10 - 30) Area = 1,425.00 s.f. Infiltration Rate (Assumed) = 1 in/hr Ponding Depth 12 in Time to Drain 12" Ponded Area 12 hrs Time to Drain 24 in Below Surface 18 hrs Max. Allowed Time to Drain Ponded Area = 12 hrs Max. Allowed Time to Drain 24" Below Surface = 48 hrs Area of Bioretention 1,425.00 s.f. Min. Required No. of Clean Outs 2 * Clean Out Pipe Required for every 1,000 S.F. Infiltration Rate (Assumed) 1 in/hr Infiltration Rate (Assumed) 2.315E-05 ft/sec Area of Bioretention 1,425.00 sf Q (Flow Rate Through Soil) 0.033 cfs Factor of Safety (5X) 0.2 cfs Pipe Diameter (D) = 4.05 inches Pipe Diameter Equation D=16(Qn/S^0.5)^0.375 n=.011 (roughness factor) s=.005 (pipe slope) THE SITE GROUP Underdrain Pipe Design Use (1) 6 inch pipe Underdrain Clean Out Design Bioretention Design Criteria Time To Drain Bioretention Area Media Design (By Volume) 30 June 2020 The SITE Group 1111 Oberlin Road 919-832-6658 (o) Raleigh NC 27605 919-839-2255 (f) PRE-POST HYDROGRAPH MODEL Project: Public Utility Building Project No.: YPUB Calculated By: Sam Nye, P.E. Drainage Area Breakdowns PRE DEVELOPMENT DRAINAGE AREA BREAKDOWN Area (SF)CN CN*A Woods 132417 45 5958765 Roof/Conc./Asph.0 98 0 Lawn 0 56 0 Total 132417 5958765 Total (Ac.)3.04 Comp CN:45.0 POST DEVELOPMENT DRAINAGE AREA BREAKDOWN TO POND Area (SF)CN CN*A Building 5613 98 550074 Asphalt 8766 98 859068 Gravel 4783 76 363508 Lawn 6077 39 237003 Total 25239 2009653 Total (Ac.)0.58 Comp CN:79.6 POST DEVELOPMENT DRAINAGE AREA BREAKDOWN POND BYPASS Area (SF)CN CN*A Asphalt 9066 98 888468 Lawn 22269 39 868491 Woods 75842 40 3033680 Total 107177 4790639 Total (Ac.)2.46 Comp CN:44.7 THE SITE GROUP Hydraflow Table of Contents YPUB-Bioretention-2.gpw Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 06 / 30 / 2020 Watershed Model Schematic...................................................................................... 1 Hydrograph Return Period Recap............................................................................. 2 1 - Year Summary Report......................................................................................................................... 3 Hydrograph Reports................................................................................................................... 4 Hydrograph No. 1, SCS Runoff, Pre Development.................................................................. 4 Hydrograph No. 3, SCS Runoff, Post Bypass.......................................................................... 5 Hydrograph No. 4, SCS Runoff, Post to Pond......................................................................... 6 Hydrograph No. 5, Reservoir, Pond Routing............................................................................ 7 Pond Report - Bioretention Area.......................................................................................... 8 Hydrograph No. 6, Combine, Post Combined.......................................................................... 9 2 - Year Summary Report.......................................................................................................................10 Hydrograph Reports.................................................................................................................11 Hydrograph No. 1, SCS Runoff, Pre Development................................................................11 Hydrograph No. 3, SCS Runoff, Post Bypass........................................................................12 Hydrograph No. 4, SCS Runoff, Post to Pond.......................................................................13 Hydrograph No. 5, Reservoir, Pond Routing..........................................................................14 Hydrograph No. 6, Combine, Post Combined........................................................................15 10 - Year Summary Report.......................................................................................................................16 Hydrograph Reports.................................................................................................................17 Hydrograph No. 1, SCS Runoff, Pre Development................................................................17 Hydrograph No. 3, SCS Runoff, Post Bypass........................................................................18 Hydrograph No. 4, SCS Runoff, Post to Pond.......................................................................19 Hydrograph No. 5, Reservoir, Pond Routing..........................................................................20 Hydrograph No. 6, Combine, Post Combined........................................................................21 25 - Year Summary Report.......................................................................................................................22 Hydrograph Reports.................................................................................................................23 Hydrograph No. 1, SCS Runoff, Pre Development................................................................23 Hydrograph No. 3, SCS Runoff, Post Bypass........................................................................24 Hydrograph No. 4, SCS Runoff, Post to Pond.......................................................................25 Hydrograph No. 5, Reservoir, Pond Routing..........................................................................26 Hydrograph No. 6, Combine, Post Combined........................................................................27 100 - Year Summary Report.......................................................................................................................28 Hydrograph Reports.................................................................................................................29 Hydrograph No. 1, SCS Runoff, Pre Development................................................................29 Hydrograph No. 3, SCS Runoff, Post Bypass........................................................................30 Hydrograph No. 4, SCS Runoff, Post to Pond.......................................................................31 Hydrograph No. 5, Reservoir, Pond Routing..........................................................................32 Contents continued...YPUB-Bioretention-2.gpw Hydrograph No. 6, Combine, Post Combined........................................................................33 IDF Report..................................................................................................................34 1 3 4 5 6 1 Watershed Model Schematic Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Project: YPUB-Bioretention-2.gpw Tuesday, 06 / 30 / 2020 Hyd.Origin Description Legend 1 SCS Runoff Pre Development 3 SCS Runoff Post Bypass 4 SCS Runoff Post to Pond 5 Reservoir Pond Routing 6 Combine Post Combined Hydrograph Return Period Recap 2 Hyd. Hydrograph Inflow Peak Outflow (cfs) Hydrograph No. type hyd(s) Description (origin) 1-yr 2-yr 3-yr 5-yr 10-yr 25-yr 50-yr 100-yr 1 SCS Runoff ------ 0.007 0.026 ------- ------- 1.448 3.459 ------- 7.599 Pre Development 3 SCS Runoff ------ 0.004 0.018 ------- ------- 1.050 2.557 ------- 5.663 Post Bypass 4 SCS Runoff ------ 1.114 1.546 ------- ------- 2.807 3.585 ------- 4.856 Post to Pond 5 Reservoir 4 0.000 0.005 ------- ------- 2.295 3.392 ------- 4.723 Pond Routing 6 Combine 3, 5 0.004 0.022 ------- ------- 3.345 5.948 ------- 10.39 Post Combined Proj. file: YPUB-Bioretention-2.gpw Tuesday, 06 / 30 / 2020 Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Hydrograph Summary Report 3 Hyd. Hydrograph Peak Time Time to Hyd. Inflow Maximum Total Hydrograph No. type flow interval Peak volume hyd(s) elevation strge used Description (origin) (cfs) (min) (min) (cuft) (ft) (cuft) 1 SCS Runoff 0.007 1 1440 163 ------ ------ ------ Pre Development 3 SCS Runoff 0.004 2 1440 103 ------ ------ ------ Post Bypass 4 SCS Runoff 1.114 2 718 2,229 ------ ------ ------ Post to Pond 5 Reservoir 0.000 2 1336 0 4 400.20 1,183 Pond Routing 6 Combine 0.004 2 1440 103 3, 5 ------ ------ Post Combined YPUB-Bioretention-2.gpw Return Period: 1 Year Tuesday, 06 / 30 / 2020 Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 06 / 30 / 2020 Hyd. No. 1 Pre Development Hydrograph type = SCS Runoff Peak discharge = 0.007 cfs Storm frequency = 1 yrs Time to peak = 1440 min Time interval = 1 min Hyd. volume = 163 cuft Drainage area = 3.040 ac Curve number = 45 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 2.87 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 4 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Q (cfs) 0.00 0.00 0.01 0.01 0.02 0.02 0.03 0.03 0.04 0.04 0.05 0.05 0.06 0.06 0.07 0.07 0.08 0.08 0.09 0.09 0.10 0.10 Q (cfs) Time (min) Pre Development Hyd. No. 1 -- 1 Year Hyd No. 1 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 06 / 30 / 2020 Hyd. No. 3 Post Bypass Hydrograph type = SCS Runoff Peak discharge = 0.004 cfs Storm frequency = 1 yrs Time to peak = 1440 min Time interval = 2 min Hyd. volume = 103 cuft Drainage area = 2.460 ac Curve number = 44.7 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 2.87 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 5 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Q (cfs) 0.00 0.00 0.01 0.01 0.02 0.02 0.03 0.03 0.04 0.04 0.05 0.05 0.06 0.06 0.07 0.07 0.08 0.08 0.09 0.09 0.10 0.10 Q (cfs) Time (min) Post Bypass Hyd. No. 3 -- 1 Year Hyd No. 3 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 06 / 30 / 2020 Hyd. No. 4 Post to Pond Hydrograph type = SCS Runoff Peak discharge = 1.114 cfs Storm frequency = 1 yrs Time to peak = 718 min Time interval = 2 min Hyd. volume = 2,229 cuft Drainage area = 0.580 ac Curve number = 79.6 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 2.87 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 6 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Q (cfs) 0.00 0.00 1.00 1.00 2.00 2.00 Q (cfs) Time (min) Post to Pond Hyd. No. 4 -- 1 Year Hyd No. 4 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 06 / 30 / 2020 Hyd. No. 5 Pond Routing Hydrograph type = Reservoir Peak discharge = 0.000 cfs Storm frequency = 1 yrs Time to peak = 1336 min Time interval = 2 min Hyd. volume = 0 cuft Inflow hyd. No. = 4 - Post to Pond Max. Elevation = 400.20 ft Reservoir name = Bioretention Area Max. Storage = 1,183 cuft Storage Indication method used. Exfiltration extracted from Outflow. 7 0 240 480 720 960 1200 1440 1680 1920 Q (cfs) 0.00 0.00 1.00 1.00 2.00 2.00 Q (cfs) Time (min) Pond Routing Hyd. No. 5 -- 1 Year Hyd No. 5 Hyd No. 4 Total storage used = 1,183 cuft Pond Report 8 Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 06 / 30 / 2020 Pond No. 1 - Bioretention Area Pond Data Contours -User-defined contour areas. Conic method used for volume calculation. Begining Elevation = 399.50 ft Stage / Storage Table Stage (ft) Elevation (ft) Contour area (sqft) Incr. Storage (cuft) Total storage (cuft) 0.00 399.50 1,425 0 0 0.50 400.00 1,715 784 784 1.50 401.00 2,335 2,017 2,801 2.00 401.50 2,668 1,250 4,050 Culvert / Orifice Structures Weir Structures [A] [B] [C] [PrfRsr] [A] [B] [C] [D] Rise (in)= 15.00 0.00 0.00 0.00 Span (in)= 15.00 0.00 0.00 0.00 No. Barrels = 1 1 0 0 Invert El. (ft)= 397.50 399.50 0.00 0.00 Length (ft)= 60.00 0.00 0.00 0.00 Slope (%)= 0.83 0.00 0.00 n/a N-Value = .013 .013 .013 n/a Orifice Coeff.= 0.60 0.60 0.60 0.60 Multi-Stage = n/a Yes No No Crest Len (ft)= 12.00 Inactive 0.00 0.00 Crest El. (ft)= 400.50 400.50 0.00 0.00 Weir Coeff.= 3.33 3.33 3.33 3.33 Weir Type = 1 Rect --- --- Multi-Stage = No No No No Exfil.(in/hr)= 1.000 (by Contour) TW Elev. (ft)= 0.00 Note: Culvert/Orifice outflows are analyzed under inlet (ic) and outlet (oc) control. Weir risers checked for orifice conditions (ic) and submergence (s). Stage / Storage / Discharge Table Stage Storage Elevation Clv A Clv B Clv C PrfRsr Wr A Wr B Wr C Wr D Exfil User Total ft cuft ft cfs cfs cfs cfs cfs cfs cfs cfs cfs cfs cfs 0.00 0 399.50 0.00 --- --- --- 0.00 0.00 --- --- 0.000 --- 0.000 0.05 78 399.55 6.48 oc --- --- --- 0.00 0.00 --- --- 0.004 --- 0.004 0.10 157 399.60 6.48 oc --- --- --- 0.00 0.00 --- --- 0.008 --- 0.008 0.15 235 399.65 6.48 oc --- --- --- 0.00 0.00 --- --- 0.012 --- 0.012 0.20 314 399.70 6.48 oc --- --- --- 0.00 0.00 --- --- 0.016 --- 0.016 0.25 392 399.75 6.48 oc --- --- --- 0.00 0.00 --- --- 0.020 --- 0.020 0.30 470 399.80 6.48 oc --- --- --- 0.00 0.00 --- --- 0.024 --- 0.024 0.35 549 399.85 6.48 oc --- --- --- 0.00 0.00 --- --- 0.028 --- 0.028 0.40 627 399.90 6.48 oc --- --- --- 0.00 0.00 --- --- 0.032 --- 0.032 0.45 705 399.95 6.48 oc --- --- --- 0.00 0.00 --- --- 0.036 --- 0.036 0.50 784 400.00 6.48 oc --- --- --- 0.00 0.00 --- --- 0.040 --- 0.040 0.60 985 400.10 6.48 oc --- --- --- 0.00 0.00 --- --- 0.041 --- 0.041 0.70 1,187 400.20 6.48 oc --- --- --- 0.00 0.00 --- --- 0.043 --- 0.043 0.80 1,389 400.30 6.48 oc --- --- --- 0.00 0.00 --- --- 0.044 --- 0.044 0.90 1,591 400.40 6.48 oc --- --- --- 0.00 0.00 --- --- 0.045 --- 0.045 1.00 1,792 400.50 6.48 oc --- --- --- 0.00 0.00 --- --- 0.047 --- 0.047 1.10 1,994 400.60 6.48 oc --- --- --- 1.26 0.00 --- --- 0.048 --- 1.312 1.20 2,196 400.70 6.48 oc --- --- --- 3.57 0.00 --- --- 0.050 --- 3.624 1.30 2,397 400.80 6.48 oc --- --- --- 6.57 0.00 --- --- 0.051 --- 6.617 1.40 2,599 400.90 6.48 oc --- --- --- 10.11 0.00 --- --- 0.053 --- 10.17 1.50 2,801 401.00 6.48 oc --- --- --- 14.13 0.00 --- --- 0.054 --- 14.18 1.55 2,926 401.05 6.48 oc --- --- --- 16.30 0.00 --- --- 0.055 --- 16.35 1.60 3,051 401.10 6.48 oc --- --- --- 18.57 0.00 --- --- 0.056 --- 18.63 1.65 3,176 401.15 6.48 oc --- --- --- 20.94 0.00 --- --- 0.056 --- 21.00 1.70 3,301 401.20 6.48 oc --- --- --- 23.40 0.00 --- --- 0.057 --- 23.46 1.75 3,425 401.25 6.48 oc --- --- --- 25.95 0.00 --- --- 0.058 --- 26.01 1.80 3,550 401.30 6.48 oc --- --- --- 28.59 0.00 --- --- 0.059 --- 28.65 1.85 3,675 401.35 6.48 oc --- --- --- 31.31 0.00 --- --- 0.059 --- 31.37 1.90 3,800 401.40 6.48 oc --- --- --- 34.11 0.00 --- --- 0.060 --- 34.17 1.95 3,925 401.45 6.48 oc --- --- --- 36.99 0.00 --- --- 0.061 --- 37.06 2.00 4,050 401.50 6.48 oc --- --- --- 39.96 0.00 --- --- 0.062 --- 40.02 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 06 / 30 / 2020 Hyd. No. 6 Post Combined Hydrograph type = Combine Peak discharge = 0.004 cfs Storm frequency = 1 yrs Time to peak = 1440 min Time interval = 2 min Hyd. volume = 103 cuft Inflow hyds. = 3, 5 Contrib. drain. area = 2.460 ac 9 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Q (cfs) 0.00 0.00 0.01 0.01 0.02 0.02 0.03 0.03 0.04 0.04 0.05 0.05 0.06 0.06 0.07 0.07 0.08 0.08 0.09 0.09 0.10 0.10 Q (cfs) Time (min) Post Combined Hyd. No. 6 -- 1 Year Hyd No. 6 Hyd No. 3 Hyd No. 5 Hydrograph Summary Report 10 Hyd. Hydrograph Peak Time Time to Hyd. Inflow Maximum Total Hydrograph No. type flow interval Peak volume hyd(s) elevation strge used Description (origin) (cfs) (min) (min) (cuft) (ft) (cuft) 1 SCS Runoff 0.026 1 808 887 ------ ------ ------ Pre Development 3 SCS Runoff 0.018 2 892 609 ------ ------ ------ Post Bypass 4 SCS Runoff 1.546 2 718 3,112 ------ ------ ------ Post to Pond 5 Reservoir 0.005 2 840 6 4 400.50 1,793 Pond Routing 6 Combine 0.022 2 840 615 3, 5 ------ ------ Post Combined YPUB-Bioretention-2.gpw Return Period: 2 Year Tuesday, 06 / 30 / 2020 Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 06 / 30 / 2020 Hyd. No. 1 Pre Development Hydrograph type = SCS Runoff Peak discharge = 0.026 cfs Storm frequency = 2 yrs Time to peak = 808 min Time interval = 1 min Hyd. volume = 887 cuft Drainage area = 3.040 ac Curve number = 45 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 3.46 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 11 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Q (cfs) 0.00 0.00 0.01 0.01 0.02 0.02 0.03 0.03 0.04 0.04 0.05 0.05 0.06 0.06 0.07 0.07 0.08 0.08 0.09 0.09 0.10 0.10 Q (cfs) Time (min) Pre Development Hyd. No. 1 -- 2 Year Hyd No. 1 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 06 / 30 / 2020 Hyd. No. 3 Post Bypass Hydrograph type = SCS Runoff Peak discharge = 0.018 cfs Storm frequency = 2 yrs Time to peak = 892 min Time interval = 2 min Hyd. volume = 609 cuft Drainage area = 2.460 ac Curve number = 44.7 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 3.46 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 12 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Q (cfs) 0.00 0.00 0.01 0.01 0.02 0.02 0.03 0.03 0.04 0.04 0.05 0.05 0.06 0.06 0.07 0.07 0.08 0.08 0.09 0.09 0.10 0.10 Q (cfs) Time (min) Post Bypass Hyd. No. 3 -- 2 Year Hyd No. 3 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 06 / 30 / 2020 Hyd. No. 4 Post to Pond Hydrograph type = SCS Runoff Peak discharge = 1.546 cfs Storm frequency = 2 yrs Time to peak = 718 min Time interval = 2 min Hyd. volume = 3,112 cuft Drainage area = 0.580 ac Curve number = 79.6 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 3.46 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 13 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Q (cfs) 0.00 0.00 1.00 1.00 2.00 2.00 Q (cfs) Time (min) Post to Pond Hyd. No. 4 -- 2 Year Hyd No. 4 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 06 / 30 / 2020 Hyd. No. 5 Pond Routing Hydrograph type = Reservoir Peak discharge = 0.005 cfs Storm frequency = 2 yrs Time to peak = 840 min Time interval = 2 min Hyd. volume = 6 cuft Inflow hyd. No. = 4 - Post to Pond Max. Elevation = 400.50 ft Reservoir name = Bioretention Area Max. Storage = 1,793 cuft Storage Indication method used. Exfiltration extracted from Outflow. 14 0 120 240 360 480 600 720 840 960 Q (cfs) 0.00 0.00 1.00 1.00 2.00 2.00 Q (cfs) Time (min) Pond Routing Hyd. No. 5 -- 2 Year Hyd No. 5 Hyd No. 4 Total storage used = 1,793 cuft Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 06 / 30 / 2020 Hyd. No. 6 Post Combined Hydrograph type = Combine Peak discharge = 0.022 cfs Storm frequency = 2 yrs Time to peak = 840 min Time interval = 2 min Hyd. volume = 615 cuft Inflow hyds. = 3, 5 Contrib. drain. area = 2.460 ac 15 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Q (cfs) 0.00 0.00 0.01 0.01 0.02 0.02 0.03 0.03 0.04 0.04 0.05 0.05 0.06 0.06 0.07 0.07 0.08 0.08 0.09 0.09 0.10 0.10 Q (cfs) Time (min) Post Combined Hyd. No. 6 -- 2 Year Hyd No. 6 Hyd No. 3 Hyd No. 5 Hydrograph Summary Report 16 Hyd. Hydrograph Peak Time Time to Hyd. Inflow Maximum Total Hydrograph No. type flow interval Peak volume hyd(s) elevation strge used Description (origin) (cfs) (min) (min) (cuft) (ft) (cuft) 1 SCS Runoff 1.448 1 720 5,173 ------ ------ ------ Pre Development 3 SCS Runoff 1.050 2 720 3,681 ------ ------ ------ Post Bypass 4 SCS Runoff 2.807 2 716 5,706 ------ ------ ------ Post to Pond 5 Reservoir 2.295 2 720 2,092 4 400.65 2,084 Pond Routing 6 Combine 3.345 2 720 5,773 3, 5 ------ ------ Post Combined YPUB-Bioretention-2.gpw Return Period: 10 Year Tuesday, 06 / 30 / 2020 Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 06 / 30 / 2020 Hyd. No. 1 Pre Development Hydrograph type = SCS Runoff Peak discharge = 1.448 cfs Storm frequency = 10 yrs Time to peak = 720 min Time interval = 1 min Hyd. volume = 5,173 cuft Drainage area = 3.040 ac Curve number = 45 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 5.04 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 17 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Q (cfs) 0.00 0.00 1.00 1.00 2.00 2.00 Q (cfs) Time (min) Pre Development Hyd. No. 1 -- 10 Year Hyd No. 1 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 06 / 30 / 2020 Hyd. No. 3 Post Bypass Hydrograph type = SCS Runoff Peak discharge = 1.050 cfs Storm frequency = 10 yrs Time to peak = 720 min Time interval = 2 min Hyd. volume = 3,681 cuft Drainage area = 2.460 ac Curve number = 44.7 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 5.04 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 18 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Q (cfs) 0.00 0.00 1.00 1.00 2.00 2.00 Q (cfs) Time (min) Post Bypass Hyd. No. 3 -- 10 Year Hyd No. 3 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 06 / 30 / 2020 Hyd. No. 4 Post to Pond Hydrograph type = SCS Runoff Peak discharge = 2.807 cfs Storm frequency = 10 yrs Time to peak = 716 min Time interval = 2 min Hyd. volume = 5,706 cuft Drainage area = 0.580 ac Curve number = 79.6 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 5.04 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 19 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 Q (cfs) 0.00 0.00 1.00 1.00 2.00 2.00 3.00 3.00 Q (cfs) Time (min) Post to Pond Hyd. No. 4 -- 10 Year Hyd No. 4 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 06 / 30 / 2020 Hyd. No. 5 Pond Routing Hydrograph type = Reservoir Peak discharge = 2.295 cfs Storm frequency = 10 yrs Time to peak = 720 min Time interval = 2 min Hyd. volume = 2,092 cuft Inflow hyd. No. = 4 - Post to Pond Max. Elevation = 400.65 ft Reservoir name = Bioretention Area Max. Storage = 2,084 cuft Storage Indication method used. Exfiltration extracted from Outflow. 20 0 120 240 360 480 600 720 840 960 Q (cfs) 0.00 0.00 1.00 1.00 2.00 2.00 3.00 3.00 Q (cfs) Time (min) Pond Routing Hyd. No. 5 -- 10 Year Hyd No. 5 Hyd No. 4 Total storage used = 2,084 cuft Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 06 / 30 / 2020 Hyd. No. 6 Post Combined Hydrograph type = Combine Peak discharge = 3.345 cfs Storm frequency = 10 yrs Time to peak = 720 min Time interval = 2 min Hyd. volume = 5,773 cuft Inflow hyds. = 3, 5 Contrib. drain. area = 2.460 ac 21 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Q (cfs) 0.00 0.00 1.00 1.00 2.00 2.00 3.00 3.00 4.00 4.00 Q (cfs) Time (min) Post Combined Hyd. No. 6 -- 10 Year Hyd No. 6 Hyd No. 3 Hyd No. 5 Hydrograph Summary Report 22 Hyd. Hydrograph Peak Time Time to Hyd. Inflow Maximum Total Hydrograph No. type flow interval Peak volume hyd(s) elevation strge used Description (origin) (cfs) (min) (min) (cuft) (ft) (cuft) 1 SCS Runoff 3.459 1 719 9,026 ------ ------ ------ Pre Development 3 SCS Runoff 2.557 2 718 6,476 ------ ------ ------ Post Bypass 4 SCS Runoff 3.585 2 716 7,348 ------ ------ ------ Post to Pond 5 Reservoir 3.392 2 718 3,515 4 400.69 2,180 Pond Routing 6 Combine 5.948 2 718 9,990 3, 5 ------ ------ Post Combined YPUB-Bioretention-2.gpw Return Period: 25 Year Tuesday, 06 / 30 / 2020 Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 06 / 30 / 2020 Hyd. No. 1 Pre Development Hydrograph type = SCS Runoff Peak discharge = 3.459 cfs Storm frequency = 25 yrs Time to peak = 719 min Time interval = 1 min Hyd. volume = 9,026 cuft Drainage area = 3.040 ac Curve number = 45 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 5.98 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 23 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Q (cfs) 0.00 0.00 1.00 1.00 2.00 2.00 3.00 3.00 4.00 4.00 Q (cfs) Time (min) Pre Development Hyd. No. 1 -- 25 Year Hyd No. 1 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 06 / 30 / 2020 Hyd. No. 3 Post Bypass Hydrograph type = SCS Runoff Peak discharge = 2.557 cfs Storm frequency = 25 yrs Time to peak = 718 min Time interval = 2 min Hyd. volume = 6,476 cuft Drainage area = 2.460 ac Curve number = 44.7 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 5.98 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 24 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Q (cfs) 0.00 0.00 1.00 1.00 2.00 2.00 3.00 3.00 Q (cfs) Time (min) Post Bypass Hyd. No. 3 -- 25 Year Hyd No. 3 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 06 / 30 / 2020 Hyd. No. 4 Post to Pond Hydrograph type = SCS Runoff Peak discharge = 3.585 cfs Storm frequency = 25 yrs Time to peak = 716 min Time interval = 2 min Hyd. volume = 7,348 cuft Drainage area = 0.580 ac Curve number = 79.6 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 5.98 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 25 0 120 240 360 480 600 720 840 960 1080 1200 1320 Q (cfs) 0.00 0.00 1.00 1.00 2.00 2.00 3.00 3.00 4.00 4.00 Q (cfs) Time (min) Post to Pond Hyd. No. 4 -- 25 Year Hyd No. 4 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 06 / 30 / 2020 Hyd. No. 5 Pond Routing Hydrograph type = Reservoir Peak discharge = 3.392 cfs Storm frequency = 25 yrs Time to peak = 718 min Time interval = 2 min Hyd. volume = 3,515 cuft Inflow hyd. No. = 4 - Post to Pond Max. Elevation = 400.69 ft Reservoir name = Bioretention Area Max. Storage = 2,180 cuft Storage Indication method used. Exfiltration extracted from Outflow. 26 0 120 240 360 480 600 720 840 960 Q (cfs) 0.00 0.00 1.00 1.00 2.00 2.00 3.00 3.00 4.00 4.00 Q (cfs) Time (min) Pond Routing Hyd. No. 5 -- 25 Year Hyd No. 5 Hyd No. 4 Total storage used = 2,180 cuft Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 06 / 30 / 2020 Hyd. No. 6 Post Combined Hydrograph type = Combine Peak discharge = 5.948 cfs Storm frequency = 25 yrs Time to peak = 718 min Time interval = 2 min Hyd. volume = 9,990 cuft Inflow hyds. = 3, 5 Contrib. drain. area = 2.460 ac 27 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Q (cfs) 0.00 0.00 1.00 1.00 2.00 2.00 3.00 3.00 4.00 4.00 5.00 5.00 6.00 6.00 Q (cfs) Time (min) Post Combined Hyd. No. 6 -- 25 Year Hyd No. 6 Hyd No. 3 Hyd No. 5 Hydrograph Summary Report 28 Hyd. Hydrograph Peak Time Time to Hyd. Inflow Maximum Total Hydrograph No. type flow interval Peak volume hyd(s) elevation strge used Description (origin) (cfs) (min) (min) (cuft) (ft) (cuft) 1 SCS Runoff 7.599 1 718 16,834 ------ ------ ------ Pre Development 3 SCS Runoff 5.663 2 718 12,153 ------ ------ ------ Post Bypass 4 SCS Runoff 4.856 2 716 10,091 ------ ------ ------ Post to Pond 5 Reservoir 4.723 2 718 5,974 4 400.74 2,273 Pond Routing 6 Combine 10.39 2 718 18,127 3, 5 ------ ------ Post Combined YPUB-Bioretention-2.gpw Return Period: 100 Year Tuesday, 06 / 30 / 2020 Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 06 / 30 / 2020 Hyd. No. 1 Pre Development Hydrograph type = SCS Runoff Peak discharge = 7.599 cfs Storm frequency = 100 yrs Time to peak = 718 min Time interval = 1 min Hyd. volume = 16,834 cuft Drainage area = 3.040 ac Curve number = 45 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 7.50 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 29 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Q (cfs) 0.00 0.00 2.00 2.00 4.00 4.00 6.00 6.00 8.00 8.00 Q (cfs) Time (min) Pre Development Hyd. No. 1 -- 100 Year Hyd No. 1 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 06 / 30 / 2020 Hyd. No. 3 Post Bypass Hydrograph type = SCS Runoff Peak discharge = 5.663 cfs Storm frequency = 100 yrs Time to peak = 718 min Time interval = 2 min Hyd. volume = 12,153 cuft Drainage area = 2.460 ac Curve number = 44.7 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 7.50 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 30 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Q (cfs) 0.00 0.00 1.00 1.00 2.00 2.00 3.00 3.00 4.00 4.00 5.00 5.00 6.00 6.00 Q (cfs) Time (min) Post Bypass Hyd. No. 3 -- 100 Year Hyd No. 3 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 06 / 30 / 2020 Hyd. No. 4 Post to Pond Hydrograph type = SCS Runoff Peak discharge = 4.856 cfs Storm frequency = 100 yrs Time to peak = 716 min Time interval = 2 min Hyd. volume = 10,091 cuft Drainage area = 0.580 ac Curve number = 79.6 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 7.50 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 31 0 120 240 360 480 600 720 840 960 1080 1200 1320 Q (cfs) 0.00 0.00 1.00 1.00 2.00 2.00 3.00 3.00 4.00 4.00 5.00 5.00 Q (cfs) Time (min) Post to Pond Hyd. No. 4 -- 100 Year Hyd No. 4 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 06 / 30 / 2020 Hyd. No. 5 Pond Routing Hydrograph type = Reservoir Peak discharge = 4.723 cfs Storm frequency = 100 yrs Time to peak = 718 min Time interval = 2 min Hyd. volume = 5,974 cuft Inflow hyd. No. = 4 - Post to Pond Max. Elevation = 400.74 ft Reservoir name = Bioretention Area Max. Storage = 2,273 cuft Storage Indication method used. Exfiltration extracted from Outflow. 32 0 120 240 360 480 600 720 840 960 Q (cfs) 0.00 0.00 1.00 1.00 2.00 2.00 3.00 3.00 4.00 4.00 5.00 5.00 Q (cfs) Time (min) Pond Routing Hyd. No. 5 -- 100 Year Hyd No. 5 Hyd No. 4 Total storage used = 2,273 cuft Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 06 / 30 / 2020 Hyd. No. 6 Post Combined Hydrograph type = Combine Peak discharge = 10.39 cfs Storm frequency = 100 yrs Time to peak = 718 min Time interval = 2 min Hyd. volume = 18,127 cuft Inflow hyds. = 3, 5 Contrib. drain. area = 2.460 ac 33 0 120 240 360 480 600 720 840 960 1080 1200 1320 Q (cfs) 0.00 0.00 2.00 2.00 4.00 4.00 6.00 6.00 8.00 8.00 10.00 10.00 12.00 12.00 Q (cfs) Time (min) Post Combined Hyd. No. 6 -- 100 Year Hyd No. 6 Hyd No. 3 Hyd No. 5 Hydraflow Rainfall Report 34 Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 06 / 30 / 2020 Return Intensity-Duration-Frequency Equation Coefficients (FHA) Period (Yrs)B D E (N/A) 1 67.1307 18.6000 0.8710 -------- 2 74.0559 13.3000 0.8788 -------- 3 0.0000 0.0000 0.0000 -------- 5 83.5115 14.8000 0.8514 -------- 10 105.7041 16.8000 0.8710 -------- 25 118.9249 17.6000 0.8582 -------- 50 137.0265 18.6000 0.8630 -------- 100 157.1766 19.6000 0.8692 -------- File name: RALEIGH.IDF Intensity = B / (Tc + D)^E Return Intensity Values (in/hr) Period (Yrs) 5 min 10 15 20 25 30 35 40 45 50 55 60 1 4.28 3.62 3.14 2.79 2.51 2.28 2.09 1.94 1.80 1.69 1.59 1.50 2 5.76 4.65 3.92 3.40 3.01 2.70 2.45 2.25 2.08 1.93 1.81 1.70 3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5 6.57 5.43 4.64 4.07 3.63 3.28 3.00 2.76 2.57 2.40 2.25 2.12 10 7.22 6.03 5.19 4.57 4.09 3.71 3.40 3.13 2.91 2.72 2.56 2.41 25 8.19 6.90 5.98 5.29 4.75 4.32 3.97 3.67 3.41 3.20 3.01 2.84 50 8.95 7.59 6.60 5.86 5.27 4.80 4.41 4.08 3.81 3.57 3.36 3.17 100 9.71 8.27 7.22 6.42 5.79 5.28 4.86 4.50 4.20 3.93 3.70 3.50 Tc = time in minutes. Values may exceed 60. Rainfall Precipitation Table (in) Precip. file name: H:\The SITE Group\Projects\RGDCAP\Hydro\APEX.pcp Storm Distribution 1-yr 2-yr 3-yr 5-yr 10-yr 25-yr 50-yr 100-yr SCS 24-hour 2.87 3.46 0.00 4.34 5.04 5.98 6.73 7.50 SCS 6-Hr 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Huff-1st 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Huff-2nd 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Huff-3rd 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Huff-4th 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Huff-Indy 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Custom 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 30 June 2020 The SITE Group 1111 Oberlin Road 919-832-6658 (o) Raleigh NC 27605 919-839-2255 (f) CULVERT DESIGN Hydrograph Return Period Recap 1 Hyd. Hydrograph Inflow Peak Outflow (cfs) Hydrograph No. type hyd(s) Description (origin) 1-yr 2-yr 3-yr 5-yr 10-yr 25-yr 50-yr 100-yr 1 SCS Runoff ------ 25.85 63.95 ------- ------- 216.91 335.35 435.75 542.16 Creek Flow Proj. file: Box Culvert Flow.gpw Friday, 06 / 26 / 2020 Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Friday, 06 / 26 / 2020 Hyd. No. 1 Creek Flow Hydrograph type = SCS Runoff Peak discharge = 25.85 cfs Storm frequency = 1 yrs Time to peak = 12.52 hrs Time interval = 1 min Hyd. volume = 287,774 cuft Drainage area = 294.160 ac Curve number = 57.8 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = TR55 Time of conc. (Tc) = 41.00 min Total precip. = 3.00 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 2 0 2 4 6 8 10 12 14 16 18 20 22 24 26 Q (cfs) 0.00 0.00 4.00 4.00 8.00 8.00 12.00 12.00 16.00 16.00 20.00 20.00 24.00 24.00 28.00 28.00 Q (cfs) Time (hrs) Creek Flow Hyd. No. 1 -- 1 Year Hyd No. 1 TR55 Tc Worksheet 3 Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Hyd. No. 1 Creek Flow Description A B C Totals Sheet Flow Manning's n-value = 0.400 0.011 0.011 Flow length (ft) = 100.0 0.0 0.0 Two-year 24-hr precip. (in) = 3.60 3.60 0.00 Land slope (%) = 2.00 0.00 0.00 Travel Time (min)=20.25 +0.00 +0.00 =20.25 Shallow Concentrated Flow Flow length (ft) = 2397.00 0.00 0.00 Watercourse slope (%) = 2.00 0.00 0.00 Surface description = Unpaved Paved Paved Average velocity (ft/s)=2.28 0.00 0.00 Travel Time (min)=17.51 +0.00 +0.00 =17.51 Channel Flow X sectional flow area (sqft) = 32.00 0.00 0.00 Wetted perimeter (ft) = 20.00 0.00 0.00 Channel slope (%) = 2.00 0.00 0.00 Manning's n-value = 0.030 0.015 0.015 Velocity (ft/s)=9.62 0.00 0.00 Flow length (ft) ({0})1900.0 0.0 0.0 Travel Time (min)=3.29 +0.00 +0.00 =3.29 Total Travel Time, Tc .............................................................................. 41.00 min Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Friday, 06 / 26 / 2020 Hyd. No. 1 Creek Flow Hydrograph type = SCS Runoff Peak discharge = 63.95 cfs Storm frequency = 2 yrs Time to peak = 12.38 hrs Time interval = 1 min Hyd. volume = 520,395 cuft Drainage area = 294.160 ac Curve number = 57.8 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = TR55 Time of conc. (Tc) = 41.00 min Total precip. = 3.60 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 4 0 2 4 6 8 10 12 14 16 18 20 22 24 26 Q (cfs) 0.00 0.00 10.00 10.00 20.00 20.00 30.00 30.00 40.00 40.00 50.00 50.00 60.00 60.00 70.00 70.00 Q (cfs) Time (hrs) Creek Flow Hyd. No. 1 -- 2 Year Hyd No. 1 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Friday, 06 / 26 / 2020 Hyd. No. 1 Creek Flow Hydrograph type = SCS Runoff Peak discharge = 216.91 cfs Storm frequency = 10 yrs Time to peak = 12.35 hrs Time interval = 1 min Hyd. volume = 1,299,445 cuft Drainage area = 294.160 ac Curve number = 57.8 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = TR55 Time of conc. (Tc) = 41.00 min Total precip. = 5.10 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 5 0 2 4 6 8 10 12 14 16 18 20 22 24 26 Q (cfs) 0.00 0.00 30.00 30.00 60.00 60.00 90.00 90.00 120.00 120.00 150.00 150.00 180.00 180.00 210.00 210.00 240.00 240.00 Q (cfs) Time (hrs) Creek Flow Hyd. No. 1 -- 10 Year Hyd No. 1 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Friday, 06 / 26 / 2020 Hyd. No. 1 Creek Flow Hydrograph type = SCS Runoff Peak discharge = 335.35 cfs Storm frequency = 25 yrs Time to peak = 12.33 hrs Time interval = 1 min Hyd. volume = 1,867,865 cuft Drainage area = 294.160 ac Curve number = 57.8 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = TR55 Time of conc. (Tc) = 41.00 min Total precip. = 6.00 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 6 0 2 4 6 8 10 12 14 16 18 20 22 24 26 Q (cfs) 0.00 0.00 50.00 50.00 100.00 100.00 150.00 150.00 200.00 200.00 250.00 250.00 300.00 300.00 350.00 350.00 Q (cfs) Time (hrs) Creek Flow Hyd. No. 1 -- 25 Year Hyd No. 1 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Friday, 06 / 26 / 2020 Hyd. No. 1 Creek Flow Hydrograph type = SCS Runoff Peak discharge = 435.75 cfs Storm frequency = 50 yrs Time to peak = 12.33 hrs Time interval = 1 min Hyd. volume = 2,349,407 cuft Drainage area = 294.160 ac Curve number = 57.8 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = TR55 Time of conc. (Tc) = 41.00 min Total precip. = 6.70 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 7 0 2 4 6 8 10 12 14 16 18 20 22 24 26 Q (cfs) 0.00 0.00 60.00 60.00 120.00 120.00 180.00 180.00 240.00 240.00 300.00 300.00 360.00 360.00 420.00 420.00 480.00 480.00 Q (cfs) Time (hrs) Creek Flow Hyd. No. 1 -- 50 Year Hyd No. 1 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Friday, 06 / 26 / 2020 Hyd. No. 1 Creek Flow Hydrograph type = SCS Runoff Peak discharge = 542.16 cfs Storm frequency = 100 yrs Time to peak = 12.32 hrs Time interval = 1 min Hyd. volume = 2,859,459 cuft Drainage area = 294.160 ac Curve number = 57.8 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = TR55 Time of conc. (Tc) = 41.00 min Total precip. = 7.40 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 8 0 2 4 6 8 10 12 14 16 18 20 22 24 26 Q (cfs) 0.00 0.00 80.00 80.00 160.00 160.00 240.00 240.00 320.00 320.00 400.00 400.00 480.00 480.00 560.00 560.00 Q (cfs) Time (hrs) Creek Flow Hyd. No. 1 -- 100 Year Hyd No. 1 Culvert Report Hydraflow Express Extension for Autodesk® AutoCAD® Civil 3D® by Autodesk, Inc. Friday, Jun 26 2020 Box Culvert Invert Elev Dn (ft) = 393.20 Pipe Length (ft) = 41.00 Slope (%) = 0.61 Invert Elev Up (ft) = 393.45 Rise (in) = 42.0 Shape = Box Span (in) = 120.0 No. Barrels = 1 n-Value = 0.013 Culvert Type = Flared Wingwalls Culvert Entrance = 30D to 75D wingwall flares Coeff. K,M,c,Y,k = 0.026, 1, 0.0347, 0.81, 0.4 Embankment Top Elevation (ft) = 399.55 Top Width (ft) = 20.00 Crest Width (ft) = 100.00 Calculations Qmin (cfs) = 335.00 Qmax (cfs) = 550.00 Tailwater Elev (ft) = (dc+D)/2 Highlighted Qtotal (cfs) = 335.00 Qpipe (cfs) = 335.00 Qovertop (cfs) = 0.00 Veloc Dn (ft/s) = 9.91 Veloc Up (ft/s) = 10.26 HGL Dn (ft) = 396.58 HGL Up (ft) = 396.71 Hw Elev (ft) = 399.45 Hw/D (ft) = 1.72 Flow Regime = Inlet Control 30 June 2020 The SITE Group 1111 Oberlin Road 919-832-6658 (o) Raleigh NC 27605 919-839-2255 (f) PIPE SIZING 30 June 2020 The SITE Group 1111 Oberlin Road 919-832-6658 (o) Raleigh NC 27605 919-839-2255 (f) SKIMMER SEDIMENT BASIN SIZING By:SRN Basin 1 Land Use "c" Value Area (acres)% Area Weighted C Graded 0.45 0.63 1.00 0.45 0.00 0.00 0.00 0.00 0.00 0.00 Total Area = 0.63 Composite c = 0.45 C 0.45 L=---feet I-25 8.19 H=--feet A (acres)0.63 Tc=5.00 minutes Q-25(cfs)2.32 I-25=8.19 *interpolate Minimum Surface Area Required(acre) A = 435 sf per cfs of Q25 Min. Area 0.02 acres 1,010.01 sf Minimum Storage Volume Required (cf) V = 1800 ft3 / acre drainage Min. Volume 1,134.00 cf Surface Area Provided(acre) 0.05 acres 2,017.00 sf Storage Volume Provided (cf) 3,610.00 cf Calculated Dimensions Provided Dimensions Skimmer Sediment Basin Design Calculations YPUB April 24, 2020 Composite C Calculation Peak Flow Q=CIA Time of Concentration Tc=((L^3/H)^0.385)/128 Calculate Skimmer Size for Faircloth Skimmer® Basin Volume in Cubic Feet 3,610 Cu.Ft Skimmer Size 1.5 Inch Days to Drain*3 Days Orifice Radius 0.6 Inch[es] Orifice Diameter 1.3 Inch[es] *In NC assume 3 days to drain If no results maximum flow rate for a single skimmer is exceeded. More than one skimmer may be required. Estimate Volume of Basin Length Width Top of water surface in feet Feet VOLUME 0 Cu. Ft. Bottom dimensions in feet Feet Depth in feet Feet Updated 5/1/19 30 June 2020 The SITE Group 1111 Oberlin Road 919-832-6658 (o) Raleigh NC 27605 919-839-2255 (f) OUTLET PROTECTION OUTLET PROTECTION DATE DESIGN PHASE DESIGN 28-Apr-20 PRELIM / / PROJECT NAME PROJECT NO CONSTR / X / Public Utility Building YPUB REVISION LOCATION BY RECORD Youngsville, NC SRN OTHER CHECKED BY (SPECIFY) SRN FES #1 Pipe Dia=15 in Q10 =1.43 cfs Qfull =5.85 cfs V =4.77 fps From Fig. 8.06.b.1:Zone =1 From Fig. 8.06.b.2:D50 =4 in DMAX =6 in Riprap Class =A Apron Thickness =9 in Apron Length =5.0 ft Apron Width = 3xDia =3.75 ft FES #3 Pipe Dia=15 in Q10 =2.71 cfs Qfull =5.37 cfs V =4.37 fps From Fig. 8.06.b.1:Zone =1 From Fig. 8.06.b.2:D50 =4 in DMAX =6 in Riprap Class =A Apron Thickness =9 in Apron Length =5 ft Apron Width = 3xDia =3.75 ft YPUB-OutletDesign.xls LATEST REVISION: 6/30/2020 11:08 AM PAGE 1 OF 5 FES #7 & HW #8 Pipe Dia=15 in Q10 =1.65 cfs Qfull =13.64 cfs V =11.12 fps From Fig. 8.06.b.1:Zone =2 From Fig. 8.06.b.2:D50 =8 in DMAX =12 in Riprap Class =B Apron Thickness =18 in Apron Length =8 ft Apron Width = 3xDia =3.75 ft FES #9 & FES #10 Pipe Dia= 15 in Q10 =1.44 cfs Qfull =5.05 cfs V =4.11 fps From Fig. 8.06.b.1:Zone =1 From Fig. 8.06.b.2:D50 =4 in DMAX =6 in Riprap Class =A Apron Thickness =9 in Apron Length =5 ft Apron Width = 3xDia =3.75 ft YPUB-OutletDesign.xls LATEST REVISION: 6/30/2020 11:08 AM PAGE 2 OF 5 D50 (in)DMAX (in)Riprap Class Apron Thickness (in) Apron Length (ft) Apron Width (ft) FES #1 4 6 A 9 5 5 FES #3 4 6 A 9 5 5 FES #7 8 12 B 18 8 5 HW #8 8 12 B 18 8 5 FES #9 4 6 A 9 5 5 FES #10 4 6 A 9 20 10 HW#11*14 21 2 32 20 20 HW#12*14 21 2 32 20 20 * Box culvert to be installed in creek bed. Invert designed 1' below stream bed bottom. RIP RAP OUTLET PROTECTION YPUB-OutletDesign.xls LATEST REVISION: 6/30/2020 11:08 AM PAGE 3 OF 5 30 June 2020 The SITE Group 1111 Oberlin Road 919-832-6658 (o) Raleigh NC 27605 919-839-2255 (f) DIVERSION DITCH LINING Channel Liner Analysis Project:YPUB Date: 6/30/2020 Outlet Ditch at FES #1 Physical Characteristics of Drainage Swale Chan Bot Side Side Slope Design Channel Wetted Hydraulic Channel Width (ft)Slope Length (ft)Depth (ft)Area (sf)Perim., Pw (ft)Radius (ft)Slope (ft/ft) 2 2 4.5 2 12.0 10.94 1.10 0.005 Rational Equation for 2 year storm Bare Soil calculations (Q2) Drainage Q2*Upstream swale#Upstream swale#Upstream swale# Intensity Area Discharge - - - Mannings Q AutoCad AutoCad Shear C Factor Inch/hr (Acres)(Cfs)Flow (cfs)Flow (cfs)Flow (cfs)"n"Allow.Depth (in)Velocity (fps)Stress (lb/sf) 0.01 0.00 0.00 0.00 0.01 0.020 67.22 0.1 0.10 0.00 Rational Equation for 10 year storm Temporary liner calculations (Q2) Drainage Q10*Upstream swale#Upstream swale#Upstream swale# Intensity Area Discharge - - - Mannings Q AutoCad AutoCad Shear C Factor Inch/hr (Acres)(Cfs)Flow (cfs)Flow (cfs)Flow (cfs)"n"Allow.Depth (in)Velocity (fps)Stress (lb/sf) 2.30 0.00 0.00 0.00 2.30 0.028 48.01 0.7 0.04 0.02 *Flow rate from pond routing in Hydrograph model Permanent liner calculations (Q10) Mannings Q AutoCad AutoCad Shear Permissible "n"Allow.Depth (in)Velocity (fps)Stress (lb/sf) 0-0.5 ft 0.5-2.0 ft > 2.0 ft velocitiy (fps)0.044 30.55 18.0 0.30 0.47 0.023 0.02 0.02 2.00 Allowable Allowable 0-0.5 ft 0.5-2.0 ft > 2.0 ft Shear Stress ( lb/sf)0-0.5 ft 0.5-2.0 ft > 2.0 ft Shear Stress ( lb/sf) 0.055 0.028 0.021 1.55 C350 Phase 2 0.044 0.044 0.044 4.50 0.055 0.028 0.021 1.65 C300 Phase 2 0.044 0.044 0.044 4.00 0.050 0.025 0.018 1.80 C350 Phase 3 0.049 0.049 0.049 8.00 0.022 0.014 0.014 2.25 P300 Phase 3 0.049 0.049 0.049 8.00 0.040 0.025 0.02 2.25 0.034 0.024 0.02 2.00 Permissible velocitiy (fps) Allowable Grass Mixture 0.030 5.00 0-0.5 ft 0.5-2.0 ft > 2.0 ft Shear Stress ( lb/sf) 0.044 0.033 0.03 1.65 0.066 0.041 0.034 3.00 0.104 0.069 0.035 4.50 - 0.078 0.04 6.00 Shear Stress, T= y*(d/12)*s Selected Temporary Liner:S75 Notes:Spreadsheet works for trapezoidal channel only T = shear stress in lb/sq. ft. Side slope = horiz./vert. y = unit weight of water, 62.4 lb/cu. ft.Selected Permanent Liner:C350 Needs input d = flow depth in in. Output taken from AutoCad's Trapezoidial Ditch Calculater s = channel slope in ft./ft. Recommended n Values Addition flow from upstream Swales Total Flow (cfs) Addition flow from upstream Swales Total Flow (cfs) Material Recommended n Values for Flow Depth*Material Permanent Liners Vegetated Permanent Liners C350 Material Class A S150 SC150 *Material Unvegetated S75 C125 Bare Soil Material Recommended n Values for Flow Depth Bare Soil Temporary Liners Recommended n Values for Flow Depth * The Material lists refers to North American Green products. Contractor to use referenced material or approved equal. P300 Recommended n Values for Flow Depth Class B Rip Rap Liners Class I Class II YPUB-swale liner calcs.xls Channel Liner Analysis Project:YPUB Date: 6/30/2020 Temporary Clean Water Diversion Ditch #1 Physical Characteristics of Drainage Swale Chan Bot Side Side Slope Design Channel Wetted Hydraulic Channel Width (ft)Slope Length (ft)Depth (ft)Area (sf)Perim., Pw (ft)Radius (ft)Slope (ft/ft) 1 2 4.5 2 10.0 9.94 1.01 0.02 Rational Equation for 2 year storm Bare Soil calculations (Q2) Drainage Q2 Upstream swale#Upstream swale#Upstream swale# Intensity Area Discharge - - - Mannings Q AutoCad AutoCad Shear C Factor Inch/hr (Acres)(Cfs)Flow (cfs)Flow (cfs)Flow (cfs)"n"Allow.Depth (in)Velocity (fps)Stress (lb/sf) 0.45 5.76 0.25 0.65 0.00 0.00 0.00 0.65 0.020 105.75 3.0 2.29 0.31 Rational Equation for 10 year storm Temporary liner calculations (Q2) Drainage Q10 Upstream swale#Upstream swale#Upstream swale# Intensity Area Discharge - - - Mannings Q AutoCad AutoCad Shear C Factor Inch/hr (Acres)(Cfs)Flow (cfs)Flow (cfs)Flow (cfs)"n"Allow.Depth (in)Velocity (fps)Stress (lb/sf) 0.45 7.22 0.25 0.81 0.00 0.00 0.00 0.81 0.028 75.54 8.2 0.41 0.85 Permanent liner calculations (Q10) Mannings Q AutoCad AutoCad Shear Permissible "n"Allow.Depth (in)Velocity (fps)Stress (lb/sf) 0-0.5 ft 0.5-2.0 ft > 2.0 ft velocitiy (fps)0.030 70.50 N/A N/A #VALUE! 0.023 0.02 0.02 2.00 Allowable Allowable 0-0.5 ft 0.5-2.0 ft > 2.0 ft Shear Stress ( lb/sf)0-0.5 ft 0.5-2.0 ft > 2.0 ft Shear Stress ( lb/sf) 0.055 0.028 0.021 1.55 C350 Phase 2 0.044 0.044 0.044 4.50 0.055 0.028 0.021 1.65 C300 Phase 2 0.044 0.044 0.044 4.00 0.050 0.025 0.018 1.80 C350 Phase 3 0.049 0.049 0.049 8.00 0.022 0.014 0.014 2.25 P300 Phase 3 0.049 0.049 0.049 8.00 0.040 0.025 0.02 2.25 0.034 0.024 0.02 2.00 Permissible velocitiy (fps) Allowable Grass Mixture 0.030 5.00 0-0.5 ft 0.5-2.0 ft > 2.0 ft Shear Stress ( lb/sf) 0.044 0.033 0.03 1.65 0.066 0.041 0.034 3.00 0.104 0.069 0.035 4.50 - 0.078 0.04 6.00 Shear Stress, T= y*(d/12)*s Selected Temporary Liner:S75 Notes:Spreadsheet works for trapezoidal channel only T = shear stress in lb/sq. ft. Side slope = horiz./vert. y = unit weight of water, 62.4 lb/cu. ft.Selected Permanent Liner:N/A Needs input d = flow depth in in. Output taken from AutoCad's Trapezoidial Ditch Calculater s = channel slope in ft./ft. * The Material lists refers to North American Green products. Contractor to use referenced material or approved equal. Material Recommended n Values for Flow Depth Class A Class B Class I Class II C350 P300 Permanent Liners Material Recommended n Values Rip Rap Liners Unvegetated Vegetated S75 S150 SC150 C125 Bare Soil Temporary Liners Permanent Liners *Material Recommended n Values for Flow Depth *Material Recommended n Values for Flow Depth Addition flow from upstream Swales Total Flow (cfs) Addition flow from upstream Swales Total Flow (cfs) Bare Soil Material Recommended n Values for Flow Depth YPUB-swale liner calcs.xls Channel Liner Analysis Project:YPUB Date: 6/30/2020 Temporary Clean Water Diversion Ditch #2 Physical Characteristics of Drainage Swale Chan Bot Side Side Slope Design Channel Wetted Hydraulic Channel Width (ft)Slope Length (ft)Depth (ft)Area (sf)Perim., Pw (ft)Radius (ft)Slope (ft/ft) 1 2 3.4 1.5 6.0 7.71 0.78 0.0185 Rational Equation for 2 year storm Bare Soil calculations (Q2) Drainage Q2 Upstream swale#Upstream swale#Upstream swale# Intensity Area Discharge - - - Mannings Q AutoCad AutoCad Shear C Factor Inch/hr (Acres)(Cfs)Flow (cfs)Flow (cfs)Flow (cfs)"n"Allow.Depth (in)Velocity (fps)Stress (lb/sf) 0.45 5.76 0.04 0.11 0.00 0.00 0.00 0.11 0.020 51.45 3.0 2.29 0.29 Rational Equation for 10 year storm Temporary liner calculations (Q2) Drainage Q10 Upstream swale#Upstream swale#Upstream swale# Intensity Area Discharge - - - Mannings Q AutoCad AutoCad Shear C Factor Inch/hr (Acres)(Cfs)Flow (cfs)Flow (cfs)Flow (cfs)"n"Allow.Depth (in)Velocity (fps)Stress (lb/sf) 0.45 7.22 0.044 0.14 0.00 0.00 0.00 0.14 0.055 18.71 4.8 0.15 0.46 Permanent liner calculations (Q10) Mannings Q AutoCad AutoCad Shear Permissible "n"Allow.Depth (in)Velocity (fps)Stress (lb/sf) 0-0.5 ft 0.5-2.0 ft > 2.0 ft velocitiy (fps)0.030 34.30 N/A N/A #VALUE! 0.023 0.02 0.02 2.00 Allowable Allowable 0-0.5 ft 0.5-2.0 ft > 2.0 ft Shear Stress ( lb/sf)0-0.5 ft 0.5-2.0 ft > 2.0 ft Shear Stress ( lb/sf) 0.055 0.028 0.021 1.55 C350 Phase 2 0.044 0.044 0.044 4.50 0.055 0.028 0.021 1.65 C300 Phase 2 0.044 0.044 0.044 4.00 0.050 0.025 0.018 1.80 C350 Phase 3 0.049 0.049 0.049 8.00 0.022 0.014 0.014 2.25 P300 Phase 3 0.049 0.049 0.049 8.00 0.040 0.025 0.02 2.25 0.034 0.024 0.02 2.00 Permissible velocitiy (fps) Allowable Grass Mixture 0.030 5.00 0-0.5 ft 0.5-2.0 ft > 2.0 ft Shear Stress ( lb/sf) 0.044 0.033 0.03 1.65 0.066 0.041 0.034 3.00 0.104 0.069 0.035 4.50 - 0.078 0.04 6.00 Shear Stress, T= y*(d/12)*s Selected Temporary Liner:S75 Notes:Spreadsheet works for trapezoidal channel only T = shear stress in lb/sq. ft. Side slope = horiz./vert. y = unit weight of water, 62.4 lb/cu. ft.Selected Permanent Liner:N/A Needs input d = flow depth in in. Output taken from AutoCad's Trapezoidial Ditch Calculater s = channel slope in ft./ft. * The Material lists refers to North American Green products. Contractor to use referenced material or approved equal. Material Recommended n Values for Flow Depth Class A Class B Class I Class II C350 P300 Permanent Liners Material Recommended n Values Rip Rap Liners Unvegetated Vegetated S75 S150 SC150 C125 Bare Soil Temporary Liners Permanent Liners *Material Recommended n Values for Flow Depth *Material Recommended n Values for Flow Depth Addition flow from upstream Swales Total Flow (cfs) Addition flow from upstream Swales Total Flow (cfs) Bare Soil Material Recommended n Values for Flow Depth YPUB-swale liner calcs.xls Channel Liner Analysis Project:YPUB Date: 6/30/2020 Temporary Diversion Ditch #3 Physical Characteristics of Drainage Swale Chan Bot Side Side Slope Design Channel Wetted Hydraulic Channel Width (ft)Slope Length (ft)Depth (ft)Area (sf)Perim., Pw (ft)Radius (ft)Slope (ft/ft) 1 2 3.4 1.5 6.0 7.71 0.78 0.008 Rational Equation for 2 year storm Bare Soil calculations (Q2) Drainage Q2 Upstream swale#Upstream swale#Upstream swale# Intensity Area Discharge - - - Mannings Q AutoCad AutoCad Shear C Factor Inch/hr (Acres)(Cfs)Flow (cfs)Flow (cfs)Flow (cfs)"n"Allow.Depth (in)Velocity (fps)Stress (lb/sf) 0.45 5.76 0.26 0.67 0.00 0.00 0.00 0.67 0.020 33.83 2.0 1.80 0.08 Rational Equation for 10 year storm Temporary liner calculations (Q2) Drainage Q10 Upstream swale#Upstream swale#Upstream swale# Intensity Area Discharge - - - Mannings Q AutoCad AutoCad Shear C Factor Inch/hr (Acres)(Cfs)Flow (cfs)Flow (cfs)Flow (cfs)"n"Allow.Depth (in)Velocity (fps)Stress (lb/sf) 0.45 7.22 0.26 0.84 0.00 0.00 0.00 0.84 0.028 24.17 9.7 0.32 0.40 Permanent liner calculations (Q10) Mannings Q AutoCad AutoCad Shear Permissible "n"Allow.Depth (in)Velocity (fps)Stress (lb/sf) 0-0.5 ft 0.5-2.0 ft > 2.0 ft velocitiy (fps)0.030 22.55 N/A N/A #VALUE! 0.023 0.02 0.02 2.00 Allowable Allowable 0-0.5 ft 0.5-2.0 ft > 2.0 ft Shear Stress ( lb/sf)0-0.5 ft 0.5-2.0 ft > 2.0 ft Shear Stress ( lb/sf) 0.055 0.028 0.021 1.55 C350 Phase 2 0.044 0.044 0.044 4.50 0.055 0.028 0.021 1.65 C300 Phase 2 0.044 0.044 0.044 4.00 0.050 0.025 0.018 1.80 C350 Phase 3 0.049 0.049 0.049 8.00 0.022 0.014 0.014 2.25 P300 Phase 3 0.049 0.049 0.049 8.00 0.040 0.025 0.02 2.25 0.034 0.024 0.02 2.00 Permissible velocitiy (fps) Allowable Grass Mixture 0.030 5.00 0-0.5 ft 0.5-2.0 ft > 2.0 ft Shear Stress ( lb/sf) 0.044 0.033 0.03 1.65 0.066 0.041 0.034 3.00 0.104 0.069 0.035 4.50 - 0.078 0.04 6.00 Shear Stress, T= y*(d/12)*s Selected Temporary Liner:S75 Notes:Spreadsheet works for trapezoidal channel only T = shear stress in lb/sq. ft. Side slope = horiz./vert. y = unit weight of water, 62.4 lb/cu. ft.Selected Permanent Liner:N/A Needs input d = flow depth in in. Output taken from AutoCad's Trapezoidial Ditch Calculater s = channel slope in ft./ft. * The Material lists refers to North American Green products. Contractor to use referenced material or approved equal. Material Recommended n Values for Flow Depth Class A Class B Class I Class II C350 P300 Permanent Liners Material Recommended n Values Rip Rap Liners Unvegetated Vegetated S75 S150 SC150 C125 Bare Soil Temporary Liners Permanent Liners *Material Recommended n Values for Flow Depth *Material Recommended n Values for Flow Depth Addition flow from upstream Swales Total Flow (cfs) Addition flow from upstream Swales Total Flow (cfs) Bare Soil Material Recommended n Values for Flow Depth YPUB-swale liner calcs.xls Channel Liner Analysis Project:YPUB Date: 6/30/2020 Temporary Diversion Ditch #4 Physical Characteristics of Drainage Swale Chan Bot Side Side Slope Design Channel Wetted Hydraulic Channel Width (ft)Slope Length (ft)Depth (ft)Area (sf)Perim., Pw (ft)Radius (ft)Slope (ft/ft) 1 2 3.4 1.5 6.0 7.71 0.78 0.014 Rational Equation for 2 year storm Bare Soil calculations (Q2) Drainage Q2 Upstream swale#Upstream swale#Upstream swale# Intensity Area Discharge - - - Mannings Q AutoCad AutoCad Shear C Factor Inch/hr (Acres)(Cfs)Flow (cfs)Flow (cfs)Flow (cfs)"n"Allow.Depth (in)Velocity (fps)Stress (lb/sf) 0.45 5.76 0.14 0.36 0.00 0.00 0.00 0.36 0.020 44.75 3.6 2.48 0.26 Rational Equation for 10 year storm Temporary liner calculations (Q2) Drainage Q10 Upstream swale#Upstream swale#Upstream swale# Intensity Area Discharge - - - Mannings Q AutoCad AutoCad Shear C Factor Inch/hr (Acres)(Cfs)Flow (cfs)Flow (cfs)Flow (cfs)"n"Allow.Depth (in)Velocity (fps)Stress (lb/sf) 0.45 7.22 0.14 0.45 0.00 0.00 0.00 0.45 0.028 31.97 7.3 0.27 0.53 Permanent liner calculations (Q10) Mannings Q AutoCad AutoCad Shear Permissible "n"Allow.Depth (in)Velocity (fps)Stress (lb/sf) 0-0.5 ft 0.5-2.0 ft > 2.0 ft velocitiy (fps)0.030 29.84 N/A N/A #VALUE! 0.023 0.02 0.02 2.00 Allowable Allowable 0-0.5 ft 0.5-2.0 ft > 2.0 ft Shear Stress ( lb/sf)0-0.5 ft 0.5-2.0 ft > 2.0 ft Shear Stress ( lb/sf) 0.055 0.028 0.021 1.55 C350 Phase 2 0.044 0.044 0.044 4.50 0.055 0.028 0.021 1.65 C300 Phase 2 0.044 0.044 0.044 4.00 0.050 0.025 0.018 1.80 C350 Phase 3 0.049 0.049 0.049 8.00 0.022 0.014 0.014 2.25 P300 Phase 3 0.049 0.049 0.049 8.00 0.040 0.025 0.02 2.25 0.034 0.024 0.02 2.00 Permissible velocitiy (fps) Allowable Grass Mixture 0.030 5.00 0-0.5 ft 0.5-2.0 ft > 2.0 ft Shear Stress ( lb/sf) 0.044 0.033 0.03 1.65 0.066 0.041 0.034 3.00 0.104 0.069 0.035 4.50 - 0.078 0.04 6.00 Shear Stress, T= y*(d/12)*s Selected Temporary Liner:S75 Notes:Spreadsheet works for trapezoidal channel only T = shear stress in lb/sq. ft. Side slope = horiz./vert. y = unit weight of water, 62.4 lb/cu. ft.Selected Permanent Liner:N/A Needs input d = flow depth in in. Output taken from AutoCad's Trapezoidial Ditch Calculater s = channel slope in ft./ft. * The Material lists refers to North American Green products. Contractor to use referenced material or approved equal. Material Recommended n Values for Flow Depth Class A Class B Class I Class II C350 P300 Permanent Liners Material Recommended n Values Rip Rap Liners Unvegetated Vegetated S75 S150 SC150 C125 Bare Soil Temporary Liners Permanent Liners *Material Recommended n Values for Flow Depth *Material Recommended n Values for Flow Depth Addition flow from upstream Swales Total Flow (cfs) Addition flow from upstream Swales Total Flow (cfs) Bare Soil Material Recommended n Values for Flow Depth YPUB-swale liner calcs.xls Channel Report Hydraflow Express Extension for Autodesk® AutoCAD® Civil 3D® by Autodesk, Inc. Tuesday, Jun 30 2020 Outlet Ditch at FES #1 - 10-Yr Storm Trapezoidal Bottom Width (ft) = 2.00 Side Slopes (z:1) = 2.00, 2.00 Total Depth (ft) = 2.00 Invert Elev (ft) = 20.00 Slope (%) = 0.01 N-Value = 0.044 Calculations Compute by: Known Q Known Q (cfs) = 2.30 Highlighted Depth (ft) = 1.51 Q (cfs) = 2.300 Area (sqft) = 7.58 Velocity (ft/s) = 0.30 Wetted Perim (ft) = 8.75 Crit Depth, Yc (ft) = 0.31 Top Width (ft) = 8.04 EGL (ft) = 1.51 0 1 2 3 4 5 6 7 8 9 10 11 12 Elev (ft) Depth (ft)Section 19.50 -0.50 20.00 0.00 20.50 0.50 21.00 1.00 21.50 1.50 22.00 2.00 22.50 2.50 23.00 3.00 Reach (ft) Channel Report Hydraflow Express Extension for Autodesk® AutoCAD® Civil 3D® by Autodesk, Inc. Tuesday, Jun 30 2020 Clean Water Diversion Ditch #1 Trapezoidal Bottom Width (ft) = 1.00 Side Slopes (z:1) = 2.00, 2.00 Total Depth (ft) = 2.00 Invert Elev (ft) = 20.00 Slope (%) = 0.02 N-Value = 0.028 Calculations Compute by: Known Q Known Q (cfs) = 0.65 Highlighted Depth (ft) = 0.68 Q (cfs) = 0.650 Area (sqft) = 1.60 Velocity (ft/s) = 0.41 Wetted Perim (ft) = 4.04 Crit Depth, Yc (ft) = 0.21 Top Width (ft) = 3.72 EGL (ft) = 0.68 0 1 2 3 4 5 6 7 8 9 10 11 Elev (ft) Depth (ft)Section 19.50 -0.50 20.00 0.00 20.50 0.50 21.00 1.00 21.50 1.50 22.00 2.00 22.50 2.50 23.00 3.00 Reach (ft) Channel Report Hydraflow Express Extension for Autodesk® AutoCAD® Civil 3D® by Autodesk, Inc. Tuesday, Jun 30 2020 Clean Water Diversion Ditch #2 Trapezoidal Bottom Width (ft) = 1.00 Side Slopes (z:1) = 2.00, 2.00 Total Depth (ft) = 2.00 Invert Elev (ft) = 20.00 Slope (%) = 0.02 N-Value = 0.055 Calculations Compute by: Known Q Known Q (cfs) = 0.11 Highlighted Depth (ft) = 0.40 Q (cfs) = 0.110 Area (sqft) = 0.72 Velocity (ft/s) = 0.15 Wetted Perim (ft) = 2.79 Crit Depth, Yc (ft) = 0.07 Top Width (ft) = 2.60 EGL (ft) = 0.40 0 1 2 3 4 5 6 7 8 9 10 11 Elev (ft) Depth (ft)Section 19.50 -0.50 20.00 0.00 20.50 0.50 21.00 1.00 21.50 1.50 22.00 2.00 22.50 2.50 23.00 3.00 Reach (ft) Channel Report Hydraflow Express Extension for Autodesk® AutoCAD® Civil 3D® by Autodesk, Inc. Tuesday, Jun 30 2020 Temporary Diversion Ditch #3 Trapezoidal Bottom Width (ft) = 1.00 Side Slopes (z:1) = 2.00, 2.00 Total Depth (ft) = 2.00 Invert Elev (ft) = 20.00 Slope (%) = 0.01 N-Value = 0.028 Calculations Compute by: Known Q Known Q (cfs) = 0.67 Highlighted Depth (ft) = 0.81 Q (cfs) = 0.670 Area (sqft) = 2.12 Velocity (ft/s) = 0.32 Wetted Perim (ft) = 4.62 Crit Depth, Yc (ft) = 0.21 Top Width (ft) = 4.24 EGL (ft) = 0.81 0 1 2 3 4 5 6 7 8 9 10 11 Elev (ft) Depth (ft)Section 19.50 -0.50 20.00 0.00 20.50 0.50 21.00 1.00 21.50 1.50 22.00 2.00 22.50 2.50 23.00 3.00 Reach (ft) Channel Report Hydraflow Express Extension for Autodesk® AutoCAD® Civil 3D® by Autodesk, Inc. Tuesday, Jun 30 2020 Temporary Diversion Ditch #4 Trapezoidal Bottom Width (ft) = 1.00 Side Slopes (z:1) = 2.00, 2.00 Total Depth (ft) = 2.00 Invert Elev (ft) = 20.00 Slope (%) = 0.01 N-Value = 0.028 Calculations Compute by: Known Q Known Q (cfs) = 0.36 Highlighted Depth (ft) = 0.61 Q (cfs) = 0.360 Area (sqft) = 1.35 Velocity (ft/s) = 0.27 Wetted Perim (ft) = 3.73 Crit Depth, Yc (ft) = 0.15 Top Width (ft) = 3.44 EGL (ft) = 0.61 0 1 2 3 4 5 6 7 8 9 10 11 Elev (ft) Depth (ft)Section 19.50 -0.50 20.00 0.00 20.50 0.50 21.00 1.00 21.50 1.50 22.00 2.00 22.50 2.50 23.00 3.00 Reach (ft) 30 June 2020 The SITE Group 1111 Oberlin Road 919-832-6658 (o) Raleigh NC 27605 919-839-2255 (f) SOIL AND USGS MAPS Project Number: SBProject Manager: 1" = 1000'Scale: 02/25/2020Date: Map Title: Source: Figure 2 - Soil Survey Map Youngsville Public WorksFranklin County, NC Frankllin County Soil Survey Sheet 9 ¯0 1,000 2,000 Feet 14158.W1 Project Number: SBProject Manager: 1" = 1000'Scale: 02/25/2020Date: Map Title: Source: Figure 1 - USGS Map Youngsville Public WorksFranklin County, NC NC One Map AerialFranklin County ¯0 1,000 2,000 Feet 14158.W1 30 June 2020 The SITE Group 1111 Oberlin Road 919-832-6658 (o) Raleigh NC 27605 919-839-2255 (f) DRAINAGE AREA MAPS SOUTH COLLEGE STREET60' PUBLIC R/WSR-1182PUBLIC UTILITY BUILDINGDA1.0 SOUTH COLLEGE STREET60' PUBLIC R/WSR-1182PUBLIC UTILITY BUILDINGDA2.0 SOUTH COLLEGE STREET60' PUBLIC R/WSR-1182PUBLIC UTILITY BUILDINGDA3.0 SOUTH COLLEGE STREET60' PUBLIC R/WSR-1182PUBLIC UTILITY BUILDINGDA2.0 PUBLIC UTILITY BUILDINGDA5.0