HomeMy WebLinkAbout19950161 Ver 1_Complete File_19950214' J 1 ?I' d y?o?
STATE OF NORTH CAROLINA
DEPARTMENT OF TRANSPORTATION
JAMES B. HUNT, JR. DIVISION OF HIGHWAYS R. SAMUEL HUNT III
GOVERNOR P.O. BOX 25201, RALEIGH. N.C. 27611-5201 SECRETARY
January 31, 1995
District Engineer
U.S. Army Corps of Engineers
P.O. Box 1890 "
Wilmington, NC 28402-1890
ATTENTION: Regulatory Branch
SUBJECT: Transylvania County, Replacement of Bridge No.69 over North Fork
French Broad River, US 64, TIP No. B-2171, State Project
No. 8.1000401, Federal Aid NO.BRF-15-1-(8).
COE Action ID. No. 199203499
Dear Sir:
ItThe N. C. Department of Transportation (NCDOT) is proposing to replace the existing
bridge on US 64 over North Fork French Broad River near Rosman, Transylvania County,
North Carolina. This project was processed by the Federal Highway Administration as a
"Categorical Exclusion" in accordance with 23 CFR 771.115(b). The project planning
report for the subject project was submitted to your agency August 25, 1992.
Consequently, the project was authorized by your agency under Nationwide Permit 23 on
July 30, 1993.
On June 10, 1994, the NCDOT requested a Nationwide Permit 6 for this project to
conduct foundation test borings. This authorization was granted September 9, 1994.
Subsequently, the NCDOT has finalized its design plans for this bridge replacement.
The overall design for the project has not been changed. However, it will be necessary to
use three cofferdams in the river during project construction. These cofferdams were not
discussed in the planning document. They will be used to minimize sedimentation caused
by construction of the new bridge and the removal of the existing bridge bent.
The French Broad River immediately downstream of the study area is considered a
Hatchery Supported Designated Public Mountain Trout Water by the North Carolina
Wildlife Resources Commission (NCWRC). Accordingly, the NCDOT has prepared
revised permit drawings that depict the proposed cofferdams. It is anticipated that the use
of these cofferdams will minimize adverse sedimentation impacts from the proposed
project.
Not
;)ace that 401 General Water Quality Certification No. 2734 (Categorical
E?. n) will still apply to this project, and are providing a copy of this information to the
North Carolina Department of Environment, Health and Natural Resources, Division of
Environmental Management, for their review.
We also anticipate that comments from the NCWRC will be required prior to authorization
by the Corps of Engineers. By copy of this letter and attachment, NCDOT hereby
requests that NCWRC review the project plans. NCDOT requests that NCWRC forward
their comments to the Corps of Engineers.
If you have any questions or need any additional information, please contact Mr. Gordon
Cashin at (919) 733-3141.
Sincerely,
C
Assistant Manager,
Planning and Environmental Branch
GEC
Attachments
CC: Mr. David Baker, COE, Asheville
Mr. John Dorney, NCEHNR, DEM
Mr. David Cox, NCWRC
Mr. David Yow, NCWRC, Asheville
Mr. Kelly Barger, PE, Program Development Branch
Mr. Don Morton, State Highway Engineer - Design
Mr. A. L. Hankins, Hydraulics Unit
Mr. Tom Shearin, PE, State Roadway Design Engineer
Mr. F. D. Martin, PE, Division 14 Engineer
Mr. John L. Smith, Jr., Structure Design Unit
Ms. Julie Hunkins, Project Planning Engineer
V L Y r%r _ -._+ur•?:'f_, \ !0 i1? Itl __B aldsvl it -S,,7 A,a NOAOlsrrn
Alin „d McD
float
Lltdi 11 '•'.,/ 1 ?) 1 SlocAfrAlt I71 S D 12 LaAr e
To A.
vernldl WtevarnUt •wfr %u,anlGarden
`,l AIluAi/er t ru,r
Y l' 1 Wno ml tr '?? Monlrest ,,, 1
Mr .^.e„e ` m lelcsst.r 4
el]r I PARK lack g 7
Moll taln 6 1
Came ,! .. •:•.' eer,? reekl teen 10 ` Idtscreft
:.. j .or• // AyerRbuee Sh i?f?f4 ' ?(7
'T" S
sugar H III
216 OI OI L •S 1 Swannanos
?(r rrHO/ff ?]L `
I EAAa 1
Valley I k,nNyf] a? ll - •II '( 10 71
ValleH
?N„ l?seu sllwooQ, _t iIYE Ii?p0 of.. rntff It f, • ?7A fauwew 9 y-?. +..
IHOAeY J ?F I II / 1•? !t tVJ
chil(et waynesvi
W4odrod (I,? ?,as SA(land Getton
..s(rroe 1 2'1 ?5 Hst91'IOOd / SMIAtdal.l Arden • J 1
Mr ('.a- 1 - ; ft ' i 7 i B.1 Cave hlmnt oc
.- alit 6 tur,doA S PI GA\- I ?5?'l •'?" - c
?r w MM. ?!"'. ¢ r` / f ttlc of 64 1 I
Ad?. dltaA i I . hrNac / 6 i ?rurn. • 'a I Moun1U FrmtlanA' 6 1 Cuie
1 •' "?11'?I/ IMI." Sunburst 116 •A .
1? ?a O Srlve * .? e ` Md11 NtXe r I Mont dnervfita 1 ....
ir1 1 e 9
nlbpo i1• ] I I w,e•+`,d \ 12
,/ webstet ' It NAT
Gree"H 1 wcu •'i Hof a p
cel,
r Etit t
reeA t to he*
I S r ?' 11 , FA 4 OIL towe? fist / f.olfrl Jeri
tU ( f Go 10 (sea LsOat set??p, FO R. ndetsonvill0 l Rock I, iMrll swims
A C fi S ,t l0 1`! said •` ' tnro
Estd. Sr / ru,t R?COCA t 5
TucAfset ae E ?, v`E,.,.
1 triAne, t;.nOdi; Stl , _
? Brevafdl'1i...It IN Rover Tuxedo Cglp
A 1F
OREST I • LIP 116 r
T R A N S Y I,VAA N I A I J?? I r fr a T-
Iltsals ITI oAr 1 Glenville Chetl Il41 d?/4 •1,S 1 0v I •?'-•'Lobt
W Lome,
.'I,r rr.l II ?. /? Ra,.
a d 1 y
Gne's t (10 6e1 IO Tnra µ leA Of C, del ,',••`„larn try, 17 R / S T
u Clsnrai t ?r,/.ti ^I Touwar r CassrsHead 6 t 1 , Ney
1
-!-'iA ut Tnmu,r •'• 6 GowtnArf110 be 10 19
L a.,eel r«I 1 H.sh r-OPAlrr 1 - Campo
L
Harnoton 10
Glsmbn
1rvu?.wrn *\ / 11 cTtVale ' IS
NyhlsndS s Rocxy nonn^ I1. 1, i
' Scar s__\l? - / 7, _Z. 10 ' (A,• 1? MIr'?JJJr 15 0 II Inman
0 S 10 hl '0
F-s? - r? - --? SCAT I OF Mlt(S ON! INCH EQUALS AI?ROR 17 Mll(S
? - - ^' --, SCAIt Of AIEOMF IERS OHIO INCH tQUA1S AFFROX 11 RIIOM(TERS ,
0 10 20 10 10 Ae
1 Mllt IS (QUAt f01 601 RIIOM(TE RS
r
r•• r t •
oSM
1m 1'OR ell
r i t"
E • ?,
1W ,
e? /I N
4r F H?•Ir"? gf
r /
Ujg
1w
11 \
U01,
.5 1
lift
cot
I11?
u
?, c.lr.n
, 11»
7 too
r:n
uw
,111.
llot `li"
1101 / •1
4
Ir /
O list
Ilot
ff
V lilt
11a'wl r ?'I'A• ?Rk G
^ i
D
%I-
Siff
wn
T
i
SCALE
' 0 t ] , e Aunts
CgFEi-Lrt?f --- -?
4 r=te L Mike
SCALE FOR ENLARGEMENTS
N. C. DEPARTMENT OF TRANSPORTATION
DIVISION OF HIGHWAYS
TRANSYLVANIA COUNTY
PROJECT NO.: 8.100401 (B-2171)
PROPOSED BRIDGE REPLACEMENT
OVER Tl-IE NORTH FORK FRENCH BROAD
RIVER BRIDGE NO. 69
SHEET 1. OF _
to e
I r emrood 1 B
Ia
? t
'- Dvsulsrdl
I _ Il-_ / jt
f
F?
11 ~ c r « ?,^ c „?
Ul r' r ? I
I I
I (
1 ? .?15 c.1,tn
Lxcq v,4 r7 ov
r' , I PNA.SE ?
? \ /? CJFFEIC D??
1 grr -? ` ? 2• I ) i ? ?
17
STI!_l-INC-,
?- ? ? 1 (fir+??•I
` _ F tom.
1 ? ? L1A?;E II..
i
b'1(? KAY'
Sc.nI _?-
o 10
R?T?ININC, _
/
W A LL
Cot'r E R T>\M
-Lf<EV-
? ? 7,t7
CLASS?Iz-
(lIV ;Znr,
?i
,
N. C. DEPARTMENT OF TRANSPORTATION
DIVISION OF HIGHWAYS
TRANSYLVANIA COUNTY
PROJECT NO.: 8.100401 (B-2171)
PROPOSED BRIDGE REPLACEMENT
OVER THE NORTH FORK FRENCH BROAD
RIVER BRIDGE NO. 69
SHEET Z. OF ?(
1A120 IrZoo \t Z20 I+ZAU
?oZ$
i
CLASS 'IE'
RIP RAP
674
ELLV.
a
?2 -4 i
c
RE"TAI N ING -
WALL.
, t?... _
r- G-70 .?.. ,
IDAV-A
(o?o?
rh_??
N. C. DEPARTMENT OF TRANSPORTATION
DIVISION OF HIGHWAYS
TRANSYLVANIA COUNTY
PROJECT NO.: 8.100401 (B-2171)
PROPOSED BRIDGE REPLACEMENT
OVER THE NORTH FORK FRENCH BROAD
RIVER BRIDGE NO. 69
SHEETS OF _ 4
SCALC
?Aur? ?To m AL
? mrF.c??. 10
C r\l_.
o
O
0
Cd
td
n
\I
w
t•1 c?? ?
3 V
I I ??
I
\, I I
I
I ,
_ I 1
I
r
1
i
O
ON `V WUo?
?pO°ac%z
[-C7U$o? W w
O O ? ? A O ? \I
ZO
?i> N
aQF-Oa?
w a;O?
p a ?
CU a"
z ?
4
s N t
1.? N
1 ?
W
M
j o
o °
. 1.
DRILLED SHAFT CONSTRUCTION
1. Install sediment control devices necessary for culvert construction, including
STILLING BASIN, SILT FENCE, AND STONE SILT SCREEN.
2. Install PHASE I cofferdams. Construct Bent 2. Pump all effluent into stilling basin.
3. Install PHASE II cofferdams. Construct Bent 1. Pump all effluent into stilling basin.
4. Install PHASE III cofferdams. Remove existing bridge bent. Pump all effluent into
stilling basin.
5. Remove all cofferdams and stilling basin. Upon stabilization of all disturbed areas
remove all temporary sediment control devices.
STATE OF NORTH CAROLINA
DEPARTMENT OF TRANSPORTATION
JAMES B. HUNT, JR. DIVISION OF HIGHWAYS R. SAMUEL HUNT III
GOVERNOR P.O. BOX 25201, RALEIGH. N.C. 27611-5201 SECRETAKY
January 31, 1995
District Engineer
U. S. Army Corps of Engineers 4
P.O. Box 1890
Wilmington, NC 28402-1890
ATTENTION: Regulatory Branch
SUBJECT: Transylvania County, Replacement of Bridge No.69 over North Fork
French Broad River, US 64, TIP No. B-2171, State Project
No. 8.1000401, Federal Aid No.BRF-15-1-(8).
COE Action ID. No. 199203499
Dear Sir:
The N. C. Department of Transportation (NCDOT) is proposing to replace the existing
bridge on US 64 over North Fork French Broad River near Rosman, Transylvania County,
North Carolina. This project was processed by the Federal Highway Administration as a
"Categorical Exclusion" in accordance with 23 CFR 771.115(b). The project planning
report for the subject project was submitted to vour agency August 25. 1992.
Consequently, the project was authorized by your agency under Nationwide Permit 23 on
July 30, 1993.
On June 10, 1994, the NCDOT requested a Nationwide Permit 6 for this project to
conduct foundation test borings. This authorization was granted September 9, 1994.
Subsequently, the NCDOT has finalized its design plans for this bridge replacement.
The overall design for the project has not been changed. However, it will be necessary to
use three cofferdams in the river during project construction. These cofferdams were not
discussed in the planning document. They will be used to minimize sedimentation caused
by construction of the new bridge and the removal of the existing bridge bent.
The French Broad River immediately downstream of the study area is considered a
Hatchery Supported Designated Public Mountain Trout Water by the North Carolina
Wildlife Resources Commission (NCWRC). Accordingly, the NCDOT has prepared
revised permit drawings that depict the proposed cofferdams. It is anticipated that the use
of these cofferdams will minimize adverse sedimentation impacts from the proposed
project.
??
pate that 401 General Water Quality Certification No. 2734 (Categorical
n) will still apply to this project, and are providing a copy of this information to the
M;i arolina Department of Environment, Health and Natural Resources, Division of
Emir iunental Management, for their review.
We also anticipate that comments from the NCWRC will be required prior to authorization
by the Corps of Engineers. By copy of this letter and attachment, NCDOT hereby
requests that NCWRC review the project plans. NCDOT requests that NCWRC forward
their comments to the Corps of Engineers.
If you have any questions or need any additional information, please contact _N/Ir. Gordon
Cashin at (919) 733-3141.
Sincerely, _
B.? uinn,-P
Assistant Manager,
Planning and Environmental Branch
GEC
Attachments
CC: Mr. David Baker, COE, Asheville
%,Ir. John Dorney, NCEHNR, DEM
Mr. David Cox, NCWRC
Mr. David Yow, NCWRC, Asheville
Mr. Kelly Barger, PE, Program Development Branch
Tv 1r. Don Morton, State Highway Engineer - Design
Mr. A. L. Hankins, Hydraulics Unit
Mr. Tom Shearin, PE, State Roadway Design Engineer
Mr. F. D. Martin, PE, Division 14 Engineer
Mr. John L. Smith, Jr., Structure Design Unit
Ms. Julie Hunkins, Project Planning Engineer
' u,r`IilI I 0 -"? '-•"--__ nw-..m.?r - -.-WoodTAwn
+
+ IT ' Old lie TrAnAnr llwd MCD
WT
rutt ) illin h+?^ 1O i1tM
r ` 1 t 1 Is st svdle Is li II -k# 1
,:,F ?y ? AIe +tder Wuverr?ll ,.eey _ Pl*asanI Gat
1\ B U E SCN 10
' Montreal ?,.. 1
+^rdirM ` ?. e? 'R.I r;l ?tlte t!/r WrM In ^
/niWL¦1 . ,: lack
ail. I PARK ?•; 6 s i MOU ain 1
j.,p?` IeeM I d Uablret ,`+ C,r `ille *". , Nm 1 10 'S Idea
? sh: eil T
'• ?y. SuaarHdl
V As W OF DF A I Swannanos `
s 22J .
rNt•a.erp 1 ? ,
„+1// f vIIIIY i amel?T •I /d 'f 11 nr? '?•?? l0 11 9 ....
r : AOin 119 I III a }}11 ' MITI 1uyr///•'yyy111? d et ft 25A itnnew /• ?
Cnirn ee y?F wayn sii • r.?.FC,?' Wrdro.if (I;, fir/ - ISSyland Colton t [yyo
'/v¦ ' 2,,Tti ?SM1111de1:` IJ4 v Arden
q-6 Naty,e•ed i M, , o?+ l rt l -no alb
Bat Cave
tdl i r,o wd MM ?w,'•d ;:'1 flNt of
/rwtUn
Alets I M? 1.. '` s MounUl !s a ore
I?.I..w Sunbursl 116 MNIa 0114 ? , Mane Y"-'
ti ?' p Sylra * F . dneywlle 9
dlsb •,• - ' NAT ' w+d.? ?A. \ r2 HI S, O N
Webster '. 17 G..I. \ . A
Glee" t 1 t (.u11RIwMe r IS - ?.::?•„•?^' • to.,•as I East
Cgea r?.I J•.+ 'L
,., /• P
. Gay to Cat opal Se) ,-.,....?fOR. • 1.::..V i ndersOnvllle I 0 Rock , Mill Spring
4u rJ A C d 5 r 0 Ie1d • oso Flei RocM 12? /
iu[Maelee I e 4s, • 1III; nil r t
/ 1 2 'N ?N,k.•, Ed.. SI rnr•II r Sat t ? Cqlurnbus
/ 71 LI IsRivet L. 116 r^l
? Brevardl-jr • M.,( Tuuao
'OREST o ITS'-`` TRANSY ViANIA ?.r O;-ta
ollasale Irh,,,r\ 1 ?.;Aneft htld?l , 1 0?/ I •,? L Lump i -
1 d • Glanville
fd \ .?.6 i\(?, ?Nr.n .'rr. It ?. ?- / Re,. t dl 1 )
-- Gne.% \ 10 bti IC T.,d1?W laa ps Cod¦r r`^n?tnn rd? 25 1 11 S ,
I I CesM•rs r `r.? 4/, 1 Touwer .? j Crisis Head 1 r I Nwl,
L -1FS¦ ue\T d v. 1 i fowensvdle Carrlp0bels 19 1
i A.. v I Hltn so00Ab• • I 1
/M. ?.. , Jiumoton to \ p?\N
I'I Gramnn '
Cteveland?/ I,
V OA Ngnlendf 1 Rocky nortr. I r, r
Inma
e ti 10 a Mallet 1.
Scotty .1I ?idl, J..r 25 a ,
j - 0r S 10 20
IW-H E A 11 MACS
FA- _ SCAT I OF ¦I ON(I EQUALS
0 - 10 20 !0 Ira 1, SCMI Of ¦AOW OMC iCRS ON I INCH EQUALS AI?ROR II RROM[TUIS
I Mltl IS EQUAL TO I We 11ROMI T(RS
N
u2i
Lrl 4, INM•rr•? ? 91
17V. s 1
lut. cot
7
L d? ?V u 12? it r
to. Cot U91
ll„
\ r '
"»
/1,94
G 1r:i) lilt
uol ua.?,
aOSMAle rs Ito/ ?
lilt POP. all `
of
I tea IF 1 3.0
E r 101 nk
1LN
?nRr
!t« utl TM G
1 1ta! /^.?
rC. Y II.( s yB,p? •
NANO?:?"
MIN,
1111 1 ?/? ?' 1,941
1>?
L
GIIw?
. &W n t?
end if
1 5 1
?
aeldn ?
1
?
' B
,o
d ,
I
Inwoo II
•-Dytulsv111 ? ?'J
10
i
1
D Sunlo
pip, t11
tfM Hdll
n
urn
osnc it
x
v
'A\
SCALE
1 0 1 2 2 1 AIRY
CB FT -
r0-?r-??_ 9L3 MRS
SCALE FOR ENLARGEMENTS
N. C. DEPARTMENT OF TRANSPORTATION
DIVISION OF HIGHWAYS
TRANSYLVANIA CO(Jt4TY
PROJECT NO.: 8.100401 (B-2171)
PROPOSED BRIDGE REPLACEMENT
OVER TI-IE NORTH FORK FRENCH BROAD
RIVER BRIDGE NO. 69
SHEET 1 OF _
,>N -?'/
15
i
LXr-,i r7
PNAS? 1 r
i /
U,7s IL'
ViF }.AP
WALL
COTE P t*>\M
'PHASL S
SC n L_ ?-
R' - .
o io
rncta%S
-LGev-
1' 7il"D
CLASS
'SIC, T . •?
N. C. DEPARTMENT OF TRANSPORTATION
DIVISION OF I-IIGI-IWAYS
TRANSYLVANIA COUNTY
PROJECT NO.: 8.100401 (B-2171)
PROPOSED BRIDGE REPLACEMENT
OVER THE NORTH FORK FRENCH BROAD
RIVER BRIDGE NO. 69
SHEET Z. OF ?e
,?-O
ro-18
i
i
i
i
`6?ro
I I I
I , k 2o I f ZOo \t Z20
Is t. \j - LrLq- - ltL?
ELEV. _ _ . I ?77 I
x.14' rr• I?Fr_?T?'E'S-Lf: C-?Ik?DEi2.
CLASS '11'
kW RAP-
C LkSS
-
I m \ RETn1 N ING
WALL
I+2a?
LCLJ
C;
VnM
4 -'IrT 'r{
?o(c?
ti`jrll7-rr
r7;>i rr nI?i7i;I17
fb: K LE.r?,E /?
(C(OG
N. C. DEPARTMENT OF TRANSPORTATION
DIVISION OF HIGHWAYS
TRANSYLVANIA COUNTY
PROJECTNO.: 8.100401 (B-2171)
PROPOSED BRIDGE REPLACEMENT
OVER THE NORTH FORK FRENCH BROAD
RIVER BRIDGE NO. 69
SHEETS OF 4_
SCALC
Hur??z_c?1+?I-AL
0 mFMi ; 10
0 2
MFZ?(?n
c?
?U
l \
lJ
I
\ I I I
? I
lam, - R\
Z
O
I I i ? I
P O
o N N W u
N Q ? UQ o
o°aWz
??aop4 w w
. wx"zzd...,,w? o
ooj*0 AO? \I
w
o oz
zHOOa z
Qo?o?w
? ? O W
a a >
z ?
i
;i
U' 1
s t
Vi
I-
S
.J
Iwv` ?u
Y
0
DRILLED SHAFT CONSTRUCTION
1. Install sediment control devices necessary for culvert construction, including
STILLING BASIN, SILT FENCE, AND STONE SILT SCREEN.
2. Install PHASE I cofferdams. Construct Bent 2. Pump all effluent into stilling basin.
3. Install PHASE II cofferdams. Construct Bent 1. Pump all effluent into stilling basin.
4. Install PHASE III cofferdams. Remove existing bridge bent. Pump all effluent into
stilling basin.
5. Remove all cofferdams and stilling basin. Upon stabilization of all disturbed areas
remove all temporary sediment control devices.