HomeMy WebLinkAbout19930750 Ver 1_Complete File_19931005OF THE ARMY
CORPS OF ENGINEERS
)X 1890
CAROLINA 28402-1890
5, 1993
Action ID No. 199100095 and State Permit No. 57-91
Mr. Barney O'Quinn
Division of Highways
North Carolina tment of Transportation
Post Office Bo 201
Raleigh, North Carolina 27611-5201
Dear O'Quinn:
Through coordination with the North Carolina Division of Coastal
Management, we have learned of the modified of your State permit which
authorizes you to place fill material in wetlands adjacent Runyon Creek
associated with the widening o `_R hway'``261t, between S.R. 1501 and North
Carolina Highway 132, Washington, _art County, North Carolina. This
modification provides for a temporary fill detour.
Your revised proposal has been reviewed and found to be consistent with
the provisions and objectives of general permit No. CESAW-C080-N-000-0291.
Therefore, you may continue construction in strict accordance with your
modified State authorization and the enclosed plans. Failure to comply with
the modified State authorization or conditions of the general permit could
result in civil and/or administrative penalties.
If any further change in your work is required because of unforeseen or
altered conditions or for any other reason, plans revised to show the change
must be sent promptly to this office and the North Carolina Division of
Coastal Management prior to performing any such change or alteration. Such
action is necessary as revised plans must be reviewed and the authorization
modified.
Questions or comments may be addressed to Mr. Norm Sanders, Washington
Field Office, Regulatory Branch, telephone (919) 975-3025.
Sincerely,
G. Wayne Wright
Chief, Regulatory Branch
Enclosures
a
-2-
Copies Furnished with enclosures:
MJohn Dorney
eivision of Environmental
Management
North Carolina Department of
Environment, Health and
Natural Resources
Post Office Box 29535
Raleigh, North Carolina 27626-0535
Mr. John Parker
Division of Coastal Management
North Carolina Department of
Environment, Health and
Natural Resources
Post Office Box 27687
Raleigh, North Carolina 27611-7687
Mr. Terry Moore
Washington Regional Office
North Carolina Division
of Coastal Management
Post Office Box 2188
Washington, North Carolina 27889-2188
a w
Q ??
ce -.. `'
0 L Ot \ . \ V
I / T? r 1
W
%
I T?7
Q
a
a
i ?
+ I a
I ?
I ? N
IJ ?
I I
I I
I I
I I
? 1N.C. DEPT. OF TRANSPORTATION
I DIVISION OF HIGHWAYS
BEAUFORT COUNTY
PROJECT 9.8024837 R-2021
PROPOSED DETOUR FILL
RUNYON CREEK
SHEET / OF L JULY 1993
'SL
a /
J
C
h h
a ?
_ w
a
? W
Q
_ Q
.y ;
1/1011,0411 alit O
q ? ?1
4 ?
3
g
I ?
(ss
I '
N.C. DEPT. OF TRANSPORTATION
I DIVISION OF HIGHWAYS
BEAUFORT COUNTY
i I PROJECT 9.8024837 R-2021
PROPOSED DETOUR FILL
RUNYON CREEK
I SHEET Z OF Z JULY 1993
State of North Carolina
Department of Environment,
Health and Natural Resources • •
Division of Environmental Management
James B. Hunt, Jr., Governor
Jonathan B. Howes, Secretary ID E H N R
A. Preston Howard, Jr„ P.E., Director
September 7, 1993
Mr. Barney O'Quinn
Planning and Environmental Branch
N.C. DOT
P.O. Box 25201
Raleigh, N.C. 27611-5201
Dear Mr. O'Quinn:
Subject: Proposed fill in Wetlands or Waters
Bridge replacement and temporart access, U.S.264
Beaufort County
DEM Project # 93750, TIP #R-2021
Upon review of your request for 401 Water Quality Certification
to place fill material in 0.61 acres. of wetlands or waters which are
tributary to Runyon Creek for bridge replacement and temporary access
located at US 264 in Beaufort County as described in your submittal
dated 1 September 1993, we have determined that the proposed fill can
be covered by General Water Quality Certification Nos. 2727 & 2732.
Copies of the General Certifications are attached. These
Certifications may be used in qualifying for coverage under Corps of
Engineers' Nationwide Permit Nos. 14 & 33. An additional condition is
that the temporary fill will be removed and the area replanted with
local, native species.
If this Certification is unacceptable to you, you have the right
to an adjudicatory hearing upon written request within thirty (30)
days following receipt of this Certification. This request must be in
the form of a written petition conforming to Chapter 150B of the North
Carolina General Statutes and filed with the Office of Administrative
Hearings, P.O. Box 27447, Raleigh, N.C. 27611-7447. Unless such
demands are made, this Certification shall be final and binding.
If you have any questions, please contact John Dorney at 919-733-
1786.
Sincerely,
P eston Howard r. P.E.
93750.1tr
Attachment
cc: Wilmington District C rps of Engineers
Corps of Engineers Washington Field Office
Washington DEM Regional Office
T -.3
-" r ey 1
Central Files
John Parker, DCM
P.O. Box 29535, Raleigh, North Carolina 27626-0535 Telephone 919-733-7015 FAX 919-733-2496
An Equal Opportunity Affirmative Action Employer 509k recycled/ 10% past-consumer paper
t1-4-,..,_.,SEP-02-1993 14:58 FROM EHNR WASH REG OFFICE I U
M E M O R A N D U M
TO: Deborah Sawyer
Division of Environmental Management
FROM: David Gossett D ('--'
Division of Coastal Management
THROUGH: Terry Moore a7x
Division of Coastal Management
DATE: 1 September 1993
SUBJECT: Request for Permit No. 57-91 Modification
North Carolina Department of Transportation
Runyon Creek, US 264
Beaufort County, North Carolina
1?1?'?5S155ti r. U1
REIVED
WASHING70N OFFICE
5EP 0 1 1993
lA F. M.
3
On 11 April 1991 the North Carolina Division of Coastal Management (DCM)
issued the subject permit to North Carolina Department of Transportation (DOT)
for the widening of U5 264 east of the City of Washington, Beaufort County into
four lanes. The permit involved the crossing of Runyon Creek which required a
temporary detour of the existing bridge at the site. When the permit was
originally issued it required a pile supported bridge to be constructed on the
south side of the existing roadway. On 6 June 1991, the permit was amended at
which time the pile supported detour was moved to the north side of the existing
roadway.
I have recently received from DOT a package of material dated 28 July 1993
requesting that the pile supported detour be changed to a temporary fill causeway
on the north side of the existing roadway.
I have sent a copy of the package to John Parker requesting that the DCM
handle this request as a minor modification of the subject permit. John has in
turned requested that I supply to you a copy of the submitted package so that you
can determine if a new 401 Certification is needed.
I will appreciate your review of this request by DOT and request that you
submit to John Parker any comments that you may have.
cc: John Parker
Norm Sanders
Post-It' brand fax transmittal memo 7671 # or pages ?
F
C Oa
Dept. Phone N
Fax # Fax #
• ISEP-02-1993 14:59 FROM EHNR WASH REG OFFICE IO
STATE OF NORTH CAROLINA
DEPARTMENT OF TRANSPORTATION
JAMES B. HUNT_ JR DIVISION OF HIGHWAYS
GOVERNOR P.O. BOX 25201. RALEIGH. N.C 27611-5201
July 28, 1993
Office of Coastal Management
Department of Environment, Health and
Natural Resources
P.O. Box 27687
Raleigh, North Carolina 27611
ATTENTION: John Parker
Dear Sir:
iyly'rssl s s? H. 02
WASHIINGTONEOF'F1CE
roEp 0 t 1993
1& 4 M.
SAM HUNT
SECRETARY
SUBJECT: Beaufort County, wetland impacts associated with
widening 5.46 miles of US 264 from SR 1501 to NC 32.
TIP #R-2021, State Project No. 9.8024837, CRC
Permit #57--91.
Reference is made to David Gossett's letter of July 19,
1993 advising us of the permit status for the proposed
project. Mr. Gossett indicated that a permit modification
will be required for the proposed temporary detour, and
requested additional information regarding the impacts
involved. Enclosed you will find a completed, application
form and plan drawings that describe the temporary detour.
Upon completion of the bridge replacement, the detour fill
will be entirely removed to natural grade. This restoration
will be conducted in comliance with Conditions 4 through 9 of
CRC Permit No. 57-91.
The NCDOT hereby requests that the proposed temporary
detour be considered as a modification of the issued permit.
A copy of this information has been sent directly to Mr.
Gossett for his review. If you need any additional
information, please contact Mr. Gordon Cashin at (919) 733--
9770. -
,ex
iyiy rs sl ss? r. e s
SEP-02-1993 14:59 FROM EHNR WHSH KEU UNF 1 CiE l u
Sincerely,
B. J. O'Quinn, PE
Assistant Manager
Planning and Environmental Branch
CC., Mr. Terry Moore, DCM, Washington NC
Mr. Kelly Barger, PE
Mr. Don Morton, PE
Mr. A_L. Hankins, PE
Mr..G.R. Shirley, Jr., PE, Division 2 Engineer
BJO/Sec
SEP-02-1993 14:59 [-HUM EHNK WHSH Ktb Urri_t
Please type or print, Carefully describe all anticipated
development activities, including construction, excava-
tion, filling, paving, land clearing, and stormwater con-
tmL If the requested information is not relevant to your
project, write N/A (not applicable)- Items 1-4 and 8-9
must be completed for all projects. b
1 APPLICANT
C.
a. Name MC Dept. of Transportation
Address Attn: B.J. O'Quinn, Asst. rant Mgr.
_po r%
City Raleigh _ Stale NC
1
tip 27611 Dayphone 91.9-733-314.1
Landowner or Authorized agent
b. Project name (if any)
C- If the applicant is not the landowner, also give the
owner's name and address.
I U 11j17 (5 51 5Jt3 r. J-F
If you plan to build a marina, also complete and
attach Form DCM-MP-2,
Is the proposed activity maintenance of an
existing pgroject, new work, or both?
Botg
Will the project be for community. private, or
commercial use?
Public
d. Describe the planned use of the project.
Public Transportation
4 LAND AND WATER
CHARACTERISTICS
a. Size of entire tract 5746 miles
-b. Size of individual lot(s) N/A
2 LOCATION OF PROPOSED
PROJECT
a. Street address or secondary road number
U. S. 264
b. City, town, community, or landmark
Washington
,c. County Beaufort
d, . Is proposed work wiibin city limits or planning
jurisdiction? Yes
e. Name of body of water nearest project
Pamlico Raver
3 DESCRIPTION AND PLANNED USE
c. Elevation of tract above mean sea level or
National Geodetic Vertical Datum
35' above MSL
d. Soil type(s) and texture(s) of tract
Lenoir Muckalee Portsmouth and Bladen foams
e. Vegetation on tract Forest and agriculture
f. Man-made features now on tract Roadway (U. S. 264)
g. What is the CAMA Land Use Plan Classification of
the site? (Consult the local land use plan.)
Conservation X Transitional
Developed X Community
Rural Other
h. How is the tract zoned b local government?
C8nsi9:E6hE With LAMA lava use 51ah.
OF PROPOSED PROJECT i. How are adjacent waters classified?
U stream of project; Class C
a. Describe all development activities you propose (for Downstream of project: Class Sc
example. building a64 motel, marina, bulkhead, a' Has a professional archaeological survey been
or pier). U . S . 264 widenin and radin avin carried out for the tract? Yes If so, by whom?
_ 911 and drainage. Bride work over Runyan and g'NCDOT Archaeolo ist and Architectural
Nistoria?
Broad Creeks. Includes detour Pi 2e.
`?
3191
SEP-02-1993 15:00 FROM EHNR WHSH REU Uf-HUE
IU 1?1?'(SS15Sti r.U?)
J00DN --'AQ07
5 UPLAND DEVELOPMENT
Complete this section if the project includes any land
development,
a. Type and number of buildings. facilities, or
structuresproposed N/A
b. Number of lots or parcels N/A
c. Density (Give the number of residential units and the
units per acre.) N / A
d. Size of area to be graded or disturbed
e. If the proposed project will disturb more than one
acre of land, the Division of Land Resources must
receive an erosion and sedimentation control plan at
least 30 days before land disturbing activity begins.
If applicable, has a sedimentation and erosion
control plan been submitted to the Division of land
Resources?
£ Give the percentage of the tract within 75 feet of
mean high water to be covered by impermeable
surfaces. such as pavement, buildings, rooffops.
N/A
g_ List the materials, such as marl, paver stone, asphalt,
or concrete, to be used for paved surfaces.
Asphalt and concrete
h. If applicable, has a stormwater management plan
been submitted to the Division of Environmental
Management?
1. Describe proposed sewage disposal and/or waste
water treatment facilities.
N/A
j. Have these facilities received state or local approval?
N(A ._. .
1c. Describe existing treatment facilities.
NIA
L Describe location and type of discharges to waters of
the state (for example. surface runoff. sanitary
wastewater, indusuial/cornmercial effluent. "wash
down"). Surfdce runoff
m. Water supply source NJ A
n. If the project is oceanfront development, describe
the steps that will be taken to maintain established
public beach accessways or provide new access.
N/A
o. If the project is on the oceanfront, what will be the
elevation above mean sea level of the first habitable
floor? N/A
6 EXCAVATION AND FILL
INFORMATION
a. Describe below the purpose of proposed excavation
or fill activities (excluding bulkheads, which are
covered in Section 7).
Access channel •
OALW) or (NWL)
Boat basin
Other (break-
water. pier,
boat ramp,
tack jetty)
Fill placed in
wetland or below
MHW DETOUR
Upland fill
areas
Length Width Depth
690' 38'
b. Amount of material to be excavated from below
water level in cubic yards 0 ,?.
c. Type of material Granular
d_ Does the area to be excavated include marshland.
swamps. or other wetlands?
Ypc.
c. High around excavation. in cubic yards
N/A
A bh
SEP-02-1993 15:01 FROM EHNR WASH REG OFFICE
IU 1y1?'ti5155ti F'.Ub
1007N Ad03
Dimensions of spoil disposal area
c. Shoreline erosion during preceding 12 months, in
feet N/A
Location of spoil disposal aria Upland Waste Site d. Type ofbulkhcad material N/A
Do you claim title to the disposal area? N./ A
If not, attach a letter granting permission from the
owner.
Will a disposal area be available for future
maintenance? N/A-
if so. where? N/A
Does the disposal area include any marshland,
swamps. or water areas?
No
Will the fill material be pplaced below mean high
water? Temporary detpur: Yes
. Amount of fill in cubic yards Detour: 3000 Yards
a. Type of fill material Earth Backfi.ll
L Source OfAUMaterial Suitable borrow
?. Will fill material be placed on marsh orother
wedands1f es
?. Dimensions of the wetland to be filled
Detour: 38 Y.690'(0.6 acres
e. -Amount of fill, in cubic yards, to be placed below
mean high water NJ A
f. Type of fill material
8 ADDITIONAL INFORMATION
In addition to the completed application form. the follow-
ing items must be submitted:
A copy of the deed (with state application only) or other
instrument under which the applicant claims title to the
affected property. If the applicant is not claiming to be
the owner of said property, then forward a copy of the
deed or other instrument under which the owner claims
title, plus written permission from the owner to carry out
the project.
An accurate work plat (including plan view and cross
sectional drawings) drawn to scale in black ink on an 8
1/2 x I I white paper. (Refer to Coastal Resour=
Commission Rule 71.0203 for a detailed description.)
;. How will excavated or fill material be kept on site
and erosion controlled?
Standard NCDOT erosion and sedimentation
control measures
r. What type of construction equipment will be used
(for cxartrple. draglim backhoe. or hydraulic
dredge)? Backhoe, bulldozer .,
s. Will wetlands be crossed in transporting equipment
to project site? If yes. explain steps that will
be taken to lessen environmental impacts.
No
7 SHORELINE STABILIZATION
a Length of bulkhead or riprap N/ A
Please note that original drawings are preferred and
only high quality copies will be accepted. Blue-line
prints or other larger plats are acceptable only if 18 high
quality copies arc provided by applicant. (Contact the
U.S. Army Corps of Engineers regarding that agency's
use of larger drawings.) A site or location asap is a part
of plat requirements and it must be.suffic iently detailed
to guide agency personnel unfamiliar with the area to the
site. Include county road (SR) numbers. landmarks, and
the like.
A stormwater management plan, if applicable, that
may have been developed in consultation with the
Division of Environmental Management.
A list of the names and complete addresses of the
adjocent waterfront (riparian) landowners. These
individuals have 30 days in which to submit comments
on the proposed project to the Division of Coastal
Management and should be advised by the applicant of
that opportunity.
b. Average distance wateiward of mean high water or
normal water level N/A -
SEP-02-1993 15:01 FROM EHNR WHSH KEU urf-iCt
i007lf - •400
Name.
` Address
Name
Address
Name
Address
A list of previous state or federal permits issued for
work on the project tract Include permit numbers,
permittee, and issuing dates.
A check for $100 made payable to the Department of
Natural Resources and Community Development to
coverthe costs of processing the application.
A signed AEC hazard notice for projects in oceanfront
and inlet areas.
A statement on the use of public funds. If the project
involves the expenditure of public funds. attach a state-
ment documenting compliance with the North Carolina
Environments; Policy Act (`LGG.S. 113A-1 to 10).
U lyiy rsslss? r. U r
9 CERTIFICATION AND PERMISSION
TO ENTER ON LAND
Any permit issued in =posse to this application will
Wow only the development described in the application.
The project will be subject to conditions and restrictions
contained in the permit.
I certify that to the best of my knowledge, the proposcd .
activity complies with the State of Notch Carolina's ap-
proved Coastal. Managernent Program and will be con
ducted in a manner consistent with such program.
I further certify that I am authorized to grant, and do in
fact, grant permission to representatives of state and
federal review agencies to enter on the aforementioned
lands in connection with evaluating information related
to this permit application and follow-up monitoring of
project.
This is the day of 19,,
X
Landowner or Authorized agent
f
4
SEP-02-1993 15:02 F-HUN EHNH WHSH KEV urr1UE
• i 3
QA% `, -
4L ?
9 k ?
wlk
4
I
-
?
4
tn
1
Iu lljl7(S5135ti r.uti
e
4t
T.
4J ••
?
o
Q Q
,;
Q?
4
n
, . a
Z
N
f
Y
1.
f N-C. DEPT. OF TRANSPORTATION
1 ( DIVISION OF HIGHWAYS
t { BEAUFORT COUNTY
` PROJECT 9.8024837 R-2021
` PROPOSED DETOUR FILL
l RUNYON CREEK
SHEEN' / OF 2 JULY 1993
E
i u lylt$ r? ?l3 Sid r. ulj
4
TOTAL P.09
SEP-02-1993 15:02 FKUN EHNK WRDH KEU Urriut