Loading...
HomeMy WebLinkAboutNC0003425_Application Submittal 8_20160815DUKE ENERGY August 15, 2016 Ms. Teresa Rodriquez North Carolina Division of Water Resources 1617 Mail Service Center Raleigh, NC 27699-1617 Re: NPDES Wastewater Permit Application Submittal #8 Duke Energy Progress, LLC. Roxboro Steam Electric Plant Permit #: NC0003425 Person County Dear Ms. Rodriquez, Harry K. Sidens Senior Vice President Environmental, Health & Safety 526 S. Church Street Mail Code: EC3XP Charlotte, NC 28202 (704) 382-4303 Duke Energy Progress, LLC (Duke) is submitting herewith three copies of supplemental information in support of the NPDES renewal application submitted in September 2011 for the subject facility. This update is in addition to the previous updates and requests submitted dated July 27, 2011, March 31, 2012, October 15, 2014, December 17, 2014, July 22, 2015 and July 5, 2016. Please include this supplemental information and the information in the previous submittals in your review. This submittal is intended to provide an update of modifications that will be necessary to comply with recently enacted laws and regulations including the Federal Steam Electric Effluent Guidelines (ELG), Federal Coal Combustion Residual (CCR) rule, the North Carolina Coal ash Management Act of 2014 and HB 630 of 2016. Specific permit requests from Duke Energy are identified in bold throughout this submittal. With numerous federal and state requirements to coordinate and implement in a short time for the site, planning and sequencing of work are paramount and dynamic. As such, final scope and sequence for all work is not complete at this time. Where scope is still not finalized, Duke has provided a range of options that are being evaluated and provided various alternate scenarios in an attempt to limit the number of subsequent submittals necessary. As there are no requests for previously unpermitted external outfalls to waters of the United States and all proposed modifications contained herein are internal to our wastewater process flows, it is Duke's belief that the information provided in this submittal is of sufficient detail to allow for review and issuance or renewed NPDES permit for the Roxboro Steam plant. This is consistent with the guidance received from DEQ staff in a meeting on November 20, 2015 and follow up correspondence dated January 11, 2016 and January 28, 2016. Roxboro Steam Plant NPDES application update #8 NC0003425 Person County Page 2 of 38 1. Duke requests a new internal outfall to be associated with a retention basin for treatment of low volume waste. North Carolina's Coal Ash Management Act and the Federal CCR rule will prohibit continued wastewater flows to the existing ash basin at Roxboro. Projects are underway to convert ash handling of all ash (both bottom ash and fly ash) to 100% dry handling and disposal systems. All other wastewater inputs to the current ash basin must be redirected and handled in another manner. Duke intends to construct a lined, retention basin to handle all flows currently directed to the active ash basin with the following exceptions: Storm water runoff from the landfill on the east side of Dunnaway road that currently flows to the ash basin will be relocated (discussed below). Cooling Tower blowdown in cases where blowdown flows exceed 500 gpm will be relocated (discussed below). Additionally, the retention basin will consist of two basins: a primary and a secondary basin. The primary basin is where the majority of solids settling will occur, while the secondary basin provides adequate retention time for settling of fine particles. The primary basin will also have a location to allow various vacuumed sediments and solids to be decanted prior to disposal of materials into the onsite landfill. Periodically, any accumulated solids in the retention basin will be disposed of in the facility's onsite landfill. The retention basin will be approximately 11 acres in area and have the capability to have additional of flocculent and pH adjustment chemicals. The primary basin will be designed for continuous flow through it. A holding basin will be constructed for high volume flows such as air heater washes, process washes, etc. The holding basin will have a chemical feed system for adjusting pH and polymer addition to enhance settling. Once acceptable, the holding basin contents will be transferred to the primary basin in the retention basin. The holding basin will be designed for batch processing and will be approximately 6.6 Acres in area. The requested internal outfall from the newly constructed retention basin will discharge into the heated water mixing zone upstream of outfall 003 and ultimately flow to Hyco reservoir thorough outfall 003 as is currently authorized by the subject permit. An aerial photo with potential locations being evaluated for the new retention basin can be found in Attachment 1. Duke is evaluating the addition of a second retention basin southeast of the generation units to be used to treat flows from silo wash water, stormwater runoff, landfill leachate and runoff from the gypsum pad area. Flows from this basin would enter the heated water effluent channel east of the generation units upstream of NPDES outfall 003. Duke requests an internal outfall be added to the permit for this basin. Roxboro Steam Plant NPDES application update #8 NC0003425 Person County Page 3 of 38 2. Duke requests that a new internal outfall for modified FGD wastewater treatment system be added to the permit. To comply with Federal ELG guidelines for FGD wastewater, a new treatment system for FGD wastewater will be constructed and utilized. This system will consist of physical/chemical treatment units, a new Bioreactor and ultrafiltration system. Solids settled and collected in the physical/chemical system will be handled via a series of filter presses and disposed of in the facility's onsite landfill. Duke intends to process legacy FGD wastewater through existing permitted outfall 010 until the treatment units associated with that outfall are decommissioned and closed. The requested new internal outfall for FGD wastewater and outfall 010 will need to both be operational for a period of time. The new internal outfall will be directed to the retention basin described in item # 1 of this letter. If the new FGD treatment system must be in service before the retention basin is constructed, treated wastewater from the FGD internal outfall will be directed to the heated water mixing zone upstream of NPDES outfall 003 until the retention basin is completed. For reference, this is the point at which current flows are released to Hyco Reservoir. The location of the new FGD wastewater treatment system is identified in Attachment 1. 3. Duke intends to install heat exchangers or small auxiliary cooling tower for influent flows to the new FGD wastewater treatment system. Duke requests that this flow be listed as a contributing flow to outfall 003. Water will be withdrawn from within the process heated water mixing zone, used to cool FGD blowdown prior to treatment in the biological system and returned to the heated water mixing zone upstream of NPDES outfall 003. The heat exchangers or small cooling tower will be utilized to assure process water remains below bioreactor operational temperature requirements, which can potentially present an operational concern during the summer months. This addition is intended to assure efficient operation of the FGD blowdown treatment system. 4. Duke is installing a new domestic package plant for plant sanitary waste. Duke intends to replace the current domestic package plant with a new above ground package plant. The new domestic package plant will have a capacity of 0.025 MGD. With this modification, Duke requests the flow limit of 0.015 MGD associated with the existing plants design capacity be removed from outfall 008 or modified to 0.025 MGD to reflect the new plant's capacity. Treated flows from the new plant will be directed to the ash basin until such time that the retention basin described in item #1 is complete. Upon completion of the retention basin, treated domestic flows will be sent to the retention basin and flow to outfall 003 as they currently do. A narrative description and Roxboro Steam Plant NPDES application update #8 NC0003425 Person County Page 4 of 38 specification sheet for the new domestic package plant is provided in Attachment 2 with this submittal for your files. 5. Duke requests modification of the terms related to internal outfall 005 (Unit # 4 cooling tower blowdown). Currently, a slip stream of blowdown from the Unit 4 cooling tower is used to sluice ash and is directed to the ash basin. With modifications to the plant to handle ash in a completely dry form and future prohibition on sending wastewaters to the ash basin, Duke is requesting outfall 005 be permitted to be released directly to the heated water mixing zone or to the retention basin described in item #1 above (based on Duke's future determination) as both of these flows paths are upstream of NPDES outfall 003. Duke requests modification of NPDES permit condition A. (14) to facilitate this change. 6. Duke intends to install a vapor suppression system in 2016 at the anhydrous ammonia tanks to be used in the case of an emergency due to a release of anhydrous ammonia. This modification is intended to enhance the safety of our employees and local residents should there be an unintended release of anhydrous ammonia from the facility's tanks. This system will use raw lake water from Hyco reservoir. The system will be tested periodically with flows from tests (consisting of raw, untreated lake water) entering the heated water mixing canal just to the west of the unit #4 cooling tower. In the event of an actual emergency operation of the system due to a release of anhydrous ammonia, flows from the vapor suppression system will follow this same flow path and will potentially contain significant concentrations of ammonia. Upon completion of the retention basin, test flows and emergency operation flows will be directed to the retention basin described in item #1 of this letter. Flow rates for tests and emergency operation of the vapor suppression system are anticipated to be approximately 1882 gallons per minute. Duke requests concurrence in the permit that any impacts associated with the emergency operation of this system do not constitute a violation of the permit. Duke requests this flow be added to the list of flows tributary to outfall 003 and, upon completion, the new retention basin described in item #1 of this submittal. 7. Landfill leachate is currently sent to the west ash basin. Landfill leachate flows will be directed to one of the retention basins (both upstream of outfall 003) described in item # 1 upon completion of that basin. Duke requests that ELG permit limits associated with landfill leachate be applied after the treatment provided in the retention basin described in item #1 of this submittal. Roxboro Steam Plant NPDES application update #8 NC0003425 Person County Page 5 of 38 8. Duke requests specific authorization within the reissued permit that upon ceasing flows to the west ash basin, decanting and dewatering of the basin through existing internal outfall 002 can occur. Specific authorization for decanting and dewatering is a condition currently in the NPDES permit at Sutton and Marshall. Duke requests specific authorization that the ash basin may be decanted and dewatered and what the permit limits associated with that activity are. A characterization of the ash basin interstitial water has been previously provided. This submittal was dated July 22, 2015. Decanting and dewatering will occur through NPDES internal outfall 002 and will ultimately flow to Hyco reservoir through NPDES outfall 003. 9. Duke requests the re-insertion of NPDES outfall 001 in the NPDES permit. This outfall was removed from the NPDES outfall by the Department in 1994. There have been no modifications to the flow since that time however, the flow originates at the retired east ash basin remnant area and contains flow from several areas recently identified as AOW's. Specifically, S-9, 5-10, 5-11, 5-12 and 5-13 flow to the point of S- 13 which is the former outfall 001 in the NPDES permit. Chemical characterization of this water was provided recently and was identified as 5-13. If a full characterization of the water is required, Duke request that this be made a condition of the permit and be submitted 6 months after the permit effective date. Flows at this point consist of stormwater through the remaining area of the retired east ash basin, the AOW's identified above and other stormwater flows not associated with industrial activity. 10. Modifications associated with the coal pile runoff pond (NPDES outfall 006). Duke is constructing an emergency gypsum stack out area on the west side of the plant near the existing limestone ball mill and FGD filter press building. The emergency stack out area is not expected to be used routinely and is being constructed to comply with Federal CCR requirements. The area is approximately 0.3 acres in size. Runoff from the emergency gypsum stack out and surrounding area including a lay down yard, truck wash facility and gypsum conveyor system will flow to the coal pile runoff pond and to Hyco reservoir after treatment through NPDES permitted outfall 006. Additionally, there is a need to periodically drain a raw lake water tank located in the area of the coal pile runoff pond for routine maintenance. As part of routine maintenance, this raw lake water tank may be allowed to drain to the coal pile runoff pond. The tank can hold up to 50,000 gallons of water. 11. Landfill storm water flows. As discussed above, storm water flows from the existing landfill must be rerouted in order to comply with CAMA 2014 and the Federal CCR rule. Landfill storm water flows consists of runoff from approximately 250 acres of landfill Roxboro Steam Plant NPDES application update #8 NC0003425 Person County Page 6 of 38 and surrounding, up gradient area. Currently, storm water flows from the landfill flow into the west ash basin for treatment prior to being released through NPDES outfall 003. Currently three options are being considered for re-routing stormwater flows. An aerial photo depicting these options is included with this submittal in Attachment 3 a. Option 1: Duke is evaluating the feasibility of constructing a stormwater retention pond in the area just west of Dunnaway road between Dunnaway and the active ash basin. Flow from this storm water retention pond would enter the once through cooling water discharge canal and flow to Hyco Reservoir through NPDES permitted outfall 003. Duke requests review and concurrence that this modification is acceptable. b. Option 2: Flows may be directed into the once through cooling water discharge canal just to the north of the retired ash basin dam. The flow would then travel to Hyco Reservoir through the heated water mixing zone and NPDES permitted outfall 003 as it currently does. This will require permitting through NC DEQ Dam Safety program. Duke requests review and concurrence that this modification is acceptable. c. Option 3: Duke is evaluating the feasibility of routing stormwater flows to the plant's intake canal through the former NPDES outfall 001 discharge channel. Outfall 001 was removed from the NPDES permit in 1994 due to the retirement of the east ash basin. Duke has identified this discharge point into the intake canal as a seep and the discharge location and sampling data is referenced as "S-13" in previous submittals. Duke believes that Option 1 and Option 2 above can be accomplished without permit modification. Duke requests concurrence of this understanding. Duke believes that if the flow identified as "S-13" in previous submittals is permitted as a seep to the intake canal, or is reinserted into the permit as outfall 001, then Option 3 above can be undertaken without additional permitting. If coverage for "S-13" is not necessary, it is Duke understands that option 3 could be undertaken but may require industrial stormwater coverage under NPDES General Permit NCG 12000. An aerial photo showing the route and location for each of these options is included in Attachment 3. Duke requests concurrence of this understanding. 12.Ongoing Landfill/Basin closure groundwater dewatering — Development of future cells of the landfill and/or basin closure will require the lowering of groundwater levels in and around the retired ash basin to meet separation and stability requirements for the landfill. Duke intends to install a dewatering system and route extracted groundwater to Roxboro Steam Plant NPDES application update #8 NC0003425 Person County Page 7 of 38 outfall 003 and/or the re -permitted outfall 001 after treatment. Duke requests this flow be listed as a contributing flow to outfall 001 and outfall 003. 13. Steam Electric Effluent Guidelines Alternate schedule justification. Duke requests an alternate applicability date for the Steam Electric Effluent Guidelines in accordance with the request found in Attachment 4. As the Steam Electric Effluent Guidelines makes clear, BAT limits may apply - depending on the individual circumstances of the facilities subject to the rule - any time within the window of November 1, 2018 to December 31, 2023. In selecting an appropriate applicability date for each waste stream subject to the new BAT limits, the permitting authority is called upon to determine an "as soon as possible" date when supplied with appropriate information by the permittee. Attachment 4 provides the appropriate information justifying the following applicability dates: — Bottom Ash Transport Water: To convert the wet bottom ash transport system at Roxboro to a closed loop system, Duke plans to install a remote mechanical drag chain system (RMDS). Duke would like to request April 30, 2021 as the applicability date for the zero discharge of bottom ash transport water, assuming a permit effective date of October 1, 2016. FGD wastewater: Duke is planning on conducting several evaluations to determine whether the FGD wastewater flow can be reduced, and the existing bioreactor can be utilized in addition to evaluating viable selenium reduction technologies. These evaluations will allow Duke to select the most cost effective FGD wastewater system for Roxboro. In addition, it has recently come to Duke's attention GE is claiming intellectual property rights on the biological treatment system for FGD wastewater, thus, making GE the sole provider of EPA's model technology. With these evaluations in process and the uncertainty of GE's intellectual property claim, Duke would like to request December 31, 2023 as the applicability date for the BAT limits for FGD wastewater, assuming a permit effective date of October 1, 2016. — Fly Ash Transport Water: Fly ash is handled dry during normal operation; therefore, Duke is not requesting an applicability date for the zero discharge of fly ash transport water beyond November 1, 2018. 14. CWA Section 316(b) alternate schedule. Duke requests an alternate schedule for compliance with Section 316(b) of the Clean Water Act. Specifics of the request can be found in Attachment 5. Roxboro Steam Plant NPDES application update #8 NC0003425 Person County Page 8 of 38 15. Area of wetness (AOW) disposition. Duke has previously identified a number of Areas of Wetness within the property. All of these AOW's are upstream of permitted outfalls. Consequently, Duke requests that there be no sampling required for the AOW's. These de mimmus AOW flows are part of existing processes and are sampled through NPDES outfalls. Duke requests that the AOW's be listed as contributing flows the respective outfall in either the NPDES permit of NPDES permit fact sheet as follows: AOW's that are contributing flows to NPDES outfall 003 are: S 1, S2, S3, S4, S5, S6, S7, S8, S 14, S 18 and S 19. AOW's that are contributing flows to requested NPDES outfall 001 are: S9, S 10, S 11, S 12 and S 13. Duke requests that any future AOW's that are identified and are tributary to these permitted outfalls not require notification to DEQ. 16. Duke has included an updated water process flow chart with this submittal that shows the water flow path for the site after the ash basin is no longer used. This can be found in Attachment 6. The only substantive change in flow volumes will be the removal of ash sluice flows. This volume is negligible at outfall 003. We appreciate your attention to these requests and look forward to finalizing the NPDES permit for the Roxboro Steam Electric plant in the near future. Should you have any questions regarding this letter or require additional information, please contact Mr. Shannon Langley at (919) 546-2439 or at shannon.langley@duke-energy.com. "I certify, under penalty of law, that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gather and evaluate the information submitted. Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering the information, the information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fines and imprisonment for knowing violations. " Sincerely, Harry Sideris SVP - Environmental, Health & Safety Enclosures Roxboro Steam Plant NPDES application update #8 NC0003425 Person County Page 9 of 38 NCDEQ cc: Sergei Chernikov Duke Energy cc: William J. Thacker, Shannon Langley, Robert Howard, Rob Miller, Danny Satterwhite Attachment 1 Proposed retention basin location August 15, 2016 NPDES application update Roxboro Steam Plant NC0003425 Attachment 2 Domestic package plant narrative description and specification sheet August 15, 2016 NPDES application update Roxboro Steam Plant NC0003425 Roxboro Steam Electric Plant Domestic package plant improvements Sanitary wastewater at Roxboro station is currently treated in an in ground package wastewater treatment system which is more than 20 years old. A new package plant is being installed to replace the existing package plant on an in -kind basis. The new package plant will be installed above grade on a concrete foundation. The plant will have an average capacity of 15,000 gallons per day with a peak capacity of 25,000 gallons per day. The process will consist of an influent comminutor, influent equalization, extended aeration, secondary clarification, disinfection, and effluent pumping. Wastewater will be pumped from the equalization tank to the aeration tank through a flow control weir box, which will maintain a constant forward flow rate as long as there is wastewater in the equalization tank. The package plant will arrive with course bubble aeration diffusers pre -installed. Air to the process will be supplied by a connection to the plant air system. Aeration piping will include a filter and pressure reducing valves to condition the air supplied to two zones: zone 1 includes the equalization tank and the waste sludge tank, and zone 2 includes the aeration tank itself. Mixed liquor from the extended aeration process will flow by gravity to the secondary clarifier. Biomass settled in the clarifier will be pumped via air lift pump back to the aeration tank as RAS or to the waste sludge tank as WAS, where sludge will be accumulated prior to disposal off - site. Clarified effluent will leave the clarifier by a series of v-notch weirs and flow to the chlorination chamber for disinfection. A two -tube tablet chlorinator will be installed in the chlorination chamber to provide chlorine for disinfection. Treated effluent will be pumped to the Unit 3-4 sump via the existing effluent pipeline for the existing package plant. Flows from the Unit 3-4 sump are currently directed to the ash basin. Upon completion of the retention basin, flows from the package plant will be redirected to the retention basin and ultimately to Hyco Reservoir through NPDES outfall 003. The package plant will be insulated to help prevent freezing. 109099 PROF COMM TO DETF 3-FT BRID WITH H, SULZER GRINDER FLOW EQUALIZATI( PUMPS 1-1/4" DISCHARG B PLAN VIEW 18' 177 0 WA 29099 ___�2-1 2 IINCH AIR MANIFOLD AERATION TANK BAFFLES L 4 OUTLET PIPE STUBOUTI 1-1/4" DIFFUSEF IIDROP TIT 7111 C LORINATOR 9 4 Tj 2"0 SKIMMER LINE 9 99 11 0 TT.rrrTz J <`J� 9 99 8 10 z w CD 0 CIO 2" NPT RAIN W/ PLUG )N 4 4' 4 J,750 GALLON FLOW EQUALIZATION 29250 GALLON �I I In(;F 15,000 GALLON EXTENDED QRRQTInNI ELEVATION VIEW 39224 GALLON HOPPER STYLE CLARIFIER J37 GALLON CHLORINE rnNITQrT 1,500 GALLON DOSING TANK 3 99 DIFFUSER DROP 1 "' PIPING WITH GAS COCK VALVE DIFFUSER CAPS COARSE AIR DIFFUSERS DIFFUSER DROP PRO -WATER SYSTEMS FLOW CONTROL BOX WITH BAR SCREEN 304 S.S. ADDITIONAL ITEMS REQUIRED: 1. HULL ACCESS BRIDGE WITH PWS HOT DIPPED GALVANIZED BAR GRATING. 2, HOT DIPPED GALVANIZED HAND RAIL 1 2" 3. ABOVE GRADE APPLICATION NO PERIMETER HANDRAIL. 4, HOT DIPPED GALVANIZED 45' ACCESS STAIR WITH 3' X 3' LANDING SLOPE 7" RISE OVER 11" RUN. 5, FLOW EQUALIZATION TANK WITH TWO (2) GUIDE RAIL ASSEMBLIES, PUMP BASES TO BE PROVIDED. 6, DIFFUSER DROPS AS SHOWN WITH AIR MANIFOLD, DIFFUSER COUNT AS SHOWN, USE 3" CONNECTION FOR DIFFUSER CAPS. 7. PWS DECANT SYSTEM IN SLUDGE HOLDING TANK. 8, ALL PIPING TO BE HOT -DIPPED GALVANIZED, SCHEDULE 40. 9. ONE (1) GALVANIZED 3-INCH RAS / WAS LINES ON AIR LIFT WITH CONTROL VALVES. 10. ONE (1) GALVAINZED 2-INCH SKIMMER RETURN LINES ON AIR LIFT 11. TWO (2) BAFFLES OUTLET SIDE OF AERATION TANK AND INLET SIDE OF CLARIFIER. 12. 4-INCH OUTLET STUB NIPPLE WEIR FLOW METER BOX. 13. AS SHOWN STANDARD PWS FLOW CONTROL SPUTTER BOX SMALL WITH MANUAL BAR SCREEN. STAINLESS STEEL 304 MATERIAL. 14. COATING FOLLOW TNEMEC 46H-413 TWO COATS FINAL DFT 16-18 MILS WEATHER PROOF CONTROL PANEL TIE DOWN TURNBUCKLE BY OTHERS CHOR GUSSET Pro -Water Systems, I nc. Process Equipment for Waste Water Treatment Pro -Water Model and Flow: CH-15 Date: March 17, 2016 1 Scale: 3/8" PER FOOT DRAWING: CH-15 Pro -Water Plant Serves: DUKE ENERGY PLANT Pro -Water Plant Location: ROXBORO, NC Pro -Water Representative: PETE DUTY AND ASSOC. Dimensions: A: AS SHOWN B: C: D: E: H: L: M: Q: S: Plant Length: SECTION B B SECTION A —A Attachment 3 Landfill Stormwater flow options aerial photo August 15, 2016 NPDES application update Roxboro Steam Plant NC0003425 O cr O 0 O ,may w ZT-Ln 3 4 Attachment 4 Steam Electric Effluent Guidelines Alternate Schedule justification August 15, 2016 NPDES application update Roxboro Steam Plant NC0003425 Roxboro Electric Generating Plant: Effluent Guidelines Rule Justification for Applicability Dates A. Introduction Duke Energy (Duke) is working diligently to develop and refine an optimized schedule for the installation and upgrades to wastewater treatment systems to comply with the Steam Electric Power Generating Effluent Limitation Guidelines (ELG) at seven coal-fired stations in North Carolina. Duke submits the following information as a justification for appropriate applicability dates for compliance with the new Effluent Guidelines Rule (ELG Rule) (80 Fed. Reg. 67,838 (Nov. 3, 2015)) at Roxboro Electric Generating Plant (Roxboro), located near Roxboro, North Carolina. Roxboro consists of four coal fired generating units with nameplate generating capacities of 410.8, 657, 745.2, and 745.2 MWe for Units 1, 2, 3, and 4 respectively. The station currently discharges treated bottom ash transport water, and FGD wastewater. Under normal plant operations, fly ash is collected dry and either disposed in a permitted on -site landfill or transported offsite for beneficial reuse. If the dry fly ash collection system is not operating, the fly ash is sluiced to the ash basin in which the transport water is treated in the ash basin and subsequently discharged through outfall 002. Bottom ash from the boilers is sluiced with transport water to the west ash pond. The transport water is treated by the ash pond system and is discharged through outfall 002. The FGD blowdown is discharges to a gypsum settling pond were suspend solids are settled out prior to flowing to the bioreactor. The bioreactor effluent is discharged to the effluent channel through outfall 010 prior to outfall 002. The ELG Rule sets a range of possible applicability dates for compliance with the new BAT limits for bottom ash transport water (zero discharge) and FGD wastewater (numeric limits for selenium, arsenic, mercury, and nitrate/nitrite), as well for fly ash transport water (zero discharge). The regulation provides that all permits issued after the effective date of the rule (January 4, 2016) should contain applicability dates for compliance with the BAT limits, and that those dates should be "as soon as possible" but not sooner than November 1, 2018 and not later than December 31, 2023. For Roxboro, since the plant's final NPDES permit will be issued after January 4, 2016, but before November 1, 2018, EPA specifically instructs permit writers to "apply limitations based on the previously promulgated BPT limitations or the plant's other applicable permit limitations until at least November 1, 2018." 80 Fed. Reg. at 67,883, col. 1 (emphasis added). As the rule makes clear, however, BAT limits may apply — depending on the individual circumstances of the facilities subject to the rule — any time within the window of November 1, 2018 to December 31, 2023. In selecting an appropriate applicability date for each waste stream subject to the new BAT limits, the permitting authority is called upon to determine an "as soon as possible" date. The ELG Rule provides a very specific definition for "as soon as possible." The permit writer — when supplied with appropriate information by the permittee — must consider a range of factors that affect the timing of compliance. Those factors are as follows: (1) Time to expeditiously plan (including to raise capital), design, procure, and install equipment to comply with the requirements of this part. (2) Changes being made or planned at the plant in response to: (i) New source performance standards for greenhouse gases from new fossil fuel - fired electric generating units, under sections 111, 301, 302, and 307(d)(1)(C) of the Clean Air Act, as amended, 42 U.S.C. 7411, 7601, 7602, 7607(d)(1)(C); (ii) Emission guidelines for greenhouse gases from existing fossil fuel -fired electric generating units, under sections 111, 301, 302, and 307(d) of the Clean Air Act, as amended, 42 U.S.C. 7411, 7601, 7602, 7607(d); or (iii) Regulations that address the disposal of coal combustion residuals as solid waste, under sections 1006(b), 1008(a), 2002(a), 3001, 4004, and 4005(a) of the Solid Waste Disposal Act of 1970, as amended by the Resource Conservation and Recovery Act of 1976, as amended by the Hazardous and Solid Waste Amendments of 1984, 42 U.S.C. 6906(b), 6907(a), 6912(a), 6944, and 6945(a). (3) For FGD wastewater requirements only, an initial commissioning period for the treatment system to optimize the installed equipment. (4) Other factors as appropriate. 40 C.F.R. § 423.11(t). The wastewater treatment systems at Roxboro will undergo significant modifications and in most cases complete replacement to comply with the revisions to the ELG Rule. Duke would like sufficient time to select, design and install the most cost effective technology at Roxboro to comply with the ELG limits and reduce the burden to the ratepayers. We have prepared a preliminary timeline for planning, designing, procuring, constructing and optimizing the technology once it is selected, for each applicable waste stream. Based on our preliminary analysis, we request the following applicability dates: Bottom Ash Transport Water: To convert the wet bottom ash transport system at Roxboro to a closed loop system, Duke plans to install a remote mechanical drag chain system (RMDS). Duke would like to request April 30, 2021 as the applicability date for the no discharge of bottom ash transport water, assuming a permit effective date of October 1, 2016. Duke anticipates that equipment will be installed by December 31, 2019 to comply with the North Carolina -Coal Ash Management Act (NC-CAMA) and the Coal Combustion Residual (CCR) rule. These rules, however, only regulate the material, not the water. As discussed below, Duke will need a 16 month window to optimize the system to operate as a zero discharge system. This additional time is needed to account managing the installation and optimization of four RMDS being installed in N. Carolina simultaneously. In addition, the extent and complexity of the permits required are unknown at this time. Duke, therefore, allocated 6 months to account for potential permitting delays. — FGD wastewater: Duke is reviewing options to determine whether the FGD wastewater system at Roxboro will need to be completely replaced or if existing components can be utilized. In addition, to construct a cost effective system, Duke is evaluating options to reduce the FGD flow to the treatment system. Furthermore, it has come to Duke's attention the availability of biological treatment systems may be limited due to intellectual property rights be claimed by GE, which would limit the available vendor resources to supply the model technology. At a minimum, we plan to evaluate the development of a new physical/chemical system augmented by a selenium reduction system. To account for the multiple evaluations needed and the limited vendor resources, Duke would like to request December, 31, 2023 as the applicability date for the best available technology (BAT) limits for FGD wastewater. — Fly Ash Transport Water: Fly ash is handled dry during normal operation; therefore, Duke is not requesting an applicability date for the zero discharge of fly ash transport water beyond November 1, 2018. The following provides necessary information justifying the requested applicability dates provided above. B. Bottom Ash Transport Water As stated above, significant portions of the bottom ash transport system at Roxboro will need to be replaced to comply with the no discharge limit of bottom ash transport water (BATW). The rule identified dry handling or closed -loop systems as the BAT technology basis for control of pollutants in bottom ash transport water. Specifically, a mechanical drag system (MDS) was identified as the technology basis for a dry handling system, where as a RMDS was identified as the technology basis for a closed -loop system. Duke is planning on installing a RMDS at Roxboro to handle bottom ash dry. The system will be designed to operate in a closed -loop mode to meet the zero discharge limits for BATW. Duke anticipates 55 months from the effective date of the permit will be needed to design, install and commission the RMDS as a zero discharge system based on the following preliminary timeline. It is important to note Duke will be installing RMDS at four stations in N. Carolina; therefore, additional time is needed compared to a single installation to account for managing multiple projects simultaneously. Remote Mechanical Drag System (RMDS) Activity I Duration (Months) Design' 8 • Siting 3 • Engineering 5 Procurement 12 Potential Permitting Delays 6 Construction/Tie-in 13 Optimization & Operational Experience' 16 • Commissioning 2 • Start -Up 6 Total: 55 1) The design tasks has been initiated and Duke estimates an additional 8 months from the permit effective (assuming Oct. 1, 2016) will be needed to complete the design. 2) Even though is it estimated that commissioning and start-up can occur in 8 months, Duke anticipates needing a 16 month window to obtain the necessary operating time at full load and account for commissioning / optimizing occurring at multiple facilities simultaneously. Assuming a permit effective date of October 1, 2016, Duke estimates the system can be installed and operated to comply with the zero discharge limit of BATW on or before April 30, 2021. To design, procure, construct and optimize the RMDS at Roxboro to operate as a closed -loop system, the following steps must be taken: Design & Engineering Duke has initiated the design phase, but, due to the simultaneous implementation of programs, such as the CCR Rule and NC-CAMA across applicable sites in North Carolina, engineering and technology resources are limited. Duke, therefore, estimates the design and engineering process will take an additional 8 months from the permit effect date. Some of the activities within the water balance and siting task will occur concurrently; however the design cannot be completed until the siting task is completed. The permitting process, if necessary, will be initiated in the design and engineering phase, but it is assumed permit receipt / approval will be conducted concurrently with the design and procurement phase and will be completed prior to the construction phase. The following tasks will need to be completed. Water Balance The first step in the design process of the RMDS is to develop a detailed water balance of the current BATW. To operate the system as a zero discharge system, there is a balance between the inputs of water into the system and the outputs of water through evaporation and bottom ash removal. This is necessary to determine if any additional treatment of the BATW is needed to avoid increase in fines and concentration of other constituents that could affect equipment operability. In addition, several non-BATW waste streams are currently commingled and treated along with BATW. The flow of these waste streams will be rerouted from the BATW system to a new wastewater treatment system. This will require the streams to be characterized for both volumetric flow and constituent make-up in order to size and design an appropriate treatment system. It is important to note that not all waste streams discharge continuously or simultaneously. Some waste streams discharge intermittently based on activity occurrence, such air preheater and precipitator washes, while others may only discharge under certain rainfall events. In addition, many waste streams do not discharge if the unit is not running. With most coal-fired units operating in an infrequent mode, the opportunities to collect samples are limited and the operation schedule could affect the schedule of this task. Upon completion of the water balance, detailed engineering of the RMDS system and piping reroutes of non-BATW can commence. Siting The RMDS will need to be sited appropriately to avoid any historical or current coal combustion product disposal (CCP) sites and avoid construction areas that will be used to complete closure of the ash basins at Roxboro. In addition, Duke will attempt to site the system to avoid waters of the U.S. (WOTUS). However, based on the final siting of the system, WOTUS may not be avoided, and permits from the U.S. Army Corps of Engineers may be required. Permitting If WOTUS cannot be avoided, then permitting from the U.S. Army Corps of Engineers (USACE) will be needed. At this time, it is unknown whether a USACE permit will be required or the type of permit that may be required (nationwide permit (NPW) or individual permit). Duke, therefore, has included 12 months in the schedule to prepare and obtain any necessary USACE permits. Once the RMDS is commissioned, the permitted discharge flows will change drastically. The amount of water discharged could be reduced by as much as 85%. In addition, these flows typically were treated along with the BATW in the ash basin. Duke, therefore, will need to design, and construct a new treatment system for these low volume wastes. The size and technology of the treatment system will be determined based on the water characterization study discussed above. In addition, based on the final siting of the low volume wastewater treatment system, a new outfall may be needed for the discharge of the effluent from this new wastewater treatment system. With significant changes to the characteristics of the permitted discharge, Duke anticipates a NPDES permit modification will be required to revise the permit to account for the changes in flow and constituent make-up. Even though the permitting task will be initiated during the design and engineering phase, it is expect to continue through the procurement phase and up to the construction phase. In addition, the extent and complexity of the permits required are unknown at this time. The required permits will be evaluated during the engineering and design phase. Since the time needed to prepare the permit applications and the time needed to receive the permits is uncertain, Duke allocated 6 months to account for potential permitting delays. Procurement After the design is complete, Duke will initiate the process to procure the necessary outside resources to construct and install the new wastewater treatment systems. This process will involve the following steps: Evaluate potential vendors for proposal solicitation; Develop and submit request for proposal (RFP) to selected vendors; Conduct a review and vendor selection based on the received bids; Develop required contract documents; — Acquire materials (potentially from overseas), which involves: o Shipment, and o Equipment Fabrication Fabrication and inspection of equipment. RMDS have a fabrication queue that is dependent on total industry -wide demand. Duke, therefore, has allocated 12 months to acquire the necessary materials. Construction Once all the necessary materials are procured, Duke estimates construction of the RMDS will take approximately 13 months. In addition, the tie-in of the RMDS to each individual generating unit will need to occur during outages, which are anticipated to occur between March to May and October to November depending on generation demand. Optimization and Operational Experience As stated above, Duke is planning to have the equipment installed by December 31, 2019 at the latest to meet the obligations under CAMA, in addition, to any CCR requirements. Again, these rules regulate the bottom ash material, not the transport water. Given the system will continue to utilize water to transport bottom ash, time will be needed to gain operational experience and optimize the system to meet the zero discharge limit. Duke estimates a 16 month window will be required to gain the necessary operational experience and fine-tune the system. The 16 month window is estimated based on the potential that the station may only be operating at full load during the winter and summer months and load and account for commissioning / optimizing occurring at multiple facilities simultaneously. In addition, with NCDEQ approving the implementation date of January 31, 2021 for Marshall Steam Station, Duke would like to stagger the commissioning / optimization activities for Roxboro by 3 months. C. New Wastewater Treatment System As discussed above, with the removal of several non-BATW waste streams from the bottom ash transport system, a new wastewater treatment system will need to be designed and constructed for co -treatment of low volume waste and other regulated process streams per the CCR rule, ELGs, and NDPES permitting requirements. The activities associated with the new wastewater treatment system will be conducted concurrently with the other design activities at the site. These waste streams are not subject to the applicability date in the ELG rule, therefore, Duke is not requesting a compliance date, but this task will need to be completed prior to the effective date of the zero discharge of BATW. Duke anticipates 30 months will be needed to design, install and commission the new wastewater treatment system, based on the following preliminary timeline. New Wastewater Treatment System Activity Duration (Months) Siting 3 Engineering 6 Procurement 3 Construction/Tie-in 9 Commissioning 3 Start -Up 6 Total: 30 D. FGD Wastewater Duke expects significant capital improvements to the FGD wastewater treatment system will be needed to meet the ELG limits. At a minimum, Duke anticipates having to install a new tank -based physical / chemical treatment system followed by a selenium reduction technology. The selenium reduction technology has not yet been selected and Duke will be evaluating suitable technologies based on cost and feasibility. A biological treatment system is currently installed at Roxboro, but the ELG limits cannot be achieved with the current system. Duke will evaluate the current biological treatment system to determine whether the system can be used as part of an upgraded treatment system or will need to be discarded and completely replaced. In addition, the FGD flow rate for Roxboro is estimated at approximately 1,094 gallons per minute (gpm). In the proposed ELG rule, EPA assumed Roxboro could reduce its FGD flow to 375 gpm by recirculating some of the FGD water back to the FGD system. This would allow for the design of a significantly smaller system, resulting in a significant reduction in cost. Duke is evaluating options to reduce the FGD flow, which would affect the technology selection, design and cost of the system. To further complicate matters, EPA's model technology for the treatment of FGD wastewater is physical/chemical followed by biological treatment. Recently, the biological treatment system vendor for the ABMet system, GE, has claimed intellectual property rights on all biological treatment technologies for FGD wastewater. This could have significant impacts on the cost and procurement schedule of the treatment system. With an EPA estimate of 88 stations within the industry expected to upgrade the FGD wastewater treatment system to comply with the ELG limits, the implementation date must take into account limited resources of EPA's chosen model technology. EPA recognizes that designing, procuring, installing, and optimizing an FGD wastewater treatment system is a complicated and time-consuming undertaking, involving much study and careful planning. For example, EPA states: "For plants that are planning to include fuel flexing in their operations, in the years prior to the installation and operation of the FGD wastewater treatment system, the plant should consider sampling the untreated FGD wastewater to evaluate the wastewater characteristics that are present based on the differing fuel blends. Based on those characteristics, the plant will be better able to design a system that can properly treat its FGD wastewater given variability that might occur at the plant, and it will be better prepared to adjust chemical dosages in the chemical precipitation system to mitigate the variability in the wastewater that enters the biological treatment system." Response to Comments, p. 5-387. EPA also states: "While EPA has based the effluent limitations and standards for selenium and nitrate/nitrite (as N) for FGD wastewater based on the performance of the Allen and Belews Creek biological treatment systems, EPA does not contend that every plant in the industry can simply take the design parameters from those two plants, install the biological treatment system, and meet the effluent limitations. Each plant will need to work with engineering and design firms to assess the wastewater characteristics present at their plant to determine the most appropriate technologies and design the system accordingly meet the effluent limitations. Therefore, some plants may need to design the bioreactors to provide additional bed contact time (as provided by the hydraulic residence time and volume of biomass and carbon substrate), while other plants may find they need less." Response to Comments, p. 5-389 Duke is requesting 87 months from the effective date of the permit to design, install and commission the FGD wastewater treatment system to meet the BAT limits based on the following preliminary timeline. FGD WWT Upgrade Activity Duration (Months) Design & Engineering 30 • Flow Reduction Evaluation 6 • Evaluation of the existing biological system 6 • Technology Evaluation 8 • Siting 4 0 Engineering 6 Procurement' 20 Potential Permitting Delays 6 Construction/Tie-in' 16 Start-up & Optimization 15 • Commissioning 6 0 Start -Up 6 Total: 87 1) Duke is allocating a 20 month window for procurement and a 16 month window for construction and tie-in to account for only one vendor available to supply and construct the biological treatment system. 2) Duke is allocating a 15 month window to complete the commissioning and start-up under all expected operating conditions from full load to partial load to periods of no load. Assuming a permit effective date of October 12016, Duke estimates the system can be installed and commissioned to meet the BAT limits on or before December 31, 2023. To design, procure, construct and commission the FGD WWT system at Roxboro, the following steps must be taken: Design & Engineering As with the RMDS, engineering and technology resources are limited due to regulatory requirements for concurrent implementation of programs, such as the CCR Rule and NC-CAMA across applicable sites in North Carolina. Duke is, therefore, estimating 30 months to complete the design and engineering phase of the project. FGD Flow Reduction Evaluation Duke is evaluating options, such as recirculating some of the FGD water back to the FGD system, to reduce the FGD wastewater flow rate to design and install a cost effective system. As stated above, EPA assumed Roxboro could reduce the FGD wastewater flow to 375 gpm. Whether recirculating some of the FGD water back to the FGD system is a viable option is dependent on the chlorides in the FGD water and chloride impacts on the materials of construction of the FGD scrubber. Duke will also determine if other flow reduction measures are available for Roxboro. This is a critical step in the design and technology evaluation to ensure a cost effective treatment system. Existing Bioreactor Evaluation A biological treatment system is installed at Roxboro. However, the current system cannot meet the final ELG limits for FGD wastewater. Currently, it is unknown whether the existing biological treatment system can be used as part of an upgraded treatment system or if the biological treatment system will need to be discarded and completely replaced. Duke, therefore, is planning on conducting an evaluation to determine the feasibility and cost of using the existing biological reactor or replacing the entire system. Siting As with the RMDS, the FGD WWT system will need to be sited to avoid any former or current CCR sites and avoid construction areas that will be used to complete closure of the ash basins at Roxboro. Additionally, Duke will need to site the system to avoid nuisance odor outside the property boundary. Duke will also attempt to site the system to avoid WOTUS. However, based on the final siting of the system WOTUS may not be avoided, and permits from the U.S. Army Corps of Engineers may be required. Technology Selection Duke has significant experience in the design, construction and operation of biological treatment systems for selenium reduction. Based on Duke's experience, biological treatment alone may not be a fool proof technology based on the characteristics of the coal. Duke, therefore, is obligated to review and evaluate whether other suitable technologies are available to treat FGD wastewater for selenium reduction at Roxboro. This is particularly important with GE claiming intellectual property rights on the biological treatment system for FGD wastewater, thus being the sole provider of this technology. Duke will be working closely with utility organizations, such as the EPRI, to identify suitable technologies for the removal of selenium from FGD wastewater and possibly additional polishing steps that may be required to meet the limits. Upon completion of the siting and technology selection, the engineering design of the system will be completed. Permitting If WOTUS cannot be avoided, then permitting from the U.S. Army Corps of Engineers (USACE) will be needed. At this time, it is unknown whether a USACE permit will be required or the type of permit that may be required (nationwide permit (NPW) or individual permit). Duke, therefore, has included 12 months in the schedule to prepare and obtain any necessary USACE permits. The installation of the FGD WWT may change the characteristics of the final discharge, therefore, a NPDES permit modification may be required to revise the permit to account for the changes in flow and constituent make-up. Even through the permitting task will be initiated during the design and engineering phase, it is expect to continue through the procurement phase and up to the construction phase. In addition, the extent and complexity of the permits required are unknown at this time. The required permits will be evaluated during the engineering and design phase. Since time needed to prepare the permit applications and the time needed to receive the permits is uncertain, Duke allocated 6 months to account for potential permitting delays. Procurement After the design is complete, Duke will initiate the process to procure the necessary outside resources to construct and install the new wastewater treatment systems. This process will involve the following steps: — Evaluate potential vendors for proposal solicitation; — Develop and submit a request for proposal (RFP) to selected vendors; — Conduct a review and vendor selection based on the received bids; Develop required contract documents; — Acquire materials (potentially from overseas), which involves: o Shipment, and o Equipment Fabrication — Fabrication and inspection of equipment. The selenium reduction technology will have a fabrication queue that is dependent on total industry -wide demand. With GE claiming intellectual property rights on biological treatment additional time will need to be factored into the implementation date. Duke, therefore, has allocated 24 months to acquire the necessary materials. Additionally, raw materials needed may have an extended lead-time from time of order to delivery, such as the granulated activated carbon used in the biological system, which has a lead time of 12 months. As stated above, GE is claiming intellectual property rights on the biological treatment system. If this claim is upheld, GE will be the only supplier of the biological treatment system. Given the potential number of facilities installing treatment system for FGD wastewater in the industry, additional 8 months is allocated to account for an extended procurement period. Construction / Tie In Once all the necessary materials are procured, Duke estimates construction of the FGD WWT will take approximately 16 months to complete. In addition, the tie-in of the FGD WWT to each individual FGD scrubber will need to occur during outages, which are anticipated to occur between March to May and October to November depending on generation demand. Furthermore, an additional 4 months were included in the schedule to account for the potential of GE being the sole provider of the biological treatment system. Commissioning & Start-up Duke estimates that commissioning and start-up of the FGD WWT will take 12 months to complete, 6 months for each task. Duke, however, is allocating a 15 month window to complete the commissioning and start-up under all expected operating conditions from full load to partial load to periods of no load. This will allow the identification of necessary actions that need to be completed in order to maintain the system under different operating scenarios. E. EPA Provided a Range of Applicability Dates To Allow For Coordination across Regulatory Requirements and to Promote Orderly Decisions The steam electric industry is in the midst of major transitions driven by new environmental regulatory requirements in the air, waste, and water arenas. In the ELG Rule, EPA explicitly acknowledged the complications of planning and executing ELG retrofits while developing and executing compliance strategies under the other rules. EPA made it clear that the range of applicability dates provided in the ELG Rule are supposed to be implemented in a manner that avoids stranded costs and promotes orderly decision making. For instance, EPA states: "From an environmental protection/coordination standpoint, with the increased use of flue gas desulfurization scrubbers and flue gas mercury controls in response to air pollution -related requirements, this rule makes sense from a holistic environmental protection perspective and from the perspective of coordinating across rules affecting the same sector. This final ELG controls the discharges associated with these particular waste streams." Response to Comments, p. 8-388. EPA also states that the permitting authority may "account for time the facility needs to coordinate all the requirements of this rule, along with other regulatory requirements, to make the correct planning and financing decisions, and to implement the new requirements in an orderly and feasible way." Response to Comments, p. 8-129. At Roxboro, we need to coordinate our ELG implementation strategy with CCR and NC-CAMA rules. For both the CCR and CAMA rules, we are evaluating the current CCR ash ponds to determine whether the ponds meet the locational restrictions of 40 C.F.R. § 257.60 - .64. The future of the ash pond under both of these rules will determine whether it is available or not to receive legacy wastewaters (i.e., those wastewaters generated before the applicability date for bottom ash transport water retrofits) and continue to receive non-BATW. In addition, as discussed above, the final determination of the extent of the ash pond, as well as the closure method could have significant ramifications for the siting of both the RMDS and FGD WWT. F. ELG Implementation Should be Coordinated with the Clean Power Plan (CPP) to Avoid Stranded Costs The ELG Rule clearly contemplates that the compliance timelines for its requirements should account for any applicable obligations under the CPP. However, the affected units at Roxboro will not know their individual obligations under the CPP until well after November 1, 2018. As promulgated by EPA, the CPP's emission guidelines do not apply directly to units. Instead, states are responsible for developing state plans setting forth requirements applicable to individual units that implement those emission guidelines. These state plans are subject to review and approval by EPA. If EPA determines that the state has not submitted an approvable plan, then EPA will promulgate a federal plan in its place. The timeline the CPP provides for developing and reviewing these state plans involves numerous steps. The initial deadline for state plan submittal was September 6, 2016. 40 C.F.R. § 60.S760(a). The vast majority of states were expected to seek and obtain a two-year extension for final state plan submittal until September 6, 2018. See id. § 60.5760(b). However, the Supreme Court issued a stay of the CPP on February 8, 2016. Thus, the timing of the requirements of the CPP is uncertain at this time, as we wait further decisions by the Supreme Court. Duke would like to request the option to revise the applicability dates for the ELG requirements if the stay of the CPP is lifted and the operation of Roxboro will be affected. Statements in the Response to Comments regarding stranded costs apply to any rule, not just the CPP. EPA explains in the Response to Comments that it provided flexibility in applicability dates so that facilities could consider all new regulatory requirements and then have an adequate time to plan and implement accordingly, and thus avoid stranded costs: "EPA is sensitive to the need to provide sufficient time for steam electric power plants to understand, plan for, and implement any changes to their operation to meet their environmental responsibilities, and agrees with the commenter that transparency of requirements is important for minimizing "stranded investments." ...Furthermore, as described in the preamble, the final rule provides time for plant owners or operators to implement changes to plant operations in order to meet the final limitations and standards, as well as flexibility to permitting authorities in implementing the final rule. The Agency specifically considered the timing of requirements of other environmental regulations in establishing implementation requirements for the ELGs, in order to provide steam electric power plants time to consider and implement their strategy for compliance." Response to Comments, p. 8-388. Even though the implementation and effects of the CPP are uncertain, North Carolina Department of Environmental Quality (NCDEQ) is justified providing flexibility in the applicability dates from other regulatory requirements such as the CCR and NC-CAMA, as discussed above. G. The Proposed Schedules Help to Maintain Roxboro's Availability to the Grid, Which Promotes Grid Reliability Duke developed the proposed BATW retrofit schedule and its applicability date with grid reliability in mind. The dispatch of units at Roxboro varies throughout the year. Typically one unit is operating throughout the year and all four units are typically dispatched from December to March and June thru September. Therefore, the final tie-in schedule will avoid these months and more than likely tie-ins will need to occur across more than one outage. EPA explicitly notes that the permitting authority should consider grid reliability in setting applicability dates: "EPA's decision is also designed to allow, more broadly, for the coordination of generating unit outages in order to maintain grid reliability and prevent any potential impacts on electricity availability, something that public commenters urged EPA to consider." 80 Fed. Reg. at 67,854, col. 2. See also Response to Comments, p. 8-138. Also, EPA clearly anticipated that much of the new technology required for retrofits to bottom ash transport water and FGD wastewater systems would be constructed in a manner that would not interrupt routine facility operations, and then tied in during regularly scheduled plant or unit outages. According to the preamble, the timing of the final rule "enables facilities to take advantage of planned shutdown or maintenance periods to install new pollution control technologies." 80 Fed. Reg. at 67,854, col. 2. EPA also recognizes that tie-ins of new equipment may need to occur across more than one outage. EPA states: "the need to span installation of equipment over separate unit outages [is] a consideration that can be incorporated into the permit writer's determination of the 'as soon as possible' date, assuming the plant provides documentation demonstrating such a need." Response to Comments, p. 8-54. Attachment 5 Clean Water Act 316(b) alternate schedule request August 15, 2016 NPDES application update Roxboro Steam Plant NC0003425 Alternate Schedule Request §316(b) of the Clean Water Act Roxboro Generating Station Final regulations to establish requirements for cooling water intake structures at existing facilities were published in the Federal Register on August 15, 2014 (i.e. regulations implementing §316(b) of the Clean Water Act) with an effective date of October 14, 2014. Per §125.91(a)(1)-(3) Applicability, the Roxboro Generating Station (Roxboro) is subject to the requirements at §125.94 through §125.99 (316(b) requirements) based on the following: — The facility is defined as an existing facility (i.e. commenced construction prior to January 17, 2002); The facility is a point source discharge; — The facility uses a cooling water intake with a design intake flow (DIF) of greater than 2 million gallons (MGD) to withdraw water from waters of the U.S.; and — Twenty-five percent or more of the water withdraws on an actual intake flow basis are exclusively used for cooling purposes. Per §125.98(b) Permitting requirements, 316(b) requirements are implemented through the NPDES permit. Facilities subject to the final rule are required to develop and submit application materials identified at § 122.21(r). The actual intake flow (AIF) of the facility determines which submittals will be required. All facilities with an DIF 2 MGD or greater are required to submit material identified at §122.21(r)(2)-(8), whereas, facilities with an AIF greater than or equal to 125 MGD are required to submit additional information presented in § 122.21(r)(9)-(13). The AIF withdrawn by the station from Hyco Reservoir is above the 125 MGD threshold; therefore, Duke Energy is planning on completing the following 316(b) submittals: • § 122.21(r)(2) Source Water Physical Data • § 122.21(r)(3) Cooling Water Intake Structure Data • § 122.21(r)(4) Source Water Baseline Biological Characterization Data • § 122.21(r)(5) Cooling Water System Data • § 122.21(r)(6) Chosen Method(s) of Compliance with Impingement Mortality Standard • § 122.21(r)(7) Entrainment Performance Studies • § 122.21(r)(8) Operational Status • § 122.21(r)(9) Entrainment Characterization Study • § 122.21(r)(10) Comprehensive Technical Feasibility and Cost Evaluation Study • § 122.21(r)(11) Benefits Valuation Study • § 122.21(r)(12) Non -water Quality and Other Environmental Impacts Study 0 § 122.21(r)(13) Peer Review Per § 125.98(b) Permitting requirements, 316(b) requirements are implemented through the NPDES permit. For Roxboro, the NPDES permit proceedings had begun prior to the effective date of the rule. Therefore, 40 C.F.R § 125.98(g) Ongoing permitting proceedings, applies to Roxboro, which states: "... whenever the Director has determined that the information already submitted by the owner or operator of the facility is sufficient, the Director may proceed with a determination of BTA standards for impingement mortality and entrainment without requiring the owner or operator of the facility to submit the information required in 40 CFR 122.21(r).." Only limited information regarding 316(b) was previously submitted to NCDEQ for Roxboro. The previously submitted information consisted of a Proposal for Informational Collection (PIC) request and a 316(b) Barrier Net Conceptual Design Report. In Duke's opinion, the previously submitted information is not sufficient for NCDEQ to proceed with a determination of BTA standards for impingement mortality and entrainment. As stated in the preamble to the rule, "In such circumstances where permit proceedings have already begun prior to the effective date of the rule, these facilities will still need to submit the appropriate permit application materials found at § 122.21(r) permit applications during their next application." 1 Furthermore, the regulation states the owner of a facility whose current effective permit expires after July 14, 2018, must submit the above information when applying for a subsequent permit and the owner of a facility whose current effective permit expires on or before Jul 14, 2018 may request an alternate schedule for the submission of the above information . As allowed under § 125.95(a)(2) and stated in the preamble to the rule, Duke Energy would like to request an alternate schedule for the submittals listed above. Duke Energy would like to request the 316(b) submittals, with the exception of §122.21 (r) (6) Chosen Method(s) of Compliance with Impingement Mortality Standard, for Roxboro be required with the subsequent permit renewal application due after July 14, 2018. Since Roxboro is subject to the entrainment best technology available (BTA) determination, a compliance schedule to complete §122.21(r)(6) Chosen Method(s) of Compliance with Impingement Mortality Standard will be requested to be included in the permit upon issuance of the entrainment BTA determination. The alternate schedule request is justified based on the following: Roxboro was not required to submit information requested in § 122.21(r)(2), (3), (4) and (5) under the remanded Phase II Rule because the station was planning to comply by installing a barrier net to meet the through screen velocity limit. Information requested in § 122.21(r)(6) — r(12) are new provisions and these submittals must be developed with r(9) requiring two years of entrainment data. ' 79 Fed. Reg. 48358 (15 August 2014) 2 Refer to §125.95(a)(1) and (2) — For the § 122.21(r)(13) Peer Review, Duke Energy estimates this could take up to 12 months to complete. This, also, takes into account the other six Duke Energy stations in N. Carolina and two stations in S. Carolina that will be undergoing the peer review process concurrently. — Additionally, the United States Environmental Protection Agency (USEPA) — Headquarters (HQ) have indicated guidance is being prepared to assist in interpreting and implementing the rule requirements, however, this guidance is not expected to be issued until the 316(b) litigation is completed, which is not expected to occur until 2017. Attachment 6 Process flow diagram with proposed future water flow path August 15, 2016 NPDES application update Roxboro Steam Plant NC0003425 �o a) U) a) 0 U T 0 LL Roxboro Steam Electric Plant Post ash basin flow outfall 003 Plant Process Streams A I Water Treatment 0. Systems Plant Drainage System Drains from oil filled equipment containment F eatment EI/Waterparator) Unit 4 Cooling 30Unit 4 Cooling To Atmosphere Water Tower D Outfall 005 (internal) F............................................................. Maintenance Drain B Unit 3 Cooling —� Water' r Alternative modes G Unit 1&2 —� Cooling Water I� Unit 3 Cooling To Atmosphere Tower E Stormwater from Gypsum Storage Pile Area H Low Volume Collection Sump Heated Water Mixing Zone Stormwater Effluent Channel AOW's and seeps From Linedretention basins above Domestic Sewage Waste Treatment Plant Hyco Reservoir P Emergency Flue Gas Discharge Desulfurization y NH3 Vapor Suppression Lined Bio Bio FGD , (Emergency) Retention �<"""' Ultra.< ............ Blowdown basins filtration (east and OR OR A h L df'II west) s an 1 Leachate A East settling West settling and SW Stormwater See pond pond below E Silo Unit 3 Cooling T c E 3 Wash Water Tower Pond Bioreactor m' �CD > EEO w: Outfall002 jinternal Outfall 010 Ash basin closure flows Flush I......• pond M Hyco `% Outfall 003 Reservoir Evaporation Form 2C — Item II A Flows, Sources of Pollution, and Treatment Technologies Outfall 003 August 2016 Roxboro Steam Plant Outfall 006 Raw water tank drainage Stormwater (maintenance) Outfall 006 Coal Pile Runoff Treatment Basin N Hyco Reservoir pile runoff Emergency Gypsum I I Truck wheel wash stack Form 2C — Item II A Flows, Sources of Pollution, and Treatment Technologies Outfall 006 August 2016 Roxboro Steam Plant Outfall 001 Stormwater through remnant of east ash basin Incidental AOW's and Gypsum and rail seepage I runoff Outfall 001 jIntakepumpsfor Plant Intake Canal plant processes Outfall 003 Form 2C — Item II A Flows, Sources of Pollution, and Treatment Technologies Outfall 001 August 2016