FYI.
From: Harrison,James A<James.Harrison@ncdenr.gov>
Sent:Tuesday, March 31, 2020 4:07 PM
To: Lane, Stephen <stephen.lane@ncdenr.gov>
Cc: Deaton,Anne <anne.deaton@ncdenr.gov>
Subject: Re: B-5620 Beaufort Bridge#30 over Campbell Creek
Stephen,
DMF does not oppose to the two week extension for the Beaufort Bridge #30 over Campbell Creek, with work
planning to be completed by 14 April. DMF does request that turbidity curtains be utilized during in-water work
to minimize the effects of increased turbidity. Thank you!
Jimmy
Jimm, Harrison
Habitat and Enhancement Section
NC Division of Marine fisheries
james.harrison@ncdenr.gov
252-9+-8-3835
c .c
}x
* PIS
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.
From: Lane, Stephen <stephen.lane@ncdenr.gov>
Sent: Friday, March 27, 2020 9:14 AM
1
To: Harrison,James A<James.Harrison@ncdenr.gov>
Cc: Deaton,Anne <anne.deaton@ncdenr.gov>
Subject: FW: B-5620 Beaufort Bridge#30 over Campbell Creek
Good morning,
Would you give me a call on this request at your earliest convenience? My cell number is 252-617-3191.
Thanks,
Stephen Lane
Coastal Management Representative
From: Lentine, Sarah F<sflentine@ncdot.gov>
Sent: Wednesday, March 25, 2020 4:14 PM
To: Lane, Stephen <stephen.lane@ncdenr.gov>
Cc: Capehart, Cadmus<ccapehart@ncdot.gov>;Johnson,Jay B<ibiohnson@ncdot.gov>
Subject: B-5620 Beaufort Bridge#30 over Campbell Creek
Importance: High
Stephen,
We would like your consideration in postponing the start of the moratorium on permit 3-18 on the
subject project by 14 days to April 14, 2020.
Attached is the Contractors planned schedule, the concrete pours are scheduled close together,but
they can use high early strength to achieve the needed strength. To drive the interior bent piles for
stage II of the bridge they intend on cutting holes through the existing bridge deck to drive them.
Then demolishing the rest of the bridge after the moratorium begins.
Thanks,
Sarah F. Lentine, PE
Resident Engineer
Resident Engineer's Office -Pitt
NC Department of Transportation
252 439 2970 office ***New Number***
sflentine@ncdot.gov
1710 North Memorial Drive
P. O. Box 1587
Greenville,NC 27835-1587
//mot,
3� rFJ.1
L ' 1
Email correspondence to and from this address is subject to the
2
North Carolina Public Records Law and may be disclosed to third parties.
Email correspondence to and from this sender is subject to the N.C.Public Records Law and may be disclosed to third parties.
3