HomeMy WebLinkAbout20200223 Ver 1_RE upcoming projects and information_20200401Strickland, Bev
From:
Mairs, Robb L
Sent:
Wednesday, April 1, 2020 10:50 AM
To:
Weychert, Curtis R
Cc:
Benson, Tyler G
Subject:
RE: upcoming projects and information
Roger that Curt. We will include this into the application, and based on these determinations, this would not require
written approval from the DWR. We will follow up with a letter as well. (Yacht Basin Holdings II-DWR 2020-0223
through GC 4175).
Thanks,
From: Weychert, Curtis R
Sent: Wednesday, April 1, 2020 10:42 AM
To: Mairs, Robb L <robb.mairs@ncdenr.gov>
Cc: Benson, Tyler G <Tyler.Benson@ncdenr.gov>
Subject: RE: upcoming projects and information
Robb, I forgot to mention my conversation with Jonathan about this project. Jonathan said that we would consider the
project to be 10 slips because the dock on the southern boundary is on the riparian property line (waived 15' buffer
from the neighbor) and we wouldn't be able to regulate dock usage on a riparian neighbors corridor. Cant remember if
we already talked about this on the phone, but I wanted to relay Jonathan's thoughts on the project.
I also talked to Jeremy Humphrey to see if the potential for additional slips on the riparian neighbor would affect the
comments he provided and he said that in either circumstance, it wouldn't cause a concern for additional shellfish
closures in the area, nor trigger a "marina" concern.
Curt
Curtis Weychert
Assistant Major Permit Coordinator
North Carolina Division of Coastal Management
North Carolina Department of Environmental Quality
252-808-2808 x211
Curt.Weychert(cancdenr.gov
400 Commerce Ave
Morehead City, NC 28557
* x� E Q
From: Mairs, Robb L <robb.mairs@ncdenr.gov>
Sent: Tuesday, March 24, 2020 4:31 PM
To: Weychert, Curtis R <curt.wevchert@ncdenr.gov>
Cc: Benson, Tyler G <Tyler.Benson@ncdenr.gov>
Subject: RE: upcoming projects and information
Hey man, thanks for the email, and sorry for the delay. I have copied Tyler Benson as well since he has been assisting
me on 401 projects until we get vacant position filled.
-Derbyshire- assigned as DWR 2020-0210, and will not require written approval through our GC 4175. Letter will follow.
-Yacht Basin- assigned as DWR 2020-0223. This appears to not require written approval with up to 10 slips per our GC
4175; however, the proposed floating dock on the most southern portion of the site appears to accommodate another
two (2) slips on the southern side that are not numbered on Sheet 3 of 4, which would make it up to 12-slips and require
written approval. Let me know if I'm missing anything.
-Culamander- assigned as DWR 2020-0272. This appears to not require written approval if this is deemed as
maintenance excavation from DCM. I see the fee schedule is 100% per Tara. If this is in fact new excavation, this will
require written approval.
Thanks again for the support, and likewise, let me know if there's anything on my end I can do to assist you.
Robb Mairs
Environmental Specialist II
Division of Water Resources
North Carolina Department of Environmental Quality
910 796.7303 office
robb.mairs(cDncdenr.gov
https://deg.nc.gov/about/divisions/water-resources/water-resources-permits/wastewater-branch/401-wetlands-buffer-
ep rmits
127 Cardinal Drive Extension
Wilmington, NC 28405
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.
From: Weychert, Curtis R
Sent: Friday, March 20, 2020 4:49 PM
To: Mairs, Robb L <robb.mairs@ncdenr.gov>
Subject: upcoming projects and information
Hey Robb, hope everything is well on your end amidst this strange situation. I was just checking in on a few projects and
things in general to touch base on. There have been a few project deadlines over the last couple of weeks that I don't
know if you have had a change to look at or comment on. Those projects are Derbyshire, Yacht Basin Holdings LLC, and
the Cumalander project. If you haven't received anything on those projects, let me know. I'm also waiting on some
guidance from Jonathan or Braxton about how we plan on dealing with things moving forward if there are restrictions
on work being done. Hopefully soon we will find out if we are going to put projects on hold or ask for extensions etc. As
soon as I find something out I will keep you in the loop. Also, if there is anything that I can help with to lighten your
workload please let me know because I imagine you're already overwhelmed before this whole situation started.
Hope all is well,
Curt
Curtis Weychert
Assistant Major Permit Coordinator
North Carolina Division of Coastal Management
North Carolina Department of Environmental Quality
252-808-2808 x211
Curt.Wevchertancdenr.aov
400 Commerce Ave
Morehead City, NC 28557