HomeMy WebLinkAbout20170799 Ver 2_2017-09-28 PCN package - Reduced_20170929TIMMONS GROUP YOUR VISION ACHIEVED THROUGH OURS. September 28, 2017 Mr. Ross Sullivan Regulatory Specialist U.S. Army Corps of Engineers Raleigh Regulatory Field Office 3331 Heritage Trade Drive, Suite 105 Wake Forest, North Carolina 27587 Mrs. Karen Higgins NC Division of Water Resources 401 and Buffer Permitting Unit 512 N. Salisbury Street Raleigh, NC 27604 5410 Trinity Road P 919.866.4951 Suite 102 F 919.859.5663 Raleigh, NC 27607 www.timmons.com RE: Pre -Construction Notification — NWP 39; General Certification 4092; Neuse River Buffer Authorization Request Mist Lake Facility Expansion Durham County, North Carolina Project #: 39722.001 Dear Mr. Sullivan and Mrs. Higgins: On behalf of the City of Durham - Department of Water Management, Timmons Group is submitting a Preconstruction Notification (PCN) for Nationwide Permit (NWP) 39, General Certification (GC) 4092, and Neuse River Buffer Authorization Request associated with proposed construction of the Mist Lake Facility Expansion located at 1600 Mist Lake Drive in Durham, North Carolina. The project site is bound by 1-85 to the south, an unnamed tributary to the west, and Camden Road to the north. The purpose of the proposed project is to expand the existing facility at Mist Lake, in order to accommodate multiple City of Durham — Department of Water Management (DWM) divisions and allow for potential growth over the next 20 years. To accomplish the goals of the proposed project, approximately 96 feet of stream impact is proposed due to infrastructure and facility layout improvements. In addition, a second entrance road to Camden Avenue is proposed due to safety requirements. As a result, a bridge is proposed to cross Stream A (Goose Creek) with the footers of the bridge placed outside the jurisdictional limits of Stream A, therefore, avoiding impacts to Stream A. Neuse River Riparian Buffer impacts are also proposed as part of the project. Please find enclosed for your review the following items: - Pre -Construction Notification Form - Signed Agent Authorization - Property Owners Map - Neuse River Riparian Area Buffer Determination (NBRRO 17-192; July 19, 2017) - Figure 1 — Vicinity Map - Figure 2 — FEMA Flood Zone Map - Figure 3 — Waters of the U.S. and Neuse River Riparian Buffer Map - Figure 4 — Waters of the U.S. and Neuse River Riparian Buffer Impact Map - Sheet 2 — Waters of the U.S. and Neuse River Riparian Buffer Impact Map — Detail Sheet 3 — Waters of the U.S. and Neuse River Riparian Buffer Impact Map — Detail - Sheet 4 — Waters of the U.S. and Neuse River Riparian Buffer Impact Map — Notes CIVIL ENGINEERING I ENVIRONMENTAL I SURVEYING I GIS I LANDSCAPE ARCHITECTURE I CONSTRUCTION SERVICES Proposed Layout and Preliminary Stormwater Plans - Riparian Buffer Variance Request; August 31, 2017 Original Layout - Compensatory Mitigation Availability Letter PROJECT HISTORY & EXISTING CONDITIONS: The project site encompasses approximately 55 acres and is located at 1600 Mist Lake Drive in Durham, North Carolina (see Figure 1: Vicinity Map). The project site is bound by 1-85 to the south and east, Goose Creek to the west, and Camden Road to the north. The project site is located within the Neuse River Basin (HUC 030202010403) and within the Upper Falls Lake watershed. Adjacent lands are composed of primarily industrial properties intermixed with undeveloped land. The project site drains to unnamed tributaries, where surface waters enter into Goose Creek. Surface waters from Goose Creek flow north to Ellerbee Creek before discharging into Falls Lake, northeast of the project site. There is a floodway and 100 -year floodplain area associated with Goose Creek. The project site currently houses a division of the City of Durham — Department of Water Management (DWM) in a 20 acre facility, along with associated vehicles, equipment and inventory. The undeveloped areas, mainly along the floodplain, are dominated by mid -successional mixed pine and hardwood forest with mixed hardwoods adjacent to the drainage ways. The topography slopes gradually from the southwestern corner to the north and east portion of the project limits. A stream and wetland delineation was conducted by the McAdams Company. NC DWR issued a Neuse River Buffer Determination (NBRRO# 17-192; July 19 ,2017). An on-site field confirmation conducted by USACE (USACE Action ID.: SAW -2017-01649) on September 19, 2017. A written Jurisdictional Determination is forthcoming. Based on the delineation there are approximately 14.21 acres of wetland and approximately 5,644.9 feet of stream located within the project site. Timmons Group conducted a Threatened and Endangered Species Assessment for the Mist Lake Facility Expansion project. There were no Federally Threatened or Endangered species observed during the field survey conducted during the week of July 10, 2017. Based on the field investigations conducted by the Timmons Group, a biological opinion of "No Effect" was rendered for the Michaux's sumac, and smooth coneflower. A Threatened or Endangered Species Assessment Initial Scoping letter was submitted to the USFWS on September 7, 2017. A response from USFWS is forth coming. A Riparian Buffer Variance Request was prepared by the Timmons Group on behalf of the City of Durham — Department of Water Management and submitted to NC DWR on August 31, 2017 due to buffer impacts associated with infrastructure and site layout improvements and are described below. PROPOSED PROJECT: The purpose of the proposed project is to expand the existing facility at Mist Lake, in order to accommodate multiple City of Durham — Department of Water Management (DWM) divisions and allow for potential growth over the next 20 years. The DWM Mist Lake Facilities Expansion project consists of two buildings totaling approximately 116,000 square feet: one to house the administration, warehouse, and shops and the other to hold the equipment maintenance shop. The project is consistent with the zoning requirements for this area (IL - industrial) and is being undertaken to consolidate multiple divisions at one location. The City of Durham — Department of Water Management (DWM) currently operates a division at 1600 Mist Lake Drive (North Campus). This 20 acre facility houses approximately 82 staff of the Administration, Plant Engineering & Maintenance, Regulatory Compliance, and Utility Engineering divisions of the Department, along with associated vehicles, equipment, and inventory. Currently, 145 DWM Water & Sewer Maintenance (WSM) employees are co -housed at a second location on Martin Luther King, Jr. Drive, the Public Works Operations Center (PWOC) along with Public Works staff. The WSM workgroups at PWOC are responsible for Outfall Maintenance, Rehabilitation Maintenance, Meter Reading, Meter Maintenance, Service Installations, and Mainline Installations, along with the necessary vehicles, light and heavy equipment, and inventory to maintain and operate approximately 2,600 miles (combined) of water and sewer mains, 8,148 hydrants, 25,896 water valves, and more than 83,000 water meters. The project will expand the DWM Mist Lake facility to accommodate the relocation of the WSM Division from the PWOC facility to the Mist Lake complex and potential growth over the next 20 years. To accomplish the goals of the project, impacts to streams and riparian buffers are proposed. The proposed infrastructure and facility layout will impact Stream H and associated riparian buffers. In addition, a second entrance road to Camden Avenue is proposed due to safety requirements associated with providing safe ingress and egress to light and heavy equipment and to allow for multiple access points for emergency responders (i.e. fire, EMS, etc.). As a result, a bridge is proposed to cross Stream A (Goose Cre with the footers of the bridge placed outside the jurisdictional limits of Stream A, therefore, avoiding impacts to Stream A. However, there are riparian buffer impacts along Stream A associated the construction of the proposed second entrance road to Camden Avenue. In addition, the project proposes to construct a chain link within small portions of the riparian buffer associated with Streams B and D. Construction of the chain link will create minimal disturbance within the riparian buffers. Stream Impact Table Impact Impact Stream Existing Existing Existing Impact Impact Number Type Type Stream Stream Stream Length Volume B1 — Stream H; Permanent 13,083 Length Width Depth (feet) (cubic yards) Permanent Total Buffer Impacts (feet) (feet) (feet)_ 16,100 96.9 3.49 Si- l Permanent Intermittent 2 0.5 96 Stream Fill for H Parking/Fire Lane _ Total Stream Impacts 96 3.49 Buffer Impact Table Stream Name Reason for Impact Mitigation Zone 1 (ft2) Zone 2 (ft2) Required [Z1] [Z2] (Yes/No) Parking/Fire Lane Yes Bride No B1 — Stream H; Permanent 13,083 11,852 B2 — Goose Creek Stream A); 3,017 4,257 Permanent Total Buffer Impacts 16,100 16,109 Stormwater Managamnt A suite of stormwater devices (e.g. underground sand filters, underground detention, and filter strips) for stormwater treatment. This reduced the need for detention ponds, which further reduced and minimized the impacts to the adjacent stream channels, wetlands, and/or riparian buffers. The site is located within the Upper Falls Lake Watershed, Neuse River Basin. The proposed development will result in 34.6% total built upon area on the site. As part of the development, peak stormwater discharges for the 1 yr, 2yr and 10-24hr storm will be controlled to ensure there is no increase in the peak stormwater discharge rates from the site. The SCS method of analysis was used for the storm event calculations. Total Disturbed acreage on the site is 21 -acres. Four underground sand filters, two underground detention systems, and two level spreaders with filter strips are proposed for the treatment of the stormwater. There are stream buffers surrounding the site, and careful planning has been utilized to avoid most of these buffer and stream impacts. The proposed development will impact some areas of buffers and streams. No wetland impacts are planned for this project. A bridge will be utilized in order to tie into Camden Avenue. The bridge will cross over the floodway and Goose Creek while avoiding disturbance to the maximum extent possible. The site will also have floodplain impacts which will be permitted through the City. There is no offsite upstream run-off entering the developed portion of the site. Any upstream flow bypasses the site and remains in the buffered streams. Stormwater piping is proposed for this site and measures have been taken such that all stormwater runoff leaves the subject property with no increase in peak runoff. Stormwater Quantity: One analysis point has been evaluated for compliance with stormwater ordinance labeled Point W. Stormwater analysis point 'A' is located at the south property line. The runoff was analyzed to determine the change in peak stormwater discharge rates for the 1 -yr, 2 -yr, 10 -yr and 100 -yr storm events. A summary of the design calculations is provided below. I With Detention I... I. I. Note: Post -development Peak Runoff is less than Pre -development Peak Runoff Stormwater Quality: By ordinance section 70-740, this project qualifies as a Redevelopment project, but we will treat this project as new development. The Site is located in the Upper Falls Lake Basin where the minimum nutrient removal requirements are 2.20-lbs/ac/yr of nitrogen and 0.33-lbs/ac/yr of phosphorous. In the Upper Falls Lake Basin for new development, there is a 50% minimum of onsite nutrient treatment. AVOIDANCE & MINIMIZATION: Impacts to jurisdictional features and buffers were avoided and minimized to the maximum extent practicable by incorporating resourceful site planning, including the utilization of the wetland delineation to adjust the layout to avoid and minimize impacts. Avoidance and minimization measures were also accomplished during the design phase of the Project. The Applicant has avoided and minimized impacts to the greatest extent practicable given the Project's purpose and need. The proposed 24,935 square feet of stream buffer impacts are the result of the necessary infrastructure and facility layout, without which, the Project goals would not be realized. This property has been owned since January 1997 and its purchase was intended for this proposed Project. If the City cannot use the existing property to consolidate the five divisions then the initial investment on the purchase of the property will be lost, additional property will need to be purchased to relieve the additional space requirements needed at the remote facilities, as well, the property cannot be used to consolidate multiple divisions in one location. Logistically this will cause inefficiencies, create other impacts associated with the development of another property that are significantly more than the proposed Project, and will not solve the original problems that were the impetus of consolidating the divisions at one location. In order to provide adequate space for parking and buildings, a minimum of 21 acres of buildable land is necessary. The southwestern portion of the site is relatively narrow and is constrained by setbacks along the Interstate and wetlands to the north. A stream and associated buffer bi-sect the property in this area and cannot be avoided. An additional constraint to the site is the need to provide access for emergency vehicles in the event of a fire. To comply with current IFC and local fire codes, pavement is proposed around the site, such that fire Storm Event (cfs) Site Condition 1 -year (cfs) ----- I2 -year (cfs)T 10 -year (cfs) T 100 -year (cfs) Pre - Development 53.39 70.78 130.54 220.9 Post - Development 103.80 127.34 205.12 318.91 Without Detention Post - Development 45.52 59.87 105.20 198.73 I With Detention I... I. I. Note: Post -development Peak Runoff is less than Pre -development Peak Runoff Stormwater Quality: By ordinance section 70-740, this project qualifies as a Redevelopment project, but we will treat this project as new development. The Site is located in the Upper Falls Lake Basin where the minimum nutrient removal requirements are 2.20-lbs/ac/yr of nitrogen and 0.33-lbs/ac/yr of phosphorous. In the Upper Falls Lake Basin for new development, there is a 50% minimum of onsite nutrient treatment. AVOIDANCE & MINIMIZATION: Impacts to jurisdictional features and buffers were avoided and minimized to the maximum extent practicable by incorporating resourceful site planning, including the utilization of the wetland delineation to adjust the layout to avoid and minimize impacts. Avoidance and minimization measures were also accomplished during the design phase of the Project. The Applicant has avoided and minimized impacts to the greatest extent practicable given the Project's purpose and need. The proposed 24,935 square feet of stream buffer impacts are the result of the necessary infrastructure and facility layout, without which, the Project goals would not be realized. This property has been owned since January 1997 and its purchase was intended for this proposed Project. If the City cannot use the existing property to consolidate the five divisions then the initial investment on the purchase of the property will be lost, additional property will need to be purchased to relieve the additional space requirements needed at the remote facilities, as well, the property cannot be used to consolidate multiple divisions in one location. Logistically this will cause inefficiencies, create other impacts associated with the development of another property that are significantly more than the proposed Project, and will not solve the original problems that were the impetus of consolidating the divisions at one location. In order to provide adequate space for parking and buildings, a minimum of 21 acres of buildable land is necessary. The southwestern portion of the site is relatively narrow and is constrained by setbacks along the Interstate and wetlands to the north. A stream and associated buffer bi-sect the property in this area and cannot be avoided. An additional constraint to the site is the need to provide access for emergency vehicles in the event of a fire. To comply with current IFC and local fire codes, pavement is proposed around the site, such that fire apparatus vehicles have access to within 150 feet from all parts of the building. To comply with this requirement, impacts to the buffer cannot be avoided. Offsite alternative sites were explored for this Project; however, in order to provide adequate building space and parking for all divisions, at least 21 acres of buildable land are needed, as well as an adjacent roadway infrastructure that supports heavy truck use. The current location allows for future growth, provides better utilization of existing personnel and equipment, utilizes parts/tools warehousing and non -duplication of housing parts, provides for better internal communication between divisions, and provides protection of parked vehicles and equipment during flooding, which is now experienced at the current location of the Public Works WSM Division, located southwest of this facility. In addition, the proposed layout provides more acceptable storage and in-house work area conditions (e.g. dedicated pedestrian walkways), which provides for a safer work environment for personnel, while utilizing the existing utility and road infrastructure. Given the design constraints associated with a shared use facility (i.e. administration buildings, maintenance warehouses, work vehicles, equipment storage) and the local zoning requirements, the applicant has minimized impacts to the greatest extent practicable. Specifically, there is a setback associated with Interstate 85 along the southern property boundary. This 50 foot setback limited useable space for parking and buildings along the southern property line and pushed the development to the north, towards the stream and stream buffer. Moreover, the southwestern portion of the property is bisected by a stream and buffer, and in order to provide space for a building and parking, buffer impacts could not be avoided. The applicant explored the use of retaining walls along the northern portion of the parking lot; however, this option provided very limited avoidance, as space is still needed for parking and emergency vehicle access. Furthermore, most of the vehicles and equipment being stored at the site are large construction vehicles and equipment, which required more storage area than a passenger car or truck. Construction equipment and vehicles require more space to maneuver (i.e. larger turning radii, larger parking areas, etc.), as well, when being serviced these vehicles require large services bays, as well as additional areas with the lay down area for the large equipment (lifts, hoists, cranes, etc.) needed to service the larger equipment. Therefore, the typical parking requirements for an office building do not apply, and are considerably larger based on the type and number of pieces of equipment. Approximately 368 parking spaces are required for the site. This includes parking for the visitors, employees, and fleet vehicles (both large and small), as well as the additional handicap spaces required by the City Ordinance. The original layout (Appendix D — Original Layout) proposed impacts to wetlands and a stream channel in the northern portion of the property for an entrance road and the proposed fill slope for the parking areas and pad sites extended into the wetlands in the central portion of the property. The layout was re -designed, in order to avoid impacts to the wetlands and stream channel through the use of retaining walls. The entrance road from Camden Avenue is a safety requirement, in order to provide safe ingress and egress, as well as allow for multiple access points for emergency responders (i.e. fire, EMS, etc.). The road was re -located in an area that avoids impacts to streams and wetlands. Moreover, stream impacts have been completely avoided through the use of bridge. In addition, impacts to riparian buffers have been minimized to the maximum extent practicable by aligning the bridge through the buffer as close to 90 degrees as possible. In an effort to confine the entire facility for security purposes, a chain link fence is proposed, in which, small portions will be constructed within the riparian buffer associated with Streams B and D resulting in minimal disturbance. Other measures taken to minimize impacts include the use of a suite of stormwater devices (e.g. underground sand filters, underground detention, and filter strips) for stormwater treatment. This reduced the need for detention ponds, which further reduced and minimized the impacts to the adjacent stream channels, wetlands, and/or riparian buffers. A project -specific Erosion and Sediment Control (ESC) plan will be developed and submitted to Durham for approval of the land disturbing activity. The ESC plan will be prepared in accordance with the North Carolina Erosion & Sediment Control Laws and Regulations and the most current version of the Erosion & Sediment Control Planning and Design Manual. The ESC plan will be approved by the locality prior to any land -disturbing activity associated with the Project. All regulated land -disturbing activities associated with the Project, including on- and off- site access roads, staging areas, borrow areas, stockpiles, and soil intentionally transported from the Project Area will be covered by the project specific ESC plan. During construction activities, the ESC Best Management Practices (BMPs) will be inspected and maintained throughout the life of the construction activity providing for enhanced protection for the avoided jurisdictional areas and further minimizing impacts to the aquatic resources. Measures will be taken to prevent oil, tar, trash, debris and other pollutants from entering the adjacent jurisdictional streams and wetlands. Any excess excavated materials not utilized as back fill will be placed and contained within upland areas and permanently stabilized to prevent erosion into adjacent jurisdictional streams and wetlands. Therefore, stockpiling of excavated material within jurisdictional streams and wetlands will be strictly prohibited as part of the construction of this project. All project construction activities initiated within jurisdictional streams and wetlands will be carried to completion in an expeditious manner to minimize the period of disturbance within the jurisdictional streams and wetlands. MITIGATION: The Mist Lake Facility Expansion proposes to impact 96 feet of intermittent stream (Stream H); and therefore, the applicant does not propose compensatory mitigation for these impacts at this time due to the avoidance minimizations measures described above. In addition, stream A (Goose Creek) will be crossed by a bridge for the purposes of a proposed second entrance road to Camden Avenue due to safety requirements associated with providing safe ingress and egress to light and heavy equipment and to allow for multiple access points for emergency responders (i.e. fire, EMS, etc.). The footers of the proposed bridge will be placed outside the jurisdictional limits Stream A; therefore, impacts to Stream A will be avoided and compensatory mitigation is not proposed. The proposed stream buffer impacts associated with the bridge crossing of Goose Creek are considered an Allowable Use within the stream buffer in accordance with 15A NCAC 02B .0259 Neuse River Basin; and therefore, compensatory mitigation is not required nor is it proposed at this time. As noted above, a Riparian Buffer Variance Request was prepared by the Timmons Group on behalf of the City of Durham — Department of Water Management and submitted to NC DWR on August 31, 2017 due to buffer impacts associated with infrastructure and site layout improvements. Compensatory mitigation for these unavoidable riparian impacts will be achieved through the purchase of off-site mitigation credits from a mitigation bank, which is approved for use in the Neuse Watershed (Hydrologic Unit Code 03020201). Buffer mitigation credits will be purchased using the Standard Compensatory Mitigation Ratios at ratios of 3:1 for Zone 1 (39,249 SF) and 1.5:1 for Zone 2 (17,778 SF). This equates to a total compensatory mitigation obligation of 57,027 SF of buffer credits. A credit availability letter from an approved bank located in HUC 03020201 was obtained from Wildlands Holdings for the North Fork Little River Buffer Bank (Compensatory Mitigation Availability Letter; Wildlands Holdings; July 27, 2017). SUMMARY: The proposed Mist Lake Facility Expansion is required to accommodate multiple City of Durham — Department of Water Management (DWM) divisions and allow for potential growth over the next 20 years. To accomplish the goals of the proposed project, approximately 96 feet of stream impact is proposed due to infrastructure and facility layout improvements. In addition, a second entrance road to Camden Avenue is proposed due to safety requirements. As a result, a bridge is proposed to cross Stream A with the footers of the bridge placed outside the jurisdictional limits of Stream A, therefore, avoiding impacts to Stream A. Neuse River Riparian Buffer impacts are also proposed as part of the project. The applicant proposes to compensate for unavoidable riparian buffer impacts by payment into the North Fork Little River Buffer Bank (Compensatory Mitigation Availability Letter; Wildlands Holdings; July 27, 2017). The entire Mist Lake Expansion project is a single and complete project with appropriate land use control and stormwater measures in place for specific areas which require them. Therefore at this time, we are requesting confirmation that the proposed project qualifies under the conditions of NWP 39 and GC 4092. In addition, we are requesting authorization of the proposed project under the Neuse River Buffer Rules. Consideration of this project is greatly appreciated. If you should have any questions or require additional information, please do not hesitate to contact me at (984)255- 2361. Sincerely, Timmons Group George Buchholz, REM, PWS Senior Environmental Project Manager Attachments: listed above APPEDIX A PRE -CONSTRUCTION NOTIFICATION FORM nF `N A rt. 1 1 �.JIIIL'c u0c %J111y. y c Corps action ID no. � DWQ project no. Form Version 1.4 January 2009 Pre -Construction Notification (PCN) Form A. Applicant Information 1. Processing 1 a lb Type(s) of approval sought from the Corps: X Section 404 Permit Section 10 Permit Specify Nationwide Permit (NWP) number: 39 or General Permit (GP) number: 4092 1c Has the NWP or GP number been verified by the Corps? X Yes 1 d Type(s) of approval sought from the DWQ (check all that apply): X 401 Water Quality Certification — Regular Non -404 Jurisdictional General Permit 401 Water Quality Certification — Express X Riparian Buffer Authorization 1 e 1f Is this notification solely for the record For the record only for For the record only for Corps Permit: because written approval is not required? DWQ 401 Certification: X No X No Is payment into a mitigation bank or in -lieu fee program proposed for mitigation of impacts? If so, attach the acceptance letter from mitigation bank X No or in -lieu fee program. 1 g Is the project located in any of NC's twenty coastal counties. If yes, answer 1 h below. X No 1 h Is the project located within a NC DCM Area of Environmental Concern (AEC)? X No 2. Project Information 2a Name of project: (Misty Lake Facility Expansion 2b County: Durham 2c Nearest municipality / town: Durham 2d Subdivision name: 2e NCDOT only, T.I.P. or state project no: 3. Owner Information 3a Name(s) on Recorded Deed: 'See attached parcel boundaries map 3b Deed Book and Page No. 3c Responsible Party (for LLC if applicable): 3d Street address: 3e City, state, zip: 3f 3g Telephone no.: Fax no.. 3h Email address: wage i or i u PCN Form — Version 1.4 January 2009 4. Applicant Information (if different from owner) 4a Applicant is: 4b Name: Same as owner (Donald Greeley City of Durham - Department of Water Management '1600 Mist Lake Drive Durham, NC 27704 4c Business name (if applicable): 4d Street address: 4e City, state, zip: 4f Telephone no.: 919-560-4381 4g Fax no.: 4h Email address: 5. Agent/Consultant Information (if applicable) George Buchholz, Senior Environmental 5a Name: Consultant/Project Manager 5b Business name (if applicable): Timmons Group 5c Street address: 5410 Trinity Road, Suite 102 Raleigh, NC 27607 1984.255.2361 5d City, state, zip: 5e Telephone no.: 5f Fax no.: 1919.859.5663 5g Email address: igeorge.buchholz@timmons.com Page 2 of 10 B. Project Information and Prior Project History 1. Property Identification 1a Property identification no. (tax PIN or parcel ID): See attached parcel boundaries map 1 b Site coordinates (in decimal degrees): Latitude: 36.0222328 Longitude: -78.859918 1c Property size: 55 acres 2. Surface Waters 2a Name of nearest body of water to proposed project: 'Goose Creek 2b Water Quality Classification of nearest receiving water: WS -IV, NSW 2c River basin: (Neuse River Basin 030202010403; Upper Falls Lake Natershed 3. Project Description 3a _ . ..... ..... . Describe the existing conditions on the site and the general land use in the vicinity of the project at the time of this application: The project site encompasses approximately 55 acres and is located at 1600 Mist Lake Drive, in Durham County, North Carolina (see Figure 1: Vicinity Map). It is bound by 1-85 to the south, an unnamed tributary to the west, and Camden Road to the north. The site is located within the Neuse River Basin (HUC 030202010403) and within the Upper Falls Lake watershed. The adjacent lands are composed of primarily industrial properties intermixed with undeveloped land. The project site drains to unnamed tributaries, where surface waters enter into Goose Creek. Surface waters from Goose Creek flow north to Ellerbee Creek before discharging into Falls Lake, northeast of the project site. The project site currently houses a division of the City of Durham — Department of Water Management (DWM) in a 20 acre facility, along with associated vehicles, equipment and inventory. The undeveloped areas, mainly along the floodplain, are dominated by mid -successional mixed pine and hardwood forest with mixed hardwoods adjacent to the drainage ways. The topography slopes gradually from the southwestern corner to the north and east portion of the project limits. 3b List the total estimated acreage of all existing wetlands on the property: +/- 14.21 AC 3c List the total estimated linear feet of all existing streams (intermittent and perennial) on the property: +/- 5,644.9 LF 3d Explain the purpose of the proposed project: The purpose of the proposed project is to expand the existing facility at Mist Lake, in order to accommodate multiple City of Durham — Department of Water Management (DWM) divisions and allow for potential growth over the next 20 years. The DWM Mist Lake Facilities Expansion project consists of two buildings totaling approximately 116,000 square feet: one to house the administration, warehouse, and shops and the other to hold the equipment maintenance shop. The project is consistent with the zoning requirements for this area (IL - industrial) and is being undertaken to consolidate multiple divisions at one location. 3e Describe the overall project in detail, including the type of equipment to be used: The City of Durham — Department of Water Management (DWM) currently operates a division at 1600 Mist Lake Drive (North Campus). This 20 acre facility houses approximately 82 staff of the Administration, Plant Engineering & Maintenance, Regulatory Compliance, and Utility Engineering divisions of the Department, along with associated vehicles, equipment, and inventory. Currently, 145 DWM Water & Sewer Maintenance (WSM) employees are co -housed at a second location on Martin Luther King, Jr. Drive, the Public Works Operations Center (PWOC) along with Public Works staff. The WSM workgroups at PWOC are responsible for Outfall Maintenance, Rehabilitation Maintenance, Meter Reading, Meter Maintenance, Service Installations, and Mainline Installations, along with the necessary vehicles, light and heavy equipment, and inventory to maintain and operate approximately 2,600 miles (combined) of water and sewer mains, 8,148 hydrants, 25,896 water valves, and more than 83,000 water meters. The project will expand the DWM Mist Lake facility to accommodate the relocation of the WSM Division from the PWOC facility to the Mist Lake complex and potential growth over the next 20 years. To accomplish the goals of the project, impacts to streams and riparian buffers are proposed. The proposed infrastructure and facility layout will impact Stream H and associated riparian buffers. In addition, a second entrance road to Camden Avenue is proposed due to safety requirements associated with providing safe ingress and egress to light and heavy equipment and to allow for multiple access points for emergency responders (i.e. fire, EMS, etc.). As a result, a bridge is proposed to cross Stream A (Goose Creek) with the footers of the bridge placed outside the jurisdictional limits of Stream A, therefore, avoiding impacts to Stream A. However, there are riparian buffer impacts along Stream A associated the construction of the proposed second entrance road to Camden Avenue. In addition, the project proposes to construct a chain link within small portions of the riparian buffer associated with Streams B and D. Construction of the chain link will create minimal disturbance within the riparian buffers. Traditional equipment will be used consisting of front-end loaders, bulldozers, paving equipment, graders, and earth movers to construct the proposed project. 4. Jurisdictional Determinations 4a Have jurisdictional wetland or stream determinations by the Corps or State been requested or obtained for this property / project (including all prior phases) in the past? X Yes Comments: A written Jurisdictional Determination is forthcoming. 4b If the Corps made the jurisdictional determination, what X Preliminary type of determination was made? 4c If yes, who delineated the jurisdictional Agency/Consultant Company: areas? Name (if known): Kevin Yates I Other: McAdams Company 4d If yes, list the dates of the Corps jurisdictional determinations or State determinations and attach documentation. - NC DWR issued a Neuse River Buffer Determination (NBRRO# 17-192; July 19 ,2017). - On-site field confirmation conducted by USACE (USACE Action ID.: SAW -2017-01649) on September 19, 2017. A written Jurisdictional Determination is forthcoming. 5. Project History 5a Have permits or certifications been requested or obtained X Yes — for this project (including all prior phases) in the past? 5b if yes, explain in detail according to `'help file" instructions. A Riparian Buffer Variance Request was prepared by the Timmons Group on behalf of the City of Durham – Department of Water Management and submitted to NC DWR on August 31, 2017. 6. Future Project Plans 6a Is this a phased project? X No 6b If yes, explain. Page 3 of 10 PCN Form – Version 1.4 January 2009 C. Proposed Impacts Inventory 1. Impacts Summary 1 a. Which sections were completed below for your project (check all that apply): Wetlands X Streams — tributaries X Buffers Open Waters Pond Construction 2. Wetland Impacts If there are wetland impacts proposed on the site, then complete this question for each wetland area impacted. 2a. 2b. 2c. 2d. 2e. 2f. Wetland impact Type of impact Type of wetland Forested Type of jurisdiction Area of number Corps (404,10) or impact Permanent (P) or DWQ (401, other) (acres) Temporary (T) W1 W2 W3 W4 W5 W6 2g. Total Wetland Impacts: i 2h. Comments: 3. Stream Impacts If there are perennial or intermittent stream impacts (including temporary impacts) proposed on the site, then complete this question for all stream sites impacted. _ ............. . .............. — — 3a. 3b. 3c. 3d. 3e. 3f. 3g. Stream impact Type of impact Stream name Perennial (PER) or Type of Average Impact number intermittent (INT)? jurisdiction stream length Permanent (P) or width Qin Temporary (T) (feet)) S1 — Stream H — Fill ;Stream H — UT to Intermittent Corps .2 96 1(p) Goose Creek S2 S3 S4 S5 S6 3h. Total stream and tributary impacts 136 3i. Comments: Stream A (Goose Creek) will be crossed by a bridge for the purposes of a proposed second entrance road to Camden Avenue due to safety requirements associated with providing safe ingress and egress to light and heavy equipment and to allow for multiple access points for emergency responders (i.e. fire, EMS, etc.). The footers of the proposed bridge will be placed outside the jurisdictional limits Stream A; therefore, impacts to Stream A will be avoided. Page 4 of 10 PCN Form — Version 1.4 January 2009 4. Open Water Impacts If there are proposed impacts to lakes, ponds, estuaries, tributaries, sounds, the Atlantic Ocean, or any other open water of the U.S. then individually list all open water impacts below. _ 4a. 4b. 4c. 4d. 4e. Open water Name of waterbody impact number (if applicable Type of impact Waterbody Area of impact (acres) Permanent (P) or type Temporary (T) 01 02 4f. Total open water impacts 4g. Comments: 5. Pond or Lake Construction If pond or lake construction proposed, the complete the chart below. _ 5a. 5b. 5c. 5d. 5e. Pond ID number Proposed use or Wetland Impacts (acres) Stream Impacts (feet) Upland purpose of pond (acres) Flooded Filled Excavated Flooded Filled Excavated P1 P2 5f. Total: 5gComments: 5his a dam high hazard permit required? Yes No If yes, permit ID no: 5i Expected pond surface area (acres): 5j Size of pond watershed (acres): 5k Method of construction. 6. Buffer Impacts (for DWQ) If project will impact a protected riparian buffer, then complete the chart below. If yes, then individually list all buffer impacts below. If any impacts require miti ation, then you MUST fill out Section D of this form. 6a Project is in which protected basin? Neuse Tar-Pamlico Catawba Randleman Other: 6b. 6c. 6d, 6e. 6f 6g Buffer Impact Reason for impact Stream name Buffer Zone 1 Zone 2 number— mitigation impact impac Permanent (P) or required? (square (squat ry (T) feet) feetParking/Fire Lane Stream H — Stream H — UT to Goose Yes 13,083 rt 11,852 (P) Creek 'Bridge Stream A — Goose Creek IVo 3,017 4,257 B2 — (P) B3 B4 6h. Total Buffer Impacts: 16,100 16,109 Page 5 of 10 Riparian Buffer Impact B1 Parkin (Fire Lane): Riparian Buffer Variance Request was prepared by the Timmons Group on behalf of the City of Durham — Department of Water Management and submitted to NC DWR on August 31, 2017. Riparian Buffer impact B2 (Bridge): Riparian buffer impacts are proposed associated with bridge placement for the entrance road to Camden Avenue. In accordance with the Neuse River Riparian Buffer Rules (15A NCAC 02B .0233) Table of Uses, bridges are an allowable use and mitigation is not required. Stream impacts have been completely avoided through the use of a bridge. Impacts to riparian buffers have been minimized to the maximum extent practicable by aligning the bridge through the buffer as close to 90 degrees as possible. D. Impact Justification and Mitigation 1. Avoidance and Minimization 1 a Specifically describe measures taken to avoid or minimize the proposed impacts in designing project. Impacts to jurisdictional features and buffers were avoided and minimized to the maximum extent practicable by incorporating resourceful site planning, including the utilization of the wetland delineation to adjust the layout to avoid and minimize impacts. Avoidance and minimization measures were also accomplished during the design phase of the Project. The Applicant has avoided and minimized impacts to the greatest extent practicable given the Project's purpose and need. The proposed 24,935 square feet of stream buffer impacts are the result of the necessary infrastructure and facility layout, without which, the Project goals would not be realized. This property has been owned since January 1997 and its purchase was intended for this proposed Project. If the City cannot use the existing property to consolidate the five divisions then the initial investment on the purchase of the property will be lost, additional property will need to be purchased to relieve the additional space requirements needed at the remote facilities, as well, the property cannot be used to consolidate multiple divisions in one location. Logistically this will cause inefficiencies, create other impacts associated with the development of another property that are significantly more than the proposed Project, and will not solve the original problems that were the impetus of consolidating the divisions at one location. In order to provide adequate space for parking and buildings, a minimum of 21 acres of buildable land is necessary. The southwestern portion of the site is relatively narrow and is constrained by setbacks along the Interstate and wetlands to the north. A stream and associated buffer bi-sect the property in this area and cannot be avoided. An additional constraint to the site is the need to provide access for emergency vehicles in the event of a fire. To comply with current IFC and local fire codes, pavement is proposed around the site, such that fire apparatus vehicles have access to within 150 feet from all parts of the building. To comply with this requirement, impacts to the buffer cannot be avoided. Offsite alternative sites were explored for this Project; however, in order to provide adequate building space and parking for all divisions, at least 21 acres of buildable land are needed, as well as an adjacent roadway infrastructure that supports heavy truck use. The current location allows for future growth, provides better utilization of existing personnel and equipment, utilizes parts/tools warehousing and non -duplication of housing parts, provides for better internal communication between divisions, and provides protection of parked vehicles and equipment during flooding, which is now experienced at the current location of the Public Works WSM Division, located southwest of this facility. In addition, the proposed layout provides more acceptable storage and in-house work area conditions (e.g. dedicated pedestrian walkways), which provides for a safer work environment for personnel, while utilizing the existing utility and road infrastructure. Given the design constraints associated with a shared use facility (i.e. administration buildings, maintenance warehouses, work vehicles, equipment storage) and the local zoning requirements, the applicant has minimized impacts to the greatest extent practicable. Specifically, there is a setback associated with Interstate 85 along the southern property boundary. This 50 foot setback limited useable space for parking and buildings along the southern property line and pushed the development to the north, towards the stream and stream buffer. Moreover, the southwestern portion of the property is bisected by a stream and buffer, and in order to provide space for a building and parking, buffer impacts could not be avoided. The applicant explored the use of retaining walls along the northern portion of the parking lot; however, this option provided very limited avoidance, as space is still needed for parking and emergency vehicle access. Furthermore, most of the vehicles and equipment being stored at the site are large construction vehicles and equipment, which required more storage area than a passenger car or truck. Construction equipment and vehicles require more space to maneuver (i.e. larger turning radii, larger parking areas, etc.), as well, when being serviced these vehicles require large services bays, as well as additional areas with the lay down area for the large equipment (lifts, hoists, cranes, etc.) needed to service the larger equipment. Therefore, the typical parking requirements for an office building do not apply, and are considerably larger based on the type and number of pieces of equipment. Approximately 368 parking spaces are required for the site. This includes parking for the visitors, employees, and fleet vehicles (both large and small), as well as the additional handicap spaces required by the City Ordinance. The original layout (Appendix D — Original Layout) proposed impacts to wetlands and a stream channel in the northern portion of the property for an entrance road and the proposed fill slope for the parking areas and pad sites extended into the wetlands in the central portion of the property. The layout was re- designed, in order to avoid impacts to the wetlands and stream channel through the use of retaining walls. The entrance road from Camden Avenue is a safety requirement, in order to provide safe ingress and egress, as well as allow for multiple access points for emergency responders (i.e. fire, EMS, etc.). The road was re -located in an area that avoids impacts to streams and wetlands. Moreover, stream impacts have been completely avoided through the use of bridge. In addition, impacts to riparian buffers have been minimized to the maximum extent practicable by aligning the bridge through the buffer as close to 90 degrees as possible. In an effort to confine the entire facility for security purposes, a chain link fence is proposed, in which, small portions will be constructed within the riparian buffer associated with Streams B and D resulting in minimal disturbance. 1 b Specifically describe measures taken to avoid or minimize the proposed impacts through construction techniques. Other measures taken to minimize impacts include the use of a suite of stormwater devices (e.g. underground sand filters, underground detention, and filter strips) for stormwater treatment. This reduced the need for detention ponds, which further reduced and minimized the impacts to the adjacent stream channels, wetlands, and/or riparian buffers. A project-specific Erosion and Sediment Control (ESC) plan will be developed and submitted to Durham for approval of the land disturbing activity. The ESC plan will be prepared in accordance with the North Carolina Erosion & Sediment Control Laws and Regulations and the most current version of the Erosion & Sediment Control Planning and Design Manual. The ESC plan will be approved by the locality prior to any land-disturbing activity associated with the Project. All regulated land-disturbing activities associated with the Project, including on- and off- site access roads, staging areas, borrow areas, stockpiles, and soil intentionally transported from the Project Area will be covered by the project specific ESC plan. During construction activities, the ESC Best Management Practices (BMPs) will be inspected and maintained throughout the life of the construction activity providing for enhanced protection for the avoided jurisdictional areas and further minimizing impacts to the aquatic resources. Measures will be taken to prevent oil, tar, trash, debris and other pollutants from entering the adjacent jurisdictional streams and wetlands. Any excess excavated materials not utilized as back fill will be placed and contained within upland areas and permanently stabilized to prevent erosion into adjacent jurisdictional streams and wetlands. Therefore, stockpiling of excavated material within jurisdictional streams and wetlands will be strictly prohibited as part of the construction of this project. All project construction activities initiated within jurisdictional streams and wetlands will be carried to completion in an expeditious manner to minimize the period of disturbance within the jurisdictional streams and wetlands. 2. Compensatory Mitigation for Impacts to Waters of the U.S. or Waters of the State 2a Does the project require Compensatory Mitigation for X No impacts to Waters of the U.S. or Waters of the State? 2blf yes, mitigation is required by (check all that apply): DWQ Corps --------- — ------------- - - — Mitigation bank 2c If yes, which mitigation option will be used for Payment to in-lieu fee program this project? Permittee Responsible Mitigation 3. Complete if Using a Mitigation Bank 3a Name of Mitigation Bank: Type Quantity: 3b Credits Purchased (attach receipt and letter) Quantity: Type Quantity. J 3c Comments: 4. Complete if Making a Payment to In-lieu Fee Program 4a Approval letter from in-lieu fee program is attached. 4b Stream mitigation requested: linear feet 4c If using stream mitigation, stream temperature: 4d Buffer mitigation requested (DWQ only): square feet 4e Riparian wetland mitigation requested: acres 4f Non-riparian wetland mitigation requested: acres 4g Coastal (tidal) wetland mitigation requested: acres 4h Comments: 5. Complete if Using a Permittee Responsible Mitigation Plan 5a. If using a permittee responsible mitigation plan, provide a description of the proposed mitigation plan. Page 6 of 10 PCN Form — Version 1.4 January 2009 6. Buffer Mitigation (State Regulated Riparian Buffer Rules) – required by DWQ 6a Will the project result in an impact within a protected riparian buffer that requires buffer mitigation? X Yes 6b If yes, then identify the square feet of impact to each zone of the riparian buffer that requires mitigation. Calculate the amount of mitigation required. 6c Zone Reason for impact 6d Total impact (square feet) rking/Fire Lane ;13,083 6e Multiplier Required mitigation (square feet) 3 (2 for Catawba) 39,249 Zone 2 (Parking/Fire Lane 11,852 1.5 17,778 i --........ — — — -- 6f 1W[57,027 n�qd 6g If buffer mitigation is required, discuss what type of mitigation is proposed (e.g., payment to private mitigation bank, permittee responsible riparian buffer restoration, payment into an approved in -lieu fee fund). As noted in the submitted Riparian Buffer Variance Request, compensatory mitigation for the unavoidable Riparian Buffer Impact B1 (Parking/Fire Lane) will be achieved through the purchase of off-site mitigation from a mitigation bank, which is approved for use in the Neuse Watershed (HUC: 03020201). Buffer mitigation credits will be purchased using the Standard Compensatory Mitigation Ratios at ratios of 3:1 for Zone 1 (39,249 SF) and 1.5:1 for Zone 2 (17,778 SF). This equates to a total compensatory mitigation obligation of 57,027 SF of buffer credits. Credit availability letter from the North Fork Little River Buffer Bank, an approved wetland and stream mitigation bank located in HUC 03020201, are attached. 6h Comments: Page 7 of 10 E. Stormwater Management and Diffuse Flow Plan (required by DWQ) 1. Diffuse Flow Plan la Does the project include oris it adjacent to protected riparian buffers identified within one of the NC Riparian Buffer Protection Rules? lb If yes, then is a diffuse flow plan included? If no, explain why. 2. Stormwater Management Plan X Yes X Yes 2a What is the overall percent imperviousness of this project? 34.6% 2b Does this prosect require a Stormwater Manaqement Plan? X Yes 2c If this project DOES NOT require a Stormwater Management Plan, explain why: 2d If this project DOES require a Stormwater Management Plan, then provide a brief, narrative description of the plan: A suite of stormwater devices (e.g. underground sand filters, underground detention, and filter strips) for stormwater treatment. This reduced the need for detention ponds, which further reduced and minimized the impacts to the adjacent stream channels, wetlands, and/or riparian buffers. The site is located within the Upper Falls Lake Watershed, Neuse River Basin. The proposed development will result in 34.6% total built upon area on the site. As part of the development, peak stormwater discharges for the 1yr, 2yr and 10-24hr storm will be controlled to ensure there is no increase in the peak stormwater discharge rates from the site. The SCS method of analysis was used for the storm event calculations. Total Disturbed acreage on the site is 21 -acres. Four underground sand filters, two underground detention systems, and two level spreaders with filter strips are proposed for the treatment of the stormwater. There are stream buffers surrounding the site, and careful planning has been utilized to avoid most of these buffer and stream impacts. The proposed development will impact some areas of buffers and streams. No wetland impacts are planned for this project. A bridge will be utilized in order to tie into Camden Avenue. The bridge will cross over the floodway and Goose Creek while avoiding disturbance to the maximum extent possible. The site will also have floodplain impacts which will be permitted through the City. There is no offsite upstream run-off entering the developed portion of the site. Any upstream flow bypasses the site and remains in the buffered streams. Stormwater piping is proposed for this site and measures have been taken such that all stormwater runoff leaves the subject property with no increase in peak runoff. Stormwater Quantity: One analysis point has been evaluated for compliance with stormwater ordinance labeled Point 'A'. Stormwater analysis point 'A' is located at the south property line. The runoff was analyzed to determine the change in peak stormwater discharge rates for the 1 -yr, 2 -yr, 10 -yr and 100 -yr storm events. A summary of the design calculations is provided below. Stormwater Quality: By ordinance section 70-740, this project qualifies as a Redevelopment project, but we will treat this project as new development. The Site is located in the Upper Falls Lake Basin where the minimum nutrient removal requirements are 2.20-lbs/ac/yr of nitrogen and 0.33-lbs/ac/yr of phosphorous. In the Upper Falls Lake Basin for new development, there is a 50% minimum of onsite nutrient treatment. 2e Who will be responsible for the review of the Stormwater Management Plan? 3. Certified Local Government Stormwater Review iDurham 3a In which local government's jurisdiction is this pLoject? Phase II 3b Which of the following locally-implemented stormwater management programs X NSW USMP apply (check all that apply): X Water Supply Watershed Other: 3c Has the approved Stormwater Management Plan with proof of approval X No been attached? 4. DWQ Stormwater Program Review Coastal counties HQW 4a Which of the following state-implemented stormwater management programs ORW apply (check all that apply): X Session Law 2006-246 Other: 4b Has the approved Stormwater Management Plan with proof of approval X No been attached? 5. DWQ 401 Unit Stormwater Review 5a Does the Stormwater Management Plan meet the appropriate requirements? X Yes 5b Have all of the 401 Unit submittal requirements been met? X Yes Page 8 of 10 PCN Form —Version 1.4 January 2009 F. Supplementary Information 1. Environmental Documentation (DWQ Requirement) 1a Does the project involve an expenditure of public (federal/state/local) funds or X Yes the use of public (federal/state) land? 1 b If you answered "yes" to the above, does the project require preparation of an environmental document pursuant to the requirements of the National or X No State (North Carolina) Environmental Policy Act (NEPA/SEPA)? 1c If you answered "yes" to the above, has the document review been finalized by the State Clearing House? (If so, attach a copy of the NEPA or SEPA final approval letter.) Yes No Comments: 2. Violations (DWQ Requirement) 2a Is the site in violation of DWQ Wetland Rules (15A NCAC 2H .0500), Isolated Wetland Rules (15A NCAC 2H .1300), DWQ Surface Water or Wetland X No Standards, or Riparian Buffer Rules (15A NCAC 2B .0200)? 2bls this an after-the-fact permit application? X No 2c If you answered "yes" to one or both of the above questions, provide an explanation of the violation(s): 3. Cumulative Impacts (DWQ Requirement) 3a Will this project (based on past and reasonably anticipated future impacts) result X No in additional development, which could impact nearby downstream water quality? 3b If you answered "yes" to the above, submit a qualitative or quantitative cumulative impact analysis in accordance with the most recent DWQ policy. If you answered "no," provide a short narrative description. The entire Mist Lake Expansion project is a single and complete project with appropriate land use control and stormwater measures in place for specific areas which require them. 4. Sewage Disposal (DWQ Requirement) 4a. Clearly detail the ultimate treatment methods and disposition (non -discharge or discharge) of wastewater generated from the proposed project, or available capacity of the subject facility. Waste water will be directed into an existing treatment facility operated by the City of Durham. Page 9 of 10 PCN Form — Version 1.4 January 2009 5. Endangered Species and Designated Critical Habitat (Corps Requirement) 5a Will this project occur in or near an area with federally protected species X Yes or habitat? X Yes 5b Have you checked with the USFWS concerning Endangered Species Act impacts? 5clf yes, indicate the USFWS Field Office you have contacted. Raleigh Field Office 5d What data sources did you use to determine whether your site would impact Endangered Species or Designated Critical Habitat? The USFWS web page http://www.fws.gov/nc-es/es/countyfr.htmi and the Natural Heritage Virtual Workroomhttp://nhpweb.enr.state.nc.us/nhis/public/gmap75_main.phtmI was accessed to determine if the project would impact Threatened or Endangered Species or Designated Critical habitat. Timmons Group conducted a Threatened and Endangered Species Assessment for the Mist Lake Facility Expansion project. There were no Federally Threatened or Endangered species observed during the field survey conducted during the week of July 10, 2017. Based on the field investigations conducted by the Timmons Group, a biological opinion of "No Effect" was rendered for the Michaux's sumac, and smooth coneflower. A Threatened or Endangered Species Assessment Initial Scoping letter was submitted to the USFWS on September 7, 2017. A response from USFWS is forth comina. 6. Essential Fish Habitat (Corps Requirement) 6a Will this project occur in or near an area designated as essential fish habitat? X No 6b What data sources did you use to determine whether your site would impact Essential Fish Habitat? The interactive map located at http://occan.fioridamarine.orge_coral/ims/viewcr.htm was utilized to determine if the project will impact Essential Fish Habitat and it was determined that it would not. 7. Historic or Prehistoric Cultural Resources (Corps Requirement) 7a Will this project occur in or near an area that the state, federal or tribal governments have designated as having historic or cultural preservation X No status (e.g., National Historic Trust designation or properties significant in North Carolina history and archaeology)? 7b What data sources did you use to determine whether your site would impact historic or archeological resources? A review of the list of properties and districts in the North Carolina in the National Registry of Historic Places (hhtp://www.hpo.ncdcr.gov/nrlist.htm) was conducted and a preliminary field assessment was conducted for the subject property. Based on the review and field assessment the proposed project will not occur in or near an area that has been designated as having historic or cultural preservation status by the state, federal, or tribal governments. 8. Flood Zone Designation (Corps Requirement) 8a Will this project occur in a FEMA -designated 100 -year floodplain? I X Yes 8b If yes, explain how project meets FEMA requirements: tic what source(s) did you use to maKe the floodplain determination-? The North Carolina Flood Insurance Rate Map 3720084200J (issued May 2, 2006) were reviewed and it was determined that there is a floodway and 100 -year floodplain area associated with Goose Creek. A Conditional Letter of Map Revision (CLOMR) is being prepared and will be submitted to the locality and state based on hydrologic and hydraulic analyses performed in accordance with standard engineering practices. It is anticipated that the proposed encroachments would not result in any increase in flood levels during the occurrence of the base flood discharge and the requirements will be met that are set forth by the City of Durham regulations. Applicant/Agent's Printed Name Applicant/Agent s Signature (Agent's signature is valid only if an authorization letter from the aoolicant is orovided.l Page 10 of 10 Xael 7 Date APPENDIX B SUPPORTING DOCUMENTS/PROPERTY OWNER & PARCEL BOUNDARIES MAP �0��•�• • a • TIMMONS GROUP YOUR VISION ACHIEVED THROUGH OURS, AGENT AUTHORIZATION and PROPERTY OWNER CERTIFICATION FORM All Blanks to be Filled in by Current Landowner The Department of the Amy US Amy Corps of Engineers Wilmington District PO Box 1890 Wilmington, NC 28402-1890 To Whom It May Concern: NCDENR- Division of Water Resources 401 & Buffer Permitting Unit 1650 Mail Service Center Raleigh, NC 27699-1650 I, the undersigned, current property owner designate and authorize representatives of Timmons Group, Inc., to act on my behalf as my agent in the processing of permit applications, to famish upon request supplemental information in support of applications, etc., from this day forward. This the /3 day of S'✓. N c , 20 P-7 (number) (Month) (Year) I, the undersigned, a duly authorized owner of record of the property/properties identified herein, do authorize representatives of the Wilmington District, U.S. Army Corps of Engineers (Corps) to enter upon the property herein described for the purpose of conducting on-site investigations and issuing a determination associated with Waters.of the U.S. subject to Federal jurisdiction under Section 404 of the Clean Water Act and/or Section 10 of the Rivers and Harbors Act of 1899. This notification supersedes any previous correspondence concerning the agent for this project. Project Name: Ks - L&K-- r- ,(_� l y EgPax,ou Location: /6w rH :T L4cE Da. I �ynANl, h. MG Property Owner's Name (Print): C-17. OF Dps,khn l7ErT eF LJ7"ru:_ MGT Property Owner's Signature: Property Owner's Mailing Address: / (-eo M aT / a ICE 711 _ Property Ovmer's Telephone:(919))560-y391 Fax Property Owner's Email co J 75 Q co 0 N N N co C 0 d 0 0- N N N r- rn M C) o co 1 \ 1 I I 1 ` 1 1-11 1-000, 2 O �oopp ooP ''/ C-) so 0o y ol,� c? , , -o �Z zoom �C�, T 2 0 Z02f� �j �o n� 7< pp o0 0� C) ' Z � 'off orn��-� =c` 0 O0\ 0 0 � 2G? pG c "-Q -7 2 1 I z O z < CL a X Q Wz J O (n (n < W W U i --a 2 �--� Q O 0 � � z 0 v J LL = W U W Q D 0 a J U) JOB NO. 39772.001 SHEET NO. 1 OF 1 0 c tn U C N d O tnm 3 m 0 0 a C CL T C a 0 0 m tn c co C CL c a a 3 cm O s V H Z L O 3 V � L U +j ui U) w m L Z O N LU _ 10 O CD 7 — O 4w _ O w E LU fl. w z O Q Q O O 47 DATE U)) Q > :Lj 08/22/2017 O (n DRAWN BY L. MAJOR • DESIGNED BY • BLAKE HALL • CHECKED BY • T. PREUNINGER • • SCALE 1 " = 150' z O z < CL a X Q Wz J O (n (n < W W U i --a 2 �--� Q O 0 � � z 0 v J LL = W U W Q D 0 a J U) JOB NO. 39772.001 SHEET NO. 1 OF 1 0 c tn U C N d O tnm 3 m 0 0 a C CL T C a 0 0 m tn c co C CL c a a 3 KC Wafer Resources ..Vaso .... 1PL WAloY July 19, 2017 City of Durham Property and Facility Management Atm; General Services Real Estate Division 101 City Hall Plaza Durham, NC 27701 ROY COOPER G—'o- MICHAEL S. REGAN ta,ym,y S. JAY ZIMMERMAN D11-1- Subject: 11-1 r Subject: Buffer Determination Letter NBRRO 417-192 Durham County Determination Type: Buffer Intermittent/Perennial ® Neuse (15A NCAC 2B.0233) StartC ❑ Tar -Pamlico (15A NCAC 26.0259) ® Intermittent/Perennial Determination (where local buffer DSGS To 0 ordinances apply) ❑ Jordan (15A NCAC 2B.0267) (governmental and/or interjunsdictional Thorn hout Property projects) X Project Name: Mist Lake Facility Expansion Address/Location: 2905 Meridian Parkway, Durham NC 27713 Streata(s): Determination Date: June 28, 2017 Staff: Jason Robinson Stream E/f/P* Not Subject Subject StartC StopC Boll Survey DSGS To 0 A P X Thorn hout Property X X B P X Throughout Property X X D P X Throu hoot Property X X E I X DWR Flag –36.022118 -78.861238 SureamA X H I X DWR Flag --36.020327 -78.859938 DWR Flag –36.020639 -78.860345 X Pond P X X X I E X X 'E/11P = Ephemera!/Intermittent/Perennial Division of Watc, Resources, Raleigh Regional Offico. Watel-Quality Opnnoions Section hu,. lmnalacdcncorghveb/wglaps 1628 Mail Service Carter. Raleigh, NC 27699-1628 Phone: (919) 791-4200 Location: 3800 Barrett Drivo, Ralcigh, NC 27609 Fax: (919) 788-7159 Mist Lake Facility Expansion Durham County July 19, 2017 Page 2 of 2 Explanation: The stream(s) listed above has been located on the most recent published NRCS Soil Survey of Durham County, North Carolina and/or the most recent copy of the USGS Topographic map at a 1:24,000 scale. Each stream that is checked "Not Subject" has been determined to not be at least intermittent or is not present. Streams that are checked "Subject" have been located on the property and possess characteristics that qualify it to be at least an intermittent stream. There may be other streams located on the property that do not show up on the maps referenced above but may be considered jurisdictional according to the US Army Corps of Engineers. This on-site determination shall expire five (5) years from the date of this letter. Landowners or affected parties that dispute a determination made by the DWR may request a determination by the Director. An appeal request must be made within sixty (60) days of date of this letter. A request for a determination by the Director shall be referred to the Director in writing. If sending via US Postal Service: c/o Karen Higgins; DWR — 401 & Buffer Permitting Unit; 1617 Mail Service Center; Raleigh, NC 27699-1617. If sending via delivery service (UPS, FedEx, etc.); Karen Higgins; DWR — 401 & Buffer Permitting Unit; 512 N. Salisbury Street; Raleigh, NC 27604. This determination is final and binding unless, as detailed above, unless an appeal is requested within sixty (60) days. This project may require a Section 404/401 Permit for the proposed activity. Any inquiries should be directed to the US Army Corp of Engineers (Raleigh Regulatory Field Office) at (919)-554-4884. If you have questions regarding this determination, please feel Gee to contact Jason Robinson at (919) 791-4200. �y, D.ySm� h Supervise"� Quality Regional Operations Center cc: RED DWR File Copy Kelly Roth, McAdams Company: 2905 Meridian Parkway, Durham, NC 27713 Legend; srn¢„` Map provided by NCDEQ DivisionofWaterRe- f;y?'p -Approximate Site O boundary: boundar : Locations are approxi - 'W.,...s'' mate and are provided for -Approximate StarUStop * reference only 17-192 Mist Lake Facility Expansion Map provided by NCDEQ Legend: Division ofwatar Re- sources -Approximate Site O Locations are approxi- bounday: mate and are provided for reference only:: APPENDIX C MAPS 7A t OIL ., 40 - .1•.' •-X�• ..'� . �j�, - � ��� , � •l4 y - ,•�y[Y�� •Yt � .rq: i � n �-�'f r� � 1 + r� `' I � v R .tip =• 9 �+y Y • ^'�� • �' , �`,-• . ' fin' +' �'{ n' t rll,••.� .-� It Fi,,�• s•� . }: ,.vi y-�•..• .'�. _ / '-. '-. -� �� .iii �'" ^tL1 j•�• '.h .-.. .q.. '•Iys 1 • '' A ^P'sy'•--1 < <IJ n� � y I 0 Legend `. Project Study Limits L cli cli AE: 1 % Annual Chance Flood Hazard 7w" X: <1 % Annual Chance Flood Hazard 0 200 400 800 Feet +" 6 ow 'o�� 0 AV� DATE j .d. a 07/25/2017 N m r t6 DRAWN BY t L. MAJOR 3 DESIGNED BY n L. MAJOR a CHECKED BY a . . T PREUNINGER o SCALE i 1=400' 3 V/ o Z zLU a J Z& oo � AV� m r t6 Z0 V/ o Z zLU a J Z& oo � X N2 0 A' LL! p o = O O E @_ a0 O J Zz J LL V Q Z H Q Z W y Z w 0 a LL p LL N W Y a w ~ 0 o 0 a= J D2§ D m N //� C9 LL > 0y X = N O �/� S :E 2 N N U N O E 'a _ U @ 06 n= 0a m n U � O � N O � U n2 NUMBER y 0 39722.001 m o SHEET NO. y N 1 OF 1 Resource Confirmation 111, fill ' Resource Identification PFO PSS (ac) (ac) PEM POW R3 (ac) (ac) (If) R4 Ditch (It) (If) Description Notes` Stream A 2,907 �'i i111�11 ��II1000, I, II NT/NV Wetland A 0.27 L. MAJOR X111 IIII \fill 1 \111 \ \ \♦, i NT/V Stream B 1,420 NT/NV Wetland B 0.38 / 1 = 150 NT/V Wetland C 0.19 NT/V Stream D 640 NT/NV Wetland D 0.57 NT/V Stream E 206 NT/NV Wetland E 7.62 NT/V Stream F 238 NT/NV Wetland F 0.78 NT/V Stream G 37 NT/NV Wetland G 0.41 NT/V Stream H 96 NT/NV Wetland H 1.00 NT/V Pond P 2.87 NT/V Pond X 0.12 NT/V Stream Y 23 NT/NV Stream Z 77 NT/NV Total 11.22 0.00 0.00 2.99 4,967 677 0 Total Wetland Area =1 14.21 ac Total Stream Length =1 5,644 If * T=Tidal; NT=Non-tidal; V=Vegetated; NV=Non-Vegetated; PFO=Palustrine Forested Wetland; PSS=Palustrine Scrub -Shrub Wetland; PEM=Palustrine Emergent Wetland; POW= Palustrine Open Water; EIW= Estuarine Intertidal Wetlands; R3= Upper Perennial Streams; R4=Intermittent Streams Legend Project Study Limits Stream Top of Bank Intermittent Stream (R4) Perennial Stream (R3) Palustrine Forested (PFO) Wetlands Palustrine Open Water (POW) Wetlands ' Neuse Riparian Buffer 1 ' NOTES: 1. WATERS OF THE U.S. WITHIN THE PROJECT STUDY LIMITS WERE DELINEATED BY MCADAMS. 2. WATERS OF THE U.S. HAVE BEEN CONFIRMED BY THE U.S. ARMY CORPS OF ENGINEERS ON SEPTEMBER 9, 2017. 3. PROJECT STUDY LIMITS ARE APPROXIMATE. 4. TOPOGRAPHY BASED ON USGS LIDAR DATA. 5. NC DWR NEUSE RIVER BUFFER CONFIRMATION (NBRRO # 17-192, JULY 19, 2017). 0 150 300 600 Feet II I •'' I''ll' I I 1 ♦•/ ■SII I II ♦ ♦y , I� I Ih IA I , I Ilk ♦ ` 1 SII �1 \ , \ 111 ■ \ . t 10 OP III o \ ♦ 1'I .' '• ` / /�` j it �` - �• � ` ' I /. 1 ♦. ♦� 1 �, , / �_ moi; /• / ,' / /' _ _ I, �\`� /"//, 11 \ _— c- � � •• --� �! if t000 ` ^\ / f\`\\' /' /—r^ / ,' /' ,' , ^_'^\ \ II — iii i,'�'/ 11 , �� \` •• '\ \,, _.ZC �� ♦1 ,1 1 I / '� © �� 1 ♦!^ \ `\ \ ' / ,' — — — — � i, ', ' ' � � — \ III jl ,,'' ` \ 1 I 11 ♦ \� \O\ \` .-- \ ,''/ �--- '/,;_� __'�'-\`,t 1111,111",1 \\\ , 1 �� 1� 1 ``�`\ —__ �\\ `' I , �,,' �'-- '' ''''//'--' /1 _— \1,•\'1111 ,III 1'�I \\\\ , 1 1 , \\ . �I I If I I 1 1 \ 1 , , / , /i \ \ \ \ \ \ \ \ \ 1 I Q 1, 11 1111 I,I'"l'I,%1' \\p11 _ ',\11 ,\ 11, 111\ , , , \ \\\ `\ \\\`\ ` \\♦\ \\`\��_ ( \ O \ \ l 1 \ \\\•,, , 1111 111; /,11,1 ,;,��' / `\ "`\ \ \N6n\-Jurisdictional _ ' \ \ %♦ Pond / I I \ \ \;\, \\\' ` ■ __- I I I I //,1 till ll,l,//It fill fill 'if V'll/\\` ' ___:\ IIII' / ,\ \ I ,I' I III/ J\ \ / \ \ \ \ \\\\ \ , II \\\\\\\ ■ 1 I III I I 1 I\ \ \\ ` \ \ \ \ \ \ I , I , \ \\ \ \\\ \\\ I III'll 1'1,11 \\ \ yam/ ` 1 t ` \ \ \\\ \` 1 1 i''' '\ \\\\ \;\\\\\�\\\\ \\ I , I I I , / I III \ \ \ \ \ \ \ \ \ ,ill 1 111 1I 'f / fill , I �`\\\. ,\\�\\�\\\\ \'\\11 \\ �,\ \ \ \ 1\ `\ ` ' II =\ e\\. ` ` \ \ \ ,•\,Illi\ !` \\\\♦\` \ ` I \`\1111'' ''1/ / �i♦♦ ' it I \\`\ —It 111 I1\\`\` 11 I /, ' � �0 it�. ,\\\ \\r\ 1\\\ \, — \\ , \ \ I . —\\1\• \#. 111 \\\\ 11 /' ' / �_�-- �vl �Ir y\\\ \\,\ \\ �\ \ \e^ � \ \ /, �%i i�—_♦/ ,11' 1 o >`,` "\\`\\` `\\` \\ \ ' .♦ ' ' 1„ , Il I, 1111 ,111 fill I / ll 1111 / 1 1 , , 1 / / l l / / / / l / ♦ 111, fill ' 09/26/2017 l / /" //"I / / 1111,1'/ Ill/ 1/�,' ,'I � l l /', 1111 11 /11111 ' l � \ ; ♦ / I 11/1 IIII // '/ I I'/ ' ' l l if[',[ fill 111 11 / / // , / ♦ \ L. MAJOR �'i i111�11 ��II1000, I, II DESIGNED BY ,Irl I III III II I, I \ , 1 , \ 1♦I L. MAJOR X111 IIII \fill 1 \111 \ \ \♦, i CHECKED BY G. BUCHHOLZ SCALE `\\`\,I / 1 = 150 \`1\ \,1, 1\11 \\ 11 \\ . �I I If I I 1 1 \ 1 , , / , /i \ \ \ \ \ \ \ \ \ 1 I Q 1, 11 1111 I,I'"l'I,%1' \\p11 _ ',\11 ,\ 11, 111\ , , , \ \\\ `\ \\\`\ ` \\♦\ \\`\��_ ( \ O \ \ l 1 \ \\\•,, , 1111 111; /,11,1 ,;,��' / `\ "`\ \ \N6n\-Jurisdictional _ ' \ \ %♦ Pond / I I \ \ \;\, \\\' ` ■ __- I I I I //,1 till ll,l,//It fill fill 'if V'll/\\` ' ___:\ IIII' / ,\ \ I ,I' I III/ J\ \ / \ \ \ \ \\\\ \ , II \\\\\\\ ■ 1 I III I I 1 I\ \ \\ ` \ \ \ \ \ \ I , I , \ \\ \ \\\ \\\ I III'll 1'1,11 \\ \ yam/ ` 1 t ` \ \ \\\ \` 1 1 i''' '\ \\\\ \;\\\\\�\\\\ \\ I , I I I , / I III \ \ \ \ \ \ \ \ \ ,ill 1 111 1I 'f / fill , I �`\\\. ,\\�\\�\\\\ \'\\11 \\ �,\ \ \ \ 1\ `\ ` ' II =\ e\\. ` ` \ \ \ ,•\,Illi\ !` \\\\♦\` \ ` I \`\1111'' ''1/ / �i♦♦ ' it I \\`\ —It 111 I1\\`\` 11 I /, ' � �0 it�. ,\\\ \\r\ 1\\\ \, — \\ , \ \ I . —\\1\• \#. 111 \\\\ 11 /' ' / �_�-- �vl �Ir y\\\ \\,\ \\ �\ \ \e^ � \ \ /, �%i i�—_♦/ ,11' 1 o >`,` "\\`\\` `\\` \\ \ ' .♦ ' ' 1„ , Il I, 1111 ,111 fill I / ll 1111 / 1 1 , , 1 / / l l / / / / l / ♦ 111, fill ' 09/26/2017 l / /" //"I / / 1111,1'/ Ill/ 1/�,' ,'I � l l /', 1111 11 /11111 ' l � \ ; ♦ / I 11/1 IIII // '/ I I'/ ' ' l l if[',[ fill 111 11 / / // , / ♦ \ L. MAJOR �'i i111�11 ��II1000, I, II DESIGNED BY ,Irl I III III II I, I \ , 1 , \ 1♦I L. MAJOR X111 IIII \fill 1 \111 \ \ \♦, i CHECKED BY G. BUCHHOLZ SCALE IW AIYi Lo E N U M N IZ W Q W U D W LL LL 0 o O W W co � 0_ Q (a) Lo Ur Q' (j O Z N X �O Y� 0 CL O (n i O H ao � N m � oW f" i W CL O Z 0 z .4 I J 0 w Q V 0 z I z D 0 V x Q N: li D 0 a LU LL LLn CID W N LU W Z Z rQ LU LL V/ 0 LUr Q M W Ce D H LL JOB NO. 39772.001 SHEET NO. 1 OF 1 DATE 09/26/2017 to DRAWN BY L. MAJOR DESIGNED BY L. MAJOR CHECKED BY G. BUCHHOLZ SCALE / 1 = 150 Z 0 z .4 I J 0 w Q V 0 z I z D 0 V x Q N: li D 0 a LU LL LLn CID W N LU W Z Z rQ LU LL V/ 0 LUr Q M W Ce D H LL JOB NO. 39772.001 SHEET NO. 1 OF 1 Legend Impacts Table r Riparian Buffer (sq. ft) Stream (If) Impact ID Impact Impact Stream Stream Temporary Permanent Temporary Permanent Permanent Name Type - No Loss Zone 1 1 Zone 2 Zone 7 1 Zone 2 131-Z1 13,083 Stream Top of Bank ---------' 131-Z2 11,852 o I 132-Z1 3,017 B2 -Z2 4,257 Neuse Riparian Buffer Zone 2 Impact S1 vo Palustrine Forested (PFO) Wetlands 96 Stream H INT Total 0 sq ft 0 sq ft 16,100 sq ft 16,109 sq ft 0 If 96 If 0 If 0.00 ac 0.00 ac 0.37 ac 0.37 ac Legend NOTES: 1. WATERS OF THE U.S. WITHIN THE PROJECT STUDY LIMITS WERE DELINEATED BY MCADAMS. 2. WATERS OF THE U.S. HAVE BEEN CONFIRMED BY THE U.S. ARMY CORPS OF ENGINEERS ON SEPTEMBER 9, 2017. 3. PROJECT STUDY LIMITS ARE APPROXIMATE. 4. TOPOGRAPHY BASED ON USGS LIDAR DATA. 5. NC DWR NEUSE RIVER BUFFER CONFIRMATION (NBRRO # 17-192, JULY 19, 2017). NUNN- e. .• • • � .. WFUMM/ � y, '\�� IIS_ �� .1•i3■ VIA�.e OP VW, 12-Z2 �� � � - �- ice« � %r�./ . � i�;•, ��I'♦ �(�• : �� r� al�ni,�n��li�/dam � 1 �%;��/��; 9 w 001 INN' 14% 11 \\ R` Mai dolt•. ,/ � � �- V .�:-. yid ki'`ifj�' i r.�.3�• ai �/� � ,r--•�.," 1V Dyw. MR e an WWI gi 0 AWS / I i i 2a I I E -Club -Blvd I I I � Project Study Limits r Lo E Limits of Disturbance - 21 Acres Riparian Buffer Zone 1 Impact Riparian Buffer Zone 2 Impact _ Permanent Stream Impact I I Intermittent Stream (R4) Stream Top of Bank ---------' Retaining Wall � o I Neuse Riparian Buffer `______ Neuse Riparian Buffer Zone 1 Impact Neuse Riparian Buffer Zone 2 Impact Perennial Stream (R3) vo Palustrine Forested (PFO) Wetlands I` x Palustrine Open Water (POW) Wetlands NOTES: 1. WATERS OF THE U.S. WITHIN THE PROJECT STUDY LIMITS WERE DELINEATED BY MCADAMS. 2. WATERS OF THE U.S. HAVE BEEN CONFIRMED BY THE U.S. ARMY CORPS OF ENGINEERS ON SEPTEMBER 9, 2017. 3. PROJECT STUDY LIMITS ARE APPROXIMATE. 4. TOPOGRAPHY BASED ON USGS LIDAR DATA. 5. NC DWR NEUSE RIVER BUFFER CONFIRMATION (NBRRO # 17-192, JULY 19, 2017). NUNN- e. .• • • � .. WFUMM/ � y, '\�� IIS_ �� .1•i3■ VIA�.e OP VW, 12-Z2 �� � � - �- ice« � %r�./ . � i�;•, ��I'♦ �(�• : �� r� al�ni,�n��li�/dam � 1 �%;��/��; 9 w 001 INN' 14% 11 \\ R` Mai dolt•. ,/ � � �- V .�:-. yid ki'`ifj�' i r.�.3�• ai �/� � ,r--•�.," 1V Dyw. MR e an WWI gi 0 AWS / I i i 2a I I E -Club -Blvd I I I � -:� Chain Linl Buffer Encr( IArez i I+ + I I 1 f \ i + % A— : 4,- O � � 0 LU I I Lo E _ Q I I N z o O I` x I I i I I---------- I 2 a O 07/25/2017 O *' j I o� > x I I I I I Q w W U CP w C.0 I_---------- ' I < p o ,- z O p 0 2-' ww M� o I x O I --------- U olf H� p c- I I z0 �� V oC -j 3: of Q U- --- U)x LU Ir I <o o 0 LID x I I 2 m p +3+ 0 -------------- I ` — — — I i Z N H x m°CC) N w I I I I i I ✓ O J � -:� Chain Linl Buffer Encr( IArez i I+ + I I 1 f \ i + % A— : 4,- O � � 0 LU CnDRAWN BY L. MAJOR DESIGNED BY L BLAKE HALL CHECKED BY G. BUCHHOLZ SCALE -Frinto(v,P\ 1" = 150' i Q V Z a 0 W znpp U.aLL M J CO IL O Ce XaLU W V oG W � O z 2P a a V u� W LL V LU LL Q O ZLUcn OC � LU � o a V H LL JOB NO. 39772.001 SHEET NO. 1 OF 4 _ Q o z o O > > DATE 07/25/2017 O *' CnDRAWN BY L. MAJOR DESIGNED BY L BLAKE HALL CHECKED BY G. BUCHHOLZ SCALE -Frinto(v,P\ 1" = 150' i Q V Z a 0 W znpp U.aLL M J CO IL O Ce XaLU W V oG W � O z 2P a a V u� W LL V LU LL Q O ZLUcn OC � LU � o a V H LL JOB NO. 39772.001 SHEET NO. 1 OF 4 Path: R:\805\39722.001 -Mist Lake\GIS\wetland impacts\MistLake-WTIM_Notes.mxd Legend C: jProject Study Limits � j3 Limits of Disturbance - 21 Acres © Riparian Buffer Zone 1 Impact LV Riparian Buffer Zone 2 Impact = Permanent Stream Impact Intermittent Stream (R4) Stream Top of Bank --- Retaining Wall L _ ; Neuse Riparian Buffer ® Neuse Riparian Buffer Zone 1 Impact ® Neuse Riparian Buffer Zone 2 Impact Perennial Stream (R3) Palustrine Forested (PFO) Wetlands D Palustrine Open Water (POW) Wetlands NOTES: 1. WATERS OF THE U.S. WITHIN THE PROJECT STUDY LIMITS WERE DELINEATED BY MCADAMS. 2. WATERS OF THE U.S. HAVE BEEN CONFIRMED BY THE U.S. ARMY CORPS OF ENGINEERS ON SEPTEMBER 9, 2017. 3. PROJECT STUDY LIMITS ARE APPROXIMATE. 4. TOPOGRAPHY BASED ON USGS LIDAR DATA. 5. NC DWR NEUSE RIVER BUFFER CONFIRMATION (NBRRO # 17-192, JULY 19, 2017). TIMMONS GROUP THIS DRAWING PREPARED AT THE ■ w+400� �yRASImNMONeI�O7N�D11oX Olgd CORPORATE OFFICE f0018oultlers Parkway, Suits 3001 RiMmonq VA 23225 � � � TEL 800.200.8500 FAX 800.580.1808 www.timmons.com Site Development I Residential I Infrastructure I Technology I Environmental om �o N 3 o z Impacts Table v D m Riparian Buffer (sq. ft) m i m Stream (If) o y o m Impact ID Impact Impact Stream Stream Temporary Permanent Zone 1 Zone 2 Zone 1 Zone 2 Permanent Temporary Permanent Permanent No Loss Name Type B1 -Z1 13,083 B1-72 11,852 B2 -Z1 3,017 132-72 4,257 S1 96 Stream H INT Total 0 sq ft 0 sq ft 16,100 sq ft 0.00 ac 0.00 ac 0.37 ac 16,109 sq ft 0.37 ac 0 If 96 If 0 If TIMMONS GROUP THIS DRAWING PREPARED AT THE ■ w+400� �yRASImNMONeI�O7N�D11oX Olgd CORPORATE OFFICE f0018oultlers Parkway, Suits 3001 RiMmonq VA 23225 � � � TEL 800.200.8500 FAX 800.580.1808 www.timmons.com Site Development I Residential I Infrastructure I Technology I Environmental om �o N 3 o z MIST LAKE FACILITIES EXPANSION DURHAM COUNTY, NORTH CAROLINA v D m = m z o o m i m o n z o y o m DATE REVISION DESCRIPTION WATERS OF THE U.S. AND NEUSE RIVER BUFFER IMPACT MAP - NOTES These plans and associated documents are the exclusive property of TIMMONS GROUP and may not be reproduced in whole or in partand shall not be used for any purpose whatsoever, inclusive, but not limited to construction, bidding, and/or construction staking without the express written consent of TIMMONS GROUP. B1 -Z1 OJOLIMCINIO B1 -Z2 B2 -Z2 B2 -Z1 B2 -Z2 OJOLMIMNIS APPENDIX D PROPOSED LAYOUT & PRELIMINARY STORMWATER PLANS L K DURHAM DEPARTMENT OF WATER MANAGEMENT DURHAM WATER - MIST LAKE 1600 MIST LAKE DRIVE DURHAM, NORTH CAROLINA SITE DATA G F E x C 0 m 0 U A m 9 0 1 Sheet List Table PROJECT TEAM_ 00-0000 J Developer OVERALL PLAN Architect PHASING PLAN DURHAM DEPARTMENT OF WATER MANAGEMENT MAINTENANCE DESIGN GROUP 00-CO04 1600 MIST LAKE DRIVE 00-S1-5 201 NORTH CHARLES STREET, SUITE 1640 00-S2-5 DURHAM, NC 27704 00-S3-5 BALTIMORE, MD 21201 00-S4-5 919-560-4381 00-S5-5 (443)524-4382 00-C200 Architect 00-C201 DEMOLITION PLAN 00-C202 RNL DESIGN Civil Engineer Landscape Architect 00-C301 SITE LAYOUT 1600 WILSON BLVD SUITE 360 TIMMONS GROUP SUSAN HATCHELL LANDSCAPE ARCHITECTURE, PLLC UTILITY PLAN - PHASE 1 ARLINGTON, VA 5410 TRINITY ROAD 711 W NORTH STREET UTILITY PLAN - PHASE 2 (571)290-7679 RALEIGH, NC 27607 RALEIGH, NC 27603 GRADING PLAN 00-C402 (919)866-4505 (919)838-9600 H APPROVALS STORM DETAILS 00-0502 G F E x C 0 m 0 U A m 9 0 1 Sheet List Table Sheet Number Sheet Title 00-0000 COVER 00-0001 OVERALL PLAN 00-CO02 PHASING PLAN 00-CO03 PHASING PLAN 00-CO04 STORMWATER COMPLIANCE 00-S1-5 EXISTING CONDITIONS 00-S2-5 EXISTING CONDITIONS 00-S3-5 EXISTING CONDITIONS 00-S4-5 EXISTING CONDITIONS 00-S5-5 EXISTING CONDITIONS 00-C200 DEMOLITION PLAN 00-C201 DEMOLITION PLAN 00-C202 DEMOLITION PLAN 00-C300 SITE LAYOUT 00-C301 SITE LAYOUT 00-C302 SITE LAYOUT 00-C303 UTILITY PLAN - PHASE 1 00-C304 UTILITY PLAN - PHASE 2 00-C305 UTILITY PLAN - PHASE 2 00-C400 GRADING PLAN 00-C401 GRADING PLAN 00-C402 GRADING PLAN 00-0500 SITE DETAILS 00-0501 STORM DETAILS 00-0502 UTILITY DETAILS 00-0503 UTILITY DETAILS 00-0504 EROSION CONTROL DETAILS 00-L100 LANDSCAPE PLAN 00-L101 LANDSCAPE PLAN 00-1-102 LANDSCAPE PLAN 01-A301 OVERALL BUILDING SECTIONS 01-A901 3D BUILDING MODEL EA101 I LIGHTING PLAN EA102 I LIGHTING PLAN 2 3 PROJECT: DURHAM DEPARTMENT OF WATER MANAGEMENT, DURHAM WATER- MIST LAKE CASE #: D1700249 DEVELOPER: DURHAM DEPARTMENT OF WATER MANAGEMENT OWNER CONTACT: DON GREELEY DURHAM DEPARTMENT OF WATER MANAGEMENT 101 CITY HALL PLAZA DURHAM, NC 27701 PHONE: 919-560-4381 FAX: 919-560-4479 DESIGNER CONTACT: TIMMONS GROUP BLAKE HALL, P.E. 5410 TRINITY ROAD, SUITE 102 RALEIGH, NC 27607 PHONE: 919-866-4933 BLAKE.HALL@TIMMONS.COM PROJECT ADDRESS: 1600 MIST LAKE DRIVE DURHAM, NC 27704 PIN: 0842-09-16-8832, 0842-09-16-0876, 0842-09-16-5055, 0842-09-16-3052, 0842-09-18-5025 PARCEL ID #: 160519,160516,160518,160584,160585 REFERENCE: DB 1630 PG 228, DB 7997 PG 68, DB 159 PG 35, DB 8055 PG 544, DB 8006 PG 182 ZONING: IL DEVELOPMENTTIER: SUBURBAN JURISDICTION: CITY OVERLAY: MAJOR TRANSPORTATION CORRIDOR FALLS/JORDAN-TYPE B BUFFER (F/J-B) EXISTING USE: GOVERNMENTAL USE/LIGHT INDUSTRIAL PROPOSED USE: GOVERNMENTAL USE/LIGHT INDUSTRIAL SETBACKS: STREET YARD - 50', SIDE YARD 25' EACH SIDE REAR YARD - 25' WATERSHED: FALLS LAKE WATERSHED RIVER BASIN: NEUSE RIVER BASIN TRACT AREA: 55.29 ACRES (2,408,520 SF) DISTURBED AREA: 21 ACRES (37.98% OF TOTAL SITE) STORMWATER MANAGEMENT: A PROPOSED CONSTRUCTED UNDERGROUND DETENTION. NO STRUCTURES (BUSINESSES, HOMES, CULVERTS, STREETS, ETC.) BETWEEN THE POINT OF DISCHARGE AND THE ANALYSIS POINT WILL BE ADVERSELY IMPACTED BY THE INCREASE IN SITE RUNOFF FOR STORM EVENTS UP TO THE 100 -YR. EVENT. OPEN SPACE & TREE COVERAGE REQUIREMENTS: 10% OF GROSS AREA REQUIRED. GROSS AREA: 55.29 ACRES REQUIRED OPEN SPACE & TREE COVERAGE: 5.53 ACRES PROVIDED OPEN SPACE AND TREE COVERAGE: 11.77 ACRES VEHICULAR SURFACE AREA: EXISTING = 208,028 SF PROPOSED = 654,879 SF SITE IMPERVIOUS SURFACE AREA: PRE -DEVELOPMENT IMPERVIOUS AREA: 6.66 ACRES / 12.04 - EX ROOF: 82,041 SF / 1.88 ACRES - EX PARKING LOT: 208,028 SF / 4.78 ACRES POST -DEVELOPMENT IMPERVIOUS AREA: 19.12 ACRES / 34.58 - ROOF 177,988 SF / 4.09 ACRES - PARKING LOT 654,879 SF / 15.03 ACRES DISTURBED AREA: 914,760 SF / 21 ACRES PARKING SUMMARY - VEHICLES REQUIRED PARKING: - GOVERNMENTAL USE (OFFICE) 1 SPACE PER 300 SF PLUS 1 PER 3 EMPLOYEES = (119000/300) + (400/3) = 530 SPACES REQUIRED PARKING: - LIGHT INDUSTRIAL USE (WAREHOUSE) 1 SPACE PER 1,000 SF = (60,000/1,000) = 60 SPACES PARKING PROVIDED: 410 SPACES PARKING SUMMARY - BICYCLES REQUIRED PARKING: - GOVERNMENTAL USE (OFFICE) 1 SPACE PER 3,000 SF PLUS 1 PER 30 EMPLOYEES - (119,000/3,000) + (400/30) - 53 SPACES REQUIRED PARKING: - LIGHT INDUSTRIAL USE WAREHOUSE 1 SPACE PER 5,000 SF Q (WAREHOUSE) = (60,000/5,000) = 12 SPACES BICYCLE PARKING SPACES PROVIDED: 108 FLOODPLAIN DATA SITE DRAINS TO GOOSE CREEK FEMA PANEL #:0842 MAP # 3720084200K THIS SITE IS IN SPECIAL FLOOD HAZARD AREAS AND HAS FUTURE FLOODPLAIN CONDITIONS HAZARD AREAS, AS SHOWN ON FIRM PANEL 0842 DATED MAY 2, 2006. SPECIAL CONDITIONS OF APPROVAL 1. TREE PROTECTION FENCING SHALL BE INSPECTED PRIOR TO START OF CONSTRUCTION. CONTACT CLAY SHEPHERD AT 919-560-4137 EXT. 28240 TO SCHEDULE AN INSPECTION. I\- L ulalrl 01. 1. -.'J li ' Su 4 11da � �' B" 1 i of Iv I r� .'P +ivy ' IS l :� i B --Y11 Aw i F'' I r 9 �li Sl TE : . /11 r 54 I . Zr 4 A I >s L '': IE fianlriy❑ns!1 t F�cF I R+# •, �f.-1 K - I I 11 . �. P' .� t-. iii + I'll. '" I I �. ' � La 3 I pve r? ti�� r = x e .. �i , 12 � � . ---, - , / <�� .L �r• ,. . .. V "...• I C1�`" .. •.0 .r Z �.[3Eef St • . Ems::..- f....: i. n , g� 7' - .....11, I ,iii , M 6 ' a �I AN " ., .:, Y . J JLnlWrer S1 vl ❑+� o -.d i' d 4 i ti. J' ..1t. L S C '�y IIIF ,. � -A C 1' S a a �Ynt1-„�..--i ---- .. - ;ab c iJ 2!1 4 1 5 1 6 1 7 9 10 DURHAM GENERAL STANDARD NOTES 1. FOR SITES CONTAINING FLOODPLAIN: ALL DEVELOPMENT WITHIN THE FLOODWAY OR NON -ENCROACHMENT AREA OR FLOODWAY FRINGE AND NON -ENCROACHMENT AREA FRINGE, INCLUDING FILL, NEW CONSTRUCTION, SUBSTANTIAL IMPROVEMENTS, MANUFACTURED HOUSING STORAGE OF MATERIALS AND STORAGE OF TOXIC OR FLAMMABLE SUBSTANCES, IS PROHIBITED EXCEPT AS PROVIDED BY APPLICABLE FLOOD HAZARD REGULATIONS OF UDO SECTION 3.22 AND 8.4. 1.1. FLOODPLAIN ELEVATION(S) 1.2. FLOODPLAIN ZONE 1.3. FEMA MAP NUMBER 1.4. FEMA MAP DATE FOR SITES WITHOUT FLOODPLAIN: THIS SITE IS NOT IN ANY SPECIAL FLOOD HAZARD AREAS OR FUTURE CONDITIONS FLOOD HAZARD AREAS, AS SHOWN ON FIRM PANEL DATED TADD CORRECT FIRM PANEL REFERENCE AND DATE] 2. NCDWQ BUFFER AUTHORIZATION NOTE: BUFFER AUTHORIZATION BY THE NORTH CAROLINA DIVISION OF WATER QUALITY (NCDWQ) IS REQUIRED PRIOR TO CONSTRUCTION DRAWING APPROVAL. SITE PLAN CHANGES OCCURRING AS A RESULT OF ALTERATIONS NEEDED TO RECEIVE BUFFER AUTHORIZATION MAY RESULT IN THE NEED FOR A SITE PLAN AMENDMENT OR A NEW SITE PLAN BASED ON THE SCOPE OF THE REQUIRED CHANGES. IF A SITE PLAN AMENDMENT OR NEW SITE PLAN IS REQUIRED IT MUST BE APPROVED PRIOR TO CONSTRUCTION DRAWING APPROVAL. CONTACT THE DURHAM CITY -COUNTY PLANNING DEPARTMENT AT 919-560-4137 TO DETERMINE IF A SITE PLAN AMENDMENT OR A NEW SITE PLAN WILL BE REQUIRED. 3. STREAM BUFFERS. FOOT WIDE UNDISTURBED STREAM BUFFER, MEASURED FROM TOP OF BANK, EACH SIDE OF STREAM. NO CLEARING OR GRADING OTHER THAN SELECTIVE THINNING AND ORDINARY MAINTENANCE OF EXISTING VEGETATION PERMITTED, EXCEPT IN ACCORDANCE WITH 15A NCAC 028.233 (6) VEGETATION MANAGEMENT° NO STRUCTURES OR FEATURES REQUIRING GRADING OR CONSTRUCTION MAY BE BUILT WITHIN THE 10 FOOT STREAM BUFFER SETBACK. ANY USE ALLOWED BY SECTION 8.5.5 OF THE UDO SHALL BE DESIGNED AND CONSTRUCTED TO MINIMIZE THE AMOUNT OF INTRUSION INTO THE STREAM BUFFER AND TO MINIMIZE CLEARING, GRADING, EROSION AND WATER QUALITY DEGRADATION. (UDO SECTION 8.5). 4. FOR SITES CONTAINING WETLANDS. STATE AND FEDERAL PERMIT AUTHORIZATION MAY BE REQUIRED FROM THE NC DENR, NC DWQ, AND THE U.S. ARMY CORPS OF ENGINEERS PRIOR TO THE COMMENCEMENT OF ANY LAND DISTURBING ACTIVITIES IN OR NEAR A LAKE, STREAM, CREEK, TRIBUTARY, OR ANY UNNAMED BODY OF WATER AND ITS ADJACENT WETLANDS (UDO SECTION 8.9) 5. WETLAND BUFFER NOTE: FOOT WIDE WETLAND BUFFER TO REMAIN IN NATURAL, UNDISTURBED VEGETATION. WETLAND BUFFERS MAY BE USED FOR PASSIVE RECREATIONAL ACTIVITIES, SUCH AS WALKING AND BICYCLING TRAILS, PROVIDED THAT SERVICE FACILITIES FOR SUCH ACTIVITIES, INCLUDING BUT NOT LIMITED TO PARKING, PICNICKING AND SANITARY FACILITIES, ARE LOCATED OUTSIDE OF THE WETLAND BUFFER. ANY USE ALLOWED BY THIS SECTION SHALL BE DESIGNED AND CONSTRUCTED TO MINIMIZE THE AMOUNT OF INTRUSION INTO THE WETLAND BUFFER AND TO MINIMIZE CLEARING, GRADING, EROSION AND WATER QUALITY DEGRADATION. (UDO SECTIONS 8.9) 6. FOR RESIDENTIAL PROJECTS APPROVED FOR PAYMENT IN LIEU OF OPEN SPACE DEDICATION. PAYMENT IN LIEU OF OPEN SPACE DEDICATION TO BE MADE PRIOR TO THE APPROVAL OF ANY FINAL PLATS PER UDO SECTION 7.2. OR SECTION 12.5. Z FOR PROJECTS WITH GREENWAYS: ON SITE PLANS. GREENWAY PLAT SHALL BE RECORDED, SHOWING METES AND BOUNDS FOR THE GREENWAY, AND EVIDENCE OF RECORDATION WITH BOOK AND PAGE NUMBER PROVIDED TO THE PARKS AND RECREATION DEPARTMENT, AT TIME OF FIRST FINAL PLAT APPROVAL OR PRIOR TO ISSUANCE OF A BUILDING PERMIT, WHICHEVER COMES FIRST. ON PRELIMINARY PLATS. GREENWAY PLAT SHALL BE RECORDED, SHOWING METES AND BOUNDS FOR THE GREENWAY, AND EVIDENCE OF RECORDATION WITH BOOK AND PAGE NUMBER PROVIDED TO THE PARKS AND RECREATION DEPARTMENT, AT TIME OF FIRST FINAL PLAT APPROVAL ON FINAL PLATS (CITY): GREENWAY EASEMENT DEDICATED TO THE CITY OF DURHAM ACCORDING TO THE TERMS STATED IN REAL ESTATE BOOK 1503, PAGES 898-899. NO BUILDING OR LAND DISTURBANCE EXCEPT ACCORDING TO THOSE TERMS; PUBLIC ACCESS GRANTED. OR "DEEDED TO THE CITY OF DURHAM IN FEE SIMPLE FOR CITY GREENWAY; PUBLIC ACCESS GRANTED." 8. FINAL PLAT OWNERS CERTIFICATE (TO BE PLACED NEAR THE ATTORNEY'S CERTIFICATE AND OUTSIDE THE GENERAL CONDITIONS OF APPROVAL BOX): THE UNDERSIGNED OWNER OF THE PROPERTY LYING WITHIN THE ATTACHED PLAT AND SUBDIVISION HEREBY CERTIFIES THAT HE/SHE ORDERED THE WORK OF SURVEYING AND PLATTING TO BE DONE, AND THAT ALL PUBLIC STREETS, ALLEYS, EASEMENTS, AND OTHER OPEN SPACES SO DESIGNATED UPON SAID PLAT ARE HEREBY DEDICATED FOR SUCH USE AND THAT ALL PUBLIC AND PRIVATE EASEMENTS SHOWN UPON SAID PLAT ARE HEREBY GRANTED FOR THE USES STIPULATED. 9. FINAL PLAT ATTORNEY'S CERTIFICATE (TO BE PLACED NEAR THE OWNER'S CERTIFICATE AND OUTSIDE THE GENERAL CONDITIONS OF APPROVAL BOX): 1, IN MY CAPACITY AS LOCAL COUNSEL FOR DO HEREBY CERTIFY THAT TO THE BEST OF MY KNOWLEDGE AND BELIEF THAT IS THE OWNER OF RECORD OF THE TRACT OF LAND DESCRIBED HEREON, AND THAT IS THE OWNER OR OWNER'S AGENT AUTHORIZED TO SIGN THE DEDICATION STATEMENT PERTAINING TO THIS RECORDING . AS OF THIS DATE, SIGNED 10. STREET EASEMENT NOTE: FOOT WIDE CITY OF DURHAM PUBLIC STREET EASEMENT, SUBJECT TO THE TERMS STATED IN THE DECLARATION IN REAL ESTATE BOOK 2350, PAGE 938. NO STRUCTURES, FILLS, EMBANKMENTS OR OBSTRUCTIONS PERMITTED WITHIN THE EASEMENT EXCEPT ACCORDING TO THOSE TERMS. 11.PRIVATE STREET DESIGN NOTE FOR TOWNHOUSES AND CONDOMINIUMS IN THE CITY LIMITS. (THE FOLLOWING NOTES SHALL BE ADDED TO THE SITE PLAN AND FINAL PLATS. THEY CAN BE MODIFIED TO THEIR SPECIFIC USES (STREETS, WATER, SEWER, STORM SEWER)): A) THE STREETS (AND UTILITIES) ARE PRIVATE AND WILL NOT BE PUBLICLY MAINTAINED; B) THE STREETS (AND UTILITIES) ARE TO REMAIN PRIVATE SINCE THE DESIGN DOES NOT MEET CITY DESIGN CRITERIA AND WILL NOT BE MADE PUBLIC NOR MAINTAINED BY THE CITY.- C) THE SELLER IS REQUIRED TO NOTIFY THE BUYER OF ITEMS A AND B ABOVE. 12. PARKING LOTS AND WHEN NO BUILDING PERMIT IS REQUIRED, PLACE THIS NOTE IN THE SPECIAL CONDITIONS OF APPROVAL BOX. OWNER EVELOPER SHALL NOTIFY THE DURHAM CITY COUNTY PLANNING DEPARTMENT SITE COMPLIANCE STAFF AT THE COMPLETION OF CONSTRUCTION AND LANDSCAPING TO REQUEST AN INSPECTION PRIOR TO USE OF THE FACILITY. 13. LANDSCAPE MULCH: PINE STRAW SHALL NOT BE USED AS MULCH OR GROUNDCOVER WITHIN TEN FEET OF ANY STRUCTURES CONSISTING OF EXTERIOR COMBUSTIBLE CONSTRUCTION AS SPECIFIED BY DURHAM CITY CODE SECTION 46-8Z 14. LANDSCAPING/C.O. STANDARDS NOTE. ALL LANDSCAPING MUST BE IN PLACE PRIOR TO REQUEST FOR A CERTIFICATE OF COMPLIANCE. CONTACT DURHAM CITY COUNTY PLANNING DEPARTMENT SITE COMPLIANCE STAFF FOR INSPECTION. 15. LANDSCAPE RE -INSPECTION FEE.• EACH LANDSCAPING COMPLIANCE INSPECTION AFTER THE INITIAL INSPECTION WILL INCUR A RE -INSPECTION FEE. PAYMENT MUST BE RECEIVED BY THE DURHAM CITY COUNTY PLANNING DEPARTMENT PRIOR TO RE -INSPECTION. 16. STREET TREE NOTE FOR ALL PRELIMINARY AND FINAL PLATS WHERE TREES WILL BE PLANTED: STREET TREES MEETING THE REQUIREMENTS OF UDO SECTION 9.6 SHALL BE PLANTED PRIOR TO THE ISSUANCE OF A CERTIFICATE OF COMPLIANCE, UNLESS THE PLANTING HAS BEEN POSTPONED IN ACCORDANCE WITH THE REQUIREMENTS OF UDO SEC. 9.11. 17° UNDISTURBED LANDSCAPE BUFFERS: FOOT WIDE UNDISTURBED LANDSCAPE BUFFER. NO CLEARING OR GRADING OTHER THAN SELECTIVE THINNING AND ORDINARY MAINTENANCE OF EXISTING VEGETATION PERMITTED. 18. CONSTRUCTION IN PRESERVED TREE COVERAGE AREAS (UDO SECTION 8.3): A. PRESERVED TREE COVERAGE AREAS SHALL NOT BE USED FOR ACTIVE RECREATIONAL PURPOSES EXCEPT FOR WALKING PATHS AND FOOT TRAILS CONSTRUCTED WITH MINIMAL DISTURBANCE OF TREE ROOTS AND EXISTING VEGETATION PROVIDED A REGISTERED ARBORIST HAS CERTIFIED THAT THE CONSTRUCTION OF THE TRAIL HAS BEEN DESIGNED TO MINIMIZE IMPACT TO THE EXISTING TREES. NO TREE OVER 10 INCHES SHALL BE REMOVED FOR THE CONSTRUCTION OF TRAILS. SITE PLAN APPROVAL IS REQUIRED FOR CONSTRUCTION OF TRAILS IN PRESERVED TREE COVERAGE AREAS. B. ALL BUILDINGS SHALL BE SET BACK AT LEAST 10 FEET FROM THE EDGE OF ANY PRESERVED TREE COVERAGE AREA. C. UTILITY LINES AND DRAINAGE CHANNELS SHALL BE MINIMIZED WITHIN THE ROOT PROTECTION ZONES OF THE TREES TO BE SAVED. PREFERABLY, SUCH FACILITIES SHOULD BE LOCATED ADJACENT TO DRIVEWAYS AND IN GROUPINGS ALLOWED BY SOUND ENGINEERING PRACTICES. 19. TREE PROTECTION NOTE (UDO SEC. 8.3): TREE PROTECTION FENCING MUST BE IN PLACE PRIOR TO ANY DEMOLITION, LAND DISTURBANCE, OR ISSUANCE OF A GRADING PERMIT AND SHALL INCLUDE WARNING SIGNS POSTED IN BOTH ENGLISH AND SPANISH, AS FOLLOWS. "NO TRESPASSING/TREE PROTECTION AREA/PROHIBIDO ENTRAR / ZONA PROTECTORA PARA LOS ARBOLES. " 20. ROOT PROTECTION ZONE (UDO SEC. 8.3): EQUALS ONE FOOT OF RADIUS FOR EVERY INCH OF DIAMETER OF EXISTING TREES, OR SIX FOOT RADIUS, WHICHEVER IS GREATER. NO DISTURBANCE ALLOWED WITHIN THIS AREA. AREA MUST BE PROTECTED WITH BOTH TREE PROTECTION FENCING AND WARNING SIGNS. 21. PROTECTION OF EXISTING VEGETATION (UDO SEC. 8.3): AT THE START OF GRADING INVOLVING THE LOWERING OF EXISTING GRADE AROUND A TREE OR STRIPPING OF TOPSOIL A CLEAN SHARP VERTICAL CUT SHALL BE MADE AT THE EDGE OF THE TREE SAVE AREA PRIOR TO OR AT THE SAME TIME AS SILT FENCE AND OTHER EROSION CONTROL MEASURES ARE INSTALLED. THE TREE PROTECTION FENCING SHALL BE INSTALLED ON THE SIDE OF THE CUT FARTHEST AWAY FROM THE TREE TRUNK AND SHALL REMAIN IN PLACE UNTIL ALL CONSTRUCTION IN THE VICINITY OF THE TREES IS COMPLETE. NO STORAGE OF MATERIALS FILL OR EQUIPMENT AND NO TRESPASSING SHALL BE ALLOWED WITHIN THE BOUNDARY OF THE PROTECTED AREA. 22. FOR PROJECTS INCLUDING MINI -WAREHOUSE (SELF -STORAGE) SPACE. THIS APPROVAL IS FOR STORAGE PURPOSES ONLY, UNLESS SPECIFICALLY AUTHORIZED OTHERWISE. ANY OTHER USE COULD CREATE BUILDING CODEIZONING VIOLATIONS. 23. FOR PROJECTS SUBJECT TO FEDERAL FAIR HOUSING REGULATIONS. BE ADVISED THAT THE PROVISIONS OF APPENDIX 11 OF THE FEDERAL FAIR HOUSING REGULATIONS (ACCESSIBILITY GUIDELINES -24 CFR, CH. 1 SUBCH. A APP 11 EFFECTIVE MARCH 6 1991 ARE REQUIRED ON THIS PROJECT. IT IS THE RESPONSIBILITY OF THE OWNER/DEVELOPER/BUILDER TO COMPLY WITH THESE REGULATIONS. ALSO BE AWARE THAT THESE REQUIREMENTS ARE BEYOND THE SCOPE OF VOLUME 1-C (HANDICAP ACCESSIBILITY) OF THE NC STATE BUILDING CODE AND AS SUCH THE BURDEN OF COMPLIANCE IS BORNE BY THE OWNER EVELOPER UILDER. 24. TRANSPORTATION FACILITY PERMIT. CONSTRUCTIONOFA PROPOSED PARKING FACILITY, OR MODIFICATION TO AN EXISTING FACILITY THAT MEETS OR EXCEEDS THE FOLLOWING THRESHOLDS MAY REQUIRE A TRANSPORTATION FACILITY PERMIT FROM NCDENR DIVISION OF AIRQUALITY, Q PRIOR TO THE START OF CONSTRUCTION. 1500 SPACES FOR SURFACE PARKING LOTS; 750 SPACES FOR PARKING STRUCTURES SUCH AS DECKS OR GARAGES,• OR 1000 SPACES FOR A COMBINATION OF SURFACE PARKING LOTS AND PARKING STRUCTURES. CONTACT NC DIVISION OF AIR QUALITY FOR MORE INFORMATION. 25. UDO SITE LIGHTING NOTEUDO SEC. Z4: MEASURES SHALL BE PROVIDED TO PREVENT LIGHT SPILLOVER ONTO ADJACENT PROPERTIES AND GLARE TOWARD MOTOR VEHICLE OPERATORS AND SHALL BE INDICATED ON THE SITE PLAN. EXTERIOR LIGHTS SHALL BE SHIELDED SO THAT THEY DO NOT CAST DIRECT LIGHT BEYOND THE PROPERTY LINE. IN ACCORDANCE WITH THESE STANDARDS: A. THE MAXIMUM ILLUMINATION AT THE EDGE OF THE PROPERTY LINE ADJACENT TO RESIDENTIAL ZONING IS 0.5 FOOT CANDLES. B. THE MAXIMUM ILLUMINATION AT THE EDGE OF THE PROPERTY LINE ADJACENT TO NONRESIDENTIAL ZONING IS 5.0 FOOT CANDLES. C. THE MAXIMUM ILLUMINATION AT THE EDGE OF THE PROPERTY LINE ADJACENT TO A STREET IS 5.0 FOOT CANDLES. D. THE LEVEL OF ILLUMINATION AS MEASURED IN FOOT CANDLES AT ANY ONE POINT SHALL MEET THE STANDARDS IN THE TABLE IN UDO SECTION 7.4 WITH MINIMUM AND MAXIMUM LEVELS MEASURED ON THE PAVEMENT WITHIN THE LIGHTED AREA. E THE MAXIMUM HEIGHT FOR DIRECTIONAL OR FULL CUT-OFF LIGHTING FIXTURESFIXTURES DESIGNED TO INSURE THAT NO LIGHT IS EMITTED ABOVE A HORIZONTAL UNE PARALLEL TO THE GROUND) SHALL BE 30 FEET ABOVE GRADE, MEASURED TO THE TOP OF THE FIXTURE. F. THE MAXIMUM HEIGHT FOR NON -DIRECTIONAL LIGHTING FIXTURES, WHICH ARE DEFINED AS FIXTURES DESIGNED TO ALLOW LIGHT TO BE EMITTED ABOVE A HORIZONTAL LINE PARALLEL TO THE GROUND, SHALL BE 15 FEET ABOVE GRADE, MEASURED TO THE TOP OF THE FIXTURE. G. THESE STANDARDS MUST BE VERIFIED BY FIELD SURVEY (BY USE OF PHOTOMETRIC SURVEY) PRIOR TO THE CERTIFICATE OF COMPLIANCE BEING ISSUED. ALL OF THIS INFORMATION, INCLUDING DETAILS, WILL BE REQUIRED ON BUILDING PLANS PRIOR TO ISSUANCE OF BUILDING PERMIT. 26. FOR PROJECTS UTILIZING ON SITE WATER SUPPLY OR WASTE WATER DISPOSAL: APPROVAL DOES NOT GUARANTEE APPROVAL OF EITHER ON-SITE WATER SUPPLY OR WASTE WATER 11 12 DISPOSAL SYSTEMS OR THAT PERMITS WILL BE ISSUED FOR THE CONSTRUCTION OF SUCH SYSTEMS. 27 SANITARY SEWER EASEMENTS: CITY. SEE PUBLIC WORKS STANDARD NOTES, BELOW. COUNTY: CENTERLINE OF FOOT WIDE COUNTY OF DURHAM SANITARY SEWER EASEMENT. SUBJECT TO TERMS STATED IN THE DECLARATION IN REAL ESTATE BOOK 1626, PAGE 145. NO STRUCTURES, FILL, EMBANKMENTS, TREES OR OBSTRUCTIONS PERMITTED WITHIN THE EASEMENT EXCEPT ACCORDING TO THOSE TERMS. 28. CITY STORM DRAINAGE EASEMENTS: SEE PUBLIC WORKS STANDARD NOTES, BELOW. COUNTY STORM OR PRIVATE DRAINAGE EASEMENTS. CENTERLINE OF FOOT WIDE DRAINAGE EASEMENT FOR THE BENEFIT OF ADJACENT PROPERTY OWNERS NOT MAINTAINED BY PUBLIC AUTHORITIES. NO BUILDINGS, STRUCTURES, FILLS, EMBANKMENTS OR OBSTRUCTIONS PERMITTED WITHIN THE EASEMENT EXCEPT ACCORDING TO THOSE TERMS. 29. FOR RESIDENTIAL DEVELOPMENTS USING CURBSIDE COLLECTION: AN AUTOMATED SOLID WASTE COLLECTION VEHICLE HAS AN 18 -FOOT WHEELBASE AND A TURNING RADIUS OF 45 FEET WALL-TO-WALL AND 43 FEET CURB -TO -CURB. THE DEPARTMENT OF SOLID WASTE MANAGEMENT RESERVES THE RIGHT TO MODIFY COLLECTION OF GARBAGE AND RECYCLABLES FOR ANY ROADWAY OR CUL-DE-SAC NOT CONSTRUCTED TO ACCOMMODATE THOSE SPECIFICATIONS. 30. FOR COMMERCIAL PROJECTS WANTING TO RECEIVE CURBSIDE COLLECTION INSTEAD OF DUMPSTERS. GARBAGE VOLUME IS NOT EXPECTED TO EXCEED THE CAPACITY OF FOUR 96 -GALLON CARTS PER WEEK. ALL TARGET (BANNED) RECYCLABLES WILL BE SEPARATED FROM GARBAGE AND PLACED IN CITY RECYCLE BINS. A WASTE HANDLING FACILITY WILL BE CONSTRUCTED AT THE OWNER'S EXPENSE AT THE LOCATION DESIGNATED ON THE PLANS IN COMPLIANCE WITH ORDINANCE AND SWM STANDARDS SHOULD GARBAGE EXCEED THE FOUR -CART PER WEEK LIMIT. 31. FOR COMMERCIAL SITES WITHOUT PROPOSED RESTAURANTS(BUT WHERE RESTAURANTS WOULD BE AN ALLOWED USE IN THE ZONING DISTRICT): AS DESIGNED, A RESTAURANT FACILITY MAY NOT BE PERMITTED IN THIS BUILDING. A REVISED SITE PLAN WILL BE REQUIRED TO ACCOMMODATE A GREASE TRAP, TRASH HANDLING AND OTHER REQUIREMENTS RELATED TO A RESTAURANT FACILITY. 32. FIRE NOTE TO BE INCLUDED ON UTILITY PLAN SHEET. PROVIDE FIRE PLANS EXAMINER ONE COPY OF UTILITY CONSTRUCTION DRAWINGS, SHOWING UNDERGROUND PIPING LAYOUT AND ALL FIRE APPURTENANCES. PERMIT FOR INSTALLATION OF PRIVATE FIRE HYDRANT(S) MUST BE ISSUED BY FIRE PLANS EXAMINER PRIOR TO INSTALLATION OF SAID HYDRANTS. 33. FIRE NOTES TO BE INCLUDED ON COVER SHEET. A. TEMPORARY OR PERMANENT ROADWAYS OF ALL-WEATHER DRIVING SURFACE, CAPABLE OF SUPPORTING A 75,000 POUND VEHICLE WEIGHT, SHALL BE ESTABLISHED PRIOR TO THE COMMENCEMENT OF BUILDING CONSTRUCTION ACTIVITIES. THESE ROADWAYS SHALL BE EXTENDED WITH THE PROGRESS OF CONSTRUCTION SO THAT.• A.A. ALL POINTS AROUND THE PERIMETER OF A BUILDING UNDER CONSTRUCTION IS NO GREATER THAN 150 FEET TRAVEL DISTANCE FROM A ROADWAY, A.B. FIRE DEPARTMENT CONNECTIONS (FDC), EITHER TEMPORARY OR PERMANENT, ARE NO GREATER THAN 100 FEET TRAVEL DISTANCE FROM A ROADWAY. B. TEMPORARY WEATHER -RESISTANT STREET SIGNS OF STANDARD SIZE AND LETTERING SHALL BE PROVIDED AT THE INTERSECTIONS OF TEMPORARY OR PERMANENT ROADWAYS AND SHALL REMAIN IN PLACE UNTIL REPLACED BY PERMANENT SIGNS. C. FIRE HYDRANTS, AS SHOWN ON THE APPROVED SITE PLAN, SHALL BE PLACED IN SERVICE AND MADE AVAILABLE TO THE FIRE DEPARTMENT AS SOON AS COMBUSTIBLE MATERIAL ARRIVES ON SITE. NO CONSTRUCTION FENCING OR OTHER BARRIERS ARE TO BE PLACED BETWEEN THE ROADWAY AND THE HYDRANTS, WITH MINIMUM 3 FEET WORKING CLEARANCE AROUND HYDRANTS. HYDRANT SERVICE SHALL BE EXTENDED WITH THE PROGRESS OF CONSTRUCTION SO THAT: C.A. ALL POINTS AROUND THE PERIMETER OF A BUILDING UNDER CONSTRUCTION IS NO GREATER THAN 500 FEET TRAVEL DISTANCE FROM A HYDRANT, C.B. FIRE DEPARTMENT CONNECTIONS (FDC), EITHER TEMPORARY OR PERMANENT, ARE NO GREATER THAN 50 FEET TRAVEL DISTANCE FROM A HYDRANT. 34. FOR COUNTY SOIL AND EROSION CONTROL: A. A SEDIMENTATION AND EROSION CONTROL PLAN MUST BE SUBMITTED AND APPROVED PRIOR TO THE ISSUANCE OF A LAND -DISTURBANCE PERMIT. B. IF AN OFFSITE SOIL SPOIL OR BORROW SITE IS UTILIZED, THEN THE DISTURBED AREA FOR THE SPOIL/BORROW SITE MUST BE INCLUDED IN THE LAND -DISTURBANCE PLAN AND PERMIT UNLESS THE SPOIL/BORROW SITE ALREADY HAS A LAND -DISTURBANCE PERMIT. ENGINEERING DIVISION NOTES N THE PUBLIC WORKS CONDITIONS OF APPROVAL BOX, ADD THE FOLLOWING NOTES. 1. THE DESIGNING PROFESSIONAL (A NCPE, NCPLS OR NCRLA - AS REQUIRED) SHALL SUBMIT THREE (3) SETS OF CONSTRUCTION DRAWINGS TO THE PUBLIC WORKS DEPARTMENT - DEVELOPMENT REVIEW FOR REVIEW AND APPROVAL. CONSTRUCTION DRAWING APPROVAL IS REQUIRED PRIOR TO COMMENCING CONSTRUCTION (SEE CONSTRUCTION PLAN APPROVAL PROCESS). THE APPROVAL OF CONSTRUCTION DRAWINGS IS SEPARATE FROM SITE PLAN APPROVAL. CITY OFFICIALS SHALL REVIEW ALL SIZES, MATERIALS, SLOPES, LOCATIONS, EXTENSIONS AND DEPTHS FOR ALL PROPOSED UTILITIES (WATERLINES, SANITARY SEWER LINES AND STORM DRAINAGE CONVEYANCE SYSTEMS) FOR COMPLIANCE WITH ALL APPLICABLE REGULATORY STANDARDS, SPECIFICATIONS, AND BEST MANAGEMENT PRACTICES. 2. THE DESIGNING PROFESSIONAL (A NCPE, NCPLS OR NCRLA - AS REQUIRED) SHALL SUBMIT ONE (1) SET OF AS -BUILT DRAWINGS TO THE PUBLIC WORKS DEPARTMENT - DEVELOPMENT REVIEW FOR REVIEW AND APPROVAL. AS -BUILT DRAWING APPROVAL IS REQUIRED PRIOR TO WATER METER INSTALLATION AND/OR SANITARY SEWER SERVICE CONNECTION AND PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY. 3. FIRE FLOW ANALYSIS REQUIRED FOR REVIEW AND APPROVAL AS PART OF THE CONSTRUCTION DRAWING APPROVAL PROCESS. TO SCHEDULE FLOW TEST OR TO OBTAIN CURRENT SYSTEM DATA, COMPLETE THE ONLINE APPLICATION (HTTP: //DURHAMNC.GOV/ICH/OP/PWD/PAGES/FIRE-FLOW°ASPX). 4. IF A METER 2" OR LARGER IS PROPOSED, CONTACT WATER MANAGEMENT AT 560-4381 PRIOR TO THE CONSTRUCTION OF THE METER VAULT TO VERIFY THE TYPE AND DIMENSIONS OF THE METER. 5. WATER PERMIT REQUIRED AFTER CONSTRUCTION DRAWING APPROVAL AND PRIOR TO COMMENCING WATER MAIN INSTALLATION. 6. SEWER PERMIT REQUIRED AFTER CONSTRUCTION DRAWING APPROVAL AND PRIOR TO COMMENCING SANITARY SEWER MAIN INSTALLATION. Z SEWER PERMIT FROM DURHAM COUNTY REQUIRED. CONTACT DURHAM COUNTY UTILITY DIVISION AT 560-7993. 8. AN NCDOT OR CITY OF DURHAM DRIVEWAY PERMIT IS REQUIRED. 9. CONSTRUCTION DRAWINGS ARE NOT REQUIRED: I. PROVIDE TWO (2) SETS OF APPROVED SITE PLAN DOCUMENTS TO ENGINEERING INSPECTIONS, 3RD FLOOR, 101 CITY HALL PLAZA, DURHAM, NC 27701 AT LEAST 5 DAYS PRIOR TO BEGINNING CONSTRUCTION AND CONTACT ENGINEERING INSPECTIONS AT 560-4326 AT LEAST 48 HOURS PRIOR TO BEGINNING CONSTRUCTION. 11. A CONSTRUCTION ON CITY RIGHT-OF-WAY / PRIVATE PROPERTY PERMIT MAY BE REQUIRED. CONTACT THE PUBLIC WORKS CUSTOMER SERVICE DESK AT 560-4326. M. AN ENCROACHMENT AGREEMENT MAY BE REQUIRED. CONTACT ENGINEERING SERVICES AT 560-4326. WATER EASEMENT NOTE. CENTERLINE OF FOOT WIDE CITY OF DURHAM WATER EASEMENT. SUBJECT TO TERMS STATED IN THE DECLARATION IN REAL ESTATE BOOK 1510, PAGE 958. NO STRUCTURES, FILL, EMBANKMENTS, TREES OR OBSTRUCTIONS PERMITTED WITHIN THE EASEMENT EXCEPT ACCORDING TO THOSE TERMS. SANITARY SEWER EASEMENT NOTE CENTERLINE OF FOOT WIDE CITY OF DURHAM SANITARY SEWER EASEMENT. SUBJECT TO TERMS STATED IN THE DECLARATION IN REAL ESTATE BOOK 1510, PAGE 958° NO STRUCTURES, FILL, EMBANKMENTS, TREES OR OBSTRUCTIONS PERMITTED WITHIN THE EASEMENT EXCEPT ACCORDING TO THOSE TERMS. CENTERLINE OF FOOT WIDE COUNTY OF DURHAM SANITARY SEWER EASEMENT. SUBJECT TO TERMS STATED IN THE DECLARATION IN REAL ESTATE BOOK 1626 PAGE 145. NO STRUCTURES FILL, EMBANKMENTS, TREES OR OBSTRUCTIONS PERMITTED WITHIN THE EASEMENT EXCEPT ACCORDING TO THOSE TERMS. SIDEWALK NOTE: THE LOCATION OF THE SIDEWALKS SHOWN ON THIS PLAN IS SCHEMATIC. A CITY OF DURHAM AND/OR NCDOT ENCROACHMENT PERMIT IS REQUIRED PRIOR TO ANY CONSTRUCTION. AFTER OBTAINING THE REQUIRED PERMITS, PLEASE CONTACT THE CITY OF DURHAM ENGINEERING CONSTRUCTION INSPECTION OFFICE AT 560-4326 FOR A PRE -CONSTRUCTION CONFERENCE AND FIELD VISIT PRIOR TO ANY WORK ON THE PROPOSED SIDEWALK. PUBLIC ACCESS EASEMENT FOR SIDEWALK NOTE: CERTIFICATION OF EXPRESS DEDICATION FOR PUBLIC USE [DESCRIPTION OF THE SIDEWALKS TO BE DEDICATED INSERTED HERE] ('SIDEWALKS" ARE EXPRESSLY DEDICATED TO USE BY THE GENERAL PUBLIC. UPON CONSTRUCTION OF THE SIDEWALKS IN CONFORMANCE WITH ALL APPLICABLE REQUIREMENTS, CITY COUNCIL MAY ACCEPT THE SIDEWALKS FOR MAINTENANCE BY THE CITY OF DURHAM"CITY" . ACCEPTANCE OF THE SIDEWALKS BY CITY COUNCIL CONVEYS THE RIGHT IN OVER, UNDER, AND THROUGH THE SIDEWALKS, NECESSARY FOR THE CITY AND ITS AGENTS AND CONTRACTORS, TO MAINTAIN AND REPAIR THE SIDEWALKS IN THE CITY'S SOLE DISCRETION. THE RIGHT OF INGRESS/EGRESS TO THE SIDEWALKS FROM THE PUBLIC RIGHT OF WAY IS ALSO GRANTED TO THE CITY SO THE CITY CAN MAINTAIN AND REPAIR THE SIDEWALKS AFTER ACCEPTANCE. THE CITY IN ITS SOLE DISCRETION HAS THE RIGHT TO DETERMINE THE POINTS OF INGRESS AND EGRESS FROM THE PUBLIC RIGHT OF WAY NECESSARY TO PERFORM MAINTENANCE OR REPAIR AFTER ACCEPTANCE. DRIVEWAY PERMIT NOTES. A CITY OF DURHAM DRIVEWAY PERMIT IS REQUIRED PRIOR TO ANY DRIVEWAY CONSTRUCTION ON PUBLIC RIGHT-OF-WAYY, SUBMIT PLANS FOR DRIVEWAY PERMIT APPROVAL TO CITY ENGINEERING DEVELOPMENT REVIEW. AFTER OBTAINING THE PERMIT, PLEASE CALL CITY OF DURHAM ENGINEERING INSPECTION OFFICE AT 560-4326 PRIOR TO START OF CONSTRUCTION. NCDOT DRIVEWAY PERMIT REQUIRED PRIOR TO CONSTRUCTION. CONTACT NCDOT AT 220-4750 FOR REQUIREMENTS. TOWNHOME NOTE TOWNHOME DEVELOPMENTS MAY BE DESIGNED AND CONSTRUCTED WITH PARKING AREAS ON BOTH SIDES OF THE TRAVEL LANES. THIS CONFIGURATION IS NOT TO BE CONSIDERED A STREET. IF THIS OPTION IS USED, THE TRAVEL AND PARKING AREAS SHALL BE NOTED AS 'PRIVATE ACCESS AND COMMON AREAS': AS SUCH, THE DEVELOPER SHALL ACKNOWLEDGE AND MAKE PROSPECTIVE BUYERS AWARE THAT THESE AREAS WILL NOT BE ASSIGNED A STREET NAME, NOR WILL THEY EVER BE ELIGIBLE FOR MAINTENANCE BY THE CITY OF DURHAM. THE DEVELOPER WILL ENSURE THAT ALL OF THE ACCESS AND COMMON AREA PROPERTY IS DESCRIBED IN THE COVENANTS AND THAT THE HOME OWNERS ASSOCIATION IS RESPONSIBLE FOR THE MAINTENANCE OF THIS AREA. THE FOLLOWING NOTE SHALL BE ADDED TO ALL SITE PLANS AND PLATS ASSOCIATED WITH THE DEVELOPMENT.• THE DRIVING AND PARKING AREAS SHOWN ON THIS DRAWING NOTED AS 'PRIVATE ACCESS AND COMMON AREAS" DO NOT MEET CITY OF DURHAM STREET STANDARDS. THE FEATURES WITHIN THIS AREA ARE PRIVATE AND WILL NEVER BE ELIGIBLE FOR PUBLIC MAINTENANCE. UTILITY NOTES. A UTILITY MAINLINE CONSTRUCTION PERMIT IS REQUIRED PRIOR TO THE INSTALLATION OF EACH UTILITY. ALL UTILITIES SHALL SUBMIT PLAN DRAWINGS AND APPLICATIONS TO THE CITY ENGINEERING DIVISION. WATER SERVICE ABANDONMENT. ABANDONMENT OF WATER SERVICES SHALL INCLUDE EXCAVATING DOWN TO CORPORATION STOP, TURNING IT OFF AND CUTTING SERVICE LINE FREE FROM CORPORATION STOP. THE METER, IF PRESENT, SHALL BE RETURNED TO CITY OF DURHAM. PRIOR TO ANY CREDIT OR REFUND BEING PROCESSED THE METER MUST BE RETURNED TO WATER MANAGEMENT DEPARTMENT AND THE METER NUMBER VERIFIED AND CODED PROPERLY AS RETURNED. UTILITY SERVICE ABANDONMENTS WILL TAKE PLACE PRIOR TO BEGINNING UTILITY CONSTRUCTION WORK FOR A PROJECT. ANY EXCAVATION AS PART OF ABANDONING UTILITIES WILL REQUIRE BACKFILLING PER CITY OF DURHAM STANDARDS. SANITARY SEWER SERVICE ABANDONMENT. ABANDONMENT OF SANITARY SEWER SERVICE LINES SHALL CONSIST OF EXCAVATING DOWN TO THE SERVICE CONNECTION TO THE MAIN, CUTTING THIS CONNECTION AND INSTALLING A WATERTIGHT PLUG IN THE MAIN. THE SERVICE LINE AND ALL CLEAN-OUT RISERS ON THE SERVICE LINE SHALL BE REMOVED. UTILITY SERVICE ABANDONMENTS WILL TAKE PLACE PRIOR TO BEGINNING UTILITY CONSTRUCTION WORK FOR A PROJECT. ANY EXCAVATION AS PART OF ABANDONING UTILITIES WILL REQUIRE BACKFILLING PER CITY OF DURHAM STANDARDS. 13 14 15 16 WATER, SANITARY SEWER AND STORM SEWER SEPARATION NOTES 1. HORIZONTAL AND VERTICAL SEPARATION A. SANITARY SEWERS SHALL BE LAID AT EAST 10 -FEET HORIZONTALLY FROM ANY EXISTING OR PROPOSED WATER MAIN. THE DISTANCE SHALL BE MEASURED EDGE TO EDGE. IN CASES WHERE IT IS NOT PRACTICAL TO MAINTAIN A 10 -FOOT SEPARATION, THE CITY OF DURHAM MAY ALLOW DEVIATION ON A CASE-BY-CASE BASIS, IF SUPPORTED BY DATA FROM THE DESIGN ENGINEER. SUCH DEVIATION ON MAY ALLOW THE INSTALLATION OF THE SANITARY SEWER CLOSER TO A WATER MAIN, PROVIDED THAT THE WATER MAIN IS IN A SEPARATE TRENCH OR ON AN UNDISTURBED EARTH SHELF LOCATED ON ONE SIDE OF THE SANITARY SEWER AND AT AN ELEVATION SO THE BOTTOM OF THE WATER MAIN IS AT EAST 18 -INCHES ABOVE THE TOP OF THE SEWER. B. IF IT IS IMPOSSIBLE TO OBTAIN PROPER HORIZONTAL AND VERTICAL SEPARATION AS DESCRIBED ABOVE OR ANYTIME THE SANITARY SEWER IS OVER THE WATER MAIN, BOTH THE WATER MAIN AND SANITARY SEWER MUST BE CONSTRUCTED OF FERROUS PIPE COMPLYING WITH THE PUBLIC WATER SUPPLY DESIGN STANDARDS AND BE PRESSURE TESTED TO 150 -PSI TO ASSURE WATER TIGHTNESS BEFORE BACKFILLING. C. A 24 -INCH VERTICAL SEPARATION SHALL BE PROVIDED BETWEEN STORM SEWER AND SANITARY SEWER LINES OR FERROUS PIPE SPECIFIED. A 12 -INCH VERTICAL SEPARATION SHALL BE PROVIDED BETWEEN STORM SEWER AND WATER MAINS. 1. IF A 12 -INCH VERTICAL SEPARATION IS NOT MAINTAINED AT A CROSSING BETWEEN STORM SEWER AND WATER MAINS (OR PRESSURE SEWERS). THE WATER MAIN SHALL BE CONSTRUCTED OF FERROUS PIPE AND A CONCRETE COLLAR SHALL BE POURED AROUND WATER MAINS AND STORM SEWER TO IMMOBILIZE THE CROSSING. Z CROSSINGS A. SANITARY SEWER CROSSING WATER MAINS SHALL BE LAID TO PROVIDE A MINIMUM VERTICAL DISTANCE OF 18 -INCHES BETWEEN THE OUTSIDE OF THE WATER MAIN AND THE OUTSIDE OF THE SANITARY SEWER. THE CROSSING SHALL BE ARRANGED SO THAT THE SANITARY SEWER JOINTS WILL BE EQUIDISTANT AND AS FAR AS POSSIBLE FROM THE WATER MAIN JOINTS. B. WHEN IT IS IMPOSSIBLE TO OBTAIN PROPER HORIZONTAL AND VERTICAL SEPARATION AS STIPULATED ABOVE, ONE OF THE FOLLOWING METHODS MUST BE SPECIFIED. 1. THE SANITARY SEWER SHALL BE DESIGNED AND CONSTRUCTED OF FERROUS PIPE AND SHALL BE PRESSURE TESTED AT 150 -PSI TO ASSURE WATER TIGHTNESS PRIOR TO BACKFILLING, OR 2. EITHER THE WATER MAIN OR THE SANITARY SEWER LINE MAY BE ENCASED IN A WATERTIGHT CARRIER PIPE, WHICH EXTENDS 10 -FEET ON BOTH SIDES OF THE CROSSING, MEASURED PERPENDICULAR TO THE WATER MAIN. THE CARRIER PIPE SHALL BE OF MATERIALS APPROVED BY THE CITY OF DURHAM FOR USE IN WATER MAIN CONSTRUCTION. STORM WATER SERVICES DIVISION NOTES A. SPECIAL CONDITIONS OF APPROVAL BOX NOTES FOR SITE PLAN/PRELIMINARY PLAT SUBMITTALS. (NOTE THAT THESE NOTES MAY OR MAY NOT APPLY TO THE PROJECT DEPENDING ON THE REQUIREMENTS OF THE PROJECT, DETERMINED DURING REVIEW) 1. FEMA FLOOD STUDY REQUIRED: "A CLOMR SHALL BE OBTAINED FROM FEMA PRIOR TO CONSTRUCTION DRAWING APPROVAL. A LOMR SHALL BE OBTAINED FROM FEMA PRIOR TO ISSUANCE OF ANY CERTIFICATES OF OCCUPANCY OR CERTIFICATES OF COMPLIANCE." 2. FOR DEVELOPMENTS WITHIN THE NEUSE RIVER BASIN (PAYMENT, IF REQUIRED, TO BE DETERMINED DURING SITE PLAN REVIEW): A SITE PLAN CANNOT BE APPROVED UNTIL A RECEIPT FROM THE NORTH CAROLINA ECOSYSTEM ENHANCEMENT PROGRAM HAS BEEN RECEIVED BY THE CITY OF DURHAM CONFIRMING THE PAYMENT OF $X.XX IN OFFSET FEES." 3. FOR DEVELOPMENTS REQUIRED TO HAVE A STORMWATER BMP FACILITY. FINAL DESIGN CALCULATIONS FOR THE STORMWATER BMP FACILITY WILL REQUIRE THE USE OF STORAGE INDICATION ROUTING METHODOLOGY SUCH AS TR -20 OR HEC -1 MODELS. FOR THE BMP FACILITY, PROVIDE STAGE -STORAGE RELATIONSHIP AND INFLOW AND OUTFLOW HYDROGRAPHS. PROVIDE ALL TABULATED DATA INCLUDING CALCULATIONS SHOWING THE OUTLET UNDER ORIFICE CONTROL, BARREL CONTROL AND WEIR CONTROL, AS APPROPRIATE, TO SHOW HOW THE ROUTING WAS DEVELOPED." 4. FOR DEVELOPMENTS REQUIRED TO HAVE A STORMWATER BMP FACILITY. L "AN EXECUTED STORMWATER FACILITY OPERATION AND MAINTENANCE PERMIT AGREEMENT (PREPARED BY STORMWATER SERVICES, CITY OF DURHAM), PAYMENT OF STORMWATER FACILITY PERMIT FEE PER BMP FACILITY AND PERPETUAL SURETY FOR THE CONTINUED OPERATION AND MAINTENANCE OF THE FACILITY IS REQUIRED PRIOR TO CONSTRUCTION PLAN APPROVAL." 11. "AN AS -BUILT CERTIFICATION FOR THE STORMWATER BMP(S), PROVIDED BY THE DESIGN ENGINEER, IS REQUIRED. THE AS -BUILT SHALL BE SUBMITTED PER THE REFERENCE GUIDE FOR DEVELOPMENT, APPROVED BY THE STORMWATER SERVICES DIVISION AND THE BMP(S) SHALL BE INSPECTED AND APPROVED BY THE STORMWATER SERVICES DIVISION PRIOR TO ISSUANCE OF ANY CERTIFICATES OF OCCUPANCY OR CERTIFICATES OF COMPLIANCE FOR THE PROJECT" 5. FOR DEVELOPMENTS REQUIRED TO HAVE A STORMWATER BMP FACILITY: A COMPLETED CITY OF DURHAM DESIGN SUMMARY IS REQUIRED FOR EACH STORMWATER BMP FACILITY NO LATER THAN AT THE FIRST CONSTRUCTION DRAWING SUBMITTAL." 6. FOR DEVELOPMENTS REQUIRED TO HAVE A STORMWATER BMP FACILITY: "STORMWATER BMP FACILITY DESIGN CALCULATIONS WILL NOT BE REVIEWED OR APPROVED WITH THE SITE PLAN/PRELIMINARY PLAT SUBMITTAL. ALL STORMWATER BMP FACILITY DESIGNS WILL BE REVIEWED AND APPROVED DURING THE CONSTRUCTION DRAWING SUBMITTAL PROCESS." B. STANDARD NOTES: (NOTE THAT THESE NOTES MAY OR MAY NOT APPLY TO THE PROJECT DEPENDING ON THE REQUIREMENTS OF THE PROJECT, DETERMINED DURING REVIEW) 1. STORMWATER DRAINAGE EASEMENT NOTE (WIDTH DETERMINED AT CONSTRUCTION DRAWINGS): "CENTERLINE OF FOOT WIDE PUBLIC STORM WATER DRAINAGE EASEMENT. OWNERSHIP OF AND RESPONSIBILITY FOR IMPROVEMENT AND MAINTENANCE OF STORM WATER FACILITIES IN THIS EASEMENT REMAINS WITH THE CURRENT OWNER. IF THE PROPERTY IS WITHIN OR BECOMES A PART OF THE CITY THE EASEMENT AND ACCESS POINTS TO THE EASEMENT ARE SUBJECT TO THE TERMS AND RESTRICTIONS STATED IN THE "REVISED DECLARATION OF RIGHTS AND PRIVILEGES OF THE CITY OF DURHAM IN STORM WATER MANAGEMENT FACILITY EASEMENTS" RECORDED IN REAL ESTATE BOOK 2298, PAGE 208, WHICH DOCUMENT IS INCORPORATED HEREIN. THIS EASEMENT AND THE REVISED DECLARATION DO NOT CREATE THE OBLIGATION TO PROVIDE PUBLIC MAINTENANCE. NO BUILDING, STRUCTURES, FILLS, EMBANKMENTS OR OBSTRUCTIONS PERMITTED WITHIN THE EASEMENT EXCEPT ACCORDING TO THOSE TERMS." 2. STREAM BUFFER NOTES (WIDTH DETERMINED AT REZONING OR SITE PLAN): FOOT WIDE UNDISTURBED STREAM BUFFER EACH SIDE OF STREAM, MEASURED FROM TOP OF BANK. NO CLEARING OR GRADING OTHER THAN SELECTIVE THINNING AND ORDINARY MAINTENANCE OF EXISTING VEGETATION PERMITTED." 3. FLOODPLAIN NOTES "ALL DEVELOPMENT WITHIN THE FLOODWAY AND FLOODWAY FRINGE, INCLUDING FILL, NEW CONSTRUCTION, SUBSTANTIAL IMPROVEMENTS MANUFACTURED HOUSING, STORAGE OF MATERIALS AND STORAGE OF TOXIC OR FLAMMABLE SUBSTANCES, IS PROHIBITED EXCEPT AS PROVIDED BY APPLICABLE FLOOD HAZARD REGULATIONS." 4. GENERAL NOTES. "STATE AND FEDERAL PERMIT AUTHORIZATION MAY BE REQUIRED FROM THE DEHNR AND THE U.S. CORPS OF ENGINEERS PRIOR TO THE COMMENCEMENT OF ANY LAND DISTURBING ACTIVITIES IN OR NEAR A LAKE, STREAM, CREEK, TRIBUTARY OR ANY UNNAMED BODY OF WATER AND ITS ADJACENT WETLANDS." DEPARTMENT OF TRANSPORTATION NOTES WHERE STREETS TERMINATE, ADD THE FOLLOWING NOTE TO THE CONSTRUCTION DRAWINGS. WHERE STREETS TERMINATE (EXAMPLE PHASE LINES) THE FOLLOWING WILL BE INSTALLED: 1) ASPHALT HEADER, 2) RIPRAP OR CONCRETE APRON FOR STORM WATER TO DISSIPATE, 3) UTILITIES TO EXTEND A MINIMUM OF 5 -FEET BEYOND THE EDGE OF PAVEMENT, 4) NCDOT TYPE 111 BARRICADE. OFF-SITE ROADWAY IMPROVEMENTS, ADD THE FOLLOWING NOTE TO THE SPECIAL CONDITIONS OF APPROVAL BOX: BY REFERENCING ROADWAY IMPROVEMENTS ON THE PLAN, THE APPLICANT AGREES TO CONSTRUCT SAID IMPROVEMENTS PRIOR TO ISSUANCE OF CERTIFICATE OF OCCUPANCY IN A MANNER THAT WILL ALLOW THEM TO FUNCTION AS NOTED ON THE PLAN AND IN ACCORDANCE WITH NCDOT AND CITY OF DURHAM STANDARDS AND POLICIES. THIS INCLUDES (WHERE APPROPRIATE) BUT IS NOT LIMITED TO. ADEQUATE TRANSITION TAPERS, ALIGNMENT OF LANES THROUGH INTERSECTIONS ASSOCIATED SIGNAL MODIFICATIONS PAVEMENT MARKINGS ASSOCIATED SIGNAGE, CURB AND GUTTER, COORDINATION WITH OTHER PROPOSED ROADWAY IMPROVEMENTS AND BIKE LANES. THE APPLICANT ALSO ACCEPTS THE FINANCIAL RESPONSIBILITY FOR ACQUISITION OF ANY ADDITIONAL RIGHT-OF-WAY NECESSARY TO ACCOMMODATE THESE IMPROVEMENTS AND ANY REQUIRED SIDEWALK CONSTRUCTION. SIGNS AND/OR PAVEMENT MARKINGS TO BE INSTALLED BY THE DEVELOPER (NEW SUBDIVISIONS OR OFF-SITE ROADWAY IMPROVEMENTS THAT NEED NEW MARKINGS FOR EXAMPLE), ADD THE FOLLOWING NOTE TO THE SPECIAL CONDITIONS OF APPROVAL BOX. THE DEVELOPER IS RESPONSIBLE FOR FABRICATION AND INSTALLATION OF ALL REQUIRED SIGNS AND PAVEMENT MARKINGS WITHIN THE PUBLIC RIGHT-OF-WAY. THE DEVELOPER SHALL SUBMIT A SIGNING AND MARKINGS PLAN TO THE CITY AT CONSTRUCTION PLAN STAGE FOR REVIEW AND APPROVAL. ALL SIGNS AND PAVEMENT MARKINGS, SHOWN ON THE CONSTRUCTION PLANS, MUST BE IN PLACE PRIOR TO THE ISSUANCE OF ANY CERTIFICATE OF OCCUPANCY AND/OR STREET ACCEPTANCE, AS DETERMINED BY THE CITY. RIGHT-OF-WAY DEDICATION ON A MAJOR/MINOR THOROUGHFARE ADJACENT TO THE SITE, ADD THE FOLLOWING NOTE TO THE SPECIAL CONDITIONS OF APPROVAL BOX. DEDICATE AN ADDITIONAL - FEET OF RIGHT-OF-WAY ALONG THE FRONTAGE OF THE SITE ON ROAD PRIOR TO THE ISSUANCE OF ANY BUILDING PERMIT. A COPY OF THE RECORDED PLAT MUST BE SUBMITTED WITH THE FIRST BUILDING PERMIT APPLICATION. BUS STOP/SHELTER IS TO BE CONSTRUCTED NEAR THE SITE, ADD THE FOLLOWING NOTE TO THE SPECIAL CONDITIONS OF APPROVAL BOX: PROVIDE BUS SHELTER WITH CONCRETE PAD ON ROAD. DESIGN SPECIFICATIONS AND EXACT LOCATION TO BE REVIEWED AND APPROVED BY DATA PRIOR TO CONSTRUCTION. OFF-SITE ROADWAY IMPROVEMENTS ON THE SITE ADD THE FOLLOWING NOTE TO THE SPECIAL CONDITIONS OF APPROVAL BOX: ALL OFF-SITE ROADWAY IMPROVEMENTS MUST BE COMPLETE PRIOR TO THE ISSUANCE OF ANY CERTIFICATE OF OCCUPANCY. VARIATIONS TO THESE STANDARD NOTES MAY BE APPLIED WITH THE EXPRESS CONSENT OF THE TRANSPORTATION DIVISION. SIGNAGE AND MARKING PLAN CONSTRUCTION DRAWING NOTES: 1. ALL SIGNS, STREET MARKERS, AND PAVEMENT MARKINGS (EVERYTHING CALLED OUT ON THE SIGNING AND MARKING SHEET) MUST BE INSTALLED ON EACH STREET PRIOR TO THE ISSUANCE OF A CERTIFICATE OF OCCUPANCY AND/OR STREET ACCEPTANCE, AS DETERMINED BY THE CITY. 2. THE STREET NAME SIGN SHALL BE REFLECTIVE TO SHOW THE SAME SHAPE AND SIMILAR COLOR BOTH DAY AND NIGHT. THE LETTERS AND BACKGROUND SHALL BE OF CONTRASTING COLORS. 3. STREET NAME SIGNS SHALL HAVE WHITE LETTERS ON A GREEN BACKGROUND. 4. LETTERING ON THE STREET NAMES SHALL BE 4 -INCHES HIGH IN CAPITAL LETTERS. 5. SUFFIX LETTERING TO INDICATE THE TYPE OF STREET SUCH AS STREET AVENUE OR ROAD OR THE SECTION OF THE CITY (SUCH AS NW) SHALL BE LETTERING 2 -INCHES HIGH. ) 6. STREET NAME SIGNS WILL BE LOCATED ON TOP OF STOP SIGNS IN A STACKED POSITION. 7. STOP BARS SHALL BE 2 -FEET WIDE WHITE THERMOPLASTIC PER NCDOT SPECIFICATIONS 8. ALL SIGNS MUST CONFORM WITH THE MANUAL ON UNIFORM TRAFFIC CONTROL DEVICES (MUTCD)° 9. STREET SIGNS SHALL SHOW BLOCK NUMBERS.(BLOCK NUMBERS ARE SHOWN ON THE RECORDED PLAT. IF THEY ARE NOT SHOWN ON RECORDEDPLAT, CONTACT THE CITY'S ENGINEERING ASSESSMENTS DIVISION AT 560-4326). 8 9 10 11 12 13 14 15 16 ==i M O 0 N > N L J Q CO Z�Cy) Z r- U)OOco J_ O l- � �LUzM C H_ J N CO a c00D�ti (n Q L0 K 0004*00 a 0. & TIMMONS GROUP CIVIL ENGINEERING I LANDSCAPE ARCHITECTURE I SURVEYING J G X H W Z W J W 0- G Z ap F� J W Q Q ILL F- o O J 10< z U m o I Q U) - z a z �o EQ W Q 0 w ti w 2i � a_ YN 0 = Q Jz U J F--- - o F- U) 2 Q LL (j) 2 Q w O ' O O� = U L c) � U) D \i\ \ \liiH lj/I i 7��\ vCA�/ 7i ,v�0 «Z 11 ,< No G :11i P6'(j\W, � T.J :, I p`✓\° • i 11 R SLA��y\,� IS G ////1llli0\\` 1 SD - 100% 08/25/17 B No REVISION/SUBMISSION DATE COPYRIGHT 2011 - RNL This document, and the ideas and design concepts incorperated herein, as an instrument of professional service, can not be used, in whole or in part for this or any other project, without the written authorization of RNL. PROJECT No: 39722.001 DATE: 08/25/2017 SCALE: AS SHOWN COVER Aoo-c000 Cn Z Z (5 � � C7 Z O,_j H � I Q J 0 w LL Q lU Y >- 2 = U Z I Q��� LL D U) W 0 J Z I W j U U Z 0 U) W p J Z U 2 , z w w Q, � W Q / 1 \..J U LU Q I � LU Z 0 CO W 0 J Z I G X H W Z W J W 0- G Z ap F� J W Q Q ILL F- o O J 10< z U m o I Q U) - z a z �o EQ W Q 0 w ti w 2i � a_ YN 0 = Q Jz U J F--- - o F- U) 2 Q LL (j) 2 Q w O ' O O� = U L c) � U) D \i\ \ \liiH lj/I i 7��\ vCA�/ 7i ,v�0 «Z 11 ,< No G :11i P6'(j\W, � T.J :, I p`✓\° • i 11 R SLA��y\,� IS G ////1llli0\\` 1 SD - 100% 08/25/17 B No REVISION/SUBMISSION DATE COPYRIGHT 2011 - RNL This document, and the ideas and design concepts incorperated herein, as an instrument of professional service, can not be used, in whole or in part for this or any other project, without the written authorization of RNL. PROJECT No: 39722.001 DATE: 08/25/2017 SCALE: AS SHOWN COVER Aoo-c000 1 12 13 14 15 16 17 18 19 110 \ VF N/F L / / \ ANIMAL PROTECTION N/F / ENERGY UNITED SOCIETY OF DURHAM \ \\ NOEF LLC PROPANE \ / PIN. -0842-09-27-4073 I \ PIN.- 0842-01-27-99 PIN: 0842-09-27-3940 / DB. 2807 PG. 476 DB. 6402 PG. 871 DB. 8094 PG. 284 N/F �c LANDUSE: INDUSTRIAL \�\ LANDUSE: VACANT � , • A USE: COMMERCIAL / \ COMMERICAL BIK PROPERTIES LLC ZONING: IL ZONING: IL / / J ',' ON/ IL / PIN: 0842-09-17-7843 ' DB. 5595 PG. 538 / 2116 CAMDEN AVE\�- 6.86 AC. \\ t LANDUSE: COMMERICAL/ CONVERTED RESIDENTIAL - -W W TA' N' ;A' K ZONING: IL `YTYP Lsi--- SHEET- C2.0, 6.6,C4.0 i _ - N/F CEMETARY PIN: 0842-09-18-5025 I SPN Y. '4L)...'.'. DB. 159 PG. 35 --- 2002 CAMDEN AVE I 0. 18AC. LANDUSE: CEMETERY I -%' MIST LAKE AFL I I� WE \�A ZONING.' IL . L --:- Ti� II .. ---- Fe� 100 I \ SHEET- C2.2, C3.2, C4.2 \ II PROPOSED H �''II�II BUILDING so I AND AR A x D , UjZ D SHEET- C2.11 C3.11 C4.1 m G �' I �I �`v `vv x -------_--_- III L loLIFJ D o_ o ,t x ;(TYPO!gAL) F E IC C B 1 1 2 1 3 4 5 �-�-.......-..-50'NEIJ UFF�R' W WLL W W W W W LL -100'FF�-- .......... I x X, .. .... �\\ I I I I I I I I I I I N/F \ TY OF DURHAM \ \ :0842-09-05-2966 B. 1150 PG. 629 \ \ \ L NIDUSE: VACANT �CO IMUNITYSERVICE \ I I x I Li I I I I I x N/F ZONING: IL I \ \ \ I I CITY OF DURHAM PIN: 0842-09-06-1562 DB. 267 PG. 540 . LANDUSE: PUBLIC SERVICE \ \ I x ZONING: IL \ \ CITY OF D\ , A I :0 -09-05 966 DB. 1150 PG. 9 �DUSE�.- INDUS 7 \ IAL \ ZO NG: IL x N C- \ 1' 1 � J \ \ \ \ \ j ' � I II I I! I I I 7 1.1 go 10 11 12 13 14 15 11 12 13 14 15 16 0 > N L m Q > Z Z ti U) (D O co J -0 �LuZ o U) Q Lr) Iff 21 TIMMONS GROUP CIVIL ENGINEERING I LANDSCAPE ARCHITECTURE J SURVEYING J G H Z W W a Z F LU J Q ILL O O J Z , m �O LULLZ ELLjQ w X J W LU Q � W � Q� M � J J W J= � C/) Q C) _moo 2i ILL O 2Oti Lu C:) U o C0 cUn U 0 Z C A i�Z �Jvii C 1 SD - 100% 08/25/17 B No REVISION/SUBMISSION DATE COPYRIGHT 2011 - RNL. This document, and the ideas and design concepts incorporated herein, as an instrument of professional service, can not be used, in whole or in part for this or any other project, without the written authorization of RNL. PROJECT No: 39722.001 DATE: 08/25/2017 SCALE: AS SHOWN OVERALL PLAN 00-0001 CO Z Z (D Y U) } W 0 Z Z = J CD CD W W I p Lj p J W a Z� J 2 W Q J H w E a Q E Q O� Z Q J 2 a 5 2 U Z OfU W U = Q? U Q U WO M 2 w G H Z W W a Z F LU J Q ILL O O J Z , m �O LULLZ ELLjQ w X J W LU Q � W � Q� M � J J W J= � C/) Q C) _moo 2i ILL O 2Oti Lu C:) U o C0 cUn U 0 Z C A i�Z �Jvii C 1 SD - 100% 08/25/17 B No REVISION/SUBMISSION DATE COPYRIGHT 2011 - RNL. This document, and the ideas and design concepts incorporated herein, as an instrument of professional service, can not be used, in whole or in part for this or any other project, without the written authorization of RNL. PROJECT No: 39722.001 DATE: 08/25/2017 SCALE: AS SHOWN OVERALL PLAN 00-0001 L I f:■1 G I F E I f71 C I B I m z 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 "--- ----------------- 7 --------------- 7 / 6 FLAGGED STREAM /' \\ <<< T/ / III v / 94.0 A/ � \ � \ / , � 111 �Q) ' A/ w \ POND / /W / \\\\\\\ 94. 5 I c \� \ RETAINING WALL i 296.0 \� \ 30 .6 1 I 3 4 T ( F1) YlJ HAM ��� PB. #3 PG. 14 \ \ v 41 w v/ v \1/% w �\ 0.03 AC. / \ `� \ \ \ \ WETLAND AREAS / N LSE.• INDUSTRIAL ��A� (TYPICAL) ZONING: IL �\ / _77— A/ � \ \\ i I it MIST LAKE \\ \ \ 04' SCM ACCESS AND — - \ MAINTENANCE - 1 EASEMENT - 1 RIP RAP / --\ i / \'/ ' z, ENERGY - - DISSIPATOR \_�,; -\\ / // / /, // / /� cow - CV' \ I \ v� \A y y v vv v v - - y SPLTTTER BOX RMWI Qb 3 - L -LEVEL - -� SPREADER W/FIUT RIP 315 ---- i IAf 0' — — — - - - S O M 3�8 v\ v\ v / CATCI / -UNDERGROUND UNDERG 379 ` \ \ BASIN (TYP}\\\\ \ \ < < < I r \ / \ FILTER I v7Hit I - - A In / \ \ \ \ \ U�� 1 1 O cY, // r - -320- \ \ \ \ \ I _ I I I I I � I � I I ✓/ I I I I I I I I I � -------------- � \ \\ TORIV I / _ - _ _ - FLOW - _ _ IPE (TYP v v I-_--SCM-ACC-ESS-A D SPUTTE_RBOX_ - - - MAINTENANCE _ EASEMENT00 - M I \ Ax v v\v EPARTMENT OF WATER- \ \ , MANAGEMENT FACILITY _----- F-F�21.00 1 1 7 7 r \ \\ \ �ETAINING WALL / L11 > \ I - I- I � / \ x I I I I I // I INLET (TYP) v I T/W I 316.0 I I I 5 L 7 I I 10 12 13 14 SCALE 1"=40' NOR 0 40' 80' 15 16 16 L K H G J O O > N J CO � Z ZO ti U) O O co J_ CO f— �WCID zM O H_ J N U) L0 a � TIMMONS GROUP CIVIL ENGINEERING I LANDSCAPE ARCHITECTURE I SURVEYING CO Z Z (D Y U) } W p Z Z = J CO Q Z� w U - W I p W p U) J W J W Q Q J OLL Z Q J I Z � H z U Q Q Z w W z Z U 0 (U v I O m Q� z C) p=w a�= U= U ULU U i (n Q z a 2 W I - Z W W Q z F � J W Q I O J z U m o LU Q D LL Z a Z Ep w< J w W Q W a_ Q2 o J J W J= 0 C� �_ U) Q vJ O O N = U o Q0 cU U 0 Z n D \\1�,�IIIIItjjj�' �. `A CA ;n-0 All, It C 1 SD - 100% 08/25/17 B No REVISION/SUBMISSION DATE COPYRIGHT 2011 - RNL. This document, and the ideas and design concepts incorporated herein, as an instrument of professional service, can not be used, in whole or in part for this or any other Project, without the written authorization of RNL. PROJECT No: 39722.001 DATE: 08/25/2017 SCALE: AS SHOWN GRADING PLAN A00 -C400 XTDROP - I 10 12 13 14 SCALE 1"=40' NOR 0 40' 80' 15 16 16 L K H G J O O > N J CO � Z ZO ti U) O O co J_ CO f— �WCID zM O H_ J N U) L0 a � TIMMONS GROUP CIVIL ENGINEERING I LANDSCAPE ARCHITECTURE I SURVEYING CO Z Z (D Y U) } W p Z Z = J CO Q Z� w U - W I p W p U) J W J W Q Q J OLL Z Q J I Z � H z U Q Q Z w W z Z U 0 (U v I O m Q� z C) p=w a�= U= U ULU U i (n Q z a 2 W I - Z W W Q z F � J W Q I O J z U m o LU Q D LL Z a Z Ep w< J w W Q W a_ Q2 o J J W J= 0 C� �_ U) Q vJ O O N = U o Q0 cU U 0 Z n D \\1�,�IIIIItjjj�' �. `A CA ;n-0 All, It C 1 SD - 100% 08/25/17 B No REVISION/SUBMISSION DATE COPYRIGHT 2011 - RNL. This document, and the ideas and design concepts incorporated herein, as an instrument of professional service, can not be used, in whole or in part for this or any other Project, without the written authorization of RNL. PROJECT No: 39722.001 DATE: 08/25/2017 SCALE: AS SHOWN GRADING PLAN A00 -C400 L 1 171 G I F I �I C I 2 3 5 7 10 12 13 14 BAN _ \ \ \� ------ ' / 299.25 --- -- �t`�� - - _)( XNiC \� 317 --- �--- -- --- J T/W / 1\\ 110" \`\JLE - - -- t90 \\� \ \ \ �\ \ \ \\ \ \ \ _ SHEET -C4.0 / / 1k)lv�� v�� �\ `\\`��_� /o oM - \ ` MATCHLINE MM`MAINTENANCEBUILDING293.E T/W \ \\\ _ IF F--320.-00oo - 303.p J ------ 2-96.0 L_ RETAINING - 7W �T \ ` \ 3 6 ` / '- -_ 293. � � \ - - - -----/ ' J, A/ J/ FC T RMW - STORMWATER- / v v v \ I T X - A)NQTIO"OX - - _ � \ � \ \ \ - U CTION BO / 292.5 `'292. \ \ \ \ \ \ / W/MANHHOLE - ST - - - - w J v V \ v \ V A M V v - \ - - — - _ _ PIP TYP i \l/ J/ A/ v J/ J/ � \V v Jr J/ V A T v A \ \ V \ Iri (� \ \ \ \ \ A — - ----- T/W \ \ FLOW ---__ - _ � � � � J, � J, � J, � J, � J, J/ v, J, v X299.0 � v v v \� \ v � � - - - - - - - _ x � � � � ITTER�OX - � \ \ \ _ _ \ 5 \ \\ 3 --- _— -- - 293.0 95.0-------- VJ J, � J A/ A/ w J, J J w v ' A/ J � � J J J �v v �\ v 01.75 Llb TIW w J, � J, � � J J \ 29 .0 3�I \ SA G E D -UNDER D -F �TE - - - - - - � \ � M� \ � D � - DROP � y J w J J, � J V B92 7� \ A A v \ 315.0 eco t� - _ _ - - - - - _ INLET TYP \ \ M \ � _ � � \ — — _ — -- �\ W J/ J/ J/ J/ J/ w J/ J/ J/ w J/ Jr w J/ Jr � y J/ Jr A/ w J/ Jr Jr w vi Jr Jr J/ J/ J/ J/ J/ I- BAN _ _ — — q 0 J J J J J J J �� w\ \ 3'1'9:0 v\ S 29RI�WAT _O Ad- _ y - y __ �� I I BASI/Id (TY J � � � vk q/ J J � � \29vv7 0 _ _ v v v J GW OId B JUNCTION �---<v J/ Jr \ J/ Jr w J/ A/ J/ Jr Jr V J Jr J/ J/ J/ J/RIP RA _ -W/ A H — j ENER��s \\\ \\ - \ - J J J J �� / v V LA�iGYfft V\� — v J w \ v J J J J- J v i I ObN J, I \ /�\ /� - - \ N / I COVERED J rI� \ - - - VEHICLE w vi J/ J/ J/ J/ A/ Jr vi J/ J/ J/ J/ J/ J/ J/ V u J, V J Jr �J Jr A10� F/J-6 BL/Fl J v I ' \ \ w A / \ _ I I STORAGE- � � J v J 41 J v + w J A/ J, J, + + ( ( ( J � f NIIdG ASL _ ' '� i J FFA 3LO.00 50' NEUA/ BUF - / EL9W/ - - \ / / v J A/ \j/ "� - - - ' - --- w � + � v/ Jr J/ J/ � Jr J/ J/ w J/ J/ � J/ � � J� \ V A �\\ \ � / w I I+ I � Op 10111/ A/ �� J/ A/ J/ \ \ \ J o i I /oo0+ v J J, J A A V A / 30 . "� A y S N/U bEQ PILT ' / / F�LI TE iJ SCM ACCESS AND \\- MAINTENANCE i w EASEMENT �' // / — / \ / 'IT/ ,' _---- z X SO�� J z Q y / / / / \ A- ER I �II / /' SCM ACCESS AND J \ UddCTION pX l MAINTENANCE i - / / v H LE v �v NORM / EASEMENT FAQ \ I / / HI HE (1\YP) /319 ' /STREAM ySTA. V ) ' FUTURE 100 \ \ \ r� 1 I I \ + �' �' �' � � SPREADER � I � I � I I I / / $FE = 29,6.9 � � v / l 41 J/ J, W/FILTER STRIP ill 30*tO- ,`SF J J vv v\ v_ X A A A V 31$ / \ i � CATCH \ �\ ASIN DROP / v J J J �� y �� \ V A I I I / INLET (TYP) / / o M t M 401 RETAINING WALL y I COLLECT v v v \v \ SYStEM T/W' /W 302.0 OIU�RFL / ,�� B/W \ BUILD�N v 302.5 v v v v v vv 317 T/W y v A \ 31� 296.0 \ \ \ \ \ \ \ \ \ \ \ \ \ , \ 295.0 �\ \NIF O Cn \ M M \ ` \ \ \ I CITY OF DURHAM \ I I I vv \v \ �\ A \\ V II X \ \ \ �4! 75 \ \ \ \ \ \ I PIN: 0842-09-05-2966 � \ � I � v V v v v v v A� v I DB. 1950 PG. �9 � \ � ` \ \ \ \ \ \ \ LANDUSE.VACANT COMMU ITYSERVICE \ \ ZONING: IL '195 0 \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ x \ \ \� \ v A\ v v v v v v v � vv 1ib07y v v vv v �s v v v v v V � �vv316 � \ \0 \ \\\\ \\ \ \ \ \ \ \ \ \ \ \ \ \ \\� \\ STORM vv v v v v v \ \ v v v v\v v v v v v v v \ \ RETAI NG AL I I 1 1 X \ \ \ \ CH BASIN �T1kP) \\� \ \ \ \ \ \ \ \ \ \ DR P \ \ FLI P P A v v v INLE�(TY�P 1 X10 \E\NAtY \ 5 V \ I I v v I O o f DiS�11 ' �O� \ I vp v v v v IX \ \ \\T \ \ \�\ \ 305 T \\\ \ \\ \\\\ \ \\ \ \ \ A/ 29 \ \ 29 vVv v`vVvv vv \v v v\ v v v 1 3 4 5 L 7 E: 10 12 13 14 15 SCALE 1"=40' 0 40' 80' 15 16 L K H G J O O Ci N > N m Q z zrn ti U)O O co J_ CO W Z M O H_ J N cC)ti cn Q LO a � TIMMONS GROUP CIVIL ENGINEERING LANDSCAPE ARCHITECTURE SURVEYING CO Z Z_ (D Y U) } W C) Z Z _C� 0 Q z w O — w I p W p z J W J W Q Q J z J Z Q I J H z U Q I W z Z U U)v O 2 m Qor_ z p p= LU U a C) U 2 U LLI U (n Q z LU a :2! W Z 01 W W O 0 Q Z F I Q� W J Q LL O J G z ULU m VJ Q LL U_ ELU W p W X Q � J JJ W W LL (N 2 O (f O U 0F-�Uo D \1�\\XIIIItj/I/'/ J �A CA O� 11 ' � 'alf�.i�.�,.•��®dam C llfill411\ 1 SD - 100% 08/25/17 B No REVISION/SUBMISSION DATE COPYRIGHT 2011 - RNL. This document, and the ideas and design concepts incorporated herein, as an instrument of professional service, can not be used, in whole or in part for this or any other project, without the written authorization of RNL. PROJECT No: 39722.001 DATE: 08/25/2017 SCALE: AS SHOWN GRADING PLAN 00-C401 01 O 0 I Y U_ _ ~ ti W O (N 2 C:) U �0z \1�\\XIIIItj/I/'/ J �A CA O� 11 ' � 'alf�.i�.�,.•��®dam C llfill411\ 1 SD - 100% 08/25/17 B No REVISION/SUBMISSION DATE COPYRIGHT 2011 - RNL. This document, and the ideas and design concepts incorporated herein, as an instrument of professional service, can not be used, in whole or in part for this or any other project, without the written authorization of RNL. PROJECT No: 39722.001 DATE: 08/25/2017 SCALE: AS SHOWN GRADING PLAN 00-C401 L K J H G F E IC C B 1 1 2 1 3 1 4 1 5 1 6 1 7 1 8 1 9 1 10 1 11 1 12 1 13 1 14 1 15 I F T/W i 296.0 �w 0 LLI vi I I I j a' I II II to It RETAINING WALL 15.01 1 I I I A/ A/ v RIP RAP S RM I v / I /W \ I <ill w � \ ENERGY , I PI E (T P) I / rn I X311. ° v I I v DISSIPATOR v I / p 1 v I h / I I I A/ �TCH 'C3) I II I I w v i BASIN (T I \ CO I / I 1 o + I � I / / co / I I / / , � T 1 I II A w I 1/ , 316.0 I I / B IN / \I 3111.5 LT I N WETLAND AREA I I I I ("TYPICAL) I R6�0' 1 STOR `v PIPE 1 , , Zz C\1 I ICY / ) A T _ R50 / CATCI T / / — - - - \ 1 I I I / m m I B ��ASI �� 30 .0 �' / � - _ — - MATCHLINE II \ / / B/W , - - - �� SHEET C4.1 I v / , //299.25 i t I II A/ � ^ \ \ (' / TNV I I� w \j/ �� I I v v v < LI ISOF � , N X -� - - ---- v v v v I v M M- I w I C) A/ II Io v i - T/W - 293.5- - - - T/W - - i 303.0 296.0 I 771 v� � � - � � �� ��_RETAINING w � w - 1 W w 293.0 \ m _ ' 293. \T 1 �� ✓- 10 w � 29 - + o T / - 292. --� I -� 292.5 � w A/ Vi/ Ji / w w A/ A/ � � � I A/ Ji A/ � \V \V � - - \V A/ \ `� �� T — \V I I � y \k 4 � 4/ 1 I w w A/ � w\11 \11 \ t 41 \L1 \P 41 \k / \L1 \k \L1 41 \k \V All A/1 I A 1\ 41 \11, \L� + \V \k \P 41 \11 I VJi V Vl \ I 1 Ji Ji Ji A/ q \V \ \k 41 1 - - - I I - 1 A I \ w I I t � `SCM ACCESS AND I I I R30' MAINTENANCE �� 700, _ \ EASEMENT R165' F�SF \ �v 41 SCALE 1"=40' R30' \ 0 40' 80' I 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 16 L K J J 07 O � N > N J CO � z -M ti U) o O c0 J_ CD � CO (D (=) W 0 O J N CD CO��ti � co TIMMONS GROUP CIVIL ENGINEERING I LANDSCAPE ARCHITECTURE I SURVEYING G I - Z W W Q Z F LU J H >. Q Q LL ~ o O J Z U m o LU Z LLZ ELLIQ w X J W W Q LU Q O � J J W J= I U)0 vJ QC 0 _5O G OLL SDI` W C:) CV 2 U o (�U (Un U 1 0 Z D \\I�Illllllfjjj�'/, CA O 0 � e �•h' BLA��°'� ��� C 1 SD - 100% 08/25/17 B No REVISION/SUBMISSION DATE COPYRIGHT 2011 RNL. This document, and the ideas and design concepts incorporated herein, as an instrument of professional service, can not be used, in whole or in part for this or any other Project, without the written authorzation of RNL. PROJECT No: 39722.001 DATE: 08/25/2017 SCALE: AS SHOWN GRADING PLAN 00-C402 C/) Z Z_ U Y � } W 0 Z Z = J U 0 O J Z Q� W W U' >- Ur w t oo C/)IL 2 Qi Q 1W J W J J Z Q I Z O J H W Q I U Q I Q W� W z _U U U 2 Q D_ Z F- _O m J C) U H U W U = Uc~r� Q z WO a 2 w G I - Z W W Q Z F LU J H >. Q Q LL ~ o O J Z U m o LU Z LLZ ELLIQ w X J W W Q LU Q O � J J W J= I U)0 vJ QC 0 _5O G OLL SDI` W C:) CV 2 U o (�U (Un U 1 0 Z D \\I�Illllllfjjj�'/, CA O 0 � e �•h' BLA��°'� ��� C 1 SD - 100% 08/25/17 B No REVISION/SUBMISSION DATE COPYRIGHT 2011 RNL. This document, and the ideas and design concepts incorporated herein, as an instrument of professional service, can not be used, in whole or in part for this or any other Project, without the written authorzation of RNL. PROJECT No: 39722.001 DATE: 08/25/2017 SCALE: AS SHOWN GRADING PLAN 00-C402 APPENDIX E RIPARIAN BUFFER VARIANCE REQUEST SUBMITTED AUGUST 31, 2017 PREPARED FOR: CITY OF DURHAM - DEPARTMENT OF WATER MANAGEMENT 1600 MIST LAKE DRIVE DURHAM, NC 27704 MIST LAKE FACILITIES EXPANSION VARIANCE REQUEST AUGUST 2017 PREPARED BY: TIMMONS GROUP .•••••� YOUR VISION ACHIEVED THROUGH OURS. • • 1001 BOULDERS PARKWAY, SUITE 300 RICHMOND, VIRGINIA 23225 PHONE: 804.200.6500 FAX: 804.560.1648 WWW.TiMMONS.COM P.N. 39722.001 EXECUTIVE SUMMARY On behalf of the City of Durham — Department of Water Management (Applicant), Timmons Group is submitting this Variance Request for the expansion of its Mist Lake Facilities (Project). The proposed Project is situated on a 55 -acre parcel and consists of the construction of two buildings totaling approximately 116,000 square feet: one to house the administration, warehouse, and the other to hold the equipment maintenance shop, as well as appurtenant facilities (utilities, stormwater, etc.). The purpose of the proposed Project is to expand the existing facility at Mist Lake, in order to accommodate multiple City of Durham Department of Water Management (DWM) divisions and allow for potential moderate growth over the next 20 years. The DWM Mist Lake Facilities Expansion project consists of two buildings totaling approximately 116,000 square feet, which will consist of a building for the administration (which will provide office space for the five divisions), and a warehouse, shops, and laydown area to store equipment when not in use or undergoing repair for the maintenance division. The Project is consistent with the zoning requirements for this area (IL - industrial) and is being undertaken to consolidate multiple divisions that at present are located across Durham in one location, which will create cost, logistical, and overall savings for the locality. This property has been owned since January 1997, and its purchase was intended for this proposed Project. If the City cannot use the existing property to consolidate the five divisions then the initial investment on the purchase of the property will be lost, additional property will need to be purchased to relieve the additional space requirements needed at the remote facilities, as well, the property cannot be used to consolidate the multiple divisions in one location. Logistically this will cause inefficiencies, create other impacts associated with the development of another greenfield property that are significantly more than the proposed Project, and will not solve the original problems that were the impetus of consolidating the divisions at one location. To accomplish the goals of the Project, impacts to the Riparian Buffer are unavoidable. A total of area of 24,935 square feet (SF) of unavoidable permanent impacts to riparian buffer is necessary (Zone 1 — 13,083, Zone 2 — 11,852SF). These unavoidable impacts will be mitigated through the purchase of compensatory buffer credits through an approved wetland mitigation bank. The total compensatory mitigation proposed is 57,027 SF of buffer credits. The purchase of this compensatory mitigation will ensure the unavoidable impacts proposed by the Project and will not result in a buffer loss that will affect the water quality within the watershed. Variance Request Timmons Group Mist Lake Facilities Expansion August 2017 Page i MIST LAKE FACILITIES EXPANSION VARIANCE REQUEST TABLE OF CONTENTS EXECUTIVE SUMMARY............................................................................................................ i 1.0 PROJECT INFORMATION SHEET................................................................................ 2 2.0 INTRODUCTION............................................................................................................ 3 3.0 SITE DESCRIPTION...................................................................................................... 3 3.1 Site Location............................................................................................... 3 3.2 Site Conditions........................................................................................... 3 4.0 PURPOSE AND NEED.................................................................................................. 4 6.0 RIPARIAN BUFFER IMPACTS...................................................................................... 4 7.0 DEMONSTRATION OF NEED FOR VARIANCE/AVOIDANCE AND MINIMIZATION ... 4 8.0 COMPENSATORY MITIGATION................................................................................... 6 FIGURES Figure 1 Vicinity Map Figure 2 FEMA Map Figure 3 Jurisdictional Waters of the U.S. Impact Map APPENDICES Appendix A Variance Application Appendix B Wetland Delineation Information Appendix C Proposed Layout and Preliminary Stormwater Plans Appendix D Original Layout Appendix E Compensatory Mitigation Documents Variance Request Timmons Group Mist Lake Facilities Expansion August 2017 Page ii 1.0 PROJECT INFORMATION SHEET Anticipated Permit Authorizations • U.S. Army Corps of Engineers: NWP 39 — Commercial and Institutional Developments • NC Department of Water Resources: 401 Water Quality Certification/Buffer Compliance General Project Name: Mist Lake Facilities Expansion State: North Carolina Location: Durham County Latitude: 36'01' 16.27" North (36.021) Longitude: -78'51'31.70" West (-78.858) Subject Property Size: 55 acres (Study Area approximately 85-95 acre) Limits of Disturbance: 21 acres (Project Area) HUC Code: 03020201 (Upper Falls Lake, Neuse) Waterbodies on Property: UNT to Goose Creek and Palustrine forested (PFO) wetlands. Correspondina Information USGS Quad Northeast Durham USDA Soils Map: http://websoilsurvey.nres.usda.gov/app/HomePage.htm County: Durham County, VA Applicant Name: City of Durham — Department of Water Management Address: 101 City Hall Plaza Durham, NC 27701 Contact: Mr. Donald Greeley, Director Telephone: (919) 560-4381 Email: don.greeley@durhamnc.gov Agent Name: Address: Contact: Telephone: Email: Variance Request Mist Lake Facilities Expansion Page 2 Timmons Group 1001 Boulders Parkway, Suite 300 Richmond, Virginia 23225 Mr. Todd Preuninger (804) 200-6399 todd.preuninger(aDtimmons.com Timmons Group August2017 2.0 INTRODUCTION On behalf of the City of Durham — DWM (Applicant), Timmons Group is submitting this Variance Request for the expansion of its Mist Lake Facilities (Project). The proposed Project is situated on a 55 -acre parcel and consists of the construction of two buildings totaling approximately 116,000 square feet: one to house the administration, warehouse, and the other to hold the equipment maintenance shop, as well as appurtenant facilities (utilities, stormwater, etc.). 3.0 SITE DESCRIPTION 3.1 Site Location The site encompasses approximately 55 acres and is located at 1600 Mist Lake Drive, in Durham County, North Carolina (see Figure 1: Vicinity Map). It is bound by 1-85 to the south, an unnamed tributary to the west, and Camden Road to the north. The site is located within the Neuse River Watershed (HUC 03020201) and entirely within the Piedmont Physiographic Province. The adjacent lands are composed of primarily industrial properties intermixed with undeveloped land. The Project drains to unnamed tributaries, where surface waters enter into Goose Creek. Surface waters from Goose Creek flow north to Ellerbee Creek before discharging into Falls Lake, northeast of the Project. A FEMA Flood Rate Insurance Map (FIRM) is included for review (Figure 2: FEMA FIRM Map). The map shows that the Project area is located within an area identified as a X flood zone. This designation by FEMA means the area is a minimal flood hazard, and is above the 500 -year flood level. Please note that a majority of the site has been designated as an "AE" type flood zone with a 1% chance of annual flood hazard. The Project has been designed to comply with applicable FEMA -approved state and local floodplain management requirements and no increase in the 100 -year flood elevations is anticipated. 3.2 Site Conditions The site currently houses several divisions of the DWM in a 20 -acre facility, along with associated vehicles, equipment and inventory. The undeveloped areas, mainly along the floodplain, are dominated by mid -successional mixed pine and hardwood forest with mixed hardwoods adjacent to the drainage ways. The topography slopes gradually from the southwestern corner to the north and east portion of the project limits. The property was delineated by McAdams, during the Summer of 2017. Jason Robinson, DWR, confirmed the Neuse Riparian Buffer locations on June 28, 2017, and a JD request has been sent to Samantha Dailey, USACE. Documents pertaining to the wetland delineation are provided in Appendix B: Wetland Delineation Information. There are no wetlands, open water, stream and associated upland buffers within the Project area that are under a deed restriction, conservation easement, restrictive covenant, or other land use protective instrument. Variance Request Timmons Group Mist Lake Facilities Expansion August2017 Page 3 4.0 PURPOSE AND NEED The purpose of the proposed Project is to expand the existing facility at Mist Lake, in order to accommodate multiple City of Durham DWM divisions and allows for potential growth over the next 20 years. The Department of Water Management Mist Lake Facilities Expansion project consists of two buildings totaling approximately 116,000 square feet: one to house the administration, warehouse, and shops and the other to hold the equipment maintenance shop. The Project is consistent with the zoning requirements for this area (IL - industrial) and is being undertaken to consolidate multiple divisions at one location. The DWM currently operates several of its divisions at 1600 Mist Lake Drive (North Campus). This 20 -acre facility houses approximately 82 staff of the Administration, Plant Engineering & Maintenance, Regulatory Compliance, and Utility Engineering divisions of the Department, along with associated vehicles, equipment, and inventory. Currently, 145 DWM Water & Sewer Maintenance (WSM) employees are co -housed at a second location on Martin Luther King, Jr. Drive, the Public Works Operations Center (PWOC) along with Public Works staff. The WSM workgroups at PWOC are responsible for Outfall Maintenance, Rehabilitation Maintenance, Meter Reading, Meter Maintenance, Service Installations, and Mainline Installations, along with the necessary vehicles, light and heavy equipment, and inventory to maintain and operate approximately 2,600 miles (combined) of water and sewer mains, 8,148 hydrants, 25,896 water valves, and more than 83,000 water meters. The project will expand the DWM Mist Lake facility to accommodate the relocation of the WSM Division from the PWOC facility to the Mist Lake complex and potential growth over the next 20 years. 6.0 RIPARIAN BUFFER IMPACTS To accomplish the goals of the Project, impacts to the Riparian Buffer are unavoidable. The location of impacts to the Neuse Riparian Buffer are shown on the attached Impacts Map (Figure 3: Mist Lake Facility Expansion — Buffer Impacts Map — Sheets 1 - 3). A jurisdictional determination for this area will be provided under separate cover. Therefore, to accomplish the goals of the Project, a total of area of 24,935 square feet (Zone 1 — 13,083, Zone 2 — 11,852SF) of unavoidable permanent impacts to riparian buffer is necessary. The stormwater and utility plans are included in Appendix C: Preliminary Stormwater Plans. 7.0 DEMONSTRATION OF NEED FOR VARIANCE/AVOIDANCE AND MINIMIZATION Impacts to jurisdictional features and buffers were avoided and minimized to the maximum extent practicable by incorporating resourceful site planning, including the utilization of the wetland delineation to adjust the layout to avoid and minimize impacts. Avoidance and minimization were also accomplished during the design phase of the Project. The Applicant has avoided and minimized impacts to greatest extent practicable given the Project's Purpose and Need. The proposed 24,935 square feet of stream buffer impacts are the result of the necessary infrastructure and facility layout, without which, the Project goals would not be realized. Variance Request Timmons Group Mist Lake Facilities Expansion August2017 Page 4 This property has been owned since January 1997 and its purchase was intended for this proposed Project. If the City cannot use the existing property to consolidate the five divisions then the initial investment on the purchase of the property will be lost, additional property will need to be purchased to relieve the additional space requirements needed at the remote facilities, as well, the property cannot be used to consolidate the multiple divisions in one location. Logistically this will cause inefficiencies, create other impacts associated with the development of another greenfield property that are significantly more than the proposed Project, and will not solve the original problems that were the impetus of consolidating the divisions at one location. In order to provide adequate space for parking and buildings, a minimum of 21 acres of buildable land is necessary. The southwestern portion of the site is relatively narrow and is constrained by setbacks along the Interstate and wetlands to the north. A stream and its corresponding buffer bi-sect the property in this area and cannot be avoided. An additional constraint to the site is the need to provide access for emergency vehicles in the event of a fire. To comply with current IFC and local fire codes, pavement is proposed around the site, such that fire apparatus vehicles have access to within 150 feet from all parts of the building. To comply with this requirement, impacts to the buffer cannot be avoided. Offsite alternative sites were explored for this Project; however, in order to provide adequate building space and parking for all divisions, at least 21 acres of buildable land are needed, as well as an adjacent roadway infrastructure that supports heavy truck use. The current location allows for future growth, provides better utilization of existing personnel and equipment, utilizes parts/tools warehousing and non -duplication of housing parts, provides for better internal communication between divisions, and provides protection of parked vehicles and equipment during flooding, which is now experienced at the current location of the Public Works WSM Division, located southwest of this facility. In addition, the proposed layout provides more acceptable storage and in-house work area conditions (e.g. dedicated pedestrian walkways), which provides for a safer work environment for personnel, while utilizing the existing utility and road infrastructure. Given the design constraints associated with a shared use facility (i.e. administration buildings, maintenance warehouses, work vehicles, equipment storage) and the local zoning requirements, the applicant has minimized impacts to the greatest extent practicable. Specifically, there is a setback associated with Interstate 85 along the southern property boundary. This 50 -foot setback limited useable space for parking and buildings along the southern property line and pushed the development to the north, towards the wetlands and stream buffer. Moreover, the southwestern portion of the property is bisected by a stream/buffer, and in order to provide space for a building and parking, buffer impacts could not be avoided. The applicant explored the use of retaining walls along the northern portion of the parking lot; however, this option provided very limited avoidance, as space is still needed for parking and emergency vehicle access. Furthermore most of the vehicles and equipment being stored at the site are large construction vehicles and equipment, which required more storage area than a passenger car or truck. Construction equipment and vehicles require more space to maneuver (i.e. larger turning radii, larger parking areas, etc.), as well, when being serviced these vehicles require large services bays, as well as additional areas with the lay down area for the large equipment (lifts, hoists, cranes, etc.) needed to service the larger equipment. Therefore, the typical parking requirements for an office building do not apply, and are considerably larger based on the type and number of pieces of equipment. Variance Request Timmons Group Mist Lake Facilities Expansion August2017 Page 5 Approximately 368 parking spaces are required for the site. This includes parking for the visitors, employees, and fleet vehicles (both large and small), as well as the additional handicap spaces required by the City Ordinance. The original layout (Appendix D — Original Layout) proposed additional impacts to the wetlands and a stream channel in the northern portion of the property for an entrance road and the proposed fill slope for the parking areas and pad sites extended into the wetlands in the central portion of the property. The layout was re -designed, in order to avoid impacts to the forested wetlands and stream channel through the use of retaining walls. The entrance road from Camden Avenue is a safety requirement, in order to provide safe ingress and egress, as well as allow for multiple access points for emergency responders (i.e. fire, EMS, etc.). The road was re -located in an area that avoids impacts to streams and wetlands. Moreover, stream impacts have been completely avoided through the use of a bridge. Other measures taken to minimize impacts include the use of a suite of stormwater devices (e.g. underground sand filters, underground detention, and filter strips) for stormwater treatment. This reduced the need for detention ponds, which further reduced and minimized the impacts to the adjacent stream channels, wetlands, and/or riparian buffers. A project -specific Erosion and Sediment Control (ESC) plan will be developed and submitted to Durham for approval of the land disturbing activity. The ESC plan will be prepared in accordance with the North Carolina Erosion & Sediment Control Laws and Regulations and the most current version of the Erosion & Sediment Control Planning and Design Manual. The ESC plan will be approved by the locality prior to any land -disturbing activity associated with the Project. All regulated land -disturbing activities associated with the Project, including on- and off- site access roads, staging areas, borrow areas, stockpiles, and soil intentionally transported from the Project Area will be covered by the project specific ESC plan. During construction activities, the ESC Best Management Practices (BMPs) will be inspected and maintained throughout the life of the construction activity providing for enhanced protection for the avoided jurisdictional areas and further minimizing impacts to the aquatic resources. 8.0 COMPENSATORY MITIGATION Compensatory mitigation for these unavoidable impacts will be achieved through the purchase of off-site mitigation credits from a mitigation bank, which is approved for use in the Neuse Watershed (Hydrologic Unit Code 03020201). Buffer mitigation credits will be purchased using the Standard Compensatory Mitigation Ratios at ratios of 3:1 for Zone 1 (39,249 SF) and 1.5:1 for Zone 2 (17,778 SF). This equates to a total compensatory mitigation obligation of 57,027 SF of buffer credits. Credit availability letters from the North Fork Little River Buffer Bank an approved wetland and stream mitigation bank located in HUC 03020201, are located in Appendix E: Compensatory Mitigation Documents. Variance Request Timmons Group Mist Lake Facilities Expansion August2017 Page 6 FIGURES �4 TIMMONS GROUP YOUR VISION ACHIEVED THROUGH OURS. WRC Wi! SOILS MAP FOR MIST LAKE DURHAM COUNTY. ' S � f r ' N- M U) Ol In 00 rn ON x a LL 7A t OIL ., 40 - .1•.' •-X�• ..'� . �j�, - � ��� , � •l4 y - ,•�y[Y�� •Yt � .rq: i � n �-�'f r� � 1 + r� `' I � v R .tip =• 9 �+y Y • ^'�� • �' , �`,-• . ' fin' +' �'{ n' t rll,••.� .-� It Fi,,�• s•� . }: ,.vi y-�•..• .'�. _ / '-. '-. -� �� .iii �'" ^tL1 j•�• '.h .-.. .q.. '•Iys 1 • '' A ^P'sy'•--1 < <IJ n� � y I 0 Legend `. Project Study Limits L cli cli AE: 1 % Annual Chance Flood Hazard " X: <1 % Annual Chance Flood Hazard 0 200 400 800 Feet +" 6 ow 'o�� 0 AV� DATE j .d. a 07/25/2017 N m r t6 DRAWN BY t L. MAJOR 3 DESIGNED BY n L. MAJOR a CHECKED BY a . . T PREUNINGER o SCALE i 1=400' 3 V/ o Z zLU a J Z& oo � AV� m r t6 Z0 V/ o Z zLU a J Z& oo � X N2 0 A' LL! p o = O O E @_ a0 O J Zz J LL V Q Z H Q Z W y Z w 0 a LL p LL N W Y a w ~ 0 o 0 a= J D2§ D m N //� C9 LL > 0y X = N O �/� S :E 2 N N U N O E 'a _ U @ 06 n= 0a m n U � O � N O � U n2 NUMBER y 0 39722.001 m o SHEET NO. y N 1 OF 1 co J 75 Q co 0 N N N co C 0 d 0 0- N N N r- rn M C) o co 1 \ 1 I I 1 ` 1 1-11 1-000, 2 O �oopp ooP ''/ C-) so 0o y ol,� c? , , -o �Z zoom �C�, T 2 0 Z02f� �j �o n� 7< pp o0 0� C) ' Z � 'off orn��-� =c` 0 O0\ 0 0 � 2G? pG c "-Q -7 2 1 I z O z < CL a X Q Wz J O (n (n < W W U i --a 2 �--� Q O 0 � � z 0 v J LL = W U W Q D 0 a J U) JOB NO. 39772.001 SHEET NO. 1 OF 1 0 c tn U C N d O tnm 3 m 0 0 a C CL T C a 0 0 m tn c co C CL c a a 3 cm O s V H Z L O 3 V � L U +j ui U) w m L Z O N LU _ 10 O CD 7 — O 4w _ O w E LU fl. w z O Q Q O O 47 DATE U)) Q > :Lj 08/22/2017 O (n DRAWN BY L. MAJOR • DESIGNED BY • BLAKE HALL • CHECKED BY • T. PREUNINGER • • SCALE 1 " = 150' z O z < CL a X Q Wz J O (n (n < W W U i --a 2 �--� Q O 0 � � z 0 v J LL = W U W Q D 0 a J U) JOB NO. 39772.001 SHEET NO. 1 OF 1 0 c tn U C N d O tnm 3 m 0 0 a C CL T C a 0 0 m tn c co C CL c a a 3 Impacts Table Impact ID Riparian Buffer (sq. ft) Impact Temporary Permanent B 1-Z1 13,083 B 1-Z2 I - 11,852 Total 0 sq ft 24,935 sq ft 0.00 ac 0.57 ac Legend Project Study Limits '---r LOD F I - Limits of Disturbance - 21 Acres CIO J © Riparian Buffer Zone 1 Impact © Riparian Buffer Zone 2 Impact --------. ... .... Stream Centerline — --- —"' Stream Top of Bank ---------' Retaining Wall 1 1 Neuse Riparian Buffer _____ `------ Neuse Riparian Buffer Zone 1 Impact Neuse Riparian Buffer Zone 2 Impact - Wetland Pond NOTES: 1. WATERS OF THE U.S. WITHIN THE PROJECT STUDY LIMITS ARE SOURCED FROM MCADAMS 2. WATERS OF THE U.S. HAVE NOT BEEN CONFIRMED BY THE U.S. ARMY CORPS OF ENGINEERS. 3. PROJECT LIMITS ARE APPROXIMATE. 4. TOPOGRAPHY BASED ON USGS LIDAR DATA. N 0 75 150 300 9 Feet ----- , I r I r � , r _ rr, oCIO-------- -- - - -- - - - - -� .' f '•�-r P la 44, jib I / •I II I — --I — ' fl r / - f ..i. ••-� ' � �+ 0.I X r I ` �' //�, ■ it f F- ♦ '` Z � I ••• ■ 1 I 1 S �11 _ I ', J/ �, //' ■ � Jf,�' �� ♦ ♦ � ■ --- �.� - y 1 x%11 1 +`` ' _ I 1 �� �� d 1 ► . �►CC 1 r a '� ! �i � � %ra't� a.vu•� �'�y� - 11 '+f.=+"=� i 1 l� ' C� �►C"'��� _ I ;j jI y � 1 0 0 ■1 yeti � �� �A � ■.1 ' ! . �'r �! _ _ ����. ,{ _ II /�,:: 'I rl ,1��■�,: ,• � �,.f \ � r;:s �\� `-i r-�1 , �+.`��=,:'1�...�� •+}y M1 1~` 1 ♦► Proposed / ■� , f.fill c� —� `■ �� �2L / ■ 11' bridge ~� tOD - +■ crossing: �h WD Ir r • -- -, �L 1 047 { �� _ ,r 1 1 f /JJ1•jj � � Ir II �` / i rrll , � _ - - - - '-I - - -� �I - f I �r�ff�� „� �,1 ri i ! � � �j I I / `•� �+ 1 II ■ ! T%� r ri rr'r r !i !i1l111 jr t \\:� 1 1 , II 1 , • r ,, i ' ♦♦ ■. E\ f^� "'�i ■ • A _ � � r`f�ri� _ I�! IIII Ili �\ �\ � � z 1 I I r/r 1 ' � 1 ♦ r♦ [,''� \ � ♦•► �►'��;� ,• ~� r - - '��� �'' 1i�11�44ii+` �t�tt f f a I �r I ► r ' r , ', � I --. J- .. r r J i 1111 .I a 1 � � 1' ■' h � 1 I .�I ff ♦ 4 ��.�: �- 1 I, r rr - i t —'� a Illi Ilii \,\!1\ I I �! �� I I � r' i : � I i tom_` - a ! rr' - :■�,I ,` i E • � $ 1 I / �' ` � • 1 Ir t 1 � ` 1 7 09L1 �'t 1 � � :�=�� � - �� � � •�� 111 , �� ��,► I 1 ! t ` i '•l� 1' I 1 1 1 f /i - �' f `' �r� I j' �, / t ,f •�_ � \ � I Irl! r _ �����. � - a� int' �� � � 1 1 1 i 1 �� I I f I 1 / I / ' r,Gp ` _ ` 1�\ _. ... ► , �iP„ 1• ' /// ` 1 I, 1 1 � -1'1-' � ■ I I II 111 rli r ♦ .�Lq •'�♦ 6 I J I t 1 1 ,� I I I I I r r , ', r a r , 1 ■ t .iu■■t, 11 s ► � 1 i ' •�-- r -'� i . \1 / L I ' 1 r 1 ' r r . , � 4 , _ � , • p` , L, ,'1� r 1 �j �-., .'"� . I � '• — fi .�� ` ' � .' � � `. 1 `Il I I I I I � 11 I J-. �„ t�} •\; I ,1'lls1V Ir11 Y. '1 tt� ' . ` r� 1' ry1ry - 1 M1 1 r Ijrl 1 I� � ��_'• `� ���� r� 1 . �� ' ► I 1 f { •i •ti , i' 1 � drjfiil _ % � ���' � � `� �. �\\_� � = tiZ =__ . 4 � ,' ■ /� f .! i< i i I I f�rf t� L`_ \O4 � I �������� ��.�.^ II 11 � ♦r ♦ / li i �� ` 7 .1jl, r •,: f [, \l t� ��\ \�,11�t,�11 • / i i + i�:. • I I � Iii '• �'�'' a��� 1',1111.1�,� ��',. i i'::;'•::•. s•... ,7 � � + �t'•:::dr;�: r•�;�;:.. �I fr ill � s ' r 1 i. _ �, I �� ,� 1, • Lo N O N d W � 2 a 0 Q w I 0 W cJ wU Q,(0 �O WW chJ 0 O � Q � 1n C d ---------, W' O I I QO U_ W I �U Cf) CLL L Z 0 I I � a H LU I ...�■ p C r 0 � ,r ++ W V E0 CL Z 0 O > > DATE 07/25/2017 OP ' / N DRAWN BY f . L. MAJOR / - ,' � DESIGNED BY BLAKE HALL 1 CHECKED BY T. PREUNINGER (SCALE 1 150' 1 r X\ 1 1 � :•;: •.::��;;#,.;;:;";: l I` L l'r I l.I. •� I l 111 � � , I Ir4 � '\ ` jrf C %� \ IF 1, 1 r. - - ilkti 1 11 ° 1 r IIYI 1 f ;3-::::;:=:e �::�::'R•::;•�'=•�'•::•::•::�::;;'c: 1�'I I't. , 1 ' li 1! +f;rr I r �� � i i,'•1;F,•:�.:�::i•:•':�:�'.�:"�.'.i''':�: �:;:.;:: ', 111 � •1 ` ° / '� I I I f � � � , 1 J ..��. :•1:=:i�' i - � 1\ter ` lilt / � 1 tib': •■:•:f•',•'�t '.1 :.:=:.;•:' �t �. � - � _ - _ f t f + r � ��+r n�Pf• =" .:j;s:�j::?":�.�;:.i{:r: :'. •.fi::;:(a:.: ;�;, :.ir: ::r: � I f' f `ice ` -- I 1\,. ...•'}� .'Y•- �� I -�-_J :''..:; �:: ' j :;::,:::.:::::::.:::::• +, Sheet 3 -. - L •. -� ' `, r - - l -� � �;•� ,Wetlands'- • • ,- � � � 1 , r ...con 'r♦ ,, rr-- - � -�`` ..' � l ,t ``t I • ....off -s ite F�'� t�:f • ,, r , / ,kms _ _ _ �` ' ' � �- - � ` ' Ali fill N . �:L�=: ••:. it f � � _1 ::.::•..::::.. �. _� 1 ��:�+�'•i:�. �:T •:•�.�� ,■■tit\e{ �r r I r l � 1 �''�;: sY:i::>''. •� •� �''; :�':1•+�:i';[ : �.'.::.: ,7' i� If r,+,7++}I++ rlir ' , T �1 j :. �:.%:?:•::. • .... •: ;];.': :..�"%.: ,•: r.•. %!. . � ! f Irl f ._ _ _ :•><:+: tit:::::;•.,:•..•::: • ..::.:+1•:::�!:;:;:.:�::.: rrl I r r I I y �- , j I 'r ,r:.•l:: •:•1Y. e: i:•i.;':::'•: :'-"•i't'r::•:: •:'.:j r IVI1}+I .'''��:':•:•:r:�is:�.�':�'•:` :�i::'#:::;:•:;•:::,: rl'+I.,�111 Siii ,!! l I}i � l j I l - _ •{'::.{.;.:.:.�!;:� :: y:•: •::.:::: `h lll� till hh1} l`.I'1 � 1;1 h � - _ ►r�:r:,;�;':• �,r X11 s '�'� •1'1`1 � �: - .♦♦rte■ J • ♦ r' = l � I r 141 41, • r I r t � 11. G Z FNNN 0 V z MLU ILL a p IL x ce D 11111 m W U z Q H Q O o� 1■� Z W MJ W z Z on LL V a LU x H Q =LU J � a M W IL JOB NO. 39772.001 SHEET NO. 1 OF 3 Path: R:\805\39722.001 -Mist Lake\GIS\Wetland Impacts\MistLake-WTIM_Notes.mxd Impacts Table These plans and associated documents are the exclusive property of TIMMONS GROUP and may not be reproduced in whole or in part and shall not be used for any purpose whatsoever, inclusive, but Legend Riparian Buffer (sq. ft) Impact C:.11 Project Study Limits Permanent B 1-Z1 a0--3 Limits of Disturbance - 21 Acres 13, 083 B1 -Z2 J© Riparian Buffer Zone 1 Impact 11,852 Tota I © Riparian Buffer Zone 2 Impact 24, 935 sq ft 0.00 ac Stream Centerline Stream Top of Bank --- Retaining Wall Neuse Riparian Buffer FZL Neuse Riparian Buffer Zone 1 Impact ® Neuse Riparian Buffer Zone 2 Impact Wetland D Pond NOTES: 1. WATERS OF THE U.S. WITHIN THE PROJECT STUDY LIMITS ARE SOURCED FROM MCADAMS 2. WATERS OF THE U.S. HAVE NOT BEEN CONFIRMED BY THE U.S. ARMY CORPS OF ENGINEERS. 3. PROJECT LIMITS ARE APPROXIMATE. 4. TOPOGRAPHY BASED ON USGS LIDAR DATA. TIMMONS . GROUP ��� 7nYIRVmIUN AGRIlVlDTRROUOR OUM THIS DRAWING PREPARED AT THE CORPORATE OFFICE ML Boo/tlers Parkway, Suite 3001 Blchmord, VA 23225 TEL 804.Y00.6500 FAX 809.560.1648 www.fimmons.com � � � Site Development I Residential I Infrastructure I Technology I Environmental W o MIST LAKE FACILITIES EXPANSION '� 2 0 m DATE REVISION DESCRIPTION p� nVNi DURHAM COUNTY, NORTH CAROLINA v D z z O n o N Z wo OOp A m Z O 0 Qz '01 o V PRELIMINARY NEUSE RIPARIAN BUFFER IMPACTS MAP - NOTES A < Impacts Table These plans and associated documents are the exclusive property of TIMMONS GROUP and may not be reproduced in whole or in part and shall not be used for any purpose whatsoever, inclusive, but Impact ID Riparian Buffer (sq. ft) Impact Temporary Permanent B 1-Z1 13, 083 B1 -Z2 11,852 Tota I 0 sq ft 24, 935 sq ft 0.00 ac 0.57 ac not limited to construction, bidding, and/or construction staking without the express written consent of TIMMONS GROUP. o 101.'"W!`I :40 APPENDIX A VARIANCE REQUEST FORM State of North Carolina DWR Department of Environment and Natural Resources Division of Water Resources Division of Water Resources 15A NCAC 02B .0233 (8)(b), .0243 (8)(b), .0250 (11)(b), .0259 (8)(b), .0267 (11)(c), .0607 (e)(2) Protection and Maintenance of Riparian Areas Rules - Variance Application FORM: VAR 10-2013 PLEASE IDENTIFY WHICH RIPARIAN AREA PROTECTION RULE APPLIES: X Neuse River Basin (15A NCAC 0213.0233) x Major Variance ❑ Minor Variance ❑ Catawba River Basin (15A NCAC 0213.0243) ❑ Randleman Lake Water Supply Watershed (15A NCAC 0213.0250) ❑ Major Variance ❑ Minor Variance ❑ Tar -Pamlico River Basin (15A NCAC 0213.0259) ❑ Major Variance ❑ Minor Variance ❑ Jordan Lake Water Supply Nutrient Strategy (15A NCAC 0213.0267) ❑ Major Variance ❑ Minor Variance ❑ Goose Creek Watershed (15A NCAC 0213.0606 & 15A NCAC 0213.0607) A. General Information 1. Applicant's Information(if other than the current property owner): Name: City of Durham — Department of Water Management Title: Attn: Mr. Don Greeley - Director Street Address: 1600 Mist Lake Drive City, State & Zip Telephone: Durham, NC 27704 919-560-4381 Email: don.ereeley@durhamnc.eov 2. Property Owner/Signing Official (person legally responsible for the property and its compliance): Name: Title: Street Address: City, State & Zip: Telephone: Email: FORM: VAR 10-2013 3. Agent Information: 3a. Name: Company Affiliation: Street Address: City, State & Zip: Telephone: E-mail: Todd Preuninger 1001 Boulders Parkway, Suite 300 Richmond. VA 804-200-6399 todd.Dreunineer(@timmons.com 3b. Attach a signed and dated copy of the Agent Authorization letter if the Agent has signatory authority for the owner. 4. Project Name (Subdivision, facility, or establishment name): Mist Lake Facility Expansion 5. Project Location: 5a. Street Address City, State & Zip: 5b. County: Mist Lake D Durham, NC 27704 Durham 5c. Site Coordinates (in decimal degrees): 36.021 Latitude -78.8595 Longitude 5d. Attach an 8 % x 11 excerpt from the most recent version of the USGS topographic map indicating the location of the site. 5e. Attach an 8 %2 x 11 excerpt from the most recent version of the published County NRCS Soil Survey Map depicting the project site. 6. Property Information: 6a. Property identification number (parcel ID): 0842-09-16-0876 (DB 7997, pg. 68), 0842-09-16-3052 (DB 8055, pg. 544), 0842- 09-16-5055 (DB 8006, pg. 182), 0842-09-16-0876 (DB 7997, pg. 68), 0842-09-16-8832 (DB 1630, pg. 228), 0842-09-16-8832 (DB 6b. Date property was purchased: January 1, 1997 (please note that a portion of the project extends into an adjacent property that was purchased in September 2016, however the buffer extends across both parcels). 6c. Deed book and page number 6d. Map book and page number 6e. Attach a copy of the recorded map that indicates when the lot was last platted. 7. Is your project in one of the 20 Coastal Counties covered under the Coastal Area Management Act (CAMA)? ❑ YES x NO 7a. If you answered yes above, in which AEC do you fall (30 ft or 75 ft)? 7b. If you answered yes above, what is the total percent of impervious cover that you have proposed within the AEC? FORM: VAR 10-2013 Page 2 of 7 8. Directions to site from nearest major intersection: The site is located south of the intersection of E. Club Boulevard (SR1669) and Camden Road (SR1671) at 1600 Mist Lake Drive, in Durham, NC (vicinity map attached). 9. Stream associated with riparian buffer to be impacted by the proposed activity: Name Water Quality Classification UT to Goose Creek WS -IV, NSW 9a. For Goose Creek only: Is the buffer in the 100 -year floodplain? ❑ YES NO 10. List any permits/approvals that have been requested or obtained for this project in the past (including all prior phases). Date Applied: Date Received: Permit Type: B. Proposed Activity 1. Project Description 1a. Provide a detailed description of the proposed activity including its purpose: The purpose of the proposed project is to expand the existing facility at Mist Lake, in order to accommodate multiple City of Durham Department of Water Management (DWM) divisions and allow for potential moderate growth over the next 20 years. The DWM Mist Lake Facility Expansion prosect consists of two buildings totaling approximately 116,000 square feet, which will consist of a building for the administration (which will provide office space for the five divisions), a warehouse, shops, and laydown area to store equipment when not in use or undergoing repair for the maintenance division. The project is consistent with the zoning requirements for this area (IL - industrial) and is being undertaken to consolidate multiple divisions that at present are located across Durham in one location, which will create cost, logistical, and overall savings for the locality. TheDWM currently operates several of its divisions at 1600 Mist Lake Drive (North Campus). This 20 -acre facility houses approximately 82 staff of the Administration, Plant Engineering & Maintenance, Regulatory Compliance, and Utility Engineering divisions of the Department, along with associated vehicles, equipment, and inventory. Currently, 145 DWM Water & Sewer Maintenance (WSM) employees are co -housed at a second location on Martin Luther King, Jr. Drive, the Public Works Operations Center (PWOC) along with Public Works staff. The WSM workgroups at PWOC are responsible for Outfall Maintenance, Rehabilitation Maintenance, Meter Reading, Meter Maintenance, Service Installations, and Mainline Installations, along with the necessary vehicles, light and heavy equipment, and inventory to maintain and operate approximately 2,600 miles (combined) of water and sewer mains, 8,148 hydrants, 25,896 water valves, and more than 83,000 water meters. The prosect will expand the DWM Mist Lake facility to accommodate the relocation of the WSM Division from the PWOC facility to the Mist Lake complex and potential growth over the next 20 years, without additional impacts. FORM: VAR 10-2013 Page 3 of 7 1b. Attach a site plan showing the following items as applicable to the project: 0 Development/Project name 0 Revision number & date 0 North arrow 0 Scale (1" = 50' is preferred) 0 Property/project boundary with dimensions 0 Adjacent streets and roads labeled with names and/or NC State Road numbers 0 Original contours and proposed contours 0 Perennial and intermittent streams, ponds, lakes, rivers and estuaries 0 Mean high water line (if applicable) 0 Wetlands delineated, or a note on plans that none exist 0 Location of forest vegetation along the streams, ponds, lakes, rivers and estuaries 0 Extent of riparian buffers on the land including Zone 1 and Zone where applicable 0 Location and dimension of the proposed buffer impact (label the area of buffer impact in ft' on the plan) 0 Details of roads, parking areas, cul-de-sacs, sidewalks, and curb and gutter systems 0 Footprint of any proposed buildings or other structures 0 Discharge points of gutters on existing structures and proposed buildings 0 Existing drainage (including off-site), drainage easements, and pipe dimensions 0 Drainage areas delineated C. Proposed Impacts and Mitigation 1. Individually list the square footage of each proposed impact to the protected riparian buffers: Buffer Impact Number'— Reason for Impact Permanent (P) or Temporary (T) Buffer Zone 1 Impact Mitigation (square feet) Required Zone 2 Impact (square feet) 61 - ® P ❑ T Parking/Fire Lane x Yes o No 13,083 11,852 B2 - ❑P D oYes oNo B3 - ❑P D oYes oNo (square feet) Total Buffer Impacts 24,935 'Label on site plan 2. Identify the square feet of impact to each zone of the riparian buffer that requires mitigation from the table above. Calculate the amount of mitigation required. 'For projects in the Goose Creek Watershed, list all riparian buffer impacts as Zone 1 and use Zone 1 multiplier. 3. Provide a description of how mitigation will be achieved at your site pursuant to the mitigation requirements of the applicable river basin/watershed. Compensatory mitigation for these unavoidable impacts will be achieved through the Durchase of off-site mitigation credits from a mitigation bank, which is approved for use in the Neuse Watershed (Hydrologic Unit Code 03020201). Buffer mitigation credits will be purchased using the Standard Compensatory Mitigation Ratios at ratios of 3:1 for Zone 1 (39,249 SF) and 1.5:1 for Zone 2 (17.778 SF). This eauates to a total comDensatory mitieation oblieation of 57.027 SF of buffer credits. Credit availabilitv FORM: VAR 10-2013 Page 4 of 7 Required Zone Total Impact Multiplier Mitigation (square feet) (square feet) Zone 1' 13,083 3 39,249 (2 for Catawba only) Zone 2 11,852 1.5 17,778 Total Buffer Mitigation Required: 57,027 'For projects in the Goose Creek Watershed, list all riparian buffer impacts as Zone 1 and use Zone 1 multiplier. 3. Provide a description of how mitigation will be achieved at your site pursuant to the mitigation requirements of the applicable river basin/watershed. Compensatory mitigation for these unavoidable impacts will be achieved through the Durchase of off-site mitigation credits from a mitigation bank, which is approved for use in the Neuse Watershed (Hydrologic Unit Code 03020201). Buffer mitigation credits will be purchased using the Standard Compensatory Mitigation Ratios at ratios of 3:1 for Zone 1 (39,249 SF) and 1.5:1 for Zone 2 (17.778 SF). This eauates to a total comDensatory mitieation oblieation of 57.027 SF of buffer credits. Credit availabilitv FORM: VAR 10-2013 Page 4 of 7 letters from the North Fork Little River Buffer Bank, an approved wetland and stream mitigation bank located in HUC 03020201, are located in Appendix E: Compensatory Mitigation Documents. 3a. Is buffer restoration or enhancement proposed? ❑ Yes x No If yes, attach a detailed planting plan to include plant type, date of plantings, the date of the one-time fertilization in the protected riparian buffers, and a plan sheet showing the proposed location of the plantings. 3b. Is payment into a buffer restoration fund proposed? x Yes ❑ No If yes, attach an acceptance letter from the mitigation bank you propose to use or the NC Ecosystem Enhancement Program stating they have the mitigation credits available for the mitigation requested. D. Stormwater 1. Provide a description of how diffuse flow will be maintained through the protected riparian buffers (e.g., re -planting vegetation or enhancement of existing vegetation, gutter splash pads, level spreader to control of runoff from impervious surfaces, etc.). Stormwater will be treated with 4 underground sand filters in conjunction with 2 UG detention systems and will be released at non-erosive flow into the buffer or wetlands. Additional details are provided in Appendix C — Preliminary Stormwater Plans. 1a. Show the location of diffuse flow measure(s) on your site plan. 1b. Attach a completed Level Spreader Supplement Form or BMP Supplement Form with all required items for each proposed measure. 1c. Attach an Operation and Maintenance (O&M) Form for each proposed level spreader or BMP. 2. For Major, Catawba, and Goose Creek variance requests, provide a description of all best management practices (BMPs) that will be used to minimize disturbance and control the discharge of nutrients and sediments from stormwater. Stormwater will be treated with four underground sand filters in conjunction with two UG detention systems and will be released at non-erosive flows into the buffer or wetlands though filter strips. Additional details are provided in Appendix C — Layout and Preliminary Stormwater Plans. 2a. Show the location of BMPs on your site plan. 2b. Attach a Supplement Form for each structural BMP proposed. 2c. Attach an Operation and Maintenance (O&M) Form for each structural BMP proposed. E. Demonstration of Need for a Variance The variance provision of the riparian buffer rules allows the Division or the Environmental Management Commission to grant a variance when there are practical difficulties or unnecessary hardships that prevent compliance with the strict letter of riparian buffer protection. 1. Explain how complying with the provisions of the applicable rule would prevent you from securing a reasonable return from or make reasonable use of your property. Merely proving that the variance would permit a greater profit from the property shall not be considered adequate justification for a variance. The Division will consider whether the variance is the minimum possible deviation from the terms of the applicable Buffer Rule that shall make reasonable use of the property possible. In order to provide adequate space for parking and buildings, a minimum of 21 acres of buildable land is necessary. The southwestern portion of the site is relatively narrow and is constrained by setbacks along the Interstate and wetlands to the north. A stream and its corresponding buffer bi-sect the property in this area and cannot be avoided. This property has been owned prior to Julv 1997. and its current and or000sed use was intended for this oroiect. If the Citv cannot use the existine FORM: VAR 10-2013 Page 5 of 7 propertV to consolidate the five divisions then the initial investment on the purchase of the property will be lost, additional Property will need to be purchased to relieve the additional space requirements needed at the remote facilities, as well, the propertV cannot be used to consolidate the multiple divisions in one location. Logistically this will cause inefficiencies, create other impacts associated with the development of another greenfield propertV that are significantly more than the proposed project, and will not solve the original problems that were the impetus of consolidating the divisions at one location. 2. Explain how the hardship results from application of the Buffer Rule to the property rather from other factors such as deed restrictions or other hardships (e.g. zoning setbacks, floodplains, etc). Given the design constraints associated with a shared use facility (i.e. administration buildings, maintenance warehouses, work vehicles, equipment storage) and the local zoning requirements, the applicant has minimized impacts to the greatest extent practicable. Specifically, there is a setback associated with Interstate 85 along the southern property boundary. This 50 -foot setback limited useable space for parking and buildings along the southern propertV line and pushed the development to the north. towards the wetlands and stream buffer. Moreover. the southwestern portion of the oroperty is bisected by a stream/buffer, and in order to provide space for a building and parking, buffer impacts could not be avoided. The applicant explored the use of retaining walls along the northern portion of the parking lot; however, this option provided very limited avoidance, as space is still needed for parking and emergency vehicle access; furthermore, most of the vehicles and equipment being stored at the site are large construction vehicles and equipment, which required more storage area than a passenger car or truck. Construction equipment and vehicles require more space to maneuver (i.e. larger turning radii, larger parking areas, etc.). When being serviced these vehicles require large services bays, as well as additional areas with the lay down area for the large equipment (lifts, hoists, cranes, etc.) needed to service the larger equipment. Therefore, the typical parking requirements for an office building do not apply, and are considerably larger based on the type and number of pieces of equipment. proposed additional impacts to the wetlands in the northern portion of the propertV, associated with roadways. However, the layout was re -designed, in order to avoid impacts to the forested wetlands and buffers within the central portion of the propertV. 3. Explain how the hardship results from physical nature of the property, such as its size, shape, or topography, which is different from that of neighboring property. As stated above, the southwestern portion of the propertV is narrow and constrained by an interstate to the south and wetlands and stream channels to the north and west. A stream channel bi-sects the propertV in this location and cannot be avoided in order to access the uplands on either side of the channel. Additional hardships include steep slopes, floodplain, and wetlands abutting the project, which severely impact the amount of developable area. In order to provide access for emergency vehicles, Local Fire Code requires a paved roadway around the buildings, which will allow fire apparatus vehicles within a minimum of 150 feet of anv portion of the buildine. Offsite alternative sites were explored for this project; however, in order to provide adequate building space and parking for all divisions, at least 21 acres of buildable land are needed, as well as an adjacent roadway infrastructure that supports heavy truck use. The current location allows for future growth, provides better utilization of existing personnel and equipment, utilizes parts/tools warehousing and non -duplication of housing parts, provides for better internal communication between divisions, and provides protection of parked vehicles and equipment during flooding, which is now experienced at the current location of the Public Works WSM Division, southwest of this site. In addition, the proposed layout provides more acceptable storage and in-house work area conditions. and dedicated pedestrian walkways. which provides for a safer work environment for personnel. while utilizing the existing utility and road infrastructure. 4. Explain whether the hardship was caused by the applicant knowingly or unknowingly violating the applicable Buffer Rule. The applicant has not violated the buffer rules. 5. For Neuse, Tar -Pamlico, Jordan Lake and Goose Creek only: Did the applicant purchase the property after the effective date of the applicable Buffer Rule and then request a variance? No — the applicant purchased the property in January 1997, prior to the effective date of the Buffer Rules. However, a portion of the project does extend into land purchased in 2016. FORM: VAR 10-2013 Page 6 of 7 6. Explain how the hardship is rare or unique to the applicant's property, rather than the result of conditions that are widespread. The subiect property was Purchased iJanuary 1997 prior to the implementation of the buffer I s There is an exist' 20 - acre facility that houses approximately82 staff of the Administration, Plant Engmeeringg, Maintenance, Regulatory Compliant and Utility En¢ need ng divisions of the Department alone with associated vehicles equipment and inventory. The applicant F. Deed Restrictions By your signature in Section G of this application, you certify that all structural stormwater BMPs required by this variance shall be located in recorded drainage easements, that the easements will run with the land, that the easements cannot be changed or deleted without concurrence from the State, and that the easements will be recorded prior to the sale of any lot. G. Applicant's Certification I, �ivMc .� �� %.CEz-lri (print or type name of person listed in Section A, Item 2), certify that the information included on this permit application farm Is correct, that the project will be constructed in conformance with the approved plans and that the deed restrictions in accordance with Section F of this form will be recorded with all required permit conditions. Signature: Date: FORM: VAR 10-2013 Page 7 of 7 APPENDIX B WETLAND DELINEATION INFORMATION Kra Water Resources ..VakON... 1PL aaA111Y July 19, 2017 City of Durham Property and Facility Management Atm; General Services Real Estate Division 101 City Hall Plaza Durham, NC 27701 ROY COOPER G—,o- MICHAEL S. REGAN taym. S. JAY ZIMMERMAN Do. Subject: Buffer Determination Letter NBRRO 417-192 Durham County Determination Type: Buffer Intermittent/Perennial ® Neuse (15A NCAC 2B.0233) StartC ❑ Tar -Pamlico (15A NCAC 28.0259) 0 Intermittent/Perennial Determination (where local buffer DSGS Tons ordinances apply) ❑ Jordan (15A NCAC 2B.0267) (governmental and/or interjurisdictional Throu hout Property projects) X Project Name: Mist Lake Facility Expansion Address/Location: 2905 Meridian Parkway, Durham NC 27713 Stream(s): Determination Date: June 28, 2017 Staff: Jason Robinson Stream ENP- Not Subject. Subject StartC StopC SOB Sury DSGS Tons A P X Throu hout Property X X B P X Throughout Property X X D P X Throu hoot Property X X E I X DWR Flag —36.022118 -78.861238 StreamA X H I X DWR Flag --36.020327 -78.859938 DWR Flag —36.020639 -78.860345 X Pond P X X X I E X X 'E/11P = Ephemeral/Intermittent/Perennial Division of Water Resources,Rnleigh Regional Office. Water Quality Operations Sel:tlon hu,i lmnalacdenr.org/welvettaps 1628 Mail Service Center. Raleigh, NC 27699-1628 Phone: (919) 791-4200 Location: 3800 Barrett Drive, Raleigh, NC 27009 Fax: (919) 788-7159 Mist Lake Facility Expansion Durham County July 19, 2017 Page 2 of 2 Explanation: The stream(s) listed above has been located on the most recent published NRCS Soil Survey of Durham County, North Carolina and/or the most recent copy of the USGS Topographic map at a 1:24,000 scale. Each stream that is checked "Not Subject" has been determined to not be at least intermittent or is not present. Streams that are checked "Subject" have been located on the property and possess characteristics that qualify it to be at least an intermittent stream. There may be other streams located on the property that do not show up on the maps referenced above but may be considered jurisdictional according to the US Army Corps of Engineers. This on-site determination shall expire five (5) years from the date of this letter. Landowners or affected parties that dispute a determination made by the DWR may request a determination by the Director. An appeal request must be made within sixty (60) days of date of this letter. A request for a determination by the Director shall be referred to the Director in writing. If sending via US Postal Service: c/o Karen Higgins; DWR — 401 & Buffer Permitting Unit; 1617 Mail Service Center; Raleigh, NC 27699-1617. If sending via delivery service (UPS, FedEx, etc.); Karen Higgins; DWR — 401 & Buffer Permitting Unit; 512 N. Salisbury Street; Raleigh, NC 27604. This determination is final and binding unless, as detailed above, unless an appeal is requested within sixty (60) days. This project may require a Section 404/401 Permit for the proposed activity. Any inquiries should be directed to the US Army Corp of Engineers (Raleigh Regulatory Field Office) at (919)-554-4884. If you have questions regarding this determination, please feel Gee to contact Jason Robinson at (919) 791-4200. mSy,w� truth Quality Regional Operations Center cc: RED DWR File Copy Kelly Roth, McAdams Company: 2905 Meridian Parkway, Durham, NC 27713 qsv� Map provided by NCDEQ Legend: qT" Division WaterRe- .Cu y � S sources -Approximate Site boundary: Y� Locations ar are approxi- mate and are provided for -Approximate Start/Stop * reference only '. 17-192 Mist Lake Facility Expansion s,. xar Map provided by NCDEQ Legend: ns" Division of Water Re- sources -Approximate Site O Locations are approxi- bounday: mate and are provided for reference only :: A SUBJECT PROPERTY -� ` I Y � STREAM WETLAND START STREAM A _C� WATER BODY 50 -FT NEUSE RIPARIAN BUFFER _ SUBJECT PROPERTY PARCELS ource: Esri, Digi alGlobe, G� eoElye, Earths}tar Get appiINg, Verogrid, IGN, IGF, swiss opo, a 2 -FT CONTOURS 0 125 250 STREAM, WETLAND, & BUFFER DELINEATION Feet FIGURE 3. EXISTING CONDITIONS 1 inch = 250 feet MIST LAKE FACILITY EXPANSION DATE: 7/6/2017 MCADAMS DURHAM, NORTH CAROLINA JOB NO: DUR-16010 DRAWN BY: roth X:\Protects\DUR\DUR-16010\Storm\Wetlands\Mist Lake Expansion\GIS\DUR16010 Fiqure 3 MistLake North 11x17 7-6-2017.mxd, 7/6/2017 12:10:55 PM, roth APPENDIX C PRELIMINARY STORMWATER AND UTILITY PLANS L K DURHAM DEPARTMENT OF WATER MANAGEMENT DURHAM WATER - MIST LAKE 1600 MIST LAKE DRIVE DURHAM, NORTH CAROLINA SITE DATA G F E x C 0 m 0 U A m 9 0 1 Sheet List Table PROJECT TEAM_ 00-0000 J Developer OVERALL PLAN Architect PHASING PLAN DURHAM DEPARTMENT OF WATER MANAGEMENT MAINTENANCE DESIGN GROUP 00-CO04 1600 MIST LAKE DRIVE 00-S1-5 201 NORTH CHARLES STREET, SUITE 1640 00-S2-5 DURHAM, NC 27704 00-S3-5 BALTIMORE, MD 21201 00-S4-5 919-560-4381 00-S5-5 (443)524-4382 00-C200 Architect 00-C201 DEMOLITION PLAN 00-C202 RNL DESIGN Civil Engineer Landscape Architect 00-C301 SITE LAYOUT 1600 WILSON BLVD SUITE 360 TIMMONS GROUP SUSAN HATCHELL LANDSCAPE ARCHITECTURE, PLLC UTILITY PLAN - PHASE 1 ARLINGTON, VA 5410 TRINITY ROAD 711 W NORTH STREET UTILITY PLAN - PHASE 2 (571)290-7679 RALEIGH, NC 27607 RALEIGH, NC 27603 GRADING PLAN 00-C402 (919)866-4505 (919)838-9600 H APPROVALS STORM DETAILS 00-0502 G F E x C 0 m 0 U A m 9 0 1 Sheet List Table Sheet Number Sheet Title 00-0000 COVER 00-0001 OVERALL PLAN 00-CO02 PHASING PLAN 00-CO03 PHASING PLAN 00-CO04 STORMWATER COMPLIANCE 00-S1-5 EXISTING CONDITIONS 00-S2-5 EXISTING CONDITIONS 00-S3-5 EXISTING CONDITIONS 00-S4-5 EXISTING CONDITIONS 00-S5-5 EXISTING CONDITIONS 00-C200 DEMOLITION PLAN 00-C201 DEMOLITION PLAN 00-C202 DEMOLITION PLAN 00-C300 SITE LAYOUT 00-C301 SITE LAYOUT 00-C302 SITE LAYOUT 00-C303 UTILITY PLAN - PHASE 1 00-C304 UTILITY PLAN - PHASE 2 00-C305 UTILITY PLAN - PHASE 2 00-C400 GRADING PLAN 00-C401 GRADING PLAN 00-C402 GRADING PLAN 00-0500 SITE DETAILS 00-0501 STORM DETAILS 00-0502 UTILITY DETAILS 00-0503 UTILITY DETAILS 00-0504 EROSION CONTROL DETAILS 00-L100 LANDSCAPE PLAN 00-L101 LANDSCAPE PLAN 00-1-102 LANDSCAPE PLAN 01-A301 OVERALL BUILDING SECTIONS 01-A901 3D BUILDING MODEL EA101 I LIGHTING PLAN EA102 I LIGHTING PLAN 2 3 PROJECT: DURHAM DEPARTMENT OF WATER MANAGEMENT, DURHAM WATER- MIST LAKE CASE #: D1700249 DEVELOPER: DURHAM DEPARTMENT OF WATER MANAGEMENT OWNER CONTACT: DON GREELEY DURHAM DEPARTMENT OF WATER MANAGEMENT 101 CITY HALL PLAZA DURHAM, NC 27701 PHONE: 919-560-4381 FAX: 919-560-4479 DESIGNER CONTACT: TIMMONS GROUP BLAKE HALL, P.E. 5410 TRINITY ROAD, SUITE 102 RALEIGH, NC 27607 PHONE: 919-866-4933 BLAKE.HALL@TIMMONS.COM PROJECT ADDRESS: 1600 MIST LAKE DRIVE DURHAM, NC 27704 PIN: 0842-09-16-8832, 0842-09-16-0876, 0842-09-16-5055, 0842-09-16-3052, 0842-09-18-5025 PARCEL ID #: 160519,160516,160518,160584,160585 REFERENCE: DB 1630 PG 228, DB 7997 PG 68, DB 159 PG 35, DB 8055 PG 544, DB 8006 PG 182 ZONING: IL DEVELOPMENTTIER: SUBURBAN JURISDICTION: CITY OVERLAY: MAJOR TRANSPORTATION CORRIDOR FALLS/JORDAN-TYPE B BUFFER (F/J-B) EXISTING USE: GOVERNMENTAL USE/LIGHT INDUSTRIAL PROPOSED USE: GOVERNMENTAL USE/LIGHT INDUSTRIAL SETBACKS: STREET YARD - 50', SIDE YARD 25' EACH SIDE REAR YARD - 25' WATERSHED: FALLS LAKE WATERSHED RIVER BASIN: NEUSE RIVER BASIN TRACT AREA: 55.29 ACRES (2,408,520 SF) DISTURBED AREA: 21 ACRES (37.98% OF TOTAL SITE) STORMWATER MANAGEMENT: A PROPOSED CONSTRUCTED UNDERGROUND DETENTION. NO STRUCTURES (BUSINESSES, HOMES, CULVERTS, STREETS, ETC.) BETWEEN THE POINT OF DISCHARGE AND THE ANALYSIS POINT WILL BE ADVERSELY IMPACTED BY THE INCREASE IN SITE RUNOFF FOR STORM EVENTS UP TO THE 100 -YR. EVENT. OPEN SPACE & TREE COVERAGE REQUIREMENTS: 10% OF GROSS AREA REQUIRED. GROSS AREA: 55.29 ACRES REQUIRED OPEN SPACE & TREE COVERAGE: 5.53 ACRES PROVIDED OPEN SPACE AND TREE COVERAGE: 11.77 ACRES VEHICULAR SURFACE AREA: EXISTING = 208,028 SF PROPOSED = 654,879 SF SITE IMPERVIOUS SURFACE AREA: PRE -DEVELOPMENT IMPERVIOUS AREA: 6.66 ACRES / 12.04 - EX ROOF: 82,041 SF / 1.88 ACRES - EX PARKING LOT: 208,028 SF / 4.78 ACRES POST -DEVELOPMENT IMPERVIOUS AREA: 19.12 ACRES / 34.58 - ROOF 177,988 SF / 4.09 ACRES - PARKING LOT 654,879 SF / 15.03 ACRES DISTURBED AREA: 914,760 SF / 21 ACRES PARKING SUMMARY - VEHICLES REQUIRED PARKING: - GOVERNMENTAL USE (OFFICE) 1 SPACE PER 300 SF PLUS 1 PER 3 EMPLOYEES = (119000/300) + (400/3) = 530 SPACES REQUIRED PARKING: - LIGHT INDUSTRIAL USE (WAREHOUSE) 1 SPACE PER 1,000 SF = (60,000/1,000) = 60 SPACES PARKING PROVIDED: 410 SPACES PARKING SUMMARY - BICYCLES REQUIRED PARKING: - GOVERNMENTAL USE (OFFICE) 1 SPACE PER 3,000 SF PLUS 1 PER 30 EMPLOYEES - (119,000/3,000) + (400/30) - 53 SPACES REQUIRED PARKING: - LIGHT INDUSTRIAL USE WAREHOUSE 1 SPACE PER 5,000 SF Q (WAREHOUSE) = (60,000/5,000) = 12 SPACES BICYCLE PARKING SPACES PROVIDED: 108 FLOODPLAIN DATA SITE DRAINS TO GOOSE CREEK FEMA PANEL #:0842 MAP # 3720084200K THIS SITE IS IN SPECIAL FLOOD HAZARD AREAS AND HAS FUTURE FLOODPLAIN CONDITIONS HAZARD AREAS, AS SHOWN ON FIRM PANEL 0842 DATED MAY 2, 2006. SPECIAL CONDITIONS OF APPROVAL 1. TREE PROTECTION FENCING SHALL BE INSPECTED PRIOR TO START OF CONSTRUCTION. CONTACT CLAY SHEPHERD AT 919-560-4137 EXT. 28240 TO SCHEDULE AN INSPECTION. I\- L ulalrl 01. 1. -.'J li ' Su 4 11da � �' B" 1 i of Iv I r� .'P +ivy ' IS l :� i B --Y11 Aw i F'' I r 9 �li Sl TE : . /11 r 54 I . Zr 4 A I >s L '': IE fianlriy❑ns!1 t F�cF I R+# •, �f.-1 K - I I 11 . �. P' .� t-. iii + I'll. '" I I �. ' � La 3 I pve r? ti�� r = x e .. �i , 12 � � . ---, - , / <�� .L �r• ,. . .. V "...• I C1�`" .. •.0 .r Z �.[3Eef St • . Ems::..- f....: i. n , g� 7' - .....11. I ,iii , M 6 ' a �I AN " ., .:, Y . J JLnlWrer S1 tj ❑+� o -.d i' d 4 i ti. J' ..1t. L S C '�y IIIF ,. � -A C 1' S a a �Ynt1-„�..--i ---- .. - ;ab c iJ 2!1 4 1 5 1 6 1 7 9 10 DURHAM GENERAL STANDARD NOTES 1. FOR SITES CONTAINING FLOODPLAIN: ALL DEVELOPMENT WITHIN THE FLOODWAY OR NON -ENCROACHMENT AREA OR FLOODWAY FRINGE AND NON -ENCROACHMENT AREA FRINGE, INCLUDING FILL, NEW CONSTRUCTION, SUBSTANTIAL IMPROVEMENTS, MANUFACTURED HOUSING STORAGE OF MATERIALS AND STORAGE OF TOXIC OR FLAMMABLE SUBSTANCES, IS PROHIBITED EXCEPT AS PROVIDED BY APPLICABLE FLOOD HAZARD REGULATIONS OF UDO SECTION 3.22 AND 8.4. 1.1. FLOODPLAIN ELEVATION(S) 1.2. FLOODPLAIN ZONE 1.3. FEMA MAP NUMBER 1.4. FEMA MAP DATE FOR SITES WITHOUT FLOODPLAIN: THIS SITE IS NOT IN ANY SPECIAL FLOOD HAZARD AREAS OR FUTURE CONDITIONS FLOOD HAZARD AREAS, AS SHOWN ON FIRM PANEL DATED TADD CORRECT FIRM PANEL REFERENCE AND DATE] 2. NCDWQ BUFFER AUTHORIZATION NOTE: BUFFER AUTHORIZATION BY THE NORTH CAROLINA DIVISION OF WATER QUALITY (NCDWQ) IS REQUIRED PRIOR TO CONSTRUCTION DRAWING APPROVAL. SITE PLAN CHANGES OCCURRING AS A RESULT OF ALTERATIONS NEEDED TO RECEIVE BUFFER AUTHORIZATION MAY RESULT IN THE NEED FOR A SITE PLAN AMENDMENT OR A NEW SITE PLAN BASED ON THE SCOPE OF THE REQUIRED CHANGES. IF A SITE PLAN AMENDMENT OR NEW SITE PLAN IS REQUIRED IT MUST BE APPROVED PRIOR TO CONSTRUCTION DRAWING APPROVAL. CONTACT THE DURHAM CITY -COUNTY PLANNING DEPARTMENT AT 919-560-4137 TO DETERMINE IF A SITE PLAN AMENDMENT OR A NEW SITE PLAN WILL BE REQUIRED. 3. STREAM BUFFERS. FOOT WIDE UNDISTURBED STREAM BUFFER, MEASURED FROM TOP OF BANK, EACH SIDE OF STREAM. NO CLEARING OR GRADING OTHER THAN SELECTIVE THINNING AND ORDINARY MAINTENANCE OF EXISTING VEGETATION PERMITTED, EXCEPT IN ACCORDANCE WITH 15A NCAC 028.233 (6) VEGETATION MANAGEMENT° NO STRUCTURES OR FEATURES REQUIRING GRADING OR CONSTRUCTION MAY BE BUILT WITHIN THE 10 FOOT STREAM BUFFER SETBACK. ANY USE ALLOWED BY SECTION 8.5.5 OF THE UDO SHALL BE DESIGNED AND CONSTRUCTED TO MINIMIZE THE AMOUNT OF INTRUSION INTO THE STREAM BUFFER AND TO MINIMIZE CLEARING, GRADING, EROSION AND WATER QUALITY DEGRADATION. (UDO SECTION 8.5). 4. FOR SITES CONTAINING WETLANDS. STATE AND FEDERAL PERMIT AUTHORIZATION MAY BE REQUIRED FROM THE NC DENR, NC DWQ, AND THE U.S. ARMY CORPS OF ENGINEERS PRIOR TO THE COMMENCEMENT OF ANY LAND DISTURBING ACTIVITIES IN OR NEAR A LAKE, STREAM, CREEK, TRIBUTARY, OR ANY UNNAMED BODY OF WATER AND ITS ADJACENT WETLANDS (UDO SECTION 8.9) 5. WETLAND BUFFER NOTE: FOOT WIDE WETLAND BUFFER TO REMAIN IN NATURAL, UNDISTURBED VEGETATION. WETLAND BUFFERS MAY BE USED FOR PASSIVE RECREATIONAL ACTIVITIES, SUCH AS WALKING AND BICYCLING TRAILS, PROVIDED THAT SERVICE FACILITIES FOR SUCH ACTIVITIES, INCLUDING BUT NOT LIMITED TO PARKING, PICNICKING AND SANITARY FACILITIES, ARE LOCATED OUTSIDE OF THE WETLAND BUFFER. ANY USE ALLOWED BY THIS SECTION SHALL BE DESIGNED AND CONSTRUCTED TO MINIMIZE THE AMOUNT OF INTRUSION INTO THE WETLAND BUFFER AND TO MINIMIZE CLEARING, GRADING, EROSION AND WATER QUALITY DEGRADATION. (UDO SECTIONS 8.9) 6. FOR RESIDENTIAL PROJECTS APPROVED FOR PAYMENT IN LIEU OF OPEN SPACE DEDICATION. PAYMENT IN LIEU OF OPEN SPACE DEDICATION TO BE MADE PRIOR TO THE APPROVAL OF ANY FINAL PLATS PER UDO SECTION 7.2. OR SECTION 12.5. Z FOR PROJECTS WITH GREENWAYS: ON SITE PLANS. GREENWAY PLAT SHALL BE RECORDED, SHOWING METES AND BOUNDS FOR THE GREENWAY, AND EVIDENCE OF RECORDATION WITH BOOK AND PAGE NUMBER PROVIDED TO THE PARKS AND RECREATION DEPARTMENT, AT TIME OF FIRST FINAL PLAT APPROVAL OR PRIOR TO ISSUANCE OF A BUILDING PERMIT, WHICHEVER COMES FIRST. ON PRELIMINARY PLATS. GREENWAY PLAT SHALL BE RECORDED, SHOWING METES AND BOUNDS FOR THE GREENWAY, AND EVIDENCE OF RECORDATION WITH BOOK AND PAGE NUMBER PROVIDED TO THE PARKS AND RECREATION DEPARTMENT, AT TIME OF FIRST FINAL PLAT APPROVAL ON FINAL PLATS (CITY): GREENWAY EASEMENT DEDICATED TO THE CITY OF DURHAM ACCORDING TO THE TERMS STATED IN REAL ESTATE BOOK 1503, PAGES 898-899. NO BUILDING OR LAND DISTURBANCE EXCEPT ACCORDING TO THOSE TERMS; PUBLIC ACCESS GRANTED. OR "DEEDED TO THE CITY OF DURHAM IN FEE SIMPLE FOR CITY GREENWAY; PUBLIC ACCESS GRANTED." 8. FINAL PLAT OWNERS CERTIFICATE (TO BE PLACED NEAR THE ATTORNEY'S CERTIFICATE AND OUTSIDE THE GENERAL CONDITIONS OF APPROVAL BOX): THE UNDERSIGNED OWNER OF THE PROPERTY LYING WITHIN THE ATTACHED PLAT AND SUBDIVISION HEREBY CERTIFIES THAT HE/SHE ORDERED THE WORK OF SURVEYING AND PLATTING TO BE DONE, AND THAT ALL PUBLIC STREETS, ALLEYS, EASEMENTS, AND OTHER OPEN SPACES SO DESIGNATED UPON SAID PLAT ARE HEREBY DEDICATED FOR SUCH USE AND THAT ALL PUBLIC AND PRIVATE EASEMENTS SHOWN UPON SAID PLAT ARE HEREBY GRANTED FOR THE USES STIPULATED. 9. FINAL PLAT ATTORNEY'S CERTIFICATE (TO BE PLACED NEAR THE OWNER'S CERTIFICATE AND OUTSIDE THE GENERAL CONDITIONS OF APPROVAL BOX): 1, IN MY CAPACITY AS LOCAL COUNSEL FOR DO HEREBY CERTIFY THAT TO THE BEST OF MY KNOWLEDGE AND BELIEF THAT IS THE OWNER OF RECORD OF THE TRACT OF LAND DESCRIBED HEREON, AND THAT IS THE OWNER OR OWNER'S AGENT AUTHORIZED TO SIGN THE DEDICATION STATEMENT PERTAINING TO THIS RECORDING . AS OF THIS DATE, SIGNED 10. STREET EASEMENT NOTE: FOOT WIDE CITY OF DURHAM PUBLIC STREET EASEMENT, SUBJECT TO THE TERMS STATED IN THE DECLARATION IN REAL ESTATE BOOK 2350, PAGE 938. NO STRUCTURES, FILLS, EMBANKMENTS OR OBSTRUCTIONS PERMITTED WITHIN THE EASEMENT EXCEPT ACCORDING TO THOSE TERMS. 11.PRIVATE STREET DESIGN NOTE FOR TOWNHOUSES AND CONDOMINIUMS IN THE CITY LIMITS. (THE FOLLOWING NOTES SHALL BE ADDED TO THE SITE PLAN AND FINAL PLATS. THEY CAN BE MODIFIED TO THEIR SPECIFIC USES (STREETS, WATER, SEWER, STORM SEWER)): A) THE STREETS (AND UTILITIES) ARE PRIVATE AND WILL NOT BE PUBLICLY MAINTAINED; B) THE STREETS (AND UTILITIES) ARE TO REMAIN PRIVATE SINCE THE DESIGN DOES NOT MEET CITY DESIGN CRITERIA AND WILL NOT BE MADE PUBLIC NOR MAINTAINED BY THE CITY.- C) THE SELLER IS REQUIRED TO NOTIFY THE BUYER OF ITEMS A AND B ABOVE. 12. PARKING LOTS AND WHEN NO BUILDING PERMIT IS REQUIRED, PLACE THIS NOTE IN THE SPECIAL CONDITIONS OF APPROVAL BOX. OWNER EVELOPER SHALL NOTIFY THE DURHAM CITY COUNTY PLANNING DEPARTMENT SITE COMPLIANCE STAFF AT THE COMPLETION OF CONSTRUCTION AND LANDSCAPING TO REQUEST AN INSPECTION PRIOR TO USE OF THE FACILITY. 13. LANDSCAPE MULCH: PINE STRAW SHALL NOT BE USED AS MULCH OR GROUNDCOVER WITHIN TEN FEET OF ANY STRUCTURES CONSISTING OF EXTERIOR COMBUSTIBLE CONSTRUCTION AS SPECIFIED BY DURHAM CITY CODE SECTION 46-8Z 14. LANDSCAPING/C.O. STANDARDS NOTE. ALL LANDSCAPING MUST BE IN PLACE PRIOR TO REQUEST FOR A CERTIFICATE OF COMPLIANCE. CONTACT DURHAM CITY COUNTY PLANNING DEPARTMENT SITE COMPLIANCE STAFF FOR INSPECTION. 15. LANDSCAPE RE -INSPECTION FEE.• EACH LANDSCAPING COMPLIANCE INSPECTION AFTER THE INITIAL INSPECTION WILL INCUR A RE -INSPECTION FEE. PAYMENT MUST BE RECEIVED BY THE DURHAM CITY COUNTY PLANNING DEPARTMENT PRIOR TO RE -INSPECTION. 16. STREET TREE NOTE FOR ALL PRELIMINARY AND FINAL PLATS WHERE TREES WILL BE PLANTED: STREET TREES MEETING THE REQUIREMENTS OF UDO SECTION 9.6 SHALL BE PLANTED PRIOR TO THE ISSUANCE OF A CERTIFICATE OF COMPLIANCE, UNLESS THE PLANTING HAS BEEN POSTPONED IN ACCORDANCE WITH THE REQUIREMENTS OF UDO SEC. 9.11. 17° UNDISTURBED LANDSCAPE BUFFERS: FOOT WIDE UNDISTURBED LANDSCAPE BUFFER. NO CLEARING OR GRADING OTHER THAN SELECTIVE THINNING AND ORDINARY MAINTENANCE OF EXISTING VEGETATION PERMITTED. 18. CONSTRUCTION IN PRESERVED TREE COVERAGE AREAS (UDO SECTION 8.3): A. PRESERVED TREE COVERAGE AREAS SHALL NOT BE USED FOR ACTIVE RECREATIONAL PURPOSES EXCEPT FOR WALKING PATHS AND FOOT TRAILS CONSTRUCTED WITH MINIMAL DISTURBANCE OF TREE ROOTS AND EXISTING VEGETATION PROVIDED A REGISTERED ARBORIST HAS CERTIFIED THAT THE CONSTRUCTION OF THE TRAIL HAS BEEN DESIGNED TO MINIMIZE IMPACT TO THE EXISTING TREES. NO TREE OVER 10 INCHES SHALL BE REMOVED FOR THE CONSTRUCTION OF TRAILS. SITE PLAN APPROVAL IS REQUIRED FOR CONSTRUCTION OF TRAILS IN PRESERVED TREE COVERAGE AREAS. B. ALL BUILDINGS SHALL BE SET BACK AT LEAST 10 FEET FROM THE EDGE OF ANY PRESERVED TREE COVERAGE AREA. C. UTILITY LINES AND DRAINAGE CHANNELS SHALL BE MINIMIZED WITHIN THE ROOT PROTECTION ZONES OF THE TREES TO BE SAVED. PREFERABLY, SUCH FACILITIES SHOULD BE LOCATED ADJACENT TO DRIVEWAYS AND IN GROUPINGS ALLOWED BY SOUND ENGINEERING PRACTICES. 19. TREE PROTECTION NOTE (UDO SEC. 8.3): TREE PROTECTION FENCING MUST BE IN PLACE PRIOR TO ANY DEMOLITION, LAND DISTURBANCE, OR ISSUANCE OF A GRADING PERMIT AND SHALL INCLUDE WARNING SIGNS POSTED IN BOTH ENGLISH AND SPANISH, AS FOLLOWS. "NO TRESPASSING/TREE PROTECTION AREA/PROHIBIDO ENTRAR / ZONA PROTECTORA PARA LOS ARBOLES. " 20. ROOT PROTECTION ZONE (UDO SEC. 8.3): EQUALS ONE FOOT OF RADIUS FOR EVERY INCH OF DIAMETER OF EXISTING TREES, OR SIX FOOT RADIUS, WHICHEVER IS GREATER. NO DISTURBANCE ALLOWED WITHIN THIS AREA. AREA MUST BE PROTECTED WITH BOTH TREE PROTECTION FENCING AND WARNING SIGNS. 21. PROTECTION OF EXISTING VEGETATION (UDO SEC. 8.3): AT THE START OF GRADING INVOLVING THE LOWERING OF EXISTING GRADE AROUND A TREE OR STRIPPING OF TOPSOIL A CLEAN SHARP VERTICAL CUT SHALL BE MADE AT THE EDGE OF THE TREE SAVE AREA PRIOR TO OR AT THE SAME TIME AS SILT FENCE AND OTHER EROSION CONTROL MEASURES ARE INSTALLED. THE TREE PROTECTION FENCING SHALL BE INSTALLED ON THE SIDE OF THE CUT FARTHEST AWAY FROM THE TREE TRUNK AND SHALL REMAIN IN PLACE UNTIL ALL CONSTRUCTION IN THE VICINITY OF THE TREES IS COMPLETE. NO STORAGE OF MATERIALS FILL OR EQUIPMENT AND NO TRESPASSING SHALL BE ALLOWED WITHIN THE BOUNDARY OF THE PROTECTED AREA. 22. FOR PROJECTS INCLUDING MINI -WAREHOUSE (SELF -STORAGE) SPACE. THIS APPROVAL IS FOR STORAGE PURPOSES ONLY, UNLESS SPECIFICALLY AUTHORIZED OTHERWISE. ANY OTHER USE COULD CREATE BUILDING CODEIZONING VIOLATIONS. 23. FOR PROJECTS SUBJECT TO FEDERAL FAIR HOUSING REGULATIONS. BE ADVISED THAT THE PROVISIONS OF APPENDIX 11 OF THE FEDERAL FAIR HOUSING REGULATIONS (ACCESSIBILITY GUIDELINES -24 CFR, CH. 1 SUBCH. A APP 11 EFFECTIVE MARCH 6 1991 ARE REQUIRED ON THIS PROJECT. IT IS THE RESPONSIBILITY OF THE OWNER/DEVELOPER/BUILDER TO COMPLY WITH THESE REGULATIONS. ALSO BE AWARE THAT THESE REQUIREMENTS ARE BEYOND THE SCOPE OF VOLUME 1-C (HANDICAP ACCESSIBILITY) OF THE NC STATE BUILDING CODE AND AS SUCH THE BURDEN OF COMPLIANCE IS BORNE BY THE OWNER EVELOPER UILDER. 24. TRANSPORTATION FACILITY PERMIT. CONSTRUCTIONOFA PROPOSED PARKING FACILITY, OR MODIFICATION TO AN EXISTING FACILITY THAT MEETS OR EXCEEDS THE FOLLOWING THRESHOLDS MAY REQUIRE A TRANSPORTATION FACILITY PERMIT FROM NCDENR DIVISION OF AIRQUALITY, Q PRIOR TO THE START OF CONSTRUCTION. 1500 SPACES FOR SURFACE PARKING LOTS; 750 SPACES FOR PARKING STRUCTURES SUCH AS DECKS OR GARAGES,• OR 1000 SPACES FOR A COMBINATION OF SURFACE PARKING LOTS AND PARKING STRUCTURES. CONTACT NC DIVISION OF AIR QUALITY FOR MORE INFORMATION. 25. UDO SITE LIGHTING NOTEUDO SEC. Z4: MEASURES SHALL BE PROVIDED TO PREVENT LIGHT SPILLOVER ONTO ADJACENT PROPERTIES AND GLARE TOWARD MOTOR VEHICLE OPERATORS AND SHALL BE INDICATED ON THE SITE PLAN. EXTERIOR LIGHTS SHALL BE SHIELDED SO THAT THEY DO NOT CAST DIRECT LIGHT BEYOND THE PROPERTY LINE. IN ACCORDANCE WITH THESE STANDARDS: A. THE MAXIMUM ILLUMINATION AT THE EDGE OF THE PROPERTY LINE ADJACENT TO RESIDENTIAL ZONING IS 0.5 FOOT CANDLES. B. THE MAXIMUM ILLUMINATION AT THE EDGE OF THE PROPERTY LINE ADJACENT TO NONRESIDENTIAL ZONING IS 5.0 FOOT CANDLES. C. THE MAXIMUM ILLUMINATION AT THE EDGE OF THE PROPERTY LINE ADJACENT TO A STREET IS 5.0 FOOT CANDLES. D. THE LEVEL OF ILLUMINATION AS MEASURED IN FOOT CANDLES AT ANY ONE POINT SHALL MEET THE STANDARDS IN THE TABLE IN UDO SECTION 7.4 WITH MINIMUM AND MAXIMUM LEVELS MEASURED ON THE PAVEMENT WITHIN THE LIGHTED AREA. E THE MAXIMUM HEIGHT FOR DIRECTIONAL OR FULL CUT-OFF LIGHTING FIXTURESFIXTURES DESIGNED TO INSURE THAT NO LIGHT IS EMITTED ABOVE A HORIZONTAL UNE PARALLEL TO THE GROUND) SHALL BE 30 FEET ABOVE GRADE, MEASURED TO THE TOP OF THE FIXTURE. F. THE MAXIMUM HEIGHT FOR NON -DIRECTIONAL LIGHTING FIXTURES, WHICH ARE DEFINED AS FIXTURES DESIGNED TO ALLOW LIGHT TO BE EMITTED ABOVE A HORIZONTAL LINE PARALLEL TO THE GROUND, SHALL BE 15 FEET ABOVE GRADE, MEASURED TO THE TOP OF THE FIXTURE. G. THESE STANDARDS MUST BE VERIFIED BY FIELD SURVEY (BY USE OF PHOTOMETRIC SURVEY) PRIOR TO THE CERTIFICATE OF COMPLIANCE BEING ISSUED. ALL OF THIS INFORMATION, INCLUDING DETAILS, WILL BE REQUIRED ON BUILDING PLANS PRIOR TO ISSUANCE OF BUILDING PERMIT. 26. FOR PROJECTS UTILIZING ON SITE WATER SUPPLY OR WASTE WATER DISPOSAL: APPROVAL DOES NOT GUARANTEE APPROVAL OF EITHER ON-SITE WATER SUPPLY OR WASTE WATER 11 12 DISPOSAL SYSTEMS OR THAT PERMITS WILL BE ISSUED FOR THE CONSTRUCTION OF SUCH SYSTEMS. 27 SANITARY SEWER EASEMENTS: CITY. SEE PUBLIC WORKS STANDARD NOTES, BELOW. COUNTY: CENTERLINE OF FOOT WIDE COUNTY OF DURHAM SANITARY SEWER EASEMENT. SUBJECT TO TERMS STATED IN THE DECLARATION IN REAL ESTATE BOOK 1626, PAGE 145. NO STRUCTURES, FILL, EMBANKMENTS, TREES OR OBSTRUCTIONS PERMITTED WITHIN THE EASEMENT EXCEPT ACCORDING TO THOSE TERMS. 28. CITY STORM DRAINAGE EASEMENTS: SEE PUBLIC WORKS STANDARD NOTES, BELOW. COUNTY STORM OR PRIVATE DRAINAGE EASEMENTS. CENTERLINE OF FOOT WIDE DRAINAGE EASEMENT FOR THE BENEFIT OF ADJACENT PROPERTY OWNERS NOT MAINTAINED BY PUBLIC AUTHORITIES. NO BUILDINGS, STRUCTURES, FILLS, EMBANKMENTS OR OBSTRUCTIONS PERMITTED WITHIN THE EASEMENT EXCEPT ACCORDING TO THOSE TERMS. 29. FOR RESIDENTIAL DEVELOPMENTS USING CURBSIDE COLLECTION: AN AUTOMATED SOLID WASTE COLLECTION VEHICLE HAS AN 18 -FOOT WHEELBASE AND A TURNING RADIUS OF 45 FEET WALL-TO-WALL AND 43 FEET CURB -TO -CURB. THE DEPARTMENT OF SOLID WASTE MANAGEMENT RESERVES THE RIGHT TO MODIFY COLLECTION OF GARBAGE AND RECYCLABLES FOR ANY ROADWAY OR CUL-DE-SAC NOT CONSTRUCTED TO ACCOMMODATE THOSE SPECIFICATIONS. 30. FOR COMMERCIAL PROJECTS WANTING TO RECEIVE CURBSIDE COLLECTION INSTEAD OF DUMPSTERS. GARBAGE VOLUME IS NOT EXPECTED TO EXCEED THE CAPACITY OF FOUR 96 -GALLON CARTS PER WEEK. ALL TARGET (BANNED) RECYCLABLES WILL BE SEPARATED FROM GARBAGE AND PLACED IN CITY RECYCLE BINS. A WASTE HANDLING FACILITY WILL BE CONSTRUCTED AT THE OWNER'S EXPENSE AT THE LOCATION DESIGNATED ON THE PLANS IN COMPLIANCE WITH ORDINANCE AND SWM STANDARDS SHOULD GARBAGE EXCEED THE FOUR -CART PER WEEK LIMIT. 31. FOR COMMERCIAL SITES WITHOUT PROPOSED RESTAURANTS(BUT WHERE RESTAURANTS WOULD BE AN ALLOWED USE IN THE ZONING DISTRICT): AS DESIGNED, A RESTAURANT FACILITY MAY NOT BE PERMITTED IN THIS BUILDING. A REVISED SITE PLAN WILL BE REQUIRED TO ACCOMMODATE A GREASE TRAP, TRASH HANDLING AND OTHER REQUIREMENTS RELATED TO A RESTAURANT FACILITY. 32. FIRE NOTE TO BE INCLUDED ON UTILITY PLAN SHEET. PROVIDE FIRE PLANS EXAMINER ONE COPY OF UTILITY CONSTRUCTION DRAWINGS, SHOWING UNDERGROUND PIPING LAYOUT AND ALL FIRE APPURTENANCES. PERMIT FOR INSTALLATION OF PRIVATE FIRE HYDRANT(S) MUST BE ISSUED BY FIRE PLANS EXAMINER PRIOR TO INSTALLATION OF SAID HYDRANTS. 33. FIRE NOTES TO BE INCLUDED ON COVER SHEET. A. TEMPORARY OR PERMANENT ROADWAYS OF ALL-WEATHER DRIVING SURFACE, CAPABLE OF SUPPORTING A 75,000 POUND VEHICLE WEIGHT, SHALL BE ESTABLISHED PRIOR TO THE COMMENCEMENT OF BUILDING CONSTRUCTION ACTIVITIES. THESE ROADWAYS SHALL BE EXTENDED WITH THE PROGRESS OF CONSTRUCTION SO THAT.• A.A. ALL POINTS AROUND THE PERIMETER OF A BUILDING UNDER CONSTRUCTION IS NO GREATER THAN 150 FEET TRAVEL DISTANCE FROM A ROADWAY, A.B. FIRE DEPARTMENT CONNECTIONS (FDC), EITHER TEMPORARY OR PERMANENT, ARE NO GREATER THAN 100 FEET TRAVEL DISTANCE FROM A ROADWAY. B. TEMPORARY WEATHER -RESISTANT STREET SIGNS OF STANDARD SIZE AND LETTERING SHALL BE PROVIDED AT THE INTERSECTIONS OF TEMPORARY OR PERMANENT ROADWAYS AND SHALL REMAIN IN PLACE UNTIL REPLACED BY PERMANENT SIGNS. C. FIRE HYDRANTS, AS SHOWN ON THE APPROVED SITE PLAN, SHALL BE PLACED IN SERVICE AND MADE AVAILABLE TO THE FIRE DEPARTMENT AS SOON AS COMBUSTIBLE MATERIAL ARRIVES ON SITE. NO CONSTRUCTION FENCING OR OTHER BARRIERS ARE TO BE PLACED BETWEEN THE ROADWAY AND THE HYDRANTS, WITH MINIMUM 3 FEET WORKING CLEARANCE AROUND HYDRANTS. HYDRANT SERVICE SHALL BE EXTENDED WITH THE PROGRESS OF CONSTRUCTION SO THAT: C.A. ALL POINTS AROUND THE PERIMETER OF A BUILDING UNDER CONSTRUCTION IS NO GREATER THAN 500 FEET TRAVEL DISTANCE FROM A HYDRANT, C.B. FIRE DEPARTMENT CONNECTIONS (FDC), EITHER TEMPORARY OR PERMANENT, ARE NO GREATER THAN 50 FEET TRAVEL DISTANCE FROM A HYDRANT. 34. FOR COUNTY SOIL AND EROSION CONTROL: A. A SEDIMENTATION AND EROSION CONTROL PLAN MUST BE SUBMITTED AND APPROVED PRIOR TO THE ISSUANCE OF A LAND -DISTURBANCE PERMIT. B. IF AN OFFSITE SOIL SPOIL OR BORROW SITE IS UTILIZED, THEN THE DISTURBED AREA FOR THE SPOIL/BORROW SITE MUST BE INCLUDED IN THE LAND -DISTURBANCE PLAN AND PERMIT UNLESS THE SPOIL/BORROW SITE ALREADY HAS A LAND -DISTURBANCE PERMIT. ENGINEERING DIVISION NOTES N THE PUBLIC WORKS CONDITIONS OF APPROVAL BOX, ADD THE FOLLOWING NOTES. 1. THE DESIGNING PROFESSIONAL (A NCPE, NCPLS OR NCRLA - AS REQUIRED) SHALL SUBMIT THREE (3) SETS OF CONSTRUCTION DRAWINGS TO THE PUBLIC WORKS DEPARTMENT - DEVELOPMENT REVIEW FOR REVIEW AND APPROVAL. CONSTRUCTION DRAWING APPROVAL IS REQUIRED PRIOR TO COMMENCING CONSTRUCTION (SEE CONSTRUCTION PLAN APPROVAL PROCESS). THE APPROVAL OF CONSTRUCTION DRAWINGS IS SEPARATE FROM SITE PLAN APPROVAL. CITY OFFICIALS SHALL REVIEW ALL SIZES, MATERIALS, SLOPES, LOCATIONS, EXTENSIONS AND DEPTHS FOR ALL PROPOSED UTILITIES (WATERLINES, SANITARY SEWER LINES AND STORM DRAINAGE CONVEYANCE SYSTEMS) FOR COMPLIANCE WITH ALL APPLICABLE REGULATORY STANDARDS, SPECIFICATIONS, AND BEST MANAGEMENT PRACTICES. 2. THE DESIGNING PROFESSIONAL (A NCPE, NCPLS OR NCRLA - AS REQUIRED) SHALL SUBMIT ONE (1) SET OF AS -BUILT DRAWINGS TO THE PUBLIC WORKS DEPARTMENT - DEVELOPMENT REVIEW FOR REVIEW AND APPROVAL. AS -BUILT DRAWING APPROVAL IS REQUIRED PRIOR TO WATER METER INSTALLATION AND/OR SANITARY SEWER SERVICE CONNECTION AND PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY. 3. FIRE FLOW ANALYSIS REQUIRED FOR REVIEW AND APPROVAL AS PART OF THE CONSTRUCTION DRAWING APPROVAL PROCESS. TO SCHEDULE FLOW TEST OR TO OBTAIN CURRENT SYSTEM DATA, COMPLETE THE ONLINE APPLICATION (HTTP: //DURHAMNC.GOV/ICH/OP/PWD/PAGES/FIRE-FLOW°ASPX). 4. IF A METER 2" OR LARGER IS PROPOSED, CONTACT WATER MANAGEMENT AT 560-4381 PRIOR TO THE CONSTRUCTION OF THE METER VAULT TO VERIFY THE TYPE AND DIMENSIONS OF THE METER. 5. WATER PERMIT REQUIRED AFTER CONSTRUCTION DRAWING APPROVAL AND PRIOR TO COMMENCING WATER MAIN INSTALLATION. 6. SEWER PERMIT REQUIRED AFTER CONSTRUCTION DRAWING APPROVAL AND PRIOR TO COMMENCING SANITARY SEWER MAIN INSTALLATION. Z SEWER PERMIT FROM DURHAM COUNTY REQUIRED. CONTACT DURHAM COUNTY UTILITY DIVISION AT 560-7993. 8. AN NCDOT OR CITY OF DURHAM DRIVEWAY PERMIT IS REQUIRED. 9. CONSTRUCTION DRAWINGS ARE NOT REQUIRED: I. PROVIDE TWO (2) SETS OF APPROVED SITE PLAN DOCUMENTS TO ENGINEERING INSPECTIONS, 3RD FLOOR, 101 CITY HALL PLAZA, DURHAM, NC 27701 AT LEAST 5 DAYS PRIOR TO BEGINNING CONSTRUCTION AND CONTACT ENGINEERING INSPECTIONS AT 560-4326 AT LEAST 48 HOURS PRIOR TO BEGINNING CONSTRUCTION. 11. A CONSTRUCTION ON CITY RIGHT-OF-WAY / PRIVATE PROPERTY PERMIT MAY BE REQUIRED. CONTACT THE PUBLIC WORKS CUSTOMER SERVICE DESK AT 560-4326. M. AN ENCROACHMENT AGREEMENT MAY BE REQUIRED. CONTACT ENGINEERING SERVICES AT 560-4326. WATER EASEMENT NOTE. CENTERLINE OF FOOT WIDE CITY OF DURHAM WATER EASEMENT. SUBJECT TO TERMS STATED IN THE DECLARATION IN REAL ESTATE BOOK 1510, PAGE 958. NO STRUCTURES, FILL, EMBANKMENTS, TREES OR OBSTRUCTIONS PERMITTED WITHIN THE EASEMENT EXCEPT ACCORDING TO THOSE TERMS. SANITARY SEWER EASEMENT NOTE CENTERLINE OF FOOT WIDE CITY OF DURHAM SANITARY SEWER EASEMENT. SUBJECT TO TERMS STATED IN THE DECLARATION IN REAL ESTATE BOOK 1510, PAGE 958° NO STRUCTURES, FILL, EMBANKMENTS, TREES OR OBSTRUCTIONS PERMITTED WITHIN THE EASEMENT EXCEPT ACCORDING TO THOSE TERMS. CENTERLINE OF FOOT WIDE COUNTY OF DURHAM SANITARY SEWER EASEMENT. SUBJECT TO TERMS STATED IN THE DECLARATION IN REAL ESTATE BOOK 1626 PAGE 145. NO STRUCTURES FILL, EMBANKMENTS, TREES OR OBSTRUCTIONS PERMITTED WITHIN THE EASEMENT EXCEPT ACCORDING TO THOSE TERMS. SIDEWALK NOTE: THE LOCATION OF THE SIDEWALKS SHOWN ON THIS PLAN IS SCHEMATIC. A CITY OF DURHAM AND/OR NCDOT ENCROACHMENT PERMIT IS REQUIRED PRIOR TO ANY CONSTRUCTION. AFTER OBTAINING THE REQUIRED PERMITS, PLEASE CONTACT THE CITY OF DURHAM ENGINEERING CONSTRUCTION INSPECTION OFFICE AT 560-4326 FOR A PRE -CONSTRUCTION CONFERENCE AND FIELD VISIT PRIOR TO ANY WORK ON THE PROPOSED SIDEWALK. PUBLIC ACCESS EASEMENT FOR SIDEWALK NOTE: CERTIFICATION OF EXPRESS DEDICATION FOR PUBLIC USE [DESCRIPTION OF THE SIDEWALKS TO BE DEDICATED INSERTED HERE] ('SIDEWALKS" ARE EXPRESSLY DEDICATED TO USE BY THE GENERAL PUBLIC. UPON CONSTRUCTION OF THE SIDEWALKS IN CONFORMANCE WITH ALL APPLICABLE REQUIREMENTS, CITY COUNCIL MAY ACCEPT THE SIDEWALKS FOR MAINTENANCE BY THE CITY OF DURHAM"CITY" . ACCEPTANCE OF THE SIDEWALKS BY CITY COUNCIL CONVEYS THE RIGHT IN OVER, UNDER, AND THROUGH THE SIDEWALKS, NECESSARY FOR THE CITY AND ITS AGENTS AND CONTRACTORS, TO MAINTAIN AND REPAIR THE SIDEWALKS IN THE CITY'S SOLE DISCRETION. THE RIGHT OF INGRESS/EGRESS TO THE SIDEWALKS FROM THE PUBLIC RIGHT OF WAY IS ALSO GRANTED TO THE CITY SO THE CITY CAN MAINTAIN AND REPAIR THE SIDEWALKS AFTER ACCEPTANCE. THE CITY IN ITS SOLE DISCRETION HAS THE RIGHT TO DETERMINE THE POINTS OF INGRESS AND EGRESS FROM THE PUBLIC RIGHT OF WAY NECESSARY TO PERFORM MAINTENANCE OR REPAIR AFTER ACCEPTANCE. DRIVEWAY PERMIT NOTES. A CITY OF DURHAM DRIVEWAY PERMIT IS REQUIRED PRIOR TO ANY DRIVEWAY CONSTRUCTION ON PUBLIC RIGHT-OF-WAYY, SUBMIT PLANS FOR DRIVEWAY PERMIT APPROVAL TO CITY ENGINEERING DEVELOPMENT REVIEW. AFTER OBTAINING THE PERMIT, PLEASE CALL CITY OF DURHAM ENGINEERING INSPECTION OFFICE AT 560-4326 PRIOR TO START OF CONSTRUCTION. NCDOT DRIVEWAY PERMIT REQUIRED PRIOR TO CONSTRUCTION. CONTACT NCDOT AT 220-4750 FOR REQUIREMENTS. TOWNHOME NOTE TOWNHOME DEVELOPMENTS MAY BE DESIGNED AND CONSTRUCTED WITH PARKING AREAS ON BOTH SIDES OF THE TRAVEL LANES. THIS CONFIGURATION IS NOT TO BE CONSIDERED A STREET. IF THIS OPTION IS USED, THE TRAVEL AND PARKING AREAS SHALL BE NOTED AS 'PRIVATE ACCESS AND COMMON AREAS': AS SUCH, THE DEVELOPER SHALL ACKNOWLEDGE AND MAKE PROSPECTIVE BUYERS AWARE THAT THESE AREAS WILL NOT BE ASSIGNED A STREET NAME, NOR WILL THEY EVER BE ELIGIBLE FOR MAINTENANCE BY THE CITY OF DURHAM. THE DEVELOPER WILL ENSURE THAT ALL OF THE ACCESS AND COMMON AREA PROPERTY IS DESCRIBED IN THE COVENANTS AND THAT THE HOME OWNERS ASSOCIATION IS RESPONSIBLE FOR THE MAINTENANCE OF THIS AREA. THE FOLLOWING NOTE SHALL BE ADDED TO ALL SITE PLANS AND PLATS ASSOCIATED WITH THE DEVELOPMENT.• THE DRIVING AND PARKING AREAS SHOWN ON THIS DRAWING NOTED AS 'PRIVATE ACCESS AND COMMON AREAS" DO NOT MEET CITY OF DURHAM STREET STANDARDS. THE FEATURES WITHIN THIS AREA ARE PRIVATE AND WILL NEVER BE ELIGIBLE FOR PUBLIC MAINTENANCE. UTILITY NOTES. A UTILITY MAINLINE CONSTRUCTION PERMIT IS REQUIRED PRIOR TO THE INSTALLATION OF EACH UTILITY. ALL UTILITIES SHALL SUBMIT PLAN DRAWINGS AND APPLICATIONS TO THE CITY ENGINEERING DIVISION. WATER SERVICE ABANDONMENT. ABANDONMENT OF WATER SERVICES SHALL INCLUDE EXCAVATING DOWN TO CORPORATION STOP, TURNING IT OFF AND CUTTING SERVICE LINE FREE FROM CORPORATION STOP. THE METER, IF PRESENT, SHALL BE RETURNED TO CITY OF DURHAM. PRIOR TO ANY CREDIT OR REFUND BEING PROCESSED THE METER MUST BE RETURNED TO WATER MANAGEMENT DEPARTMENT AND THE METER NUMBER VERIFIED AND CODED PROPERLY AS RETURNED. UTILITY SERVICE ABANDONMENTS WILL TAKE PLACE PRIOR TO BEGINNING UTILITY CONSTRUCTION WORK FOR A PROJECT. ANY EXCAVATION AS PART OF ABANDONING UTILITIES WILL REQUIRE BACKFILLING PER CITY OF DURHAM STANDARDS. SANITARY SEWER SERVICE ABANDONMENT. ABANDONMENT OF SANITARY SEWER SERVICE LINES SHALL CONSIST OF EXCAVATING DOWN TO THE SERVICE CONNECTION TO THE MAIN, CUTTING THIS CONNECTION AND INSTALLING A WATERTIGHT PLUG IN THE MAIN. THE SERVICE LINE AND ALL CLEAN-OUT RISERS ON THE SERVICE LINE SHALL BE REMOVED. UTILITY SERVICE ABANDONMENTS WILL TAKE PLACE PRIOR TO BEGINNING UTILITY CONSTRUCTION WORK FOR A PROJECT. ANY EXCAVATION AS PART OF ABANDONING UTILITIES WILL REQUIRE BACKFILLING PER CITY OF DURHAM STANDARDS. 13 14 15 16 WATER, SANITARY SEWER AND STORM SEWER SEPARATION NOTES 1. HORIZONTAL AND VERTICAL SEPARATION A. SANITARY SEWERS SHALL BE LAID AT EAST 10 -FEET HORIZONTALLY FROM ANY EXISTING OR PROPOSED WATER MAIN. THE DISTANCE SHALL BE MEASURED EDGE TO EDGE. IN CASES WHERE IT IS NOT PRACTICAL TO MAINTAIN A 10 -FOOT SEPARATION, THE CITY OF DURHAM MAY ALLOW DEVIATION ON A CASE-BY-CASE BASIS, IF SUPPORTED BY DATA FROM THE DESIGN ENGINEER. SUCH DEVIATION ON MAY ALLOW THE INSTALLATION OF THE SANITARY SEWER CLOSER TO A WATER MAIN, PROVIDED THAT THE WATER MAIN IS IN A SEPARATE TRENCH OR ON AN UNDISTURBED EARTH SHELF LOCATED ON ONE SIDE OF THE SANITARY SEWER AND AT AN ELEVATION SO THE BOTTOM OF THE WATER MAIN IS AT EAST 18 -INCHES ABOVE THE TOP OF THE SEWER. B. IF IT IS IMPOSSIBLE TO OBTAIN PROPER HORIZONTAL AND VERTICAL SEPARATION AS DESCRIBED ABOVE OR ANYTIME THE SANITARY SEWER IS OVER THE WATER MAIN, BOTH THE WATER MAIN AND SANITARY SEWER MUST BE CONSTRUCTED OF FERROUS PIPE COMPLYING WITH THE PUBLIC WATER SUPPLY DESIGN STANDARDS AND BE PRESSURE TESTED TO 150 -PSI TO ASSURE WATER TIGHTNESS BEFORE BACKFILLING. C. A 24 -INCH VERTICAL SEPARATION SHALL BE PROVIDED BETWEEN STORM SEWER AND SANITARY SEWER LINES OR FERROUS PIPE SPECIFIED. A 12 -INCH VERTICAL SEPARATION SHALL BE PROVIDED BETWEEN STORM SEWER AND WATER MAINS. 1. IF A 12 -INCH VERTICAL SEPARATION IS NOT MAINTAINED AT A CROSSING BETWEEN STORM SEWER AND WATER MAINS (OR PRESSURE SEWERS). THE WATER MAIN SHALL BE CONSTRUCTED OF FERROUS PIPE AND A CONCRETE COLLAR SHALL BE POURED AROUND WATER MAINS AND STORM SEWER TO IMMOBILIZE THE CROSSING. Z CROSSINGS A. SANITARY SEWER CROSSING WATER MAINS SHALL BE LAID TO PROVIDE A MINIMUM VERTICAL DISTANCE OF 18 -INCHES BETWEEN THE OUTSIDE OF THE WATER MAIN AND THE OUTSIDE OF THE SANITARY SEWER. THE CROSSING SHALL BE ARRANGED SO THAT THE SANITARY SEWER JOINTS WILL BE EQUIDISTANT AND AS FAR AS POSSIBLE FROM THE WATER MAIN JOINTS. B. WHEN IT IS IMPOSSIBLE TO OBTAIN PROPER HORIZONTAL AND VERTICAL SEPARATION AS STIPULATED ABOVE, ONE OF THE FOLLOWING METHODS MUST BE SPECIFIED. 1. THE SANITARY SEWER SHALL BE DESIGNED AND CONSTRUCTED OF FERROUS PIPE AND SHALL BE PRESSURE TESTED AT 150 -PSI TO ASSURE WATER TIGHTNESS PRIOR TO BACKFILLING, OR 2. EITHER THE WATER MAIN OR THE SANITARY SEWER LINE MAY BE ENCASED IN A WATERTIGHT CARRIER PIPE, WHICH EXTENDS 10 -FEET ON BOTH SIDES OF THE CROSSING, MEASURED PERPENDICULAR TO THE WATER MAIN. THE CARRIER PIPE SHALL BE OF MATERIALS APPROVED BY THE CITY OF DURHAM FOR USE IN WATER MAIN CONSTRUCTION. STORM WATER SERVICES DIVISION NOTES A. SPECIAL CONDITIONS OF APPROVAL BOX NOTES FOR SITE PLAN/PRELIMINARY PLAT SUBMITTALS. (NOTE THAT THESE NOTES MAY OR MAY NOT APPLY TO THE PROJECT DEPENDING ON THE REQUIREMENTS OF THE PROJECT, DETERMINED DURING REVIEW) 1. FEMA FLOOD STUDY REQUIRED: "A CLOMR SHALL BE OBTAINED FROM FEMA PRIOR TO CONSTRUCTION DRAWING APPROVAL. A LOMR SHALL BE OBTAINED FROM FEMA PRIOR TO ISSUANCE OF ANY CERTIFICATES OF OCCUPANCY OR CERTIFICATES OF COMPLIANCE." 2. FOR DEVELOPMENTS WITHIN THE NEUSE RIVER BASIN (PAYMENT, IF REQUIRED, TO BE DETERMINED DURING SITE PLAN REVIEW): A SITE PLAN CANNOT BE APPROVED UNTIL A RECEIPT FROM THE NORTH CAROLINA ECOSYSTEM ENHANCEMENT PROGRAM HAS BEEN RECEIVED BY THE CITY OF DURHAM CONFIRMING THE PAYMENT OF $X.XX IN OFFSET FEES." 3. FOR DEVELOPMENTS REQUIRED TO HAVE A STORMWATER BMP FACILITY. FINAL DESIGN CALCULATIONS FOR THE STORMWATER BMP FACILITY WILL REQUIRE THE USE OF STORAGE INDICATION ROUTING METHODOLOGY SUCH AS TR -20 OR HEC -1 MODELS. FOR THE BMP FACILITY, PROVIDE STAGE -STORAGE RELATIONSHIP AND INFLOW AND OUTFLOW HYDROGRAPHS. PROVIDE ALL TABULATED DATA INCLUDING CALCULATIONS SHOWING THE OUTLET UNDER ORIFICE CONTROL, BARREL CONTROL AND WEIR CONTROL, AS APPROPRIATE, TO SHOW HOW THE ROUTING WAS DEVELOPED." 4. FOR DEVELOPMENTS REQUIRED TO HAVE A STORMWATER BMP FACILITY. L "AN EXECUTED STORMWATER FACILITY OPERATION AND MAINTENANCE PERMIT AGREEMENT (PREPARED BY STORMWATER SERVICES, CITY OF DURHAM), PAYMENT OF STORMWATER FACILITY PERMIT FEE PER BMP FACILITY AND PERPETUAL SURETY FOR THE CONTINUED OPERATION AND MAINTENANCE OF THE FACILITY IS REQUIRED PRIOR TO CONSTRUCTION PLAN APPROVAL." 11. "AN AS -BUILT CERTIFICATION FOR THE STORMWATER BMP(S), PROVIDED BY THE DESIGN ENGINEER, IS REQUIRED. THE AS -BUILT SHALL BE SUBMITTED PER THE REFERENCE GUIDE FOR DEVELOPMENT, APPROVED BY THE STORMWATER SERVICES DIVISION AND THE BMP(S) SHALL BE INSPECTED AND APPROVED BY THE STORMWATER SERVICES DIVISION PRIOR TO ISSUANCE OF ANY CERTIFICATES OF OCCUPANCY OR CERTIFICATES OF COMPLIANCE FOR THE PROJECT" 5. FOR DEVELOPMENTS REQUIRED TO HAVE A STORMWATER BMP FACILITY: A COMPLETED CITY OF DURHAM DESIGN SUMMARY IS REQUIRED FOR EACH STORMWATER BMP FACILITY NO LATER THAN AT THE FIRST CONSTRUCTION DRAWING SUBMITTAL." 6. FOR DEVELOPMENTS REQUIRED TO HAVE A STORMWATER BMP FACILITY: "STORMWATER BMP FACILITY DESIGN CALCULATIONS WILL NOT BE REVIEWED OR APPROVED WITH THE SITE PLAN/PRELIMINARY PLAT SUBMITTAL. ALL STORMWATER BMP FACILITY DESIGNS WILL BE REVIEWED AND APPROVED DURING THE CONSTRUCTION DRAWING SUBMITTAL PROCESS." B. STANDARD NOTES: (NOTE THAT THESE NOTES MAY OR MAY NOT APPLY TO THE PROJECT DEPENDING ON THE REQUIREMENTS OF THE PROJECT, DETERMINED DURING REVIEW) 1. STORMWATER DRAINAGE EASEMENT NOTE (WIDTH DETERMINED AT CONSTRUCTION DRAWINGS): "CENTERLINE OF FOOT WIDE PUBLIC STORM WATER DRAINAGE EASEMENT. OWNERSHIP OF AND RESPONSIBILITY FOR IMPROVEMENT AND MAINTENANCE OF STORM WATER FACILITIES IN THIS EASEMENT REMAINS WITH THE CURRENT OWNER. IF THE PROPERTY IS WITHIN OR BECOMES A PART OF THE CITY THE EASEMENT AND ACCESS POINTS TO THE EASEMENT ARE SUBJECT TO THE TERMS AND RESTRICTIONS STATED IN THE "REVISED DECLARATION OF RIGHTS AND PRIVILEGES OF THE CITY OF DURHAM IN STORM WATER MANAGEMENT FACILITY EASEMENTS" RECORDED IN REAL ESTATE BOOK 2298, PAGE 208, WHICH DOCUMENT IS INCORPORATED HEREIN. THIS EASEMENT AND THE REVISED DECLARATION DO NOT CREATE THE OBLIGATION TO PROVIDE PUBLIC MAINTENANCE. NO BUILDING, STRUCTURES, FILLS, EMBANKMENTS OR OBSTRUCTIONS PERMITTED WITHIN THE EASEMENT EXCEPT ACCORDING TO THOSE TERMS." 2. STREAM BUFFER NOTES (WIDTH DETERMINED AT REZONING OR SITE PLAN): FOOT WIDE UNDISTURBED STREAM BUFFER EACH SIDE OF STREAM, MEASURED FROM TOP OF BANK. NO CLEARING OR GRADING OTHER THAN SELECTIVE THINNING AND ORDINARY MAINTENANCE OF EXISTING VEGETATION PERMITTED." 3. FLOODPLAIN NOTES "ALL DEVELOPMENT WITHIN THE FLOODWAY AND FLOODWAY FRINGE, INCLUDING FILL, NEW CONSTRUCTION, SUBSTANTIAL IMPROVEMENTS MANUFACTURED HOUSING, STORAGE OF MATERIALS AND STORAGE OF TOXIC OR FLAMMABLE SUBSTANCES, IS PROHIBITED EXCEPT AS PROVIDED BY APPLICABLE FLOOD HAZARD REGULATIONS." 4. GENERAL NOTES. "STATE AND FEDERAL PERMIT AUTHORIZATION MAY BE REQUIRED FROM THE DEHNR AND THE U.S. CORPS OF ENGINEERS PRIOR TO THE COMMENCEMENT OF ANY LAND DISTURBING ACTIVITIES IN OR NEAR A LAKE, STREAM, CREEK, TRIBUTARY OR ANY UNNAMED BODY OF WATER AND ITS ADJACENT WETLANDS." DEPARTMENT OF TRANSPORTATION NOTES WHERE STREETS TERMINATE, ADD THE FOLLOWING NOTE TO THE CONSTRUCTION DRAWINGS. WHERE STREETS TERMINATE (EXAMPLE PHASE LINES) THE FOLLOWING WILL BE INSTALLED: 1) ASPHALT HEADER, 2) RIPRAP OR CONCRETE APRON FOR STORM WATER TO DISSIPATE, 3) UTILITIES TO EXTEND A MINIMUM OF 5 -FEET BEYOND THE EDGE OF PAVEMENT, 4) NCDOT TYPE 111 BARRICADE. OFF-SITE ROADWAY IMPROVEMENTS, ADD THE FOLLOWING NOTE TO THE SPECIAL CONDITIONS OF APPROVAL BOX: BY REFERENCING ROADWAY IMPROVEMENTS ON THE PLAN, THE APPLICANT AGREES TO CONSTRUCT SAID IMPROVEMENTS PRIOR TO ISSUANCE OF CERTIFICATE OF OCCUPANCY IN A MANNER THAT WILL ALLOW THEM TO FUNCTION AS NOTED ON THE PLAN AND IN ACCORDANCE WITH NCDOT AND CITY OF DURHAM STANDARDS AND POLICIES. THIS INCLUDES (WHERE APPROPRIATE) BUT IS NOT LIMITED TO. ADEQUATE TRANSITION TAPERS, ALIGNMENT OF LANES THROUGH INTERSECTIONS ASSOCIATED SIGNAL MODIFICATIONS PAVEMENT MARKINGS ASSOCIATED SIGNAGE, CURB AND GUTTER, COORDINATION WITH OTHER PROPOSED ROADWAY IMPROVEMENTS AND BIKE LANES. THE APPLICANT ALSO ACCEPTS THE FINANCIAL RESPONSIBILITY FOR ACQUISITION OF ANY ADDITIONAL RIGHT-OF-WAY NECESSARY TO ACCOMMODATE THESE IMPROVEMENTS AND ANY REQUIRED SIDEWALK CONSTRUCTION. SIGNS AND/OR PAVEMENT MARKINGS TO BE INSTALLED BY THE DEVELOPER (NEW SUBDIVISIONS OR OFF-SITE ROADWAY IMPROVEMENTS THAT NEED NEW MARKINGS FOR EXAMPLE), ADD THE FOLLOWING NOTE TO THE SPECIAL CONDITIONS OF APPROVAL BOX. THE DEVELOPER IS RESPONSIBLE FOR FABRICATION AND INSTALLATION OF ALL REQUIRED SIGNS AND PAVEMENT MARKINGS WITHIN THE PUBLIC RIGHT-OF-WAY. THE DEVELOPER SHALL SUBMIT A SIGNING AND MARKINGS PLAN TO THE CITY AT CONSTRUCTION PLAN STAGE FOR REVIEW AND APPROVAL. ALL SIGNS AND PAVEMENT MARKINGS, SHOWN ON THE CONSTRUCTION PLANS, MUST BE IN PLACE PRIOR TO THE ISSUANCE OF ANY CERTIFICATE OF OCCUPANCY AND/OR STREET ACCEPTANCE, AS DETERMINED BY THE CITY. RIGHT-OF-WAY DEDICATION ON A MAJOR/MINOR THOROUGHFARE ADJACENT TO THE SITE, ADD THE FOLLOWING NOTE TO THE SPECIAL CONDITIONS OF APPROVAL BOX. DEDICATE AN ADDITIONAL - FEET OF RIGHT-OF-WAY ALONG THE FRONTAGE OF THE SITE ON ROAD PRIOR TO THE ISSUANCE OF ANY BUILDING PERMIT. A COPY OF THE RECORDED PLAT MUST BE SUBMITTED WITH THE FIRST BUILDING PERMIT APPLICATION. BUS STOP/SHELTER IS TO BE CONSTRUCTED NEAR THE SITE, ADD THE FOLLOWING NOTE TO THE SPECIAL CONDITIONS OF APPROVAL BOX: PROVIDE BUS SHELTER WITH CONCRETE PAD ON ROAD. DESIGN SPECIFICATIONS AND EXACT LOCATION TO BE REVIEWED AND APPROVED BY DATA PRIOR TO CONSTRUCTION. OFF-SITE ROADWAY IMPROVEMENTS ON THE SITE ADD THE FOLLOWING NOTE TO THE SPECIAL CONDITIONS OF APPROVAL BOX: ALL OFF-SITE ROADWAY IMPROVEMENTS MUST BE COMPLETE PRIOR TO THE ISSUANCE OF ANY CERTIFICATE OF OCCUPANCY. VARIATIONS TO THESE STANDARD NOTES MAY BE APPLIED WITH THE EXPRESS CONSENT OF THE TRANSPORTATION DIVISION. SIGNAGE AND MARKING PLAN CONSTRUCTION DRAWING NOTES: 1. ALL SIGNS, STREET MARKERS, AND PAVEMENT MARKINGS (EVERYTHING CALLED OUT ON THE SIGNING AND MARKING SHEET) MUST BE INSTALLED ON EACH STREET PRIOR TO THE ISSUANCE OF A CERTIFICATE OF OCCUPANCY AND/OR STREET ACCEPTANCE, AS DETERMINED BY THE CITY. 2. THE STREET NAME SIGN SHALL BE REFLECTIVE TO SHOW THE SAME SHAPE AND SIMILAR COLOR BOTH DAY AND NIGHT. THE LETTERS AND BACKGROUND SHALL BE OF CONTRASTING COLORS. 3. STREET NAME SIGNS SHALL HAVE WHITE LETTERS ON A GREEN BACKGROUND. 4. LETTERING ON THE STREET NAMES SHALL BE 4 -INCHES HIGH IN CAPITAL LETTERS. 5. SUFFIX LETTERING TO INDICATE THE TYPE OF STREET SUCH AS STREET AVENUE OR ROAD OR THE SECTION OF THE CITY (SUCH AS NW) SHALL BE LETTERING 2 -INCHES HIGH. ) 6. STREET NAME SIGNS WILL BE LOCATED ON TOP OF STOP SIGNS IN A STACKED POSITION. 7. STOP BARS SHALL BE 2 -FEET WIDE WHITE THERMOPLASTIC PER NCDOT SPECIFICATIONS 8. ALL SIGNS MUST CONFORM WITH THE MANUAL ON UNIFORM TRAFFIC CONTROL DEVICES (MUTCD)° 9. STREET SIGNS SHALL SHOW BLOCK NUMBERS.(BLOCK NUMBERS ARE SHOWN ON THE RECORDED PLAT. IF THEY ARE NOT SHOWN ON RECORDEDPLAT, CONTACT THE CITY'S ENGINEERING ASSESSMENTS DIVISION AT 560-4326). 8 9 10 11 12 13 14 15 16 ==i M O 0 N > N L J Q CO Z�Cy) Z r- U)OOco J_ O l- � �LUzM C H_ J N CO a c00D�ti (n Q L0 K 0 000*00 ■ *- TIMMONS GROUP CIVIL ENGINEERING I LANDSCAPE ARCHITECTURE I SURVEYING J G X H W Z W J W 0- G Z ap F� J W Q Q ILL F- o O J 10< z U m o I Q U) - z a z �o EQ W Q 0 w ti w 2i � a_ YN 0 = Q Jz U J F--- - o F- U) 2 Q LL (j) 2 Q w O ' O O� = U L c) � U) D \i\ \ \liiH lj/I i 7��\ vCA�/ 7i ,v�0 «Z 11 ,< No G :11i P6'(j\W, � T.J :, I p`✓\° • i 11 R SLA��y\,� IS G ////1llli0\\` 1 SD - 100% 08/25/17 B No REVISION/SUBMISSION DATE COPYRIGHT 2011 - RNL This document, and the ideas and design concepts incorperated herein, as an instrument of professional service, can not be used, in whole or in part for this or any other project, without the written authorization of RNL. PROJECT No: 39722.001 DATE: 08/25/2017 SCALE: AS SHOWN COVER Aoo-c000 Cn Z Z (5 � � C7 Z O,_j H � I Q J 0 w LL Q lU Y >- 2 = U Z I Q��� LL D U) W 0 J Z I W j U U Z 0 U) W p J Z U 2 , z w w Q, � W Q / 1 \..J U LU Q I � LU Z 0 CO W 0 J Z I G X H W Z W J W 0- G Z ap F� J W Q Q ILL F- o O J 10< z U m o I Q U) - z a z �o EQ W Q 0 w ti w 2i � a_ YN 0 = Q Jz U J F--- - o F- U) 2 Q LL (j) 2 Q w O ' O O� = U L c) � U) D \i\ \ \liiH lj/I i 7��\ vCA�/ 7i ,v�0 «Z 11 ,< No G :11i P6'(j\W, � T.J :, I p`✓\° • i 11 R SLA��y\,� IS G ////1llli0\\` 1 SD - 100% 08/25/17 B No REVISION/SUBMISSION DATE COPYRIGHT 2011 - RNL This document, and the ideas and design concepts incorperated herein, as an instrument of professional service, can not be used, in whole or in part for this or any other project, without the written authorization of RNL. PROJECT No: 39722.001 DATE: 08/25/2017 SCALE: AS SHOWN COVER Aoo-c000 1 12 13 14 15 16 17 18 19 110 \ VF N/F L / / \ ANIMAL PROTECTION N/F / ENERGY UNITED SOCIETY OF DURHAM \ \\ NOEF LLC PROPANE \ / PIN. -0842-09-27-4073 I \ PIN.- 0842-01-27-99 PIN: 0842-09-27-3940 / DB. 2807 PG. 476 DB. 6402 PG. 871 DB. 8094 PG. 284 N/F �c LANDUSE: INDUSTRIAL \�\ LANDUSE: VACANT � , • A USE: COMMERCIAL / \ COMMERICAL BIK PROPERTIES LLC ZONING: IL ZONING: IL / / J ',' ON/ IL / PIN: 0842-09-17-7843 ' DB. 5595 PG. 538 / 2116 CAMDEN AVE\�- 6.86 AC. \\ t LANDUSE: COMMERICAL/ CONVERTED RESIDENTIAL - -W W TA' N' ;A' K ZONING: IL `.FTYP Lsi--- SHEET- 62.0, 6.6,C4.0 i _ - N/F CEMETARY PIN: 0842-09-18-5025 I SPN Y. '4L)...'.'. DB. 159 PG. 35 --- 2002 CAMDEN AVE I 0. 18AC. LANDUSE: CEMETERY I . -%' MIST LAKE AFL II WE \ AA ZONING.' IL . L --:- �i� . II .. ---- Fe� 100 I \ SHEET- C2.2, C3.2, C4.2 \ II PROPOSED H �''II�II BUILDING so I AND AR A D x Z ' II I Z D SHEET- C2.1, 63.1, 64.1 m G � I I I I I I I I I I I I I I I I I I I I I x -------_--_--_ III L� M-�- loJ o ,t I I n —� lip_n _ ... -WETLAND AREA- I x F E IC C B 1 1 2 1 3 4 5 �-�.............. 50'NEIIUFF�R' \! \ W WLL W W .. .. . . . .�.�. I l ...... ..... I x X, �\\ I I I I I I I I I I I N/F \ TY OF DURHAM \ \ Pl :0842-09-05-2966 B. 1150 PG. 629 \ \ \ Ll NIDUSE: VACANT CO) MUNITYSERVICE \ I I x I I I I I I x N/F ZONING: IL I \ \ \ I I CITY OF DURHAM PIN: 0842-09-06-1562 DB. 267 PG. 540 . . LANDUSE: PUBLIC SERVICE \ \ I x ZONING: IL \ IV/F� \ CITY OF D I 0842-09-0 966 DB. 1150 PG. 9 �DUSE�.- INDUS 7 \ IAL x \ ZO NG: IL N \ n \ 1' 1 � J \ \ \ \ ' � I II I I! I I I 7 1.1 go 10 11 12 13 14 15 11 12 13 14 15 16 0 > N L m Q > Z Z ti U) (D O co J -0 �LuZ o U) Q Lr) Iff 21 TIMMONS GROUP CIVIL ENGINEERING I LANDSCAPE ARCHITECTURE f SURVEYING J G H Z W W a Z F LU J Q ILL O O J Z , m �O LULLZ ELLjQ w X J W LU Q W Q� 0 � J J W J= I C/) 0�' Q o () _5o 2i ILL O Cid 2 0 ti Lu C:) U o C0 cUn U 0 Z C� O���i� GINS C G ''rrriiri����\ 1 SD - 100% 08/25/17 B No REVISION/SUBMISSION DATE COPYRIGHT 2011 - RNL. This document, and the ideas and design concepts incorporated herein, as an instrument of professional service, can not be used, in whole or in part for this or any other project, without the written authorization of RNL. PROJECT No: 39722.001 DATE: 08/25/2017 SCALE: AS SHOWN OVERALL PLAN 00-0001 CO Z Z (D Y U) } W 0 Z Z = J CD CD W W I p LJ p J W Q Z � J 2 W Q J H w E a Q E Q O� Z Q J 2 a 5 2 U U W DU = Q? U J W WO � M 2 W G H Z W W a Z F LU J Q ILL O O J Z , m �O LULLZ ELLjQ w X J W LU Q W Q� 0 � J J W J= I C/) 0�' Q o () _5o 2i ILL O Cid 2 0 ti Lu C:) U o C0 cUn U 0 Z C� O���i� GINS C G ''rrriiri����\ 1 SD - 100% 08/25/17 B No REVISION/SUBMISSION DATE COPYRIGHT 2011 - RNL. This document, and the ideas and design concepts incorporated herein, as an instrument of professional service, can not be used, in whole or in part for this or any other project, without the written authorization of RNL. PROJECT No: 39722.001 DATE: 08/25/2017 SCALE: AS SHOWN OVERALL PLAN 00-0001 L I f:■1 G I F E I f71 C I B I m z 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 "--- ----------------- FLAGGED --------------- FLAGGED STREAM T/ / /B .0 94.0/)/ A/ 111 ���Q) /T \ \\0 8.5 / POND / /W / \� \ RETAINING WALL i 296.0 \� \ 30,/.6 1 I 3 4 T ( F1) YlJ HAM ��� PB. #3 PG. 14 \ \ v 41 w v/ v \1/% w �\ 0.03 AC. / \ `� \ \ \ \ WETLAND AREAS / N LSE.• INDUSTRIAL ��A� (TYPICAL) ZONING: IL �\ / _77— A/ � \ \\ i I it MIST LAKE \\ \ \ 04' SCM ACCESS AND — — \ MAINTENANCE - 1 EASEMENT — 1 1 �- RIP RAP / --\ i / \'/ ' \ \ \ ENERGY - - /'/ DISSIPATOR \_�,; -\\ / //// / C13 zzz SPLITTER BOX Qb L —LEVEL SPRE ADER_ W/FIUT RIP 315 I bo0' — — — — — — S O M PI E TY — — — \ \ CAT CI II I j R25 _ — — — _ —UNDERGROUND UNDERG 379 ` \ \ BASIN (TYP}\\\\ \ \ < < < I \ / \ FILTER I v Hit - A O 1-7 ;3 II I II I e- ' ' \ J '� _ �_ - - — — — — — — _ \ \ \ \ \ \ \ I cY, // r - -320- \ \ \ \ \ I _ I I I I I � I � I I ✓/ I I I I I I I I I � -------------- � \ \\ �\ �\ l ` STOR I / _ — _ _ — FLOW — _ _ I1PE (Ty P C v v I—_——SCMACCESS-AND SPLITTE_RBOX_--- MAINTENANCE _-- — -------o \\ \ \ \ \\ _ EASEMENT — — — N� — _ — 81 �" v v\v EPARTMENT OF WATER- \ \ , MANAGEMENT FACILITY F-F�21.00 1 1 r \ \\ \ �ETAINING WALL / L11 > \ I - � I � / x TAN I I I I // I DROT (TYP) v I I 316.0RAN 5 L 7 I I 10 12 13 14 SCALE 1"=40' NOR 0 40' 80' 15 16 16 L K H G J O O > N J CO � Z ZO ti U) O O co J_ O f— �WCID zM O H_ J N U) L0 TIMMONS GROUP CIVIL ENGINEERING I LANDSCAPE ARCHITECTURE I SURVEYING CO Z Z U Y U) } W p Z Z = J QZ w U — W I p W p U) 1 W J W Q Q J O _j LL Z Q J I Z 0- H z U Q LL 2_ Q p w LL W z z U 0 �U v� O m Q� z p p= w a� M U 2 U Z)U U � (n Q z a 2 W I— Z W W Q z F � J W Q I O J z U m o LULL Z a Z Ep w< J w W Q W a_ Q2 o J J W J= 0 Q ILL � G O W W O O N = U o C) U)U 0 Z D \\1\,�IIIIItjjj�' `�.- IA CA GIN C 1 SD - 100% 08/25/17 B No REVISION/SUBMISSION DATE COPYRIGHT 2011 - RNL. This document, and the ideas and design concepts incorporated herein, as an instrument of professional service, can not be used, in whole or in part for this or any other Project, without the written authorization of RNL. PROJECT No: 39722.001 DATE: 08/25/2017 SCALE: AS SHOWN GRADING PLAN A00 -C400 XTDROP - I 10 12 13 14 SCALE 1"=40' NOR 0 40' 80' 15 16 16 L K H G J O O > N J CO � Z ZO ti U) O O co J_ O f— �WCID zM O H_ J N U) L0 TIMMONS GROUP CIVIL ENGINEERING I LANDSCAPE ARCHITECTURE I SURVEYING CO Z Z U Y U) } W p Z Z = J QZ w U — W I p W p U) 1 W J W Q Q J O _j LL Z Q J I Z 0- H z U Q LL 2_ Q p w LL W z z U 0 �U v� O m Q� z p p= w a� M U 2 U Z)U U � (n Q z a 2 W I— Z W W Q z F � J W Q I O J z U m o LULL Z a Z Ep w< J w W Q W a_ Q2 o J J W J= 0 Q ILL � G O W W O O N = U o C) U)U 0 Z D \\1\,�IIIIItjjj�' `�.- IA CA GIN C 1 SD - 100% 08/25/17 B No REVISION/SUBMISSION DATE COPYRIGHT 2011 - RNL. This document, and the ideas and design concepts incorporated herein, as an instrument of professional service, can not be used, in whole or in part for this or any other Project, without the written authorization of RNL. PROJECT No: 39722.001 DATE: 08/25/2017 SCALE: AS SHOWN GRADING PLAN A00 -C400 L I f71 G I F I E I �I C I 2 3 5 7 10 12 13 14 BAN _ \ \ \� ------ ' / 299.25 --- -- �t`�� - - _)( XNiC \� 317 --- �--- -- --- J T/W / 1\\ 1101- \`\JLE - - -- t90 \\� \ \ \ \\ \ \ \ _ SHEET-C4.0�� v�� �\`�� o oM — \ ` MATCHLINE MM`MAINTENANCEBUILDING293.E T/W \ \\\ _ IF F--320.-00oo - 303.p J ------ 2-96.0 L_ RETAINING — 7W �T \ ` \ 3 6 ` / '- -_ 293. � � \ - -----/ ' J, A/ J/ FC T RMW - STORMWATER— / v v v \ I T X - A)NQTIO"OX - - _ � \ � \ \ \ - U CTION BO / 292.5 `'292. \ \ \ \ \ \ / W/MANHHOLE — ST - - - - w J v V \ v \ V A M V v - \ - - — - _ _ PIP TYP i \l/ J/ A/ v J/ J/ � \V v Jr J/ V A T v A \ \ V \ Iri (� \ \ \ \ \ A — - ----- T/W \ \ FLOW ---__ - _ � � � � J, � J, � J, � J, � J, J/ v, J, v X299.0 � v v v \� \ v � � - - - - - - - _ x � � � � ITTER�OX - � \ \ \ _ _ \ 5 \ \\ 3 --- _— -- - 293.Q 95.0-------- VJ J J + J J - v ' J J J J TIW UND w J, J, J, J \ 29 .0 3�I \ SA G D D D -F �TE - — - - - - \ M� \ D - DROP y J/ J, w J A/ J V \13/W 92 7� v \ V A A v \ 315.0 eco t� - _ _ - - - - - _ INLET TYP \ \ M \ _ \ — — _ — -- �\ \ BANV A/ W � J/ J/ J/ J/ J/ w J/ J/ J/ w J/ Jr w J/ Jr Ji J/ Jr J/ \ A \ \ V A A �\ 2 \ 5'-320-j_ — \ q 0 CAYCH J v J v J v J J J J J �� w v\ S 29RI�WAT _0 M- _ y c� y y y y - y \ �� I I BASI/Id (TY v J v v v� J �� v v � J A297.Q _ _ v v v JGWOId B J TSA Cv J/ Jr w J/ J/ v/ Jr Jr V J Jr J/ J/ J/ J/ _ -W/ A H — � RP A _ \ j ENERQg.s �� � J� � w / v'\ � � LA�iG�Yf.ft � V �\� — v J w \ v J J J J- J v i I _ kJ O N / V �/ ' /n, X \ /�\ /� - - \ N / I COVERED J r VEHICLE w v/ J/ J/ J/ J/ A/ w v/ J/ J/ J/ J/ J/ J/ J/ V u J, V J Jr J Ji A10� F/J-6 BL/Fl J/ v/ w A / \ < / % - \ � J v J J v A/ w J A/ J, v ( ( ( J ��� f NIIdG ASL _ ' '� �// i J Fr 320.00 50' NEUSE BUF v J J, A/ J v v + J, v Jr \\��"� - - - ' - --- w � + � v/ Jr J/ J/ � Jr J/ J/ w J/ J/ � J/ � � J\ \ V A �\\ \ � / w I I+ 1 �� J/ + J/ A/ \ \ J i I �op�v J J A A V / 30�. "� A y S NQ �I S ' / / F�LI TER -13 iJ SCM ACCESS AND \\ � J, MAINTENANCE w EASEMENT �' ' ' \ / / X zQ ER I �II / /' SCM ACCESS AND ��S J \ UNCTION pX � � � l MAINTENANCE - v H LE � v �v NORM / EASEMENT FAQ \ I / / 01PE (TYP) /319 ' /ST/REAM §TA. FUTURE 100 \ \ \ r� 1 I I \ + �' �' �' � � SPREADER $FE = 29,6.9 v, J/ \t/ W/FILTER STRIP I I I I I / G� \\ill I \ \ \ \ 30x0_ �`SF J J vv v\ v_ x \ FF J \ J J J 41 \\ \ 3(10\ \ CATCH \ I I / 3 \ \ \ \ / / 1 ASIN Y') 8 v J\J w DROP / v J / J �� y �� \ V A I I I / INLET (TYP) / / Mt M 401 RETAINING WALL y I 'COLLECT v v v \v \ SYStEM 302.0 B/W 302.5 v v v v v vv 317 I /W y v A \ 317 296.0 \ \ \ \ \ \ \ \ \ \ \ \ \ , \ 295.0 v v� 1� 0 S� v o v �\ \NIF O Cn \ M M CITY OF DURHAM \ I I I \ \ \ \ \ \ I PIN: 0842-09-05-2966 � \ � I � DB. 1950 PG. 29 LANDUSE.VACANT COMMU ITYSERVICE \ \ ZONING: IL '195 0 \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ x � vv 1ib07y STORM \ \ 31g` \ \ TCH RETAI NG AL I I 1 1 x BASIN (171 ) \\� \ \ \ \ \ \ \ \ \ DR P \ \ \ \ v I I v FLI P%AP1Av v v IN LET 1 14 \ y �jA X10 ��E�\\NY \ 5 V \ I I v v I O o f DI SIP v\ v v Id \ \\ \ �\\T \ 310 \ \ \�\ \ 305 T \\\ \ \\ \\\\ \ \\ \ \ \ \ \ 29 vVv v`vVvv vv \v v v\ v v v 1 3 4 5 L 7 E: 10 12 13 14 15 SCALE 1"=40' 0 40' 80' 15 16 L K H G J O O Ci N > N m Q z zrn ti U)O O co J_ O W Z M O F- J N cC)ti cn Q LO TIMMONS GROUP CIVIL ENGINEERING LANDSCAPE ARCHITECTURE SURVEYING CQ Z Z_ (D Y U) } W p Z Z _ 0 o LL -Q z w O - w I p W p U) J W J W Q Q J J A Z Q I z J z v Q Q Z w W z Z U �U v O m Qor_ z p p= w a= U= U Z) U U LU � (n Q z a w Z W W O 0 Q Z F � I � W J U) LL O J G LULU U m VJ Q LL U_ Ea W p W< X J JJ W W LL �N 2 O (f � O � ��Uo D \1�\\11IIItj11/'/ JVA CA O� � 'alf�.i�.�,.•��®dam C llfill411\ 1 SD -100% 08/25/17 B No REVISION/SUBMISSION DATE COPYRIGHT 2011 - RNL. This document, and the ideas and design concepts incorporated herein, as an instrument of professional service, can not be used, in whole or in part for this or any other project, without the written authorization of RNL. PROJECT No: 39722.001 DATE: 08/25/2017 SCALE: AS SHOWN GRADING PLAN 00-C401 O 0 I U) Y 0 U_ _ ~ ti W O �N 2 U (-0 �0z \1�\\11IIItj11/'/ JVA CA O� � 'alf�.i�.�,.•��®dam C llfill411\ 1 SD -100% 08/25/17 B No REVISION/SUBMISSION DATE COPYRIGHT 2011 - RNL. This document, and the ideas and design concepts incorporated herein, as an instrument of professional service, can not be used, in whole or in part for this or any other project, without the written authorization of RNL. PROJECT No: 39722.001 DATE: 08/25/2017 SCALE: AS SHOWN GRADING PLAN 00-C401 L K J H G F E IC C B 1 1 2 1 3 1 4 1 5 1 6 1 7 1 8 1 9 1 10 1 11 1 12 1 13 1 14 1 15 I F T/W i 296.0 �w Z vi I I I j a' I II II to It RETAINING WALL 15.01 I I A/ A/v RIP RAP S RM I v / I /W \ I < � w A/ \ ENERGY, DISSIPI PI E (T P) I / I X311. ° v I I v ATOR v I / o f v v v v M h I I I �TCH o II I I v i BASIN (T I \ o I / I 1 CD + I M T 1 I II Aw I 1 316.0 I I / B IN / \ I , 3111.5 N WETLAND AREA I I I I ("TYPICAL) I R6�0' 1 STOR j/ `v APIPE 1 , , ' I A/ � /114/ / C\1 TICY\ / ) A I _ _ P. T / _ R50 / CA�`C-I T / / — - - - \T'y 1 I I I \j// m m I B - _ ��ASI �P) 30 .0 iz — _ — - MATCHLINE II m / / / B/W , - - - � SHEET C4.1 I v / z , //299.25 i t I II ^ \ \ (' / TNV i o�� - 315— I I� w w I I � w � � v v v I < � LI � � � ��F — I� I / p� / - - --- N- \ �, v v v II v � M M- I IM 300 A/ II I A + I/ T/W 293.E - - — T/W - - i I Z 303.0 296.0 I �� �� / _RETAINING 293. � 299 \2 1 w �� ✓- - - / 293.0 - JI o T / - 292. w A/ A / m � w A/ � � / w w A/ A/ � � � I w \ � A/ � � \1 A/ A \V � 4/ - - w w �- /' II � y A/\t/A/ 4/ A/I A / T v / 1 A/ A/ I \ t 1 I A I VJi V Vl \ I 1 Ji Ji Ji A \V \V � \ V I - - - I I I I t � `SCM ACCESS AND I I I R30' MAINTENANCE �� 700, _ \ EASEMENT R165' F�SF \ �v R30' X/ SCALE 1"=40' � � � \ 0 40' 80' I 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 16 L K J J 07 O � N > N J CO � z -M ti U) o O c0 J_ CD � CO (D (=) LU 0 O J N CD Q0 � co see* TIMMONS GROUP CIVIL ENGINEERING I LANDSCAPE ARCHITECTURE f SURVEYING G I - Z W W Q Z F LU J H >- Q Q LL ~ o O J Z U m o LULL Z Z 0 ELLjQ w X J w W Q LU 0- Q O T -J J W J= � ��� Q V) D Q C O W2DI` W o C:) CV 2 U o �",U (Un U 1 0 Z D \\I�Illllllfjjj�'/, CA O 0 � e. C;IN�� �\ �•h' BLA��°'� ��� C 1 SD - 100% 08/25/17 B No REVISION/SUBMISSION DATE COPYRIGHT 2011 RNL. This document, and the ideas and design concepts incorporated herein, as an instrument of profess onal service, can not be used, in whole or in part for this or any other project, without the written authonzation of RNL. PROJECT No: 39722.001 DATE: 08/25/2017 SCALE: AS SHOWN GRADING PLAN 00-C402 C/) Z Z_ U Y U) } W 0 Z Z = U 0 O -1 LL J z W W U' Ur w t o o C/) J W a Q J W J J Z Q I Z O � � H W Q I U Q I Q w w z _U U U Q 0_ Z _O m F-- H U W U = U � c~r� G I - Z W W Q Z F LU J H >- Q Q LL ~ o O J Z U m o LULL Z Z 0 ELLjQ w X J w W Q LU 0- Q O T -J J W J= � ��� Q V) D Q C O W2DI` W o C:) CV 2 U o �",U (Un U 1 0 Z D \\I�Illllllfjjj�'/, CA O 0 � e. C;IN�� �\ �•h' BLA��°'� ��� C 1 SD - 100% 08/25/17 B No REVISION/SUBMISSION DATE COPYRIGHT 2011 RNL. This document, and the ideas and design concepts incorporated herein, as an instrument of profess onal service, can not be used, in whole or in part for this or any other project, without the written authonzation of RNL. PROJECT No: 39722.001 DATE: 08/25/2017 SCALE: AS SHOWN GRADING PLAN 00-C402 APPENDIX D ORIGINAL LAYOUT =�_—rte � ' ,` 0 PERSONAL VEHICLE - 402 s' h �' '' ti ®� + D PEM PERSONAL VEHICLE - 131 0 WSM PERSONAL VEHICLE - 251 - • OTHER PERSONAL VEHICLE - 20 VISITOR VEHICLE 60 17 .- IV=31258' 15"RL. J ' / SMALL AGENCY VEHICLE - 43 `s - �' — PEM SMALL (10X15) AGENCY VEHICLE - 28 Q I ° WSM SMALL (10X15) AGENCY VEHICLE - 15 . � INV=311.99. 15"RCP, . MEDIUM AGENCY VEHICLE - 202 PEM 1 OX20) AGENCY ` MEDIUM ( VEHICLE 0 WSM MEDUM(10X20) AGENCY VEHCLE - 11 3 ik . //// i/ ,�• I, OTHER MEDIUM (10X20) AGENCY VEHICLE - 35 / "I , LARGE AGENCY VEHICLE - 89 •� �- I _ �_�� f�. — PEM LARGE (12X30) AGENCY VEHICLE - 13 �' I � I •, •. p WSM LARGE (12X30) AGENCY VEHICLE - 76 EXTRA LARGE AGENCY VEHICLE - 49 PEM EXTRA LARGE (12X40) AGENCY VEHICLE - 33 WSM EXTRA LARGE (12X40) AGENCY VEHICLE 16qwr� LE qtr';; TIMMONS GROUP CIVIL ENGINEERING LANDSCAPE ARCHITECTURE I SURVEYING 14 r '� i L ,, . •rte' �a � .fit '' F - i 1 DURHAM 4, 'Aii AW .. .E r �r''f• _�, x _ � / � ae'-.. ,�r {I.,` y� jf:r■�F �,�fP:C: ,rfr/"y.;r-J'1''. r1i ..^; iY r .✓�`.�Y• ,�_ - / � ,�• I7 .J f:'- rl�J�--.'-�'�Jr �=J �;I''•±•! '+� F .1 ^;. VA ;i ;. Fr 1 - / _ / t '• ;� :'�T"•,�! I liC .' jd _.' i Ji- •fir 1 I / \ / ::I ,.�J� "llw. .j'.: �. r, - Y[ "•r'' .Y. -:i -. .x, +. / �y'�. ly �f' �� �• � ''I._ • . \— � r � ./ /If S7''\.(If `.�.. !,r �' :�.J•�:F•.F.=`-.C, ra• .�+. Yy O 1!. .r :TJ . 'IVA' i ,%-�� • L + � r•�a � w� 'r ' i ` ^�` �v •( - ^.I� ,�' "a r `-. ,,`,,t .:f f `�;IF?1� 1_ :� . r i n ,;t i - "i.' . 869 CITY OF MEDICINE -..k. :, ,+ ,� ..d !• - _ - L ol0 0 0 0 0 0 o I I I - U /` •_� •' -?' rv.'- r/1. 'rf' f I'f II I , ,� • -.. .- . � • � y � - i� Tom] - - - �� , / o lift di l;�f•�A rte. ` i,�•�...� - - ,/ � � \ o\ �� \ 2 UJ } t 1 r:`.,�;•~`� •�je , � \\ C�'/ y. to ' o . °J N 0 / , •�, p N CD >- jrjf o 0 Y / 7 0 o o a, �1 ` \� MW o a \ �.i�•• \ 0 _° 0 0 `0 0 0 ilib 0 0 0/ \ _ *1 .1 -_ , 1, {� LU . W ' _ o \ 0 0 o °M I OIOltOTI \ ' I LU I Iap o_!11,0000LC O 0 p \ t00{ o-o,go° O,p O p ° O OIJ O00O V -- O Vol A�O43 a 0 0 0\ O o 0 0 0 0 0 010 p O 0 n 0 001 00 P` •_. _�4' ■ .� o - _ 0 0 0 0 0 0 0 0 0 0 0 °� \\-� �'--\1 - o° o _ • - 0 0 0400, o c 0 oro -� \ �Q P 01 0\0\0 0 0 � / M o 0 0 0.0-0 0 ,: o o t-- -\ -- �. /� ; • °_ �I c c, I o �o 0 0 0 0 0 0 0 0 -=1� r _ -- i alk'n \-C y J - F�.- -. G CI(`lo l° ciolo 0 olo 1p 1p lV .plo OI I ) c ="So c4•o q0 L I`I L) o L cJ 9 0 0 0� 4� 000 a � _ 40 /+co r , / I ♦ } UJ fi r r f CD /J �f // ///// // / �Y x. U_ NO -10k / ./ / / 7 rn Iii4. d is L V UJ 40 Ilk vil LU LIJ 0) f• M. .r ' /'� UJ � sa •� I t rr'4 �'• r.. t . . Y CD PIP CID Mn ,.-, is •. JJf � 11 / i / 'fir •s •��'': J. �' ''f!' •• tr... ` - J`• - 4 - _ _ N .- _ e - »i%, •,; � Ndj 7 '/, / � ,� COPYRIGHT 2015 -RNL. This document, and the ideas and design concepts incorperated herein, as an _Y'- .r• i} _ instrument of professional service, can not be used, in whole or in part for this or any other project, without the '4 1L% 'wdtten authorization of RNL. co `!�I.: 'r { PROJECT No: PROJECT NUMBER �A L_ APPENDIX E COMPENSATORY MITIGATION DOCUMENTS WILDLANDS HOLDINGS Neuse 01 Riparian Buffer Credits Statement of Availability July 27, 2017 Mr. Todd Preuninger Timmons Group 1001 Boulders parkway, Suite 300 Richmond, VA 23225 RE: Availability of Riparian Buffer Credits for the Mist Lake Facility Expansion project Bank Name: North Fork Little River Nutrient Offset & Buffer Bank Bank Sponsor: Wildlands Holdings, II, LLC DWR Project Number: 2016-0130 Permittee: City of Durham — Department of Water Management Riparian Buffer Credits Needed: 57,027 sq. ft. Riparian Buffer Credits Available: 181,645 sq. ft. Neuse 03020201 River Basin (Upper Falls Watershed) Dear Todd: Wildlands Holdings III, LLC currently has sufficient riparian Buffer credits from the North Fork Little River Nutrient Offset & Buffer Bank to satisfy the riparian buffer mitigation requirements related to the above-mentioned project. The project is located within the service area (HUC 03020201 Upper Falls Watershed) of the Bank. This letter is simply a statement of availability of credits as of the date written. It is not a guarantee of availability as credits will be sold on a first come, first serve basis. An invoice for this transaction will be sent upon your request and we will formally reserve both the credits and price quoted for a period of 30 days from the invoice. Final transfer of the credits will be made upon receipt of a copy of the 401 Water Quality Certification Authorization Certificate from the NC Department of Environmental Quality approving the Riparian Buffer mitigation purchase from the Bank and upon receipt of your payment to Wildlands Holding III, LLC. We will then issue a credit transfer certificate verifying your credit purchase to the North Carolina Division of Water Resources and to you for your records We appreciate the opportunity to assist you with your mitigation requirements. Please contact me at 704-719-2100 or rbugg@wildlandseng.com if you have any questions or need any additional information. Sincerely, Robert W. Bugg NC & SC Realtor®, Broker, ALC Director: Mitigation Development & Credit Sales Wildlands Engineering, Inc. rbugg@wildlandseng.com o) 704-332-7754 ex. 105 m) 704-719-2100 Wildlands Holding III, LLC • Wildlands Engineering, Inc • 312 West Millbrook Road, Suite 225, Raleigh, NC 27609 APPENDIX F ORIGINAL LAYOUT PERSONAL VEHICLE - 402 s' h �' '' ti ®� + D PEM PERSONAL VEHICLE - 131 0 WSM PERSONAL VEHICLE - 251 - • OTHER PERSONAL VEHICLE - 20 VISITOR VEHICLE 60 17 .- IV=31258' 15"RL. J ' / SMALL AGENCY VEHICLE - 43 `s - �' - PEM SMALL (10X15) AGENCY VEHICLE - 28 Q I ° WSM SMALL (10X15) AGENCY VEHICLE - 15 . � INV=311.99. 15"RCP, . MEDIUM AGENCY VEHICLE - 202 PEM MEDIUM (10X20) AGENCY VEHICLE - 54 `,t �� / �, /� 0 WSM MEDIUM (10X20) AGENCY VEHICLE - 113 J k'{`' e / I � y� OTHER MEDIUM (10X20) AGENCY VEHICLE - 35 LARGE AGENCY VEHICLE - 89 •� �- I _ �_�� f�. — PEM LARGE (12X30) AGENCY VEHICLE - 13 ; �' I � I •, •. p WSM LARGE (12X30) AGENCY VEHICLE - 76 EXTRA LARGE AGENCY VEHICLE - 49 PEM EXTRA LARGE (12X40) AGENCY VEHICLE - 33 WSM EXTRA LARGE (12X40) AGENCY VEHICLE 16� 5' if I Off TIMMONS GROUP CIVIL ENGINEERING LANDSCAPE ARCHITECTURE I SURVEYING r '� i L ,, . •rte' �a � .fit '' F - i 1 DURHAM 7 i 1 a: ,3i ✓� t *,X.. NJ/ lir,:! ."a , a::• ea r 4 eo ! / ! .. .E r �r''f• _�, x _ � / � ae'-.. ,�r {I.,` y� ! jf:r■�F ,�fP:C: ,rfr/"y.;r-J'1''. r1i ^; iY r .✓ ` . Y • _ - / I7 . J f: ' - rlJ --.'- ' J r = J ;I ''• ±•! gyp. '• ;� :'�T '"•,�! I li�C .'� jd� � f'.,I� _ �.' .� i Ji- �� • r 1 I / \ / �. ::I ,.� �J� "llw. .j' �.: �. r, - Y[ "•r''�. .Y �.-:i -. .x, +. /� �y'�. ly . �f' �� �• � ''I._ • . \— � r � ./ /If S7''\.(If `.�.. !,r �' :�.J•�:F•.F.=`-.C, ra• .�+. Yy O 1!. .r :TJ . c o 0 0 0 o I 1 ' i ,%-�� • L + r•�a � w� 'r ' i ` ^�` �v •( - ^.I� ,�' "a r hl�ryr . _ I 11 869 I I ISI I i�3i;., r�, CITY OF MEDICINE 74 -.. :, ,+ , ..d !• - _ - L ol0 0 0 0 0 0 o I I I - U /` •_� •' -?'rv.'-'!f' f f ,. ,� • -.. .- . � • � y � - i� Tom] - - - �� , / o � ''yam l;�f•�'•�.i rte. ` i,�•�...� - - ,/ � � \ o\ �� \ 2 Lld F=1 10 10 ele 1-1 4A } t 1 r:`.,�;•~`� •�je , � \\ C�'/ y '0 o 'A' 02�- 0 C, f o 0 - ° O '\ G Y / 7 0 ° o a, �1 ` \� a \ MW g o \ `0 0 Nib 0 0 0/ \ _ o W 0 0 • 7 .0, ,0 C0 O0 0 q,\0, \ + ' 0- 0 0 0{ o ° 0QoT O 1 \�00 0 0 OAOt 0, O pO 01"o I P` •_. _�4' ■ .� — _ 0 0 0 0 0 0 0 0 0 0 0 °� \\-� �'--\1 — o° o _ • —TO 0 0 o c 0 0ro� —� \ �Q P ��01 0\0\0 �. /� ; • °_ I [O[ c, I 0 —=1�\ \ i \ -C J - F�.- -. r, clr to to ciolo 0 0lolo 1p to cillo 01 I c ='60 c-C'o 0 "eo 0�qO r.f • ri L I`I LU 00, a _ r r ,IF 0/00 / I .0 f C:) /J �f // ///// /// / / �Y s. LL V T. LU LU vi 17 OliiM LLI UJ � sa •� - � I (� fir, - - n Q CD to Cq CID t rr'4 �'• r.. t . . Y ,.-, is •. JJf � 11 / i / 'fir •s � •�'': J. � ' ''f!' •• tr... � ` � - J `�• - r• 4 - _ _ N COPYRIGHT 2015 - RNL. This document, and the ideas and design concepts incorperated herein, as an _Y'- .r• i} _ instrument of professional service, can not be used, in whole or in part for this or any other project, without the ' written authorization of RNL. M/ `!�I.: 'r { PROJECT No: PROJECT NUMBER co �A L_ APPENDIX G COMPENSATORY MITIGATION AVAILABILITY LETTER WILDLANDS HOLDINGS Neuse 01 Riparian Buffer Credits Statement of Availability July 27, 2017 Mr. Todd Preuninger Timmons Group 1001 Boulders parkway, Suite 300 Richmond, VA 23225 RE: Availability of Riparian Buffer Credits for the Mist Lake Facility Expansion project Bank Name: North Fork Little River Nutrient Offset & Buffer Bank Bank Sponsor: Wildlands Holdings, II, LLC DWR Project Number: 2016-0130 Permittee: City of Durham — Department of Water Management Riparian Buffer Credits Needed: 57,027 sq. ft. Riparian Buffer Credits Available: 181,645 sq. ft. Neuse 03020201 River Basin (Upper Falls Watershed) Dear Todd: Wildlands Holdings III, LLC currently has sufficient riparian Buffer credits from the North Fork Little River Nutrient Offset & Buffer Bank to satisfy the riparian buffer mitigation requirements related to the above-mentioned project. The project is located within the service area (HUC 03020201 Upper Falls Watershed) of the Bank. This letter is simply a statement of availability of credits as of the date written. It is not a guarantee of availability as credits will be sold on a first come, first serve basis. An invoice for this transaction will be sent upon your request and we will formally reserve both the credits and price quoted for a period of 30 days from the invoice. Final transfer of the credits will be made upon receipt of a copy of the 401 Water Quality Certification Authorization Certificate from the NC Department of Environmental Quality approving the Riparian Buffer mitigation purchase from the Bank and upon receipt of your payment to Wildlands Holding III, LLC. We will then issue a credit transfer certificate verifying your credit purchase to the North Carolina Division of Water Resources and to you for your records We appreciate the opportunity to assist you with your mitigation requirements. Please contact me at 704-719-2100 or rbugg@wildlandseng.com if you have any questions or need any additional information. Sincerely, .r Robert W. Bugg NC & SC Realtor®, Broker, ALC Director: Mitigation Development & Credit Sales Wildlands Engineering, Inc. rbugg@wildlandseng.com o) 704-332-7754 ex. 105 m) 704-719-2100 Wildlands Holding III, LLC • Wildlands Engineering, Inc • 312 West Millbrook Road, Suite 225, Raleigh, NC 27609