HomeMy WebLinkAbout20191252 Ver 2_Revised B 4635 dated December 17_ 2019_20200214Carpenter, Kristi
From: Rivenbark, Chris
Sent: Friday, February 14, 2020 6:37 AM
To: Shaver, Brad E CIV USARMY CESAW (USA); Steenhuis, Joanne
Cc: Herndon, T. Mason; Dilday, Jason L
Subject: RE: [External] Revised B 4635 dated December 17, 2019
Thank you Brad
Chris Rivenbark
NCDOT- Environmental Analysis Unit
(919) 707-6152
-----Original Message -----
From: Shaver, Brad E CIV USARMY CESAW (USA) <Brad.E.Shaver@usace.army.mil>
Sent: Thursday, February 13, 2020 2:53 PM
To: Rivenbark, Chris <crivenbark@ncdot.gov>; Steenhuis, Joanne <joanne.steenhuis@ncdenr.gov>
Cc: Herndon, T. Mason <tmherndon@ncdot.gov>; Dilday, Jason L <jldilday@ncdot.gov>
Subject: RE: [External] Revised B 4635 dated December 17, 2019
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an
attachment to report.spam@nc.gov<mailto:report.spam@nc.gov>
Chris,
I have been back through the record and I can confirm that the attached utility drawings were part of the verification
decision.
I have filed the remaining adjustments in the record.
If you have any further questions please don't hesitate to give me a call,
Brad
-----Original Message -----
From: Rivenbark, Chris [mailto:crivenbark@ncdot.gov]
Sent: Wednesday, February 12, 2020 1:20 PM
To: Shaver, Brad E CIV USARMY CESAW (USA) <Brad.E.Shaver@usace.army.mil>; Steenhuis, Joanne
<joanne.steenhuis@ncdenr.gov>
Cc: Herndon, T. Mason <tmherndon@ncdot.gov>; Dilday, Jason L <jldilday@ncdot.gov>
Subject: [Non-DoD Source] RE: [External] Revised B 4635 dated December 17, 2019
Brad and Joanne,
I was looking at this one again and had a couple of concerns.
At some point during the revised applications, we (1) did not include a note about temp fill for erosion control in hand
clearing areas on the impact summary sheet that was on our original application. Due to hand clearing being reduced,
the amount of temp fill in hand clearing areas went down but a portion (0.03ac) is still needed. Also, four impact
amounts were not lined up with the correct impact (impervious dikes). Both of these have been corrected and are
shown on the attached impact summary sheet (w/ and w/o notes showing the changes).
Also when Brad issued the 404 below, the utility drawings (attached) were not included in the email though it looks like
impacts were included with the verification. If you don't mind please check to make sure that we're authorized.
Chris Rivenbark
NCDOT- Environmental Analysis Unit
(919) 707-6152
-----Original Message -----
From: Shaver, Brad E CIV USARMY CESAW (USA) <Brad.E.Shaver@usace.army.mil>
Sent: Tuesday, December 17, 2019 10:05 AM
To: Harris, Philip S <pharris@ncdot.gov>; Dilday, Jason L <jldilday@ncdot.gov>
Cc: Rivenbark, Chris <crivenbark@ncdot.gov>; Steenhuis, Joanne <joanne.steenhuis@ncdenr.gov>; Tugwell, Todd J CIV
USARMY CESAW (US) <Todd.J.Tugwell@usace.army.mil>; Harmon, Beth <beth.harmon@ncdenr.gov>; Herndon, T.
Mason <tmherndon@ncdot.gov>
Subject: [External] Revised B 4635 dated December 17, 2019
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an
attachment to report.Spam@nc.gov<maiIto: report.spam@nc.gov>
Attached is the revised tear sheet, Mr T form, RGP full version, and revised work plans.
If you have any questions please let me know,
Brad
Email correspondence to and from this sender is subject to the N.C. Public Records Law and may be disclosed to third
parties.