SW6190903_Plan (SCM Detail)_20200102
CONSTRUCTION SEQUENCE FOR WET DETENTION POND: 1. INSTALL EROSION CONTROLS. 2. CONSTRUCT DAM BASE AND AREAS BELOW THE NORMAL POOL. CONSTRUCTION TO BE PERFORMED UNDER THE INSPECTION OF THE GEOTECHNICAL ENGINEER. SEED UPON COMPLETION. EMBANKMENT WIDTH 3. INSTALL OUTLET PIPE, RIP -RAP APRON AND STONE FILTER RING. 6" TOPSOIL FOR ALL AREAS ABOVE THE 4. CONSTRUCT OUTLET STRUCTURE. NORMAL POND ELEVATION 5. REMOVE ACCUMULATED SEDIMENT AND SEED UPON COMPLETION. 15" HOPE WITH WATER TIGHT SEAL PIPE TO BE BEDDED PER DIRECTION OF GEOTECHNICAL ENGINEER 3 1 6" CLAY SOIL LINER ON INSIDE FACE OF EMBANKMENT CUTOFF TRENCH APPROXIMATE SIZE EXCAVATE AND BACKFILL WITH COMPACTED 4' MIN STAGE/STORAGE TABLE \OFTOP OF NOT (EM VABLEUCTURE TRASH R CK)HOWM FOR CLARITY RISER STRUCTURE STAGE ELEVATION CONTOUR INCREMENTAL TOTAL wflQ 4" PVC SCREW CAP (FT) (FT) AREA (SF) STORAGE (CF) STORAGE (CF) /3JS FOR CLEANING ACCESS 0.0 132.5 3195 0 0 /NTfpM f0/AT \� 0.5 133.0 3990 1796 1796 f Wf/R 0.7 1331 4675 867 2563 (WQv) 7T3a FT TOTAL 1.5 134.0 9325 5600 8263 WEIR LENGTH 12" MIN, AT ELEV=133.2 F I 4.p p0 4"x4" PVC TEE TRASH RACK REFER TO DETAIL PERM. POND ELEV.=132.5 THIS SHEET TOP OF EMBANKMENT ELEVATION=134.0 EXISTING GRADE=138.0± 100 YEAR STORM EiEVATION=133.97 OUTLET CONTROL STRUCTURE INCREMENTAL WEIR - REFER TO DETAIL SCALE:N.T.S. FOR INCREMENTAL WEIR 6" TOPSOIL FOR ALL AREAS ABOVE THE 10 YEAR STORM ELEVATION=133.74 NORMAL POND ELEVATION PRECAST FOREBAY BERM CONCRETE RISER li -� (INSTALL STEPS Iq AS NECESSARY) 2 YEAR STORM ELEVATION=133.47 6" TOPSOIL ABOVE i YEAR STORM ELEVA1ION=133.35 6" CLAY LINER 3:1 I 1.0-INCH STORM ELEVATION=132.81 ON LITTORAL SHELF -- 17 NORMAL POND ELEVATION=132.5 _ - -6FT LITTORAL 6:1 1 - SHELF - PVC ELBOW - J ' ' SEE DETAIL 2 NOTE; PUMPS SHALL BE USED TO DRAIN _'� THE POND. WHEN NECESSARY. REFER TO, DETAIL _� I IT 5' GRASS FOREBAY THIS SHEET FOR DEWATERING REQUIREMENTS. i I �.� WEIR AT ELEV=131.0 BOTTOM OF POND (TOP OF SEDIMENTISTORAGE)=127.0 CONCRETE SHALL BE PLACED IN RISER AFTER �- r BOTTOM F SEDIMENT SORAGE =26.i ANGLES ARE SECUREDOOETT ���4 I - ( 10 ) TO BASE AND RISER. STRUCTURAL FILL A5 2-A307 "J" HOOKS 3/4" DIA. X 12" LONG FROM ANGLE TO BASE.I� -- -- - - ANGLE TO BE FIELD COATED WITH ZINC RICH PAINT AFTER- _ DIRECTED BY GEOTECHNICAL CONSTRUCTION. "J" HOOKS TO BE PLACED UNDER LOWER REINFORCING ENGINEER STEEL 6" CLAY SOIL 5'x5'xi.5' CONC. BASE REINFORCE WITH #4 BARS AT 12" O.C. TOP LINER AND BOTTOM OF EACH DIRECTION PROVIDE 3" MIN. CLEARANCE MAIN POOL NOT S: BETWEEN EDGE OF CONC. AND STEEL REINFORCING. 10'-15" HOPE � 1.0% 1. SEE DESIGN PLANS FOR SPECIFIED DIMENSIONS OF RISER.' 2. TRASH RACK DIMENSION CRITERIA SPECIFIED IS APPROXIMATE AND VARIES BY MANUFACTURER. 3. INSTALLATION OF TRASH RACK SHALL BE ACCORDING TO MANUFACTURER'S RECOMMENDATIONS. ILTER MEDIA (SEE NOTE 2) 4. ALL COMPONENTS OF TRASH RACK SHALL BE OF STAINLESS STEEL OR OTHER NON -CORROSIVE MATERIAL. PROFILE OF WET POND DETENTION SYSTEM 5. ALL MOUNTING HARDWARE SHALL BE OF STAINLESS STEEL OR OTHER NON -CORROSIVE MATERIAL SILT FENCE AS NEEDED PUMP SCALE: .T.S. TRASH RACK FL_.-� -- O NON CORROSIVE MATERIAL / /� \\ \ 5.5" ® 5.5" SPACING / \ TRi1SH RACK 5.5" � I WATER LEVEL _ 5.5" I PRIOR TO INSTALLATION, MANUFACTURER SPECIFICATIONS OF FILTER MEDIA SHALL BE REVIEWED TO ENSURE THAT DISCHARGE FROM j( FILTER MEDIA SHALL MEET OR EXCEED THE PROVISIONS OF THE CLEAN WATER ACT. ENSURE THAT PUMP PRESSURE DOES NOT EXCEED FILTER MEDIA PRESSURE RATING. T ❑L ,1dOM RISER TRASH RACK SHALL BE INSPECTED FILTER MEDIA MAY BE, BUT NOT LIMITED TO, SAND MEDIA FILTRATION DEVICES, RATED FILTER FABRIC PERIODICALLY AND ANY DEBRIS ON BAGS OR POLYMER BASED DEWATERING PRACTICES. THE TRASH RACK IS TO BE REMOVED fiL LI I PUMP STRAINER SHALL NOT 8E IN CONTACT WITH BOTTOM OF POND. AND PROPERLY DISPOSED OF. -IIIII' BMP POND DEWATERING -" SLOW POINT RISER RISER TRASH RACK DETAIL SCALE: N.T.S. SEEDBED PREPARATION: STORMWATER \ �/ 1. CHISEL COMPACTED AREAS AND SPREAD TOPSOIL THREE INCHES DEEP OVER ADVERSE SOIL CONDITIONS, IF AVAILABLE. MANAGEMENT 2. RIP THE ENTIRE AREA TO SIX INCHES DEER EASEMENT 3. REMOVE ALL LOOSE ROCK, ROOTS AND OTHER OBSTRUCTIONS, LEAVING SURFACE REASONABLY SMOOTH AND UNIFORM. / r 4. APPLY AGRICULTURAL LIME, FERTILIZER, AND SUPERPHOSPHATE UNIFORMLY AND MIX WITH SOIL (SEE SEEDING MIXTURE). FES INV=132.4 5. CONTINUE TILLAGE UNTIL A WELL -PULVERIZED, FIRM, REASONABLY UNIFORM SEEDBED IS PREPARED FOUR TO SIX INCHES DEER 6. SEED ON A FRESHLY PREPARED SEEDBED AND COVER SEED LIGHTLY WITH SEEDING EQUIPMENT OR CULTIPACK AFTER SEEDING. 7. MULCH IMMEDIATELY AFTER SEEDING AND ANCHOR MULCH. RIP RAP / B. INSPECT ALL SEEDED AREAS AND MAKE NECESSARY REPAIRS OR RE-SEEDINGS WITHIN THE PLANTING SEASON, IF POSSIBLE. IF -� i EMERGENCY STAND SHOULD BE MORE THAN 60% DAMAGED, RE-ESTABLISH FOLLOWING THE ORIGINAL LIME, FERTILIZER AND SEEDING RATES. SPILLWAY / 1 O, -15„ HDPE 9. CONSULT S&EC ENVIRONMENTAL ENGINEERS ON MAINTENANCE TREATMENT AND FERTILIZATION AFTER PERMANENT COVER IS (c� j O% ESTABLISHED. LANDSCAPE NOTES: TOP of uTLET CONTROL ALL LANDSCAPING SHALL BE IN COMPLIANCE WiTH THE NCDEQ BMP REQUIREMENTS. EMBANKMENT 1 STRUCTURE ELEV=134 0 / � / ©a .� 1 � 3' MIN 6" TOPSOIL ABOVE 6" CLAY LINER ON LITTORAL SHELF 1- 3 - � 1 6 6FT LITTORAL 1 SHELF ; 1= i INV=132.! 1�0 _/_1 � zo i ELEV=129.5 --� 1 4' MIN. ASTM C-923 SEAL KEY BETWEEN BARREL & RISER. RISER BASE TO BE FILLED WiTH CONC. TO INVERT OF BARREL 8"XS"X1"X12" LONG ANGLE (6 TOT. REQUIRED) TO ANCHOR RISER TO _ BASE. PROVIDE 2-3/4" A307 BOLTS FROM ANGLE TO RISER AND FOREBAY TOP ELEV= 134.0 WIDTH AT TOP = 2.0 FT " DIA. HOLE DRILLED -J INTO BOTTOM CAP PVC DRAIN OUTLET NOTE: PUMPS SHALL BE USED TO DRAIN FOREBAY BOTTOM THE FOREBAY WHEN NECESSARY. REFER TO DETAIL THIS SHEET FOR DEWATERING REQUIREMENTS. ELEV=129.0 NORMAL POND ELEVATION FOREBAY ENTRANCE SHALL BE I �`! DEEPER THAN FOREBAY EXIT BOTTOM OF SEDIMENT STORAGE ELEV=128.0 FOREBAY 6" TOPSOIL FOR ALL AREAS ABOVE THE NORMAL POND ELEVATION SHALLOW LAND ZONE HERBACEOUS PLANTS SHALLOW WATER ZONE HERBACEOUS PLANTS POND (NORMAL POOL) 1 6 TYPICAL LITTORAL SHELF VEGETATION DETAIL SCALE: N.T.S. SCIENTIFIC NAME COMMON NAME PLANTING ZONE QUANTITY NURSERY CONTAINER TYPE SPACING PLANTING SEASON Jancus effusus Soft Rush SHALLOW WATER 51 PEAT POT 6' O.C. SPRING/SUMMER Iris virginica Blue Flag Iris SHALLOW WATER 51 PEAT POT 6' O.C. SPRING/SUMMER Schoenoplectus tobemoemontani Eupotoriadelphus moculatus Soft Stem Bulrush Spotted Trumpetweed SHALLOW WATER SHALLOW LAND 51 51 PEAT POT PEAT POT 6' O.C. 6' O.C. SPRING/SUMMER SPRING/SUMMER Eupatorium purpureum Joe-Pye Weed SHALLOW LAND 51 PEAT POT 6' O.C. SPRING/SUMMER Rhynchospora colorata Starrush Whitetop SHALLOW LAND 51 PEAT POT 6' O.C. SPRING/SUMMER TYPICAL LITTORAL SHELF PLANTING SCHEDULE SPILLWAY CREST ELEV.=133.25 TOP OF EMBANKMENT ELEV = 134.0 4' 2' B 8" 1' 3 1� LEVEL III I 3 SPILLWAY III 1 CREST III III COMPACTED SUBGRADE III III CLASS B RIP RAP II I'I I I RIP RAP SPILLWAY CLASS B RIP RAP - LANDSCAPE CONTRACTOR SHALL PROVIDE ATWO-YEAR WARRANTY FOR BMP PLANTING SURVIVAL/REPLACEMENT. / a U aq\ INV.OUT=132.5 , - \ STORMWATER MANAGEMENT NOTES: AT THE END OF THE FIRST YEAR AND AT THE END OF THE TWO-YEAR WARRANTY PERIOD, ALL PLANTS THAT DO NOT SURVIVE MUST BE / ` \�/ OS�o \ No p / / 1. THE DEVELOPER OR HIS AGENT SHALL CONTACT THE DESIGN ENGINEER WHEN THE REPLACED. 0,001 O \ - ✓ \ BEST MANAGEMENT PRACTICE(S) ARE CONSTRUCTED AND ABOUT TO BECOME ESTABLISHMENT PROCEDURES, SUCH AS CONTROL OF INVASIVE WEEDS, ANIMAL AND VANDAL DAMAGE, MULCHING, RE -STAKING, WATERING, AND EPl - / D U1 O q10 q tj O \ OPERATIONAL SO A FINAL INSPECTION CAN BE PERFORMED TO DETERMINE MESH OR TUBE PROTECTION REPLACEMENT, SHALL BE IMPLEMENTED TO THE EXTEND NEEDED TO ENSURE PLANT SURVIVAL. STAKING MUST BE Up -' O a \ ` ` -SHORT STOP COMPLIANCE WITH THE APPROVED PLAN CAN BE PERFORMED. REMOVED AFTER ESTABLISHMENT APPROXIMATELY 12 MONTHS), TO PREVENT GIRDLING (STRANGLING) OF ALL WOODY PLANTS. q <%q \ ( ) O a " "Q�O � FFE j ' 2. ANNUAL MAINTENANCE INSPECTION AND REPORT REQUIRED -THE OWNER OF A SOD WITHIN BMP AND SURROUNDING AREAS TO BE BERMUDA OR CENTIPEDE GRASS. U U ap y O\ - - _ / 6' \ PERMITTED STRUCTURAL STORMWATER BMP/CONTROL SHALL ANNUALLY SUBMIT A GRASS OR WILDFLOWER SEED MUST BE APPLIED AT THE RATES SPECIFIED BY THE SUPPLIERS. IF PLANT ESTABLISHMENT CANNOT BE ACHIEVED MAIN PON i q a O / MAINTENANCE AND INSPECTION REPORT FOR EACH BMP TO THE STORMWATER WHit SEEDING BY THE TIME OF SUBSTANTIAL COMPLETION OF THE STORMWATER FACILITY PORTION OF THE PROJECT, THEN THE CONTRACTOR _ \ U /iT' I I ADMINISTRATOR. ANNUAL INSPECTIONS SHALL BEGIN WITHIN ONE YEAR OF THE. SHALL PLANT THE AREA WITH WILDFLOWER SOD, PLUGS, CONTAINER PLANTS, OR OTHER MEANS TO COMPLETE THE SPECIFIED PLANTING AND VOLUME=5,681CF \ ,� a ,�v, \ / �' RECORDATION OF ANY DEED(S) SHOWING STORMWATER BMPs/CONTROL PROTECT AGAINST EROSION BEFORE WATER IS ALLOWED TO ENTER THE STORMWATER BMP FACILITY. / a O gpX7 \ /J�. !� / 1 STRUCTURES. ALL MATERIALS SHALL BE ACQUIRED FROM AN APPROVED NCDEQ PLANT VENDOR. PLANT MATERIAL SHOULD BE PURCHASED FROM A LOCAL \� \ q� aq U / �^ \ 3. UPON C014PLET1UN OF THE PROJECT, AND BEFORE A CERTIFICATE OF OCCUPANCY SOURCE TO ENSURE SURVNABIUTY. LOCAL VENDORS FOR THIS SITE INCLUDE: MAI - CILL IDE NATIVE PLANT NURSERY 919-662-5566 O a�2 \ / SHALL BE GRANTED, THE ENGINEER OF RECORD SHALL CERTIFY THAT THE - GROWING WILD NURSERY 910-259-6361 POND a0ga O \ / / / COMPLETED PROJECT IS IN ACCORDANCE WITH THE APPROVED STORMWATER - NC FOREST SERVICE 919-731-7988 AREA / \ p 41 \ % / MANAGEMENT PLANS AND DESIGNS. - PLANT DELIGHTS NURSERY 919-772-4794 O Q cl' \ / - TARHEEL NATIVE TREES 919-553-5927 S� q� cf?S �\_ - / 4. A FINAL INSPECTION OF THE SITE AND STORMWATER MANAGEMENT BMP/CONTROLS IMMEDIATELY AFTER THE WET DETENTION BASIN IS ESTABLISHED THE PLANTS ON THE VEGETATED SHELF AND PERIMETER OF THE BASIN SHOULD O `� O�% 1 �' TO BE SCHEDULED WiTH AND COMPLETED BY THE PROJECT ENGINEER. N SOD AREAS ABOVE / o w o BE WATERED ;TWICE WEEKLY IF NEEDED UNTIL THE PLANTS BECOME ESTABLISHED (COMMONLY SIX WEEKS) \ �- O i, I _- ._ __.- NORMAL POOL O q .pp 5. NCDEQ AND THEIRASSIGNSHAVE RIGHT TO ACCESS THE STORAIWATER THE PORTION OF THE WET TATE SHELF. POND SHOULD BE FERTILIZED AFTER THE FIRST INITIAL FERTILIZATION THAT IS REQUIRED TO ESTABLISH ` \ CONTROL(s) FOR INSPECTIONS OR MAINTENANCE AS NECESSARY. THE PLANTS ON THE VEGETATED SHELF. ELEVATION - � � S, �a I r£� 1 _ / r 6. THE ENGINEER'S CERTIFICATION OF COMPLETION WILL BE REQUIRED PRIOR TO THE Ln `J FINAL PLAT OR CERTIFICATE OF OCCUPANCY. THE STORMWATER CONTROL IS TO -LANDSCAPING NOTES: 9�'/ \Ua> \ / BE INSPECTED TO ENSURE IT IS FUNCTIONING AS DESIGNED AND HAS FULL 1. CONTRACTOR SHALL COMPLY WITH ALL APPLICABLE CODES AND ORDINANCES REGARDING LANDSCAPING. LITTORAL SHELF \ q�j O O \ a \ O �i I� DESIGN VOLUME PRIOR TO ISSUANCE OF THE FINAL CERTIFICATE OF OCCUPANCY. 2. IT IS THE RESPONSIBILITY OF THE CONTRACTOR TO ESTABLISH A HEALTHY STAND OF GRASS ON ALL SEEDED AREAS. AREA=1,215SF \ O\O it, THE PROPERTY OWNER IS RESPONSIBLE FOR MAINTAINING THE STORMWATER REFER TO DETAIL \ q O a Op a\ OREBAY CONTROLS(s) ACCORDING TO THE APPROVED MAINTENANCE PLAN AND DIRECTION 3. CONTRACTOR SHALL PROVIDE NATURAL TOPSOIL THAT IS FERTILE, FRIABLE, WITHOUT MIXTURE OF SUBSOIL MATERIALS, AND , OBTAINED FROM A WELL DRAINED, AVAILABLE SITE. IT SHALL NOT CONTAIN SUBSTANCES WHICH MAY BE HARMFUL TO PLANT FOR PLANTINGS �/ Sir/ \ U / r \\ \ WEIR OF NCDEQ GROWTH. TOPSOIL SHALL BE SCREENED AND FREE FROM CLAY, LUMPS, STONES, ROOTS, PLANTS, OR SIMILAR SUBSTANCES 1" OR MORE IN DIAMETER, DEBRIS, OR OTHER OBJECTS WHICH MIGHT BE A HINDERANCE TO PLANTING OPERATIONS. TOPSOIL SHALL CONTAIN AT LEAST 4-6% ORGANIC MATTER BY WEIGHT AND HAVE A PH RANGE Or 5.5 TO 7.0. \ / / / / p 4. CONTRACTOR SHALL BE RESPONSIBLE FOR THE WATERING AND THE MAINTENANCE OF ALL LANDSCAPED AREAS UNTIL THE LATER STORMWATER , FOREBAY / / STORMWATER MANAGEMENT DESIGN OF; (a) THIRTY (30) DAYS FOLLOWING THE PLANTING OF THE GRASS AND SHRUBS, OR (b) THE DATE THAT STORE OPENS FOR \ / / - _ (1 BUSINESS TO THE PUBLIC. CONTRACTOR SHALL ALSO BE RESPONSIBILITY FOR THE SURVIVAL OF THE BMP PLANTING MATERIALS MANAGEMENT �� \ \ /s WET DETENTION POND DURING THE TWO-YEAR WARRANTY PERIOD AND SHALL REPLACE ALL PLANTS THAT DO NOT SURVIVE AT THE END OF THE FIRST EASEMENT \ C1' YEAR AND AT THE END OF THE SECOND YEAR OF THE WARRANTY PERIOD. \ \ \\ / i RIVER BASIN: CAPE FEAR / / 1 i ' RECEIVING STREAM: ROCKFISH CREEK 5. CONTRACTOR TO VERIFY QUANTITIES PRIOR TO COMMENCING WORK. �❑ \ / x STREAM INDEX: 18-31-(18) 6. ANY DISTURBED AREAS NOT SCHEDULED FOR HARDSCAPE, PLANTINGS, OR MULCH SHALL BE SEEDED LAWN. REFER TO SITE PLAN CLASSIFICAITON: B FOR LOCATION OF AREAS TO BE SODDED. , ~ HOC: 03030004 7. NO PLANT SUBSTITUTIONS ARE PERMITTED WITHOUT WRITTEN APPROVAL OF THE OWNERS REPRESENTATIVE. FOREBAY INLET FLUME WIT OZ-i£ i• 8. FOR NEW PLANTING AREAS, REMOVE ALL PAVEMENT, GRAVEL SUB -BASE AND CONSTRUCTION DEBRIS; REMOVE COMPACTED SOIL VOLUME=1 O28CF , RIP -RAP APRON/ POND DESIGN SUMMARY AND ADD 18" NEW TOPSOIL, OR TILL AND AMEND THE TOP 18" OF EXISTING SOIL TO MEET TOPSOIL/PLANTING MIX STANDARDS I / DRAINAGE AREA TO POND: 1.15 ACRES FOR TREES. i O SITE IMPERVIOUS AREA TO POND: 0.75 ACRES 9. ADJUST TREE PLANTING LOCATIONS TO AVOID UNDERGROUND UTILITIES. PLANT 15' FROM ALL UNDERGROUND UTILITIES (SEWER \ - OFF -SITE DESIGN IMPERVIOUS AREA TO POND: 0.0 ACRES AND STORM DRAINAGE, GAS, WATER, PHONE, AND ELECTRICAL LINES.) �J GRAPHIC SCALE TOTAL DESIGN IMPERVIOUS AREA TO POND: 0.75 ACRES 20 0 - 10 20 1111,j,,! I�1i�jll PRE -DEVELOPED' POST -DEVELOPED POST DEVELOPED THROUGH POND DRAINAGE AREA: 1.15 AC 1.15 AC STORMWATER MANAGEMENT SYSTEM DETAILS STORMWATE \ CURVE NUMBER: 74.6 89.7 1 MANAGEMENT 1 INCH = 20 FEET TIME OF CONCENTRATION: 10 MIN 5 MIN NOT TO SCALE \ EASEMENT , 1.0" STORM EVENT: 0.282 CFS 0.008 CFS i PLAN VIEW �/� , 1-YEAR STORM EVENT: 1.539 CFS 3.765 CFS 1.387 CFS Z 2-YEAR STORM EVENT: 2.286 CFS 4.828 CFS 1.939 CFS 10-YEAR STORM EVENT: 4,526 CFS 7.805 CFS 4.526 CFS 100-YEAR STORM EVENT 8.855 CFS 12.62 CFS 9.843 CFS I < SPILLWAY SECTION 1.0' A 1'0 TOP OF EMBANKMENT ELEV=134.0 SPILLWAY B ELEV=133.75 SPILLWAY A 6 'BASIN 5 FT 0.25 FT PROPOSED RIP RAP APRON OPERATION & MAINTENANCE BMP element: Potential problem: How I will remedlate the problem The entire BMP Trash/debris is present Remove the trash/debris ePerimeter n e we etention basin Areas of bare soil and/or erosive gullies have formed Regrade the soil If necessary to remove the gully, and then plant a ground cover and water until It is established. Provide lime and a one-time fertilizer application Vegetation is too short or too long anon vegetation a a height of approximately six inches. e Inlet ev ce: pipe or wale e pipe s c ogge , Unclog e pipe. Dispose o e sediment oN-site, The pipe Is cracked or Replace the pipe. otherwise damaged Erosion is occurring in the Regrade he swale if necessary Swale. to smooth it over and provide erosion control devices such as reinforced turf matting or riprop to avoid future problems with erosion. The foreboy Sediment as accumul ed to o depth greater than the ears or he source of e sediment and remedy the original design depth for problem if possible. Remove the sediment storage. sediment and dispose of it in a location whore it will not cause impacts to streams or the BMP. Erosion as occurs . Provide additional eros on protection such as reinforced turf matting or riprop if needed to prevent future erosion roblems. e s are present. Remove a woods, pre era y y hand. If pesticide Is used, wipe it on the plants rather than spraying. The vegetate shelfBestprofessional practices show that pruning is needed rune according o e professional practices to maintain optimal plant health. Plants are dead, diseased or Determine the source of the dying. problem: soils, hydrology, disease, etc. Remedy the problem and replace plants. Provide a one-time fertilizer application to establish the ground cover If a soil test indicates ti is necessa . Woods are present. Remove the woods, pro ferably by hand. If pesticide is used, wipe it on the plants rather than spraying. The main treatment area Sediment as accumulated to Searchforte source o the a depth greater than the sediment and remedy the original design sediment problem if possible. Remove the storage depth. sediment and dispose of it in a location where it will not cause Impacts to streams or the BMP. ga gro covers over of the area. Consulta professionalo remove and control the al al rowth. Cattails p rogmites or other Remove e p an s by w ping invasive plants cover 50% of them with pesticide (do no the basin surface, IN T e embankmentShrubs have started to grow on the embankment Rves rubs immedi ely. Evidence of muskrat or beaver Use traps to remove muskrats activity is present. and consult a professional to remove beavers, tree has started to grow on Consult a dam safetyspecialist the embankment. to remove the tree. An annual innspectlon by an Make all needed repairs. appropriate professional shows that the embankment needs repair. if applicable) The outletdevice Clogging has occurred. can outa outlet ev ce, Dispose of the sediment off -site. The outlet device is damaged Repair or replace the outlet device. The receiving water Erosion or other signs of damage have occurred at the outlet. Contact the local NC Division of Water Quality Regional Office, or the 401 Oversight Unit at H C7 r-+ CO MSsom W 0? CONSULTANT: Triangle Site Design, PLLC 4004 Barrett Drive Suite 101 Raleigh, NC 27609 (919)553-6570 mlowder®trionglesitedesign.com NC License #P-0619 *'0%% %%. eeea," A R '+ C SEAL I, �•' 244j4ctiGl° � we.Eey�O`®�t OWNER/DEVELOPER: Lee Humphrey Double D Engineering, PLLC 150 S. Page Street Southern Pines, NC 28387 910-684-8646 (Office) 910-206-1808 (cell) lee@doubledeng.com O 0 V) 0 O O --I ® 0 This document, together with the concepts and designs presented herein, as an instrument of services, is intended only for the specific purpose and client for which it was prepared. Reuse of and improper reliance on this. document without written authorization and adaptation by Triangle Site. Design, PLLC shall be without liability to Triangle Site Design, PLLC. v a N L w�- 0 N c w 0 Drawn Checked Approved Project No: 038007 Date: December 31, 2019 Title STORMWATER CONTROL MEASURE DETAILS Sheet No. S M a3i a�i w Cr z z N N a � w w r- N