HomeMy WebLinkAboutSW1191001_18-161 - NCDEQ SW 2ND SUB_11/26/2019STGRMWATER NARRATIVE STATEMENT AND DESIGN CALCULATIONS Rutherfordton-Spindale Middle School Thompson Rd Rutherfordton, North Carolina November 2019 ■ %A nR s 53 CLH design, p.a. 400 rieSoicy Forest Drive, Suite 120 Cary, North Carolina 2751127918 Phone: (919) 319-6716 Fax• (919) 319-7516 Narrative Statement Proiect Description Rutherfordton-Spindale Middle School will be a new middle school located along Thompson Road and Westbrook Drive in Rutherfordton, NC. The Rutherfordton-Spindale Middle School project includes the construction of a proposed middle school, parking and bus loop areas, various outbuildings, as well as a baseball field, track and field events, and soccer field. This project will impact approximately 41 acres. The stormwater runoff from the site discharges to the Hollands Creek (Stream Index: 9-41-13-7-(1); Classification: WS-V), which is located within the Broad River Basin. FEMA FIRM # 3710161100J dated July 2, 2008 indicates that the site is not located within the limits of the 100-year flood plain. Soils on the site consist of Ridgewood fine sand, Croatan-Dorovan mucks, Leon sand, and Rudege sand. These soils represent Hydrologic Soil Groups (HSG) A, B/D and A/D. The majority of the site is HSG B/D soils, and therefore HSG D soils shall be used for stormwater calculations. Existing wetlands are present on site, however, limits of disturbance area outside of the limits of the wetlands. Riparian buffers are not present on site. Stormwater Management Methodology The proposed middle school is located in an unincorporated area and in the Municipal Sphere of Influence (MSI) and is subject to Phase H requirements. This total impervious surface makes up 15% of the total project area, but because the site employs a stormwater network to convey runoff, this site is considered high -density. Treatment of runoff is being handled by two wet ponds. Wet pond #1 is located to the north of the track and field areas and discharges upstream of nearby wetlands. Wet pond #2 is located to the west of the fire lane and discharges upstream to a nearby stream. Maps G a f—J 1 1i1Ao r f 'n Rutherford County Board of Education Portion of USGS Quad Map Rutherfordton Spindale Middle School North Rutherfordton, NC - 1966 Scale: 1" = 2,000' OIL OL Pat YRU Fla flE ww M Mon Nip UIrA YA6 i Ing He raft YQ CIA Y �.,.^i� 1; Us �1 J OWE? � a 1 1 TI 111q Yl� A YVI FW1 4 L %7.. 1 tc 511574 ' Ymn Rutherford County Board of Education Portion of NRCS Soil Map Rutherfordton Spindale Middle School North Rutherford North NC - #9 Scale: 1" = 2,000' m Stormwater Calculations DATE 20-Sep-19 Q Q PROJECT NAME PROJECT NO Ruth erfordton-S indale Middle School 18-161 LOCATION BY Rutherfordton, NC HLB Drainage Area, (DA) = 10.00 ac Impervious Area c= 0.95 4.52 ac Pervious Area c= 0.30 5.48 ac Cc = 0.59 % Impervious = 45.20 % Soil Type: Hiwasse (Type B) Temporary Water Quality Pool Design Storm Rainfall 1.00 in (Typically 1-in) Runoff Coeff. (Rv = 0.05 + 0.009 (% Imperv.)) = 0.46 in/in Required Volume (design rainfall)(Rv)(DA) = 16,582 cf Main Pool Volume Required, Vmp = 40,393 cf Main Pool Volume: Main Pool Max. Depth = 6.00 ft Area of Pond Bottom (Above PSS) = 2,711 sf Area at Bottom of Shelf = 10,040 sf Area of Permanent Pool = 11,780 sf Area at Top of Shelf = 13,600 sf Perm. Pool Volume Provided = 40,520 cf > 40,393 cf Surface Area at 1" Storage Volume = 19,370 sf 1" Storage Volume Provided = 18,709 cf > 16,582 Temp. Storage Depth above Dewatering Hole = 1.25 ft Diameter of Dewatering Hole = 2.00 in Detention (Draw -Down) Time = 2.9 days (2-5 days Required) T days=(Temp. Storage Vol Req / (0.6 * A (2*g*(h))Al /2) * 86400 (where h = one third temp. storage depth measured to centroid of orifice) Max Drawdow Rate= 0.11 cfs Main Pool Volume= 40,520 cf > 40,393 Forebay Volume: Forebay Max. Depth = 4.50 ft Area of Forebay Bottom (Above PSS) = 269 sf Area at Bottom of Shelf = 2,212 sf Area of Permanent Pool = 2,949 sf Forebay Volume Required = 6,078 - 8,104 Forebay Volume Provided = 6,252 cf 15.43 % = 15-20 s:\1319\0001\calcs\18-161 - PondSize-Wet Pond-MDC-Piedmont and Mountain-HR_PrXt€d: 10/4/2019 12:42 PM Page 1 of 1 DATE Q 8/15/19 /J PROJECT NAME PROJECT NO Lewisville MS 17-116 LOCATION BY Forsyth County, NC KAL Drainage Area, (DA) = 27.25 ac Impervious Area c= 0.95 8.16 ac Pervious Area c= 0.30 19.09 ac Cc = 0.49 % Impervious = 29.94 % Soil Type: Hiwasse (Type B) Temporary Water Quality Pool Design Storm Rainfall 1.00 in (Typically 1-in) Runoff Coeff. (Rv = 0.05 + 0.009 (% Imperv.)) = 0.32 in/in Required Volume (design rainfall)(Rv)(DA) = 31,605 cf Main Pool Volume Required, Vmp = 76,989 cf Main Pool Volume: Main Pool Max. Depth = 3.50 ft Area of Pond Bottom (Above PSS) = 26,200 sf Area at Bottom of Shelf = 32,830 sf Area of Permanent Pool = 35,180 sf Area at Top of Shelf = 37,580 sf Perm. Pool Volume Provided = 105,548 cf > 76,989 cf Surface Area at 1" Storage Volume = 47,970 sf 1" Storage Volume Provided = 39,578 cf > 31,605 Temp. Storage Depth above Dewatering Hole = 1.00 ft Diameter of Dewatering Hole = 2.50 in Detention (Draw -Down) Time = 4.1 days (2-5 days Required) T days=(Temp. Storage Vol Req / (0.6 * A (2*g*(h))Al /2) * 86400 (where h = one third temp. storage depth measured to centroid of orifice) Max Drawdow Rate= 0.16 cfs Main Pool Volume= 105,548 cf > 76,989 Forebay Volume: Forebay Max. Depth = 4.50 ft Area of Forebay Bottom (Above PSS) = 1,800 sf Area at Bottom of Shelf = 5,810 sf Area of Permanent Pool = 7,000 sf Forebay Volume Required = 15,832 - 21,110 Forebay Volume Provided = 18,423 cf 17.45 % = 15-20 OK s:\1319\0001\calcs\18-161 - PondSize-Wet Pond-MDC-Piedmont and Mountain-HgTnXteg: 11/26/2019 12:58 PM Page 1 of 1 Hydraflow Table of Contents 18-161 -SCM Routing_WET PONDS.gpw Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 11 / 26 / 2019 Hydrograph Return Period Recap............................................................................. 1 1 -Year SummaryReport......................................................................................................................... 2 HydrographReports................................................................................................................... 3 Hydrograph No. 2, SCS Runoff, Area to SCM 1....................................................................... 3 Hydrograph No. 3, Reservoir, Route SCM-1............................................................................ 4 PondReport - SCM-1.......................................................................................................... 5 Hydrograph No. 5, SCS Runoff, Area to SCM 2....................................................................... 6 Hydrograph No. 6, Reservoir, Route SCM-2............................................................................ 7 PondReport - SCM-2.......................................................................................................... 8 10 -Year SummaryReport ......................................................................................................................... 9 HydrographReports................................................................................................................. 10 Hydrograph No. 2, SCS Runoff, Area to SCM 1..................................................................... 10 Hydrograph No. 3, Reservoir, Route SCM-1.......................................................................... 11 Hydrograph No. 5, SCS Runoff, Area to SCM 2..................................................................... 12 Hydrograph No. 6, Reservoir, Route SCM-2.......................................................................... 13 100 - Year SummaryReport ....................................................................................................................... 14 HydrographReports................................................................................................................. 15 Hydrograph No. 2, SCS Runoff, Area to SCM 1..................................................................... 15 Hydrograph No. 3, Reservoir, Route SCM-1.......................................................................... 16 Hydrograph No. 5, SCS Runoff, Area to SCM 2..................................................................... 17 Hydrograph No. 6, Reservoir, Route SCM-2.......................................................................... 18 OFReport.................................................................................................................. 19 Hydrograph Return Period ReHydra cap w Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Hyd. Hydrograph Inflow Peak Outflow (cfs) Hydrograph No. type hyd(s) Description (origin) 1-yr 2-yr 3-yr 5-yr 10-yr 25-yr 50-yr 100-yr 2 SCS Runoff ------ 18.16 ------- ------- ------- 46.43 ------- ------- 81.22 Area to SCM 1 3 Reservoir 2 0.754 ------- ------- ------- 7.693 ------- ------- 54.05 Route SCM-1 5 SCS Runoff ------ 34.91 ------- ------- ------- 104.45 ------- ------- 196.26 Area to SCM 2 6 Reservoir 5 0.957 ------- ------- ------- 8.670 ------- ------- 108.34 Route SCM-2 Proj. file: 18-161-SCM Routing_WET PONDS.gpw Tuesday, 11 / 26 / 2019 Hydrograph Summary Repo rtHydraflowHydrographsExtension for AutodeskO Civil 3DO2019byAutodesk,Inc. v202O Hyd. No. Hydrograph type (origin) Peak flow (cfs) Time interval (min) Time to Peak (min) Hyd. volume (cuft) Inflow hyd(s) Maximum elevation (ft) Total strge used (cuft) Hydrograph Description 2 SCS Runoff 18.16 2 722 47,667 ------ ------ ------ Area to SCM 1 3 Reservoir 0.754 2 878 43,982 2 1005.08 28,848 Route SCM-1 5 SCS Runoff 34.91 2 722 94,833 ------ ------ ------ Area to SCM 2 6 Reservoir 0.957 2 1090 74,956 5 999.88 64,687 Route SCM-2 18-161-SCM Routing_WET PONDS.gpw Return Period: 1 Year Tuesday, 11 / 26 / 2019 3 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 11 / 26 / 2019 Hyd. No. 2 Area to SCM 1 Hydrograph type = SCS Runoff Peak discharge = 18.16 cfs Storm frequency = 1 yrs Time to peak = 722 min Time interval = 2 min Hyd. volume = 47,667 cuft Drainage area = 10.000 ac Curve number = 78* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 11.50 min Total precip. = 3.20 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 * Composite (Area/CN) = [(4.520 x 98) + (5.480 x 61)] / 10.000 Q (cfs) 21.00 18.00 15.00 12.00 3.00 Area to SCM 1 Hyd. No. 2 -- 1 Year Q (cfs) 21.00 18.00 15.00 12.00 M 3.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 — Hyd No. 2 Time (min) 4 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 11 / 26 / 2019 Hyd. No. 3 Route SCM-1 Hydrograph type = Reservoir Peak discharge = 0.754 cfs Storm frequency = 1 yrs Time to peak = 878 min Time interval = 2 min Hyd. volume = 43,982 cuft Inflow hyd. No. = 2 - Area to SCM 1 Max. Elevation = 1005.08 ft Reservoir name = SCM-1 Max. Storage = 28,848 cuft Storage Indication method used. Route SCM-1 Q (cfs) Hyd. No. 3 -- 1 Year Q (cfs) 21.00 21.00 18.00 18.00 15.00 15.00 12.00 12.00 9.00 9.00 6.00 6.00 3.00 3.00 0.00 0.00 0 600 1200 1800 2400 3000 3600 4200 4800 5400 6000 Time (min) — Hyd No. 3 Hyd No. 2 Total storage used = 28,848 cult Pond Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 11 / 26 / 2019 Pond No. 1 - SCM-1 Pond Data Contours -User-defined contour areas. Average end area method used for volume calculation. Begining Elevation = 1003.50 ft Stage / Storage Table Stage (ft) Elevation (ft) Contour area (sqft) Incr. Storage (cuft) Total storage (cuft) 0.00 1003.50 15,740 0 0 0.50 1004.00 17,793 8,383 8,383 1.50 1005.00 19,910 18,852 27,235 2.50 1006.00 22,090 21,000 48,235 3.50 1007.00 24,320 23,205 71,440 4.50 1008.00 26,610 25,465 96,905 5.50 1009.00 28,958 27,784 124,689 Culvert / Orifice Structures [A] [B] [C] [PrfRsr] Rise (in) = 36.00 2.00 0.00 0.00 Span (in) = 36.00 2.00 0.00 0.00 No. Barrels = 1 1 0 0 Invert El. (ft) = 1002.00 1003.50 0.00 0.00 Length (ft) = 56.00 0.50 0.00 0.00 Slope (%) = 1.79 0.00 0.00 n/a N-Value = .013 .013 .013 n/a Orifice Coeff. = 0.60 0.60 0.60 0.60 Multi -Stage = n/a Yes No No Stage (ft) 6.00 lasill 4.00 r m M Weir Structures [A] [B] [C] [D] Crest Len (ft) = 15.00 8.00 1.00 Inactive Crest El. (ft) = 1006.50 1007.50 1004.75 1004.75 Weir Coeff. = 3.33 2.60 3.33 3.33 Weir Type = 1 Broad Rect Rect Multi -Stage = Yes No Yes Yes Exfil.(in/hr) = 0.000 (by Contour) TW Elev. (ft) = 0.00 Note: Culvert/Orifice outflows are analyzed under inlet (ic) and outlet (oc) control. Weir risers checked for orifice conditions (ic) and submergence (s). Stage / Discharge Elev (ft) 1009.50 11111111[+I1R1'% 1007.50 1006.50 E11111- 6 1004.50 0.00 ' ' ' ' ' ' ' ' ' ' ' ' ' 1003.50 0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0 90.0 100.0 110.0 120.0 Total Q Discharge (cfs) A Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 11 / 26 / 2019 Hyd. No. 5 Area to SCM 2 Hydrograph type = SCS Runoff Peak discharge = 34.91 cfs Storm frequency = 1 yrs Time to peak = 722 min Time interval = 2 min Hyd. volume = 94,833 cuft Drainage area = 27.250 ac Curve number = 72* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 11.50 min Total precip. = 3.20 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 * Composite (Area/CN) = [(8.160 x 98) + (19.090 x 61)] / 27.250 Q (cfs) 35.00 25.00 20.00 15.00 10.00 5.00 Area to SCM 2 Hyd. No. 5 -- 1 Year Q (cfs) 35.00 30.00 25.00 20.00 15.00 10.00 5.00 0.00 ' 1 1 1 1�w ' ' ' ' ' ' M ' 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 — Hyd No. 5 Time (min) 7 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 11 / 26 / 2019 Hyd. No. 6 Route SCM-2 Hydrograph type = Reservoir Peak discharge = 0.957 cfs Storm frequency = 1 yrs Time to peak = 1090 min Time interval = 2 min Hyd. volume = 74,956 cuft Inflow hyd. No. = 5 - Area to SCM 2 Max. Elevation = 999.88 ft Reservoir name = SCM-2 Max. Storage = 64,687 cuft Storage Indication method used. Q (cfs) 35.00 25.00 20.00 15.00 10.00 5.00 0.00 ' 0 600 — Hyd No. 6 Route SCM-2 Hyd. No. 6 -- 1 Year Q (cfs) 35.00 30.00 25.00 20.00 15.00 10.00 5.00 -I I I I ' 0.00 1200 1800 2400 3000 3600 4200 4800 5400 6000 Time (min) Hyd No. 5 Total storage used = 64,687 cult Pond Report C Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 11 / 26 / 2019 Pond No. 2 - SCM-2 Pond Data Contours -User-defined contour areas. Average end area method used for volume calculation. Begining Elevation = 998.50 ft Stage / Storage Table Stage (ft) Elevation (ft) Contour area (sqft) Incr. Storage (cuft) Total storage (cuft) 0.00 998.50 43,816 0 0 0.50 999.00 46,571 22,597 22,597 1.50 1000.00 49,483 48,027 70,624 2.50 1001.00 52,250 50,867 121,490 3.50 1002.00 55,175 53,713 175,203 4.50 1003.00 58,156 56,666 231,868 5.50 1004.00 61,193 59,675 291,543 Culvert / Orifice Structures [A] [B] [C] [PrfRsr] Rise (in) = 36.00 2.50 0.00 0.00 Span (in) = 48.00 2.50 0.00 0.00 No. Barrels = 1 1 0 0 Invert El. (ft) = 996.00 998.50 0.00 0.00 Length (ft) = 59.00 0.50 0.00 0.00 Slope (%) = 1.70 0.00 0.00 n/a N-Value = .013 .013 .013 n/a Orifice Coeff. = 0.60 0.60 0.60 0.60 Multi -Stage = n/a Yes No No Stage (ft) 6.00 lasill 4.00 c m ►�1I17 M 0.00 0.0 30.0 Total Q Weir Structures [A] [B] [C] [D] Crest Len (ft) = 23.00 20.00 1.00 0.00 Crest El. (ft) = 1001.50 1002.25 999.50 0.00 Weir Coeff. = 3.33 2.60 3.33 3.33 Weir Type = 1 Broad Rect --- Multi-Stage = Yes No Yes No Exfil.(in/hr) = 0.000 (by Contour) TW Elev. (ft) = 0.00 Note: Culvert/Orifice outflows are analyzed under inlet (ic) and outlet (oc) control. Weir risers checked for orifice conditions (ic) and submergence (s). 60.0 90.0 Stage / Discharge Elev (ft) 1004.50 1002.50 1001.50 11111111NI1111 % 999.50 1 1 998.50 120.0 150.0 180.0 210.0 240.0 270.0 Discharge (cfs) Hydrograph Summary Repo rtHydraflowHydrographsExtension for AutodeskO Civil 3DO2019byAutodesk,Inc. v202O Hyd. No. Hydrograph type (origin) Peak flow (cfs) Time interval (min) Time to Peak (min) Hyd. volume (cuft) Inflow hyd(s) Maximum elevation (ft) Total strge used (cuft) Hydrograph Description 2 SCS Runoff 46.43 2 720 120,511 ------ ------ ------ Area to SCM 1 3 Reservoir 7.693 2 738 116,596 2 1006.47 59,147 Route SCM-1 5 SCS Runoff 104.45 2 720 271,490 ------ ------ ------ Area to SCM 2 6 Reservoir 8.670 2 772 250,349 5 1001.35 140,423 Route SCM-2 18-161-SCM Routing_WET PONDS.gpw Return Period: 10 Year Tuesday, 11 / 26 / 2019 10 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 11 / 26 / 2019 Hyd. No. 2 Area to SCM 1 Hydrograph type = SCS Runoff Peak discharge = 46.43 cfs Storm frequency = 10 yrs Time to peak = 720 min Time interval = 2 min Hyd. volume = 120,511 cuft Drainage area = 10.000 ac Curve number = 78* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 11.50 min Total precip. = 5.59 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 * Composite (Area/CN) = [(4.520 x 98) + (5.480 x 61)] / 10.000 Q (cfs) 50.00 40.00 20.00 10.00 Area to SCM 1 Hyd. No. 2 -- 10 Year Q (cfs) 50.00 40.00 30.00 20.00 10.00 0.00 - 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 — Hyd No. 2 Time (min) Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 11 / 26 / 2019 Hyd. No. 3 Route SCM-1 Hydrograph type = Reservoir Peak discharge = 7.693 cfs Storm frequency = 10 yrs Time to peak = 738 min Time interval = 2 min Hyd. volume = 116,596 cuft Inflow hyd. No. = 2 - Area to SCM 1 Max. Elevation = 1006.47 ft Reservoir name = SCM-1 Max. Storage = 59,147 cuft Storage Indication method used. Route SCM-1 Q (cfs) Hyd. No. 3 -- 10 Year Q (cfs) 50.00 50.00 40.00 40.00 30.00 30.00 20.00 20.00 10.00 10.00 0.00 - 0.00 0 360 720 1080 1440 1800 2160 2520 2880 3240 3600 3960 Time (min) Hyd No. 3 — Hyd No. 2 Total storage used = 59,147 cult 12 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 11 / 26 / 2019 Hyd. No. 5 Area to SCM 2 Hydrograph type = SCS Runoff Peak discharge = 104.45 cfs Storm frequency = 10 yrs Time to peak = 720 min Time interval = 2 min Hyd. volume = 271,490 cuft Drainage area = 27.250 ac Curve number = 72* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 11.50 min Total precip. = 5.59 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 * Composite (Area/CN) = [(8.160 x 98) + (19.090 x 61)] / 27.250 Q (cfs) 120.00 100.00 40.00 20.00 Area to SCM 2 Hyd. No. 5 -- 10 Year Q (cfs) 120.00 100.00 40.00 20.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 — Hyd No. 5 Time (min) 13 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 11 / 26 / 2019 Hyd. No. 6 Route SCM-2 Hydrograph type = Reservoir Peak discharge = 8.670 cfs Storm frequency = 10 yrs Time to peak = 772 min Time interval = 2 min Hyd. volume = 250,349 cuft Inflow hyd. No. = 5 - Area to SCM 2 Max. Elevation = 1001.35 ft Reservoir name = SCM-2 Max. Storage = 140,423 cuft Storage Indication method used. Q (cfs) 120.00 100.00 40.00 20.00 0.00 ' -kcdu 0 600 — Hyd No. 6 Route SCM-2 Hyd. No. 6 -- 10 Year Q (cfs) 120.00 100.00 40.00 20.00 0.00 1200 1800 2400 3000 3600 4200 4800 5400 6000 Time (min) Hyd No. 5 Total storage used = 140,423 cult 14 Hydrograph Summary Repo rtHydraflowHydrographsExtension for AutodeskO Civil 3DO2019byAutodesk,Inc. v202O Hyd. No. Hydrograph type (origin) Peak flow (cfs) Time interval (min) Time to Peak (min) Hyd. volume (cuft) Inflow hyd(s) Maximum elevation (ft) Total strge used (cuft) Hydrograph Description 2 SCS Runoff 81.22 2 720 213,954 ------ ------ ------ Area to SCM 1 3 Reservoir 54.05 2 726 209,910 2 1007.40 81,308 Route SCM-1 5 SCS Runoff 196.26 2 720 510,337 ------ ------ ------ Area to SCM 2 6 Reservoir 108.34 2 728 488,695 5 1002.57 206,590 Route SCM-2 18-161-SCM Routing_WET PONDS.gpw Return Period: 100 Year Tuesday, 11 / 26 / 2019 15 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 11 / 26 / 2019 Hyd. No. 2 Area to SCM 1 Hydrograph type = SCS Runoff Peak discharge = 81.22 cfs Storm frequency = 100 yrs Time to peak = 720 min Time interval = 2 min Hyd. volume = 213,954 cuft Drainage area = 10.000 ac Curve number = 78* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 11.50 min Total precip. = 8.35 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 * Composite (Area/CN) = [(4.520 x 98) + (5.480 x 61)] / 10.000 Q (cfs) 90.00 80.00 70.00 60.00 50.00 40.00 30.00 20.00 Area to SCM 1 Hyd. No. 2 -- 100 Year 1 1 �1 •1 �:1 •11 1 :�1 •.1 1:1 11 1 ��1 •1 Q (cfs) 90.00 80.00 70.00 60.00 50.00 40.00 30.00 20.00 16 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 11 / 26 / 2019 Hyd. No. 3 Route SCM-1 Hydrograph type = Reservoir Peak discharge = 54.05 cfs Storm frequency = 100 yrs Time to peak = 726 min Time interval = 2 min Hyd. volume = 209,910 cuft Inflow hyd. No. = 2 - Area to SCM 1 Max. Elevation = 1007.40 ft Reservoir name = SCM-1 Max. Storage = 81,308 cuft Storage Indication method used. Q (cfs) 90.00 80.00 70.00 60.00 50.00 40.00 30.00 20.00 Route SCM-1 Hyd. No. 3 -- 100 Year Q (cfs) 90.00 80.00 70.00 60.00 50.00 40.00 30.00 20.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Time (min) — Hyd No. 3 — Hyd No. 2 Total storage used = 81,308 cult 17 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 11 / 26 / 2019 Hyd. No. 5 Area to SCM 2 Hydrograph type = SCS Runoff Peak discharge = 196.26 cfs Storm frequency = 100 yrs Time to peak = 720 min Time interval = 2 min Hyd. volume = 510,337 cuft Drainage area = 27.250 ac Curve number = 72* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 11.50 min Total precip. = 8.35 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 * Composite (Area/CN) = [(8.160 x 98) + (19.090 x 61)] / 27.250 Q (cfs) 210.00 180.00 150.00 120.00 Q (cfs) 210.00 180.00 150.00 120.00 30.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 — Hyd No. 5 Time (min) Hydrograph Report 18 Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Tuesday, 11 / 26 / 2019 Hyd. No. 6 Route SCM-2 Hydrograph type = Reservoir Peak discharge = 108.34 cfs Storm frequency = 100 yrs Time to peak = 728 min Time interval = 2 min Hyd. volume = 488,695 cuft Inflow hyd. No. = 5 - Area to SCM 2 Max. Elevation = 1002.57 ft Reservoir name = SCM-2 Max. Storage = 206,590 cuft Storage Indication method used Q (cfs) 210.00 180.00 150.00 120.00 Route SCM-2 Hyd. No. 6 -- 100 Year Q (cfs) 210.00 180.00 150.00 120.00 30.00 0.00 1 1 1 1 1 1 10.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 1680 Time (min) — Hyd No. 6 — Hyd No. 5 Total storage used = 206,590 cult 19 Hydraflow Rainfall Report Hydraflow Hydrographs Extension for Autodesk0 Civil 3DO 2019 by Autodesk, Inc. v2020 Tuesday, 11 / 26 / 2019 Return Period Intensity -Duration -Frequency Equation Coefficients (FHA) (Yrs) B D E (N/A) 1 59.3109 12.3000 0.8785 -------- 2 73.7368 13.1000 0.8868 -------- 3 0.0000 0.0000 0.0000 -------- 5 72.9920 12.9000 0.8387 -------- 10 70.3899 12.3000 0.7992 -------- 25 62.7327 11.1000 0.7421 -------- 50 56.2148 10.1000 0.6951 -------- 100 50.6364 9.0000 0.6529 -------- File name: Raleigh 2,5,10,25,50,100.idf Intensity = B / (Tc + D)^E Return Period Intensity Values (in/hr) (Yrs) 6 min 10 16 20 26 30 36 40 46 60 66 60 1 4.85 3.88 3.25 2.80 2.47 2.21 2.00 1.83 1.69 1.57 1.47 1.38 2 5.65 4.56 3.83 3.31 2.92 2.62 2.38 2.18 2.01 1.87 1.75 1.64 3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5 6.49 5.28 4.48 3.90 3.46 3.12 2.84 2.62 2.43 2.26 2.12 2.00 10 7.21 5.89 5.01 4.38 3.90 3.53 3.23 2.98 2.77 2.59 2.44 2.30 25 7.98 6.53 5.57 4.89 4.38 3.98 3.65 3.39 3.16 2.97 2.80 2.65 50 8.52 6.98 5.98 5.27 4.74 4.32 3.98 3.70 3.46 3.26 3.08 2.93 100 9.04 7.40 6.36 5.62 5.06 4.63 4.28 3.99 3.74 3.53 3.35 3.19 Tc = time in minutes. Values may exceed 60. Precip. file name: Sample.pcp Storm Rainfall Precipitation Table (in) Distribution 1-yr 2-yr 3-yr 6-yr 10-yr 26-yr 60-yr 100-yr SCS 24-hour 3.20 4.68 0.00 3.30 5.59 9.14 9.01 8.35 SCS 6-Hr 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Huff-1 st 0.00 0.00 0.00 2.75 0.00 0.00 0.00 0.00 Huff-2nd 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Huff-3rd 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Huff-4th 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Huff-Indy 0.00 0.00 0.00 2.75 0.00 0.00 0.00 0.00 Custom 0.00 0.00 0.00 2.80 0.00 0.00 0.00 0.00 Stormwater Network DATE 5/14/2019 DESIGN PHASE PRELIM CONSTR / X REVISION /TION RECORD OTHER rPROJE!CTNAME Spindale Middle School PROJECT NO 18-161 Rutherfordton, NC BY HLB CHECKED BY KL (SPECIFY) n= 0.013 g= 149 h= 15 1= 7.45 STORM DRAINAGE SCHEDULE CONTINUED INLET AREA (SF) INLET AREA (AC) IMPERVIOUS (ON INLET Cc RUNOFF COEFF. INLET DISCHARGE (CFS) TOTAL AREAS (AC) INLET TIME (MIN) PIPE TIME (MIN) Tc TIME OF CONC. (MIN) I INTENSITY (IN/HR) Cc RUNOFF COEFF. FROM TO Al A2 293,710 6.74 0 0.30 0.00 6.74 5.00 0.00 5.00 7.45 0.30 A2 A3 2,660 0.06 30 0.50 0.23 6.80 5.00 0.01 5.01 7.44 0.30 A3 A4 700 0.02 100 0.95 0.11 6.82 5.00 0.03 5.03 7.44 0.30 A4 A5 10,890 0.25 90 0.89 1.65 7.07 5.00 0.63 5.63 7.22 0.32 A5 A6 11,080 0.25 90 0.89 1.68 7.32 5.00 0.78 5.78 7.17 0.34 A6 A7 10,540 0.24 90 0.89 1.60 7.57 5.00 0.92 5.92 7.12 0.36 A7 A8 18,980 0.44 90 0.89 2.87 8.00 5.00 1.10 6.10 7.06 0.39 A8 A9 36,060 0.83 50 0.63 3.85 8.83 5.00 1.26 6.26 7.01 0.41 A9 A10 13,430 0.31 40 0.56 1.29 9.14 5.00 1.54 6.54 6.92 0.42 A10 All 10,830 0.25 30 0.50 0.92 9.39 5.00 1.67 6.67 6.88 0.42 All Al2 37,240 0.85 100 0.95 6.05 10.24 5.00 1.70 6.70 6.87 0.46 Al2 A13 17,570 0.40 30 0.50 1.49 10.64 5.00 1.87 6.87 6.81 0.46 A13 A14 30,250 0.69 50 0.63 3.23 11.34 5.00 2.07 7.07 6.75 0.47 A14 A27 31,330 0.72 40 0.56 3.00 12.06 5.00 2.28 7.28 6.69 0.48 A40 A4 50,740 1.16 20 0.43 0.00 1.16 5.00 0.00 5.00 7.45 0.43 A70 A71 25,220 0.58 60 0.69 0.00 0.58 5.00 0.00 5.00 7.45 0.69 A71 A7 6,400 0.15 90 0.89 0.97 0.73 5.00 0.14 5.14 7.40 0.73 A710 A711 20,390 0.47 60 0.69 0.00 0.47 5.00 0.00 5.00 7.45 0.69 A711 A71 15,150 0.35 70 0.76 1.96 0.82 5.00 0.08 5.08 7.42 0.72 A80 A81 19,960 0.46 80 0.82 0.00 0.46 5.00 0.00 5.00 7.45 0.82 A81 A8 12,970 0.30 60 0.69 1.53 0.76 5.00 0.12 5.12 7.41 0.77 A90 A9 16,120 0.37 80 0.82 0.00 0.37 5.00 0.00 5.00 7.45 0.82 A120 A121 1 5,620 1 0.13 100 0.95 0.00 0.13 5.00 0.00 5.00 7.45 0.95 18-161-STRM-I-INVERTS.XLSSTORM Page 1 of 28 (J • ' ' ' - ' ' ' ' ' = DATE 5/14/2019 DESIGN PHASE PRELIM CONSTR / X / REVISION RECORD OTHER (SPECIFY) PROJECT NAME Rutherfordton Spindale Middle School PROJECT NO 18-161 LOCATION Rutherfordton, NC BY IHLB CHECKED BY KL n= 0.013 g= 149 h= 15 1= 7.45 STORM DRAINAGE SCHEDULE - CONTINUED Q DISCHARGE (CFS) Q SIDE- STREAM (CFS) SLOPE DIA. (IN) CAPACITY (FULL) (CFS) V FULL (FPS) LENGTH (FT) SEGMENT TIME (MIN) UPPER INV. (FT) LOWER INV. (FT) UPSTREAM TOP ELEV. (FT) PIPE COVER (FT) FROM TO Al A2 15.07 0.00 0.0933 18 32.1 18.1 15 0.01 1040.50 1039.10 1043.75 1.61 A2 A3 15.28 0.00 0.1444 24 86.0 27.3 27 0.02 1039.00 1035.10 1043.75 2.57 A3 A4 15.39 0.00 0.0103 24 23.0 7.3 262 0.60 1035.00 1032.30 1043.50 6.32 A4 A5 20.27 3.73 0.0110 30 43.0 8.7 82 0.16 1032.20 1031.30 1038.10 3.17 A5 A6 21.76 0.00 0.0383 30 80.3 16.3 133 0.14 1031.20 1026.10 1037.50 3.57 A6 A7 23.17 0.00 0.0106 30 42.3 8.6 94 0.18 1026.00 1025.00 1036.05 7.32 A7 A8 33.98 8.26 0.0101 30 41.3 8.4 79 0.16 1024.90 1024.10 1030.90 3.27 A8 A9 41.75 4.30 0.0101 36 66.9 9.5 159 0.28 1024.00 1022.40 1029.00 1.73 A9 A10 44.88 2.26 0.0107 36 68.9 9.7 75 0.13 1022.30 1021.50 1032.50 6.93 A10 A11 45.57 0.00 0.0192 36 92.5 13.1 26 0.03 1021.40 1020.90 1031.75 7.08 A11 Al2 51.10 0.00 0.0177 36 88.8 12.6 124 0.16 1020.80 1018.60 1031.75 7.68 Al2 A13 54.92 2.71 0.0309 36 117.3 16.6 207 0.21 1018.50 1012.10 1031.20 9.43 A13 A14 57.53 0.00 0.0305 36 116.5 16.5 200 0.20 1012.00 1005.90 1026.50 11.23 A14 A27 62.69 2.79 0.0051 36 47.7 6.7 176 0.44 1005.80 1004.90 1022.55 13.48 A40 A4 3.73 0.00 0.0138 15 7.6 6.2 29 0.08 1034.00 1033.60 1038.10 2.74 A70 A71 2.98 0.00 0.0426 15 13.3 10.8 94 0.14 1030.00 1026.00 1034.95 3.59 A71 A7 8.26 4.34 0.0101 18 10.6 6.0 89 0.25 1025.90 1025.00 1032.50 4.96 A710 A711 2.41 0.00 0.0111 15 6.8 5.5 27 0.08 1028.40 1028.10 1032.25 2.49 A711 A71 4.34 0.00 0.0870 15 19.0 15.5 23 0.02 1028.00 1026.00 1032.00 2.64 A80 A81 2.80 0.00 0.0105 15 6.6 5.4 38 0.12 1026.30 1025.90 1030.10 2.44 A81 A8 4.30 0.00 0.0304 15 11.3 9.2 56 0.10 1025.80 1024.10 1029.90 2.74 A90 A9 2.26 0.00 0.0121 15 7.1 5.8 33 0.10 1026.60 1026.20 1030.50 2.54 A120 A121 0.91 0.00 0.0172 15 8.5 6.9 29 0.07 1026.00 1025.50 1029.75 1 2.39 18-161-STRM-I-INVERTS.XLSSTORM Page 2 of 28 (J • ' - ■ ' = DATE 5/14/2019 DESIGN PHASE PRELIM CONSTR / X / REVISION / / RECORD OTHER PROJECT NAME Rutherfordton Spindale Middle School PROJECT NO 18-161 LOCATION Rutherfordton, NC BY HLB CHECKED BY KL (SPECIFY) n= 0.013 g= 149 h= 15 1= 7.45 HYDRAULIC GRADE LINE CONTINUED BEND LOSS K's 90' = 0.70 70° = 0.61 50' = 0.47 30' = 0.28 20° = 0.16 80' = 0.66 60' = 0.55 40' = 0.38 25' = 0.22 15° = 0.10 PIPE HYDRAULIC SIDESTREAM HEAD LOSS BEND FRICTION FRICTION AREA RADIUS SUMMATION Hf He He Hb Ht LOSS SLOPE VELOCITY (FT) (FT) (CFS) K (FT/FT) (FPS) FROM TO Al A2 1.7671 0.3750 0.00 0.31 0.28 0.00 0.00 0.59 0.00 0.0205 8.49 A2 A3 3.1416 0.5000 0.00 0.12 0.09 0.39 0.00 0.61 0.00 0.0045 4.84 A3 A4 3.1416 0.5000 0.00 1.20 0.09 0.13 0.04 1.46 0.10 0.0046 4.87 A4 A5 4.9087 0.6250 3.73 0.20 0.07 0.13 0.24 0.64 0.66 0.0024 4.10 A5 A6 4.9087 0.6250 3.73 0.37 0.08 0.09 0.17 0.71 0.66 0.0028 4.41 A6 A7 4.9087 0.6250 3.73 0.30 0.09 0.11 0.11 0.60 0.38 0.0032 4.69 A7 A8 4.9087 0.6250 11.99 0.54 0.18 0.12 0.05 0.90 0.16 0.0068 6.88 A8 A9 7.0686 0.7500 16.30 0.62 0.13 0.26 0.51 1.52 0.70 0.0039 5.87 A9 A10 7.0686 0.7500 18.56 0.34 0.15 0.19 0.05 0.73 0.10 0.0045 6.31 A10 All 7.0686 0.7500 18.56 0.12 0.16 0.22 0.43 0.93 0.70 0.0046 6.40 All Al2 7.0686 0.7500 18.56 0.72 0.20 0.22 0.06 1.21 0.10 0.0058 7.18 Al2 A13 7.0686 0.7500 21.26 1.39 0.23 0.28 0.08 1.98 0.10 0.0067 7.72 A13 A14 7.0686 0.7500 21.26 1.47 0.25 0.32 0.00 2.05 0.00 0.0074 8.09 A14 A27 7.0686 0.7500 24.06 1.54 0.30 0.36 0.71 2.91 0.70 0.0087 8.81 A40 A4 1.2272 0.3125 0.00 0.10 0.04 0.00 0.00 0.13 0.00 0.0033 3.03 A70 A71 1.2272 0.3125 0.00 0.20 0.02 0.00 0.00 0.22 0.00 0.0021 2.42 A71 A7 1.7671 0.3750 4.34 0.55 0.08 0.03 0.01 0.67 0.10 0.0061 4.66 A710 A711 1.2272 0.3125 0.00 0.04 0.01 0.00 0.00 0.05 0.00 0.0014 1.95 A711 A71 1.2272 0.3125 0.00 0.10 0.05 0.02 0.04 0.21 0.70 0.0045 3.53 A80 A81 1.2272 0.3125 0.00 0.07 0.02 0.00 0.00 0.09 0.00 0.0019 2.27 A81 A8 1.2272 0.3125 0.00 0.25 0.05 0.03 0.06 0.38 0.70 0.0044 3.49 A90 A9 1.2272 0.3125 0.00 0.04 0.01 0.00 0.00 0.05 0.00 0.0012 1.84 A120 A121 1.2272 0.3125 0.00 0.01 0.00 0.00 0.00 0.01 0.00 0.0002 0.74 18-161-STRM-I-INVERTS.XLSSTORM Page 3 of 28 (J • ' ' ' ' ' = DATE 5/14/2019 DESIGN PHASE PRELIM CONSTR / X / REVISION / / RECORD IOTHER PROJECT NAME Rutherfordton Spindale Middle School PROJECT NO 18-161 LOCATION Rutherfordton, NC BY HLB CHECKED BY KL (SPECIFY) n= 0.013 g= 149 h= 15 1= 7.45 HYDRAULIC GRADE LINE - CONTINUED DESIGN CRITERIA: 1. DESIGN FOR THE 10 YR STORM 2. ASSUME TIME OF CONCENTRATION TO AN INDIVIDUAL INLET = 5 MIN. 3. INTENSITY = g/(h+T), FOR 10 YR STORM 4. MANNINGS "n" FACTOR= .013 5. RATIONAL METHOD: C= .30 GRASS, C= .95 PAVEMENT OUTLET W.S. ELEV (FT) INLET W.S.ELEV. FLOW CONDITION CONTROL FREE- BOARD (FT) UPSTREAM INLET TYPE COMMENTS FROM TO OUTLET CONTOL (FT) INLET CONTROL (FT) USE (FT) Al A2 1041.02 1041.61 1044.39 1044.39 INLET (0.64) FES OVERFLOW A2 A3 1037.03 1037.64 1041.02 1041.02 INLET 2.23 CB OK A3 A4 1034.19 1035.64 1037.03 1037.03 INLET 5.97 CB OK A4 A5 1033.30 1033.93 1034.19 1034.19 INLET 3.41 CB OK A5 A6 1029.23 1029.94 1033.30 1033.30 INLET 3.70 CB OK A6 A7 1028.63 1029.23 1028.21 1029.23 OUTLET 6.32 CB OK A7 A8 1027.74 1028.63 1028.22 1028.63 OUTLET 1.77 CB OK A8 A9 1026.21 1027.74 1027.00 1027.74 OUTLET 0.76 CB OK A9 A10 1025.48 1026.21 1025.54 1026.21 OUTLET 5.79 CB OK A10 All 1024.55 1025.48 1024.69 1025.48 OUTLET 5.77 CB OK All Al2 1022.60 1023.81 1024.55 1024.55 INLET 6.70 CB OK Al2 A13 1020.23 1022.21 1022.60 1022.60 INLET 8.60 DI OK A13 A14 1018.18 1020.23 1016.36 1020.23 OUTLET 6.27 DI OK A14 A27 1015.27 1018.18 4.89 1018.18 OUTLET 4.37 DI OK Tailwater Elev= 1015.27 A40 A4 1037.03 1037.17 1 1035.02 1037.17 OUTLET 0.43 CB OK Tailwater Elev= 1037.03 A70 A71 1029.23 1029.45 1030.88 1030.88 INLET 3.57 CB OK A71 A7 1029.23 1029.91 1027.59 1029.91 OUTLET 2.09 CB OK Tailwater Elev= 1029.23 A710 A711 1030.88 1030.93 1029.19 1030.93 OUTLET 0.82 CB OK A711 A71 1030.88 1031.09 1029.17 1031.09 OUTLET 0.41 CB OK Tailwater Elev= 1030.88 A80 A81 1029.01 1029.10 1027.15 1029.10 OUTLET 1.00 DI OK A81 A8 1028.63 1029.01 1026.96 1029.01 OUTLET 0.89 DI OK Tailwater Elev= 1028.63 A90 A9 1027.74 1027.79 1 1027.37 1027.79 OUTLET 2.21 CB OK Tailwater Elev= 1027.74 A120 A121 1026.12 1026.12 1 1026.65 1026.65 INLET 2.60 CB OK 18-161-STRM-I-INVERTS.XLSSTORM Page 4 of 28 DATE 5/14/2019 DESIGN PHASE PRELIM CONSTR / X REVISION /TION RECORD OTHER rPROJE!CTNAME Spindale Middle School PROJECT NO 18-161 Rutherfordton, NC BY HLB CHECKED BY KL (SPECIFY) n= 0.013 g= 149 h= 15 1= 7.45 STORM DRAINAGE SCHEDULE CONTINUED INLET AREA (SF) INLET AREA (AC) IMPERVIOUS (ON INLET Cc RUNOFF COEFF. INLET DISCHARGE (CFS) TOTAL AREAS (AC) INLET TIME (MIN) PIPE TIME (MIN) Tc TIME OF CONC. (MIN) I INTENSITY (IN/HR) Cc RUNOFF COEFF. FROM TO A121 A122 5,840 0.13 90 0.89 0.88 0.26 5.00 0.07 5.07 7.42 0.92 A122 Al2 18,040 0.41 0 0.30 0.93 0.68 5.00 0.12 5.12 7.40 0.54 A16 A17 4,530 0.10 100 0.95 0.00 0.10 5.00 0.00 5.00 7.45 0.95 A17 A18 24,310 0.56 70 0.76 3.14 0.66 5.00 0.27 5.27 7.35 0.79 A18 A19 40,900 0.94 90 0.89 6.19 1.60 5.00 0.67 5.67 7.21 0.84 A19 A20 28,560 0.66 90 0.89 4.32 2.26 5.00 0.90 5.90 7.13 0.86 A20 A21 27,180 0.62 70 0.76 3.51 2.88 5.00 1.09 6.09 7.06 0.83 A21 A22 12,750 0.29 10 0.37 0.80 3.17 5.00 1.13 6.13 7.05 0.79 A22 A23 0 0.00 0 0.30 0.00 3.17 5.00 1.19 6.19 7.03 0.79 A23 A24 7,480 0.17 95 0.92 1.17 3.35 5.00 1.28 6.28 7.00 0.80 A24 A25 8,330 0.19 90 0.89 1.26 3.54 5.00 1.42 6.42 6.96 0.80 A25 A26 17,650 0.41 10 0.37 1.10 3.94 5.00 1.61 6.61 6.89 0.76 A26 A27 33,470 0.77 50 0.63 3.58 4.71 5.00 1.87 6.87 6.81 0.74 A27 A15 0 0.00 0 0.30 0.00 4.71 5.00 2.09 7.09 6.75 0.74 A140 A14 18,450 0.42 90 0.89 0.00 0.42 5.00 0.00 5.00 7.45 0.89 A171 A17 57,370 1.32 0 0.30 0.00 1.32 5.00 0.00 5.00 7.45 0.30 A170 A17 15,470 0.36 30 0.50 0.00 0.36 5.00 0.00 5.00 7.45 0.50 A250 A251 21,750 0.50 70 0.76 0.00 0.50 5.00 0.00 5.00 7.45 0.76 A251 A25 4,750 0.11 100 0.95 0.77 0.61 5.00 0.32 5.32 7.33 0.79 A260 A261 17,590 0.40 80 0.82 0.00 0.40 5.00 0.00 5.00 7.45 0.82 A261 A26 14,510 0.33 80 0.82 2.03 0.74 5.00 0.34 5.34 7.32 0.82 18-161-STRM-I-INVERTS.XLSSTORM Page 5 of 28 (J • ' ' ' - ' ' ' ' ' = DATE 5/14/2019 DESIGN PHASE PRELIM CONSTR / X / REVISION RECORD OTHER (SPECIFY) PROJECT NAME Rutherfordton Spindale Middle School PROJECT NO 18-161 LOCATION Rutherfordton, NC BY IHLB CHECKED BY KL n= 0.013 g= 149 h= 15 1= 7.45 STORM DRAINAGE SCHEDULE - CONTINUED Q DISCHARGE (CFS) Q SIDE- STREAM (CFS) SLOPE DIA. (IN) CAPACITY (FULL) (CFS) V FULL (FPS) LENGTH (FT) SEGMENT TIME (MIN) UPPER INV. (FT) LOWER INV. (FT) UPSTREAM TOP ELEV. (FT) PIPE COVER (FT) FROM TO A121 A122 1.79 0.00 0.0182 15 8.7 7.1 22 0.05 1025.40 1025.00 1030.00 3.24 A122 Al2 2.71 0.00 0.0175 15 8.5 6.9 361 0.87 1024.90 1018.60 1029.75 3.49 A16 A17 4.99 4.25 0.0055 15 4.8 3.9 64 0.27 1024.65 1024.30 1028.45 2.44 A17 A18 8.08 0.00 0.0103 24 22.9 7.3 175 0.40 1024.20 1022.40 1030.30 3.92 A18 A19 13.99 0.00 0.0103 24 23.0 7.3 97 0.22 1022.30 1021.30 1030.45 5.97 A19 A20 18.03 0.00 0.0096 24 22.2 7.1 83 0.20 1021.20 1020.40 1029.20 5.82 A20 A21 21.23 0.00 0.0105 24 23.2 7.4 19 0.04 1020.30 1020.10 1026.50 4.02 A21 A22 21.94 0.00 0.0111 24 23.8 7.6 27 0.06 1013.50 1013.20 1025.60 9.92 A22 A23 21.89 0.00 0.0111 30 43.2 8.8 45 0.09 1013.10 1012.60 1026.85 11.02 A23 A24 22.93 0.00 0.0100 30 41.0 8.3 70 0.14 1012.50 1011.80 1025.95 10.72 A24 A25 23.98 0.00 0.0102 30 41.4 8.4 98 0.19 1011.70 1010.70 1025.95 11.52 A25 A26 28.35 3.52 0.0105 30 42.1 8.6 133 0.26 1010.60 1009.20 1026.00 12.67 A26 A27 35.80 4.43 0.0104 36 68.0 9.6 125 0.22 1009.10 1007.80 1023.50 11.13 A27 A15 98.26 62.69 0.0485 36 146.8 20.7 130 0.10 1004.80 998.50 1025.50 17.43 A140 A14 2.79 0.00 0.0909 15 19.5 15.9 66 0.07 1024.50 1018.50 1031.50 5.64 A171 A17 2.94 0.00 0.0547 15 15.1 12.3 137 0.19 1031.80 1024.30 1035.25 2.09 A170 A17 1.31 0.00 0.0500 15 14.4 11.8 48 0.07 1026.70 1024.30 1030.10 2.04 A250 A251 2.81 0.00 0.0107 15 6.7 5.4 103 0.32 1028.50 1027.40 1031.90 2.04 A251 A25 3.52 0.00 0.0950 15 19.9 16.2 119 0.12 1027.30 1016.00 1031.75 3.09 A260 A261 2.47 0.00 0.0101 15 6.5 5.3 109 0.34 1028.70 1027.60 1032.15 2.09 A261 A26 4.43 0.00 0.0966 15 20.1 16.3 119 0.12 1027.50 1016.00 1032.15 3.29 18-161-STRM-I-INVERTS.XLSSTORM Page 6 of 28 (J • ' - ■ ' = DATE 5/14/2019 DESIGN PHASE PRELIM CONSTR / X / REVISION / / RECORD OTHER PROJECT NAME Rutherfordton Spindale Middle School PROJECT NO 18-161 LOCATION Rutherfordton, NC BY HLB CHECKED BY KL (SPECIFY) n= 0.013 g= 149 h= 15 1= 7.45 HYDRAULIC GRADE LINE CONTINUED BEND LOSS K's 90' = 0.70 70° = 0.61 50' = 0.47 30' = 0.28 20° = 0.16 80' = 0.66 60' = 0.55 40' = 0.38 25' = 0.22 15° = 0.10 PIPE HYDRAULIC SIDESTREAM HEAD LOSS BEND FRICTION FRICTION AREA RADIUS SUMMATION Hf He He Hb Ht LOSS SLOPE VELOCITY (FT) (FT) (CFS) K (FT/FT) (FPS) FROM TO A121 A122 1.2272 0.3125 0.00 0.02 0.01 0.00 0.00 0.03 0.42 0.0008 1.45 A122 Al2 1.2272 0.3125 0.00 0.63 0.02 0.01 0.00 0.66 0.00 0.0017 2.20 A16 A17 1.2272 0.3125 4.25 0.38 0.06 0.00 0.00 0.44 0.00 0.0059 4.05 A17 A18 3.1416 0.5000 4.25 0.22 0.03 0.09 0.18 0.51 0.70 0.0013 2.56 A18 A19 3.1416 0.5000 4.25 0.37 0.08 0.04 0.00 0.48 0.00 0.0038 4.43 A19 A20 3.1416 0.5000 4.25 0.52 0.13 0.11 0.07 0.82 0.22 0.0063 5.71 A20 A21 3.1416 0.5000 4.25 0.17 0.18 0.18 0.35 0.87 0.70 0.0087 6.72 A21 A22 3.1416 0.5000 4.25 0.25 0.19 0.25 0.28 0.97 0.40 0.0093 6.95 A22 A23 4.9087 0.6250 4.25 0.13 0.08 0.26 0.30 0.77 0.40 0.0028 4.43 A23 A24 4.9087 0.6250 4.25 0.22 0.08 0.11 0.21 0.62 0.70 0.0031 4.64 A24 A25 4.9087 0.6250 4.25 0.33 0.09 0.12 0.13 0.67 0.40 0.0034 4.86 A25 A26 4.9087 0.6250 7.78 0.63 0.13 0.13 0.00 0.89 0.00 0.0047 5.74 A26 A27 7.0686 0.7500 12.20 0.36 0.10 0.18 0.00 0.63 0.00 0.0029 5.03 A27 A15 7.0686 0.7500 74.90 2.79 0.74 0.14 0.28 3.95 0.70 0.0215 13.81 A140 A14 1.2272 0.3125 0.00 0.12 0.02 0.00 0.00 0.14 0.00 0.0019 2.27 0.03 A171 A17 1.2272 0.3125 0.00 0.28 0.02 0.00 0.00 0.31 0.00 0.0021 2.39 0.03 A170 A17 1.2272 0.3125 0.00 0.02 0.00 0.00 0.00 0.02 0.00 0.0004 1.06 A250 A251 1.2272 0.3125 0.00 0.19 0.02 0.00 0.00 0.21 0.00 0.0019 2.28 A251 A25 1.2272 0.3125 0.00 0.35 0.03 0.03 0.00 0.41 0.00 0.0030 2.86 0.04 A260 A261 1.2272 0.3125 0.00 0.16 0.02 0.00 0.00 0.17 0.00 0.0015 2.00 A261 A26 1.2272 0.3125 0.00 0.56 0.05 0.02 0.00 0.63 0.00 0.0047 3.59 18-161-STRM-I-INVERTS.XLSSTORM Page 7 of 28 (J • ' ' ' = DATE 5/14/2019 DESIGN PHASE PRELIM CONSTR / X / REVISION / / RECORD IOTHER PROJECT NAME Rutherfordton Spindale Middle School PROJECT NO 18-161 LOCATION Rutherfordton, NC BY HLB CHECKED BY KL (SPECIFY) n= 0.013 g= 149 h= 15 1= 7.45 HYDRAULIC GRADE LINE - CONTINUED DESIGN CRITERIA: 1. DESIGN FOR THE 10 YR STORM 2. ASSUME TIME OF CONCENTRATION TO AN INDIVIDUAL INLET = 5 MIN. 3. INTENSITY = g/(h+T), FOR 10 YR STORM 4. MANNINGS "n" FACTOR= .013 5. RATIONAL METHOD: C= .30 GRASS, C= .95 PAVEMENT OUTLET W.S. ELEV (FT) INLET W.S.ELEV. FLOW CONDITION CONTROL FREE- BOARD (FT) UPSTREAM INLET TYPE COMMENTS FROM TO OUTLET CONTOL (FT) INLET CONTROL (FT) USE (FT) A121 A122 1025.48 1025.51 1026.12 1026.12 INLET 3.38 CB OK A122 Al2 1018.60 1019.26 1025.73 1025.73 INLET 4.02 DI OK Tailwater Elev= 1025.48 A16 A17 1025.49 1025.93 1025.99 1025.99 INLET 2.46 DI OK A17 A18 1024.57 1025.09 1025.49 1025.49 INLET 4.81 DI OK A18 A19 1024.09 1024.57 1024.16 1024.57 OUTLET 5.38 CB OK A19 A20 1023.27 1024.09 1023.62 1024.09 OUTLET 4.61 CB OK A20 A21 1020.10 1020.97 1023.27 1023.27 INLET 2.73 CB OK A21 A22 1018.22 1019.18 1016.60 1019.18 OUTLET 6.42 DI OK A22 A23 1017.45 1018.22 1015.21 1018.22 OUTLET 8.13 CB OK A23 A24 1016.83 1017.45 1014.69 1017.45 OUTLET 8.00 CB OK A24 A25 1016.15 1016.83 1013.98 1016.83 OUTLET 8.62 CB OK A25 A26 1015.27 1016.15 1013.29 1016.15 OUTLET 9.85 DI OK A26 A27 1014.64 1015.27 1011.71 1015.27 OUTLET 8.23 DI OK A27 A15 1000.90 1004.85 1014.64 1014.64 INLET 10.86 DI OK Tailwater Elev= 1000.90 A140 A14 1020.23 1020.37 1 1025.35 1025.35 INLET 6.15 DI OK Tailwater Elev= 1020.23 A171 A17 1025.99 1026.29 1 1032.67 1032.67 INLET 2.58 DI OK Tailwater Elev= 1025.99 A170 A17 1025.99 1026.01 1 1027.37 1027.37 INLET 2.73 DI OK Tailwater Elev= 1025.99 A250 A251 1028.28 1028.49 1029.35 1029.35 INLET 2.55 DI OK A251 A25 1016.83 1017.24 1028.28 1028.28 INLET 3.47 DI OK Tailwater Elev= 1016.83 A260 A261 1028.69 1028.86 1029.50 1029.50 INLET 2.65 DI OK A261 A26 1016.15 1016.78 1028.69 1028.69 INLET 3.46 DI OK 18-161-STRM-I-INVERTS.XLSSTORM Page 8 of 28 DATE 5/14/2019 DESIGN PHASE PRELIM CONSTR / X REVISION /TION RECORD OTHER rPROJE!CTNAME Spindale Middle School PROJECT NO 18-161 Rutherfordton, NC BY HLB CHECKED BY KL (SPECIFY) n= 0.013 g= 149 h= 15 1= 7.45 STORM DRAINAGE SCHEDULE CONTINUED INLET AREA (SF) INLET AREA (AC) IMPERVIOUS (ON INLET Cc RUNOFF COEFF. INLET DISCHARGE (CFS) TOTAL AREAS (AC) INLET TIME (MIN) PIPE TIME (MIN) Tc TIME OF CONC. (MIN) I INTENSITY (IN/HR) Cc RUNOFF COEFF. FROM TO B4 B5 8,560 0.20 95 0.92 1.34 5.44 5.00 0.32 5.32 7.33 0.46 B5 B6 3,640 0.08 95 0.92 0.57 5.53 5.00 0.55 5.55 7.25 0.47 B6 B7 1,200 0.03 95 0.92 0.19 5.56 5.00 0.69 5.69 7.20 0.47 B7 137A 18,170 0.42 40 0.56 1.74 5.97 5.00 0.86 5.86 7.14 0.48 B7A B8 18,170 0.42 40 0.56 1.74 6.39 5.00 1.10 6.10 7.06 0.49 B8 B9 18,170 0.42 40 0.56 1.74 6.81 5.00 1.34 6.34 6.98 0.49 B9 B10 0 0.00 0 0.30 0.00 6.81 5.00 1.47 6.47 6.94 0.49 B40 B41 85,270 1.96 0 0.30 0.00 1.96 5.00 0.00 5.00 7.45 0.30 B41 B4 14,210 0.33 75 0.79 1.91 2.28 5.00 0.02 5.02 7.44 0.37 B50 B51 3,280 0.08 0 0.30 0.00 0.08 5.00 0.00 5.00 7.45 0.30 B51 B5 4,620 0.11 0 0.30 0.24 0.18 5.00 0.06 5.06 7.43 0.30 B60 B61 10,020 0.23 95 0.92 0.00 0.23 5.00 0.00 5.00 7.45 0.92 B61 B6 10,800 0.25 60 0.69 1.27 0.48 5.00 0.21 5.21 7.37 0.80 B62 B63 5,290 0.12 95 0.92 0.00 0.12 5.00 0.00 5.00 7.45 0.92 B63 B6 37,400 0.86 10 0.37 2.33 0.98 5.00 0.03 5.03 7.44 0.43 B70 B71 5,480 0.13 0 0.30 0.00 0.13 5.00 0.00 5.00 7.45 0.30 B71 B72 26,800 0.62 40 0.56 2.57 0.74 5.00 0.25 5.25 7.36 0.52 B72 B7 28,080 0.64 30 0.50 2.38 1.39 5.00 0.82 5.82 7.16 0.51 B80 B81 24,750 0.57 30 0.50 0.00 0.57 5.00 0.00 5.00 7.45 0.50 B81 B8 28,080 0.64 30 0.50 2.38 1.21 5.00 0.57 5.57 7.24 0.50 Cl C2 46,790 1.07 0 0.30 0.00 1.07 5.00 0.00 5.00 7.45 0.30 18-161-STRM-I-INVERTS.XLSSTORM Page 9 of 28 (J • ' ' ' - ' ' ' ' ' = DATE 5/14/2019 DESIGN PHASE PRELIM CONSTR / X / REVISION RECORD OTHER (SPECIFY) PROJECT NAME Rutherfordton Spindale Middle School PROJECT NO 18-161 LOCATION Rutherfordton, NC BY IHLB CHECKED BY KL n= 0.013 g= 149 h= 15 1= 7.45 STORM DRAINAGE SCHEDULE - CONTINUED Q DISCHARGE (CFS) Q SIDE- STREAM (CFS) SLOPE DIA. (IN) CAPACITY (FULL) (CFS) V FULL (FPS) LENGTH (FT) SEGMENT TIME (MIN) UPPER INV. (FT) LOWER INV. (FT) UPSTREAM TOP ELEV. (FT) PIPE COVER (FT) FROM TO B4 B5 24.85 6.28 0.0328 24 41.0 13.0 183 0.23 1022.00 1016.00 1034.55 10.37 B5 B6 25.59 0.40 0.0110 30 42.9 8.7 73 0.14 1015.90 1015.10 1030.00 11.37 B6 B7 31.63 5.98 0.0103 30 41.7 8.5 87 0.17 1015.00 1014.10 1028.10 10.37 B7 137A 33.14 0.00 0.0106 30 42.2 8.6 123 0.24 1014.00 1012.70 1025.90 9.17 B7A B8 39.58 5.02 0.0106 30 42.2 8.6 123 0.24 1012.60 1011.30 1025.90 10.57 B8 B9 45.31 4.35 0.0221 30 61.0 12.4 95 0.13 1011.20 1009.10 1025.90 11.97 B9 B10 45.17 0.00 0.0932 30 125.2 25.5 59 0.04 1009.00 1003.50 1016.20 4.47 B40 B41 4.38 0.00 0.0789 18 29.5 16.7 19 0.02 1030.80 1029.30 1034.55 2.11 B41 B4 6.28 0.00 0.0963 18 32.6 18.4 27 0.02 1024.70 1022.10 1034.55 8.21 B50 B51 0.17 0.00 0.0686 15 16.9 13.8 51 0.06 1022.40 1018.90 1025.85 2.09 B51 B5 0.40 0.00 0.0933 15 19.7 16.1 30 0.03 1018.80 1016.00 1027.25 7.09 B60 B61 1.57 0.00 0.0104 15 6.6 5.4 67 0.21 1022.50 1021.80 1025.95 2.09 B61 B6 2.82 0.00 0.0795 15 18.2 14.8 83 0.09 1021.70 1015.10 1025.95 2.89 B62 B63 0.83 0.00 0.0111 15 6.8 5.5 9 0.03 1024.50 1024.40 1028.10 2.24 B63 B6 3.16 0.00 0.0963 15 20.0 16.3 27 0.03 1017.70 1015.10 1028.25 9.19 B70 B71 0.28 0.00 0.0110 15 6.8 5.5 82 0.25 1021.50 1020.60 1024.95 2.09 B71 B72 2.81 0.00 0.0104 15 6.6 5.4 183 0.57 1020.50 1018.60 1025.90 4.04 B72 B7 5.02 0.00 0.0240 15 10.0 8.2 183 0.37 1018.50 1014.10 1025.90 6.04 B80 B81 2.10 0.00 0.0104 15 6.6 5.4 183 0.57 1022.50 1020.60 1025.90 2.04 B81 B8 4.35 0.00 0.0503 15 14.5 11.8 183 0.26 1020.50 1011.30 1025.90 4.04 C1 C2 2.40 0.00 0.0962 15 20.0 16.3 78 0.08 1003.50 996.00 1019.60 14.74 18-161-STRM-I-INVERTS.XLSSTORM Page 10 of 28 (J • ' - ■ ' = DATE 5/14/2019 DESIGN PHASE PRELIM CONSTR / X / REVISION / / RECORD OTHER PROJECT NAME Rutherfordton Spindale Middle School PROJECT NO 18-161 LOCATION Rutherfordton, NC BY HLB CHECKED BY KL (SPECIFY) n= 0.013 g= 149 h= 15 1= 7.45 HYDRAULIC GRADE LINE CONTINUED BEND LOSS K's 90' = 0.70 70° = 0.61 50' = 0.47 30' = 0.28 20° = 0.16 80' = 0.66 60' = 0.55 40' = 0.38 25' = 0.22 15° = 0.10 PIPE HYDRAULIC SIDESTREAM HEAD LOSS BEND FRICTION FRICTION AREA RADIUS SUMMATION Hf He He Hb Ht LOSS SLOPE VELOCITY (FT) (FT) (CFS) K (FT/FT) (FPS) FROM TO 0.07 B4 B5 3.1416 0.5000 6.28 2.19 0.24 0.17 0.33 2.93 0.70 0.0120 7.87 B5 B6 4.9087 0.6250 6.69 0.28 0.10 0.34 0.00 0.72 0.00 0.0039 5.18 B6 B7 4.9087 0.6250 12.67 0.51 0.16 0.15 0.09 0.91 0.22 0.0059 6.40 B7 137A 4.9087 0.6250 12.67 0.80 0.17 0.22 0.27 1.46 0.42 0.0065 6.71 B7A B8 4.9087 0.6250 17.69 1.13 0.25 0.24 0.29 1.92 0.42 0.0092 8.01 B8 B9 4.9087 0.6250 22.03 1.15 0.33 0.35 0.42 2.24 0.42 0.0121 9.18 B9 B10 4.9087 0.6250 22.03 0.71 0.32 0.46 0.00 1.49 0.00 0.0120 9.15 B40 B41 1.7671 0.3750 0.00 0.03 0.02 0.00 0.00 0.06 0.00 0.0017 2.47 B41 B4 1.7671 0.3750 0.00 0.10 0.05 0.03 0.07 0.24 0.70 0.0036 3.54 B50 B51 1.2272 0.3125 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0000 0.14 B51 B5 1.2272 0.3125 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0000 0.33 B60 B61 1.2272 0.3125 0.00 0.04 0.01 0.12 0.00 0.16 0.00 0.0006 1.28 B61 B6 1.2272 0.3125 0.00 0.16 0.02 0.01 0.00 0.19 0.00 0.0019 2.29 B62 B63 1.2272 0.3125 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0002 0.67 B63 B6 1.2272 0.3125 0.00 0.06 0.03 0.00 0.00 0.09 0.00 0.0024 2.57 B70 B71 1.2272 0.3125 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0000 0.23 B71 B72 1.2272 0.3125 0.00 0.35 0.02 0.00 0.00 0.37 0.10 0.0019 2.28 B72 B7 1.2272 0.3125 0.00 1.10 0.06 0.03 0.06 1.25 0.70 0.0060 4.08 B80 B81 1.2272 0.3125 0.00 0.19 0.01 0.02 0.00 0.22 0.00 0.0010 1.70 B81 B8 1.2272 0.3125 0.00 0.83 0.05 0.02 0.03 0.92 0.66 0.0045 3.53 Cl C2 1.2272 0.3125 0.00 0.11 0.01 0.05 0.00 0.17 0.00 0.0014 1.95 18-161-STRM-I-INVERTS.XLSSTORM Page 11 of 28 (J • ' ' ' = DATE 5/14/2019 DESIGN PHASE PRELIM CONSTR / X / REVISION / / RECORD IOTHER PROJECT NAME Rutherfordton Spindale Middle School PROJECT NO 18-161 LOCATION Rutherfordton, NC BY HLB CHECKED BY KL (SPECIFY) n= 0.013 g= 149 h= 15 1= 7.45 HYDRAULIC GRADE LINE - CONTINUED DESIGN CRITERIA: 1. DESIGN FOR THE 10 YR STORM 2. ASSUME TIME OF CONCENTRATION TO AN INDIVIDUAL INLET = 5 MIN. 3. INTENSITY = g/(h+T), FOR 10 YR STORM 4. MANNINGS "n" FACTOR= .013 5. RATIONAL METHOD: C= .30 GRASS, C= .95 PAVEMENT OUTLET W.S. ELEV (FT) INLET W.S.ELEV. FLOW CONDITION CONTROL FREE- BOARD (FT) UPSTREAM INLET TYPE COMMENTS FROM TO OUTLET CONTOL (FT) INLET CONTROL (FT) USE (FT) 1019.68 Tailwater Elev= 1022.61 1025.70 1016.15 1025.70 INLET 8.35 CB OK B4 B5 B5 B6 1018.96 1019.68 1018.32 1019.68 OUTLET 9.82 CB OK B6 B7 1018.05 1018.96 1018.04 1018.96 OUTLET 8.64 CB OK B7 137A 1016.13 1017.59 1017.22 1017.59 OUTLET 8.31 DI OK B7A B8 1016.13 1018.05 1016.65 1018.05 OUTLET 7.85 DI OK B8 B9 1009.10 1011.34 1016.13 1016.13 INLET 9.77 DI OK B9 B10 1003.50 1004.99 1013.90 1013.90 INLET 2.30 DI OK Tailwater Elev= 1005.50 B40 B41 1033.58 1033.64 1031.81 1033.64 OUTLET 0.91 FES OK B41 B4 1033.34 1033.58 1026.00 1033.58 OUTLET 0.47 CB OK Tailwater Elev= 1033.34 B50 B51 1025.70 1025.70 1023.03 1025.70 OUTLET 0.15 DI OK B51 B5 1025.70 1025.70 1019.43 1025.70 OUTLET 1.55 DI OK Tailwater Elev= 1025.70 B60 B61 1022.55 1022.72 1023.20 1023.20 INLET 2.25 CB OK B61 B6 1018.05 1018.23 1022.55 1022.55 INLET 2.90 CB OK Tailwater Elev= 1018.05 B62 B63 1024.40 1024.40 1025.14 1025.14 INLET 2.96 DI OK B63 B6 1015.10 1015.19 1018.61 1018.61 INLET 9.14 CB OK Tailwater Elev= 1005.50 B70 B71 1021.35 1021.35 1022.13 1022.13 INLET 2.82 DI OK B71 B72 1020.93 1021.30 1021.35 1021.35 INLET 4.55 DI OK B72 B7 1019.68 1020.93 1019.85 1020.93 OUTLET 4.97 DI OK Tailwater Elev= 1019.68 B80 B81 1021.67 1021.89 1023.25 1023.25 INLET 2.65 DI OK B81 B8 1011.30 1012.22 1021.67 1021.67 INLET 4.23 DI OK Cl C2 997.00 997.17 1004.29 1004.29 INLET 15.31 FES OK 18-161-STRM-I-INVERTS.XLSSTORM Page 12 of 28 Outlet Protection •4:1 MR101 Mlo 0 101FFDATE 5/14/2019 PROJECT NAME PROJECT NO Rutherfordton Spindale Middle School 18-161 LOCATION BY Rutherfordton, NC HLB CHECKED BY KL Storm Outlet Structure FES No.= SCM1 Pipe Dia= 36 in Q10 = 7.70 cfs Qfull = 89.20 cfs Vfull = 12.60 fps From Fig. 8.06.b.1: From Fig. 8.06.b.2: Storm Outlet Structure FES No.= SCM2 Pipe Dia= 48 in Q10 = 8.70 cfs Qfull = 187.30 cfs Vfull = 14.90 fps From Fig. 8.06.b.1: From Fig. 8.06.b.2: Zone D50 DMAX Riprap Class Apron Thickness Apron Length Apron Width = 3xDia Zone D50 DMAX Riprap Class Apron Thickness Apron Length Apron Width = 3xDia Q10/Qfull = V/Vfull = V= Q10/Qfull = V/Vfull = V= DESIGN PHASE PRELIM CONSTR REVISION RECORD OTHER (SPECIFY) 0.09 0.59 7.4 fps 3 10 in 17 in 1 24 in 24 ft 9 ft 0.05 0.52 7.8 fps 3 10 in 17 in 1 24 in 32 ft 12 ft 1• ' ' • • DATE 5/14/2019 PROJECT NAME PROJECT NO Rutherfordton S indale Middle School 18-161 LOCATION BY Rutherfordton, NC HLB CHECKED BY KL Storm Outlet Structure FES No.= B10 Pipe Dia= 30 in Q10 = 45.17 cfs Qfull = 125.23 cfs Vfull = 25.48 fps From Fig. 8.06.b.1: From Fig. 8.06.b.2: Storm Outlet Structure FES No.= A15 Pipe Dia= 36 in Q10 = 98.26 cfs Qfull = 116.30 cfs Vfull = 16.40 fps From Fig. 8.06.b.1: From Fig. 8.06.b.2: Zone D50 DMAX Riprap Class Apron Thickness Apron Length Apron Width = 3xDia Zone D50 DMAX Riprap Class Apron Thickness Apron Length Apron Width = 3xDia Q10/Qfull = V/Vfull = V= Q10/Qfull = V/Vfull = V= DESIGN PHASE PRELIM CONSTR REVISION RECORD OTHER (SPECIFY) 0.36 0.91 23.2 fps 3 10 in 17 in 1 24 in 20 ft 8 ft 0.84 1.12 18.3 fps 3 10 in 17 in 1 24 in 24 ft 9 ft • ' ' • • ` DATE 43599 DESIGN PHASE PRELIM CONSTR REVISION RECORD OTHER (SPECIFY) / X / PROJECT NAME Rutherfordton S indale Middle School PROJECT NO 18-161 LOCATION Rutherfordton, NC BY HLB CHECKED BY KL Storm Outlet Structure FES No.= C2 Qio/Qfull = 0.12 Pipe Dia= 15 in V/Vfull = 0.67 Qio = 2.40 cfs V = 10.9 fps Qfull = 20.00 cfs Vfull = 16.30 fps From Fig. 8.06.b.1: Zone = 2 From Fig. 8.06.b.2 s Length D50 = 8 in DMAX = 12 in Riprap Class = B Apron Thickness = 18 in Apron Length = 8 ft Apron Width = 3xDia = 4 ft