LETTER OF APPROVAL
RE: Project Name: Catfish Pond Mitigation Site
Project ID: DURHA-2019-016
Approved Acres: 16.2
County: DURHAM, City: Bahama Address: Roxboro Road
River Basin: Neuse, Stream CIassification: Falls Lake Watershed
Submitted By: Wildlands Engineering, Inc.
Date Received by LQS: May 7, 2019
Plan Type: Revised
Dear Mr. Hutton:
The subject erosion and sedimentation control plan has been approved. The enclosed
Certificate of Approval must be posted at the job site. This plan approval shall expire three
(3) years following the date of approval, if no land -disturbing activity has been undertaken,
as is required by Title 15A NCAC 413.0129.
As of April 1, 2019, all new construction activities are required to complete and submit an
electronic Notice of Intent (NOI) form requesting a Certificate of Coverage (COC) under the
NCGO10000 Construction Stormwater General Permit. This form MUST be submitted and
COC issued prior to the commencement of any land disturbing activity on the above -named
project. The N01 form may be accessed at deq.nc.gov/NCg01, Please direct questions about
the NOI form to Annette Lucas at Annette.lucas@ricdenr.gov or Paul Clark at
Paul.clarkftncdenr.gov. After you submit a complete and correct N01 Form, a COC will be
emailed to you within three business days. Initially, DEMLR will not charge a fee for
coverage under the NCG01 permit. However, a $100 fee will soon be charged annually. This
fee is to be sent to the DEMLR Stormwater Central Office staff in Raleigh.
Title 15A NCAC 4B .0118(a) and the NCGO1 permit require that the following documentation
be kept on file at the job site:
1. The approved E&SC plan as well as any approved deviation.
Q%orili Carolina DcPartmcnt of Em ironmcntal Qvahty Division of Energy. moral and Land I:csources,
�r` D-E�rjy Rale gb Reginrtal off ce I I6LB Mail Semcv Center 3800 Darren Orke Raleigh. North Caralina 11b0't
Letter of Disapproval
Wildlands Engineering, Inc.
October 9, 2019
Page 2of2
2. The NCG01 permit and the COC, once it is received.
3. Records of inspections made during the previous 12 months.
Also, this letter gives the notice required by G.S. 113A-61.1(a) of our right of periodic
inspection to insure compliance with the approved plan.
Title 15A NCAC 413.0118(a) requires that a copy of the approved erosion control plan be on
file at the job site. Also, this letter gives the notice required by G.S. 113A-61.1(a) of our right
of periodic inspection to insure compliance with the approved plan.
North Carolina's Sedimentation Pollution Control Act is performance -oriented, requiring
protection of existing natural resources and adjoining properties. If, following the
commencement of this project, it is determined that the erosion and sedimentation control
plan is inadequate to meet the requirements of the Sedimentation Pollution Control Act of
1973 (North Carolina General Statute 113A-51 through 66), this office may require revisions
to the plan and implementation of the revisions to ensure compliance with the Act.
Acceptance and approval of this plan is conditioned upon your compliance with Federal and
State water quality laws, regulations, and rules. In addition, local city or county ordinances
or rules may also apply to this land -disturbing activity. This approval does not supersede
any other permit or approval.
Please note that this approval is based in part on the accuracy of the information provided
in the Financial Responsibility Form, which you provided. You are requested to file an
amended form if there is any change in the information included on the form. This permit
allows for a land -disturbance, as called for on the application plan, not to exceed the
approved acres. Exceeding the acreage will be a violation of this permit and would require
a revised plan and additional application fee. In addition, it would be helpful if you notify this
office of the proposed starting date for this project. Please notify us if you plan to have a
preconstruction conference.
Sincerely,
G
Dylan Reinhardt, El
Regional Engineering Associate
DEMLR Raleigh Regional Office
Enclosures: Certificate of Approval
NCG01 Fact Sheet
cc: Chris Roessler, Project Manager (crnessler a wildlandseng.cnm) - Electronic Copy
DEMLR— Raleigh Regional Office File