HomeMy WebLinkAboutNIFMP Advisory Board Presentation July 11 2024AGENDA
July 11, 2024
DMS NIFMP Advisory Board Meeting
10:00 Welcome Marc Recktenwald
10:05 Updates and Progress Periann Russell
Strategic plan
Modeling effects of traditional mitigation
Carolina Bays : potential for restoration and flood mitigation
Stoney Creek pilot project
10:30 Workshop Topics and Scheduling Periann Russell
Project size and scale
NBS/NI definitions for program
Currency for RFPs and tracking
10:50 Questions
11:00 Adjourn
Advisory Board meeting July 11, 2024
Updates and Progress
Management Strategy Plan for Natural Infrastructure Mitigation Program (NIFMP)
•Conceptual Framework complete
•Finalizing detail
Advisory Board meeting July 11, 2024
Updates and Progress
Modeling Effects of Traditional Mitigation
•Initial modeling and analysis complete
•Results shared with the Secretary and her executive leadership team
•Contracting additional work to further evaluate
•Curve Number Sensitivity
•Timing and refinement (thresholds of trends)
•Stacking NBS within a watershed
•Effects of size and location
•Refine NBS Selection Tool
Aid in RFP/Procurement process
Evaluate/test individual projects
Evaluate/test multiple project to package
Update and refine with monitoring data
Advisory Board meeting July 11, 2024
Updates and Progress
Advisory Board meeting July 11, 2024
•Carolina Bays: potential for restoration and flood
mitigation
•Accepted proposal to evaluate, quantify and rank
bays for potential flood mitigation
•Addresses watershed planning need
•In contracting
•Stoney Creek
•Feasibility complete
•H&H 1-D complete
•Two stakeholder meetings complete
•1st project (WCC) construction design complete
•WCC easement draft in final review
•2nd project in landowner negotiations
•Watershed tour with Rep. Bell
Advisory Board meeting July 11, 2024
• Project size and scale
Determine realistic size and scale for the NIFMP to be effective
Blueprint projects may be more suited for very large-scaled projects
Best project size or scale to balance cost/benefit
• NBS/NI definitions for program
Nature-Based Solutions and Natural infrastructure have different definitions in
the literature
Need agreement on the definitions
• Currency for RFPs and tracking
House bill requires ‘currency’ as acre-feet
Is acre-feet applicable for all projects?
Should acre -feet be used in the RFP advertisement?
Acre-feet may be suitable for overall flood storage tracking
May need other currencies for project level (or is this success criteria?)
Workshop Topics and Scheduling
Advisory Board meeting July 11, 2024
Questions?