HomeMy WebLinkAbout20220707_ADI_ReceivedJuly 1, 2022
Division of Energy, Mineral and Land Resources
Department of Environmental Quality
Attn: Adam Parr
1612 Mail Service Center
Raleigh, NC 27699-1612
RE: Huffman Pit #2
Mining Permit # 18-08
Catawba County
Catawba River Basin
Dear Mr. Parr:
Please find enclosed modification application additional documents per your letter dated June 28, 2022:
1) Two copies of proof of approval letter from Catawba County for the Erosion and Sediment Control
Plan.
2) Two copies of the map indicating the mine permit boundary, current limits of disturbance from the
mining operation, and the proposed limits of disturbance of the E&SC plan.
Please let me know if you need anything else.
Sincerely,
Douglas B Huffman
RECEIVED
,JOL 0 7 2022
MINING RHO(3'RAM
catawba county
utilities & engineering
March 29, 2022
Huffman Equipment Leasing LLC
2608 Springs Road
Hickory, NC 28601
RE: LETTER OF APPROVAL WITH MODIFICATIONS
Project Name:
Case Number:
Disturbed Area:
Submitted By:
Date Received:
New Submittal
Dear Mr. Huffman:
Huffman Property Subdivision
ECPR-02-2022-39958
22.7 acres
McGill
March 24, 2022
Revision X
RECEIVED
JUL 0 7 2022
LAND QUALITY
MINING PROGRAM
This office has reviewed the subject erosion and sedimentation control plan. We find the
plan to be acceptable and hereby issue this Letter of Approval with Modifications. The
Erosion Control Permit must be posted at the job site. This plan approval shall expire
three (3) years following the date of approval, if no land -disturbing activity has been
undertaken, as is required by Title 15A NCAC 4B .0129.
As of April 1, 2019, all new construction activities are required to complete and submit an
electronic Notice of Intent (NOI) form requesting a Certificate of Coverage (COC) under
the NCG010000 Construction Stormwater General Permit. This form MUST be submitted
prior to the commencement of any land disturbing activity on the above named project.
The NOI form may be accessed at deg.nc.gov/NCG01. After submittal of a complete and
correct NOI Form. a COC will be emailed to you within three business days.
Title 15 NCAC 4B .0018(a) requires that a copy of the approved erosion control plan,
NCG01 permit and COC, and records of inspections made be on file at the job site. Also,
this letter gives the notice required by G.S. 113A-61.1(a) of our right of periodic inspection
to insure compliance with the approved plan.
North Carolina's Sedimentation Pollution Control Act is performance -oriented, requiring
protection of existing natural resources and adjoining properties. If, following the
commencement of this project, the erosion and sedimentation control plan is inadequate
to meet the requirements of the Sedimentation Pollution Control Act of 1973 (North
Carolina General Statue 113A- 51 through 66), this office may require revision to the plan
and implementation of the revisions to insure compliance with the Act.
catawbacountync.gov
Cotowbo County Government Center
25 Government Drive I Newton NC 28658 1 828.465.8261
MAKING. LIVING. BETTER.
Acceptance and approval of this plan is conditioned upon your compliance with federal
and state water quality laws, regulations and rules. In addition, local city ordinances or
rules may also apply to this land -disturbing activity. This approval does not supersede
any other permit or approval.
Please note that this approval is based in part on the accuracy of the information provided
in the Financial Responsibility/Ownership Form that you have provided. You are
requested to file an amended form if there is any change in the information included on
the form.
Please ensure the approved plans and permit are picked up from the Government
Center, see address above. In addition, please notify this office of the proposed
start date for this project and to schedule a preconstruction conference.
Your cooperation is appreciated.
Sincerely,
Toni Norton, P.E., LEED A.P., CPESC
Water Resources Engineer
Cc: File
McGill
NC DEMLR
MODIFICATIONS
Erosion and sediment control measures shall be installed
immediately upon this approval.
Overall Initial Erosion Control Plan, Sheet C-101
Initial Erosion Control Plan Area 1. Sheet C-102
Initial Erosion Control Plan Area 2. Sheet C-103
Initial Erosion Control Plan Area 3, Sheet C-104
• Erosion control measures required at toe of stockpile areas
• Additional drainage ditches may be required for flows into basins