Loading...
HomeMy WebLinkAbout20180817_Modification_74-91Energy, Mineral and Land Resources ENVIRONMENTAL QUALITY Mr. Bobby Tripp Tripp's Mining, LLC 4158 Norris Store Road Ayden, North Carolina 28513 RE: Permit No. 74-91 Dail Farm Mine Pitt County Tar River Basin Dear Mr. Tripp: August 17, 2018 ROY COOPER rove....,. MICHAEL S. REGAN Sra nrnn WILLIAM E. VINSON, Jr. Gllerun Durolnr Your recent request to have the above referenced mining permit modified has been approved. The modification is to increase the permitted acreage to 32.30 acres and the affected acreage at this site to 31.19 acres as indicated on the mine map received April 12, 2018. The modification includes the addition of mine area located north of the existing mine. A copy of the modified permit is enclosed. The conditions in the modified permit were based primarily upon the initial application. Modifications were made as indicated by the modification request and as required to insure compliance with The Mining Act of 1971. The mine name and permit number shall remain the same as before the modification. I would like to draw your particular attention to the following conditions where minor additions or changes were made: Operating Condition Nos. 4E, 5, 9B, 11 and 13. The issuance of a mining permit and/or any modification to it does not supersede local zoning regulations. The responsibility of compliance with any applicable zoning regulations lies with you. As a reminder, your permitted acreage at this site is 32.30 acres and the amount of land you are approved to disturb is 31.19 acres. Please review the modified permit and contact Judy Wehner, Assistant Mining Specialist, at (919) 707-9220 should you have any questions concerning this matter. Sincerely, David Miller, PE State Mining Engineer DM/jw Enclosures cc: Mr. Samir Dumpor, PE Mr. William Gerringer-Mine and Quarry Bureau, w/o enclosures State of North Carolina I Environmental Quality I Energy, Mineral and Land Resources 1612 Mail Service Center 1 512 N. Salisbury St. I Raleigh, NC 27699 919 707 9220 4 DEPARTMENT OF ENVIRONMENTAL QUALITY DIVISION OF ENERGY, MINERAL AND LAND RESOURCES PERMIT for the operation of a mining activity In accordance with the provisions of G.S. 74-46 through 68, "The Mining Act of 1971," Mining Permit Rule 15A NCAC 5 B, and other applicable laws, rules and regulations Permission is hereby granted to: Tripp's Mining LLC Dail Farm Mine Pitt County - Permit No. 74-91 for the operation of a Sand Mine which shall provide that the usefulness, productivity and scenic values of all lands and waters affected by this mining operation will receive the greatest practical degree of protection and restoration. N Page 2 In accordance with the application for this mining permit, which is hereby approved by the Department of Environmental Quality, hereinafter referred to as the Department, and in conformity with the approved Reclamation Plan attached to and incorporated as part of this permit, provisions must be made for the protection of the surrounding environment and for reclamation of the land and water affected by the permitted mining operation. This permit is expressly conditioned upon compliance with all the requirements of the approved Reclamation Plan. However, completed performance of the approved Reclamation Plan is a separable obligation, secured by the bond or other security on file with the Department, and may survive the revocation or suspension of this permit. This permit is not transferable by the permittee with the following exception: If another operator succeeds to the interest of the permittee in the permitted mining operation, by virtue of a sale, lease, assignment or otherwise, the Department may release the permittee from the duties imposed upon him by the conditions of his permit and by the Mining Act with reference to the permitted operation, and transfer the permit to the successor operator, provided that both operators have complied with the requirements of the Mining Act and that the successor operator agrees to assume the duties of the permittee with reference to reclamation of the affected land and posts a suitable bond or other security. In the event that the Department determines that the permittee or permittee's successor is not complying with the Reclamation Plan or other terms and conditions of this permit, or is failing to achieve the purposes and requirements of the Mining Act, the Department may give the operator written notice of its intent to modify, revoke or suspend the permit, or its intent to modify the Reclamation Plan as incorporated in the permit. The operator shall have right to a hearing at a designated time and place on any proposed modification, revocation or suspension by the Department. Alternatively and in addition to the above, the Department may institute other enforcement procedures authorized by law. Definitions Wherever used or referred to in this permit, unless the context clearly indicates otherwise, terms shall have the same meaning as supplied by the Mining Act, N.C.G.S. 74-49. Modifications December 1, 2017: This permit has been issued for the life of site or the duration of the lease term. August 17, 2018: This permit has been modified to increase the permitted acreage to 32.30 acres and the affected acreage at this site to 31.19 acres as indicated on the mine map received April 12, 2018. The modification includes the addition of mine area located north of the existing mine. This permit is valid for the life of the site or life of lease, if applicable, as defined by Session Law 2017-209 and has no expiration date. However, all provisions of GS 74-51 and GS 74-52 still apply for new, transferred and modified mining permits. Page 3 Conditions This permit shall be subject to the provisions of the Mining Act, N.C.G.S. 74-46, et. seq., and to the following conditions and limitations: OPERATING CONDITIONS: 1. A. Any wastewater processing or mine dewatering shall be in accordance with the permitting requirements and rules promulgated by the N.C. Environmental Management Commission. B. Any stormwater runoff from the affected areas at the site shall be in accordance with any applicable permit requirements and regulations promulgated by the Environmental Protection Agency and enforced by the N.C. Environmental Management Commission. It shall be the permittee's responsibility to contact the Stormwater Program to secure any necessary stormwater permits or other approval documents. 2. A. Any mining process producing air contamination emissions shall be subject to the permitting requirements and rules promulgated by the N.C. Environmental Management Commission and enforced by the Division of Air Quality. B. During mining operations, water trucks or other means that may be necessary shall be utilized to prevent dust from leaving the permitted area. 3. A. Sufficient buffer (minimum 50 foot undisturbed) shall be maintained between any affected land and any adjoining waterway or wetland to prevent sedimentation of that waterway or wetland from erosion of the affected land and to preserve the integrity of the natural watercourse or wetland. B. Any mining activity affecting waters of the State, waters of the U. S., or wetlands shall be in accordance with the requirements and regulations promulgated and enforced by the N. C. Environmental Management Commission. 4. A. Adequate mechanical barriers including but not limited to diversions, earthen dikes, sediment check dams, sediment retarding structures, rip rap pits, or ditches shall be provided in the initial stages of any land disturbance and maintained to prevent sediment from discharging onto adjacent surface areas or into any lake, wetland or natural watercourse in proximity to the affected land. B. All drainage from the affected areas around the mine excavation shall be diverted internal to said excavation. C. No dewatering activities shall occur at this site. Page 4 D. Mining activities shall occur as indicated on the mine map last revised November 30, 2012 and the supplemental information received by the Land Quality Section on October 15, 2012 and December 3, 2012. E. Mining activities associated with the northern pit expansion shall occur as indicated on the mine map received April 12, 2018 and the supplemental information received on February 21, 2018, April 12, 2018 and July 20, 2018. 5. All affected area boundaries (31.19 acres) shall be permanently marked at the site on 100-foot intervals unless the line of sight allows for larger spacing intervals. 6. The angle for graded slopes and fills shall be no greater than the angle, which can be retained by vegetative cover or other adequate erosion control measure, structure, or device. In any event, exposed slopes or any excavated channels, the erosion of which may cause off -site damage because of sedimentation, shall be planted or otherwise provided with ground cover, devices or structures sufficient to restrain such erosion. 7. The affected land shall be graded so as to prevent collection of pools of water that are, or likely to become, noxious or foul. Necessary structures such as drainage ditches or conduits shall be constructed or installed when required to prevent such conditions. 8. Existing vegetation or vegetated earthen berms shall be maintained between the mine and public thoroughfares whenever practical to screen the operation from the public. 9. A. Sufficient buffer shall be maintained between any excavation and any mining permit boundary to protect adjacent property. B. Buffers shall be maintained as indicated on the mine map received April 12, 2018. 10. A. No on -site disposal of refuse or other solid waste that is generated outside of the mining permit area shall be allowed within the boundaries of the mining permit area unless authorization to conduct said disposal has first been obtained from both the Division of Waste Management and the Division of Energy, Mineral and Land Resources, Department of Environmental Quality. The method of disposal shall be consistent with the approved reclamation plan. B. Mining refuse as defined by G.S. 74-49 (14) of The Mining Act of 1971 generated on -site and directly associated with the mining activity may be disposed of in a designated refuse area. All other waste products must be disposed of in a disposal facility approved by the Division of Waste Management. No petroleum products, acids, solvents or their storage containers or any other material that may be considered hazardous shall be disposed of within the permitted area. Page 5 C. For the purposes of this permit, the Division of Energy, Mineral and Land Resources considers the following materials to be "mining refuse" (in addition to those specifically listed under G.S. 74-49 (14) of the N.C. Mining Act of 1971): 1. on -site generated land clearing debris 2. conveyor belts 3. wire cables 4. v-belts 5. steel reinforced air hoses 6. drill steel D. If mining refuse is to be permanently disposed within the mining permit boundary, the following information must be provided to and approved by the Division of Energy, Mineral and Land Resources prior to commencement of such disposal: 1. the approximate boundaries and size of the refuse disposal area; 2. a list of refuse items to be disposed; 3. verification that a minimum of 4 feet of cover will be provided over the refuse; 4. verification that the refuse will be disposed at least 4 feet above the seasonally high water table; and, 5. verification that a permanent vegetative groundcover will be established. 11. An Annual Reclamation Report and Annual Operating Fee of $400.00 shall be submitted to the Department by July 1 of each year until reclamation is completed and approved for release by the Department. 12. The operator shall notify the Department in writing of the desire to delete, modify or otherwise change any part of the mining, reclamation, or erosion/sediment control plan contained in the approved application for a mining permit or any approved revision to it. Approval to implement such changes must be obtained from the Department prior to on -site implementation of the revisions. 13. The security, which was posted pursuant to N.C.G.S. 74-54 in the form of a $31,200.00 surety bond, is sufficient to cover the operation as indicated in the approved application. This security must remain in force for this permit to be valid. The total affected land shall not exceed the bonded acreage. 14. A. Authorized representatives of the Division of Archives and History shall be granted access to the site to determine the presence of significant archaeological resources. Page 6 B. Pursuant to N. C. G. S. 70 Article 3, "The Unmarked Human Burial and Human Skeletal Remains Protection Act," should the operator or any person in his employ encounter human skeletal remains, immediate notification shall be provided to the county medical examiner and the chief archaeologist, North Carolina Division of Archives and History. Page 7 APPROVED RECLAMATION PLAN The Mining Permit incorporates this Reclamation Plan, the performance of which is a condition on the continuing validity of that Mining Permit. Additionally, the Reclamation Plan is a separable obligation of the permittee, which continues beyond the terms of the Mining Permit. The approved plan provides: Minimum Standards as Provided by G.S. 74-53 The final slopes in all excavations in soil, sand, gravel and other unconsolidated materials shall be at such an angle as to minimize the possibility of slides and be consistent with the future use of the land. 2. Provisions for safety to persons and to adjoining property must be provided in all excavations in rock. 3. All overburden and spoil shall be left in a configuration which is in accordance with accepted conservation practices and which is suitable for the proposed subsequent use of the land. 4. No small pools of water shall be allowed to collect or remain on the mined area that are, or are likely to become noxious, odious or foul. 5. The revegetation plan shall conform to accepted and recommended agronomic and reforestation practices as established by the North Carolina Agricultural Experiment Station and the North Carolina Forest Service. 6. Permittee shall conduct reclamation activities pursuant to the Reclamation Plan herein incorporated. These activities shall be conducted according to the time schedule included in the plan, which shall to the extent feasible provide reclamation simultaneous with mining operations and in any event, provide reclamation at the earliest practicable time after completion or termination of mining on any segment of the permit area and shall be completed within two years after completion or termination of mining. RECLAMATION CONDITIONS: 1. Provided further, and subject to the Reclamation schedule, the planned reclamation shall be to restore the mine excavation to a lake area and to grade and revegetate the adjacent disturbed areas. 2. The specifications for surface gradient restoration to a surface suitable for the planned future use are as follows: A. The lake area shall be excavated to maintain a minimum water depth of four feet measured from the low water table elevation. Page 8 3. B. The side slopes to the lake excavation shall be graded to a 3 horizontal to 1 vertical or flatter to the water line and 2 horizontal to 1 vertical or flatter below the water line. C. Any areas used for wastepiles, screening, stockpiling or other processing shall be leveled and smoothed. D. No contaminants shall be permanently disposed of at the mine site. On -site disposal of waste shall be in accordance with Operating Condition Nos. 10A through D. E. The affected land shall be graded to prevent the collection of noxious or foul water. Revegetation Plan: After site preparation, all disturbed land areas shall be revegetated as per the following: Permanent Seeding Specifications Dates February 15- April 1 April 1- July 31 August 1- October October 25- February 15 Soil Amendments S ecies Rate, Lbs/Acre Kobe Lespedeza 10 Bahiagrass 50 Redtop 1 Winter rye (grain) 15 Common Bermuda 50 Lespedeza (unscarified) 30 German millet 40 Rye (grain- temporary) 120 Lime - 2000 Ibs/acre or follow recommendations from a soil test. Fertilizer - 1000 Ibs/acre 8-8-8 or 10-10-10, or follow recommendations from a soil test. Mulch - All seeded areas shall be mulched using small grain straw at a rate of 2000 Ibs/acre and anchored appropriately. Whenever possible, disturbed areas should be vegetated with native warm season grasses such as switch grass, Indian grass, bluestem and gamma grass. Page 9 In addition, the permittee shall consult with a professional wildlife biologist with the N.C. Wildlife Resources Commission to enhance post -project wildlife habitat at the site. 4. Reclamation Plan: Reclamation shall be conducted simultaneously with mining to the extent feasible. In any event, reclamation shall be initiated as soon as feasible after completion or termination of mining of any mine segment under permit. Final reclamation, including revegetation, shall be completed within two years of completion or termination of mining. This permit, issued December 18, 2012 and modified December 1, 32017, is hereby modified this 17th day of August, 2018 pursuant to GS 74-52. By: � 74?'e' '4�v� William E. Vinson, Jr., Interim Director Division of Energy, Mineral, and Land Resources By Authority of the Secretary Of the Department of Environmental Quality NOTICE OF ISSUANCE OF MINING PERMIT You have previously expressed an interest and/or are listed as an adjoining landowner in the application to modify this mining permit filed by Tripp's Mining LLC to conduct mining activities off SR 1114 (Rountree Road) in Pitt County. The mining permit (no. 74-91) was modified on August 17, 2018. North Carolina law allows persons aggrieved by the issuance of a mining permit to contest the decision by filing a petition for a contested case in the Office of Administrative Hearings pursuant to N.C.G.S. 150B-23 of the Administrative Procedure Act (APA). If you believe that you are an aggrieved party within the meaning of the APA and NC General Statute 74-61, a petition for a contested case must be filed in the Office of Administrative Hearings within thirty (30) days of the mailing of this notice to you. If you file a contested case petition, it must be in writing and in the form prescribed by N.C. General Statutes 15013-23. File the original petition and one copy with the Office of Administrative Hearings, 6714 Mail Service Center, Raleigh, NC 27699-6714. Any questions about filing a petition may be directed to the Clerk of the Office of Administrative Hearings by telephoning (919) 431-3000. You must serve the Department of Environmental Quality by mailing a copy of the petition to Mr. Bill Lane, Registered Agent and General Counsel, Department of Environment and Natural Resources, 1601 Mail Service Center, Raleigh, NC 27699-1601. a zz- William E Vinson, Jr. Interim Director Division of Energy, Mineral, and Land Resources North Carolina Department of Environmental Quality This notice was mailed on 9-g4) - / 4). Brenda Harris Mining Program Secretary