HomeMy WebLinkAbout20220331_1_Mine_planAttachment 1 Mining Plan RECEIVE) MAR 3 1 2022 LAND QUALITY MINING PROGRAM Attachment A Buechel Stone —Steel Gray Mine Spruce Pine, North Carolina Permit Application Item C.1 Mining sequence 15` year: In year one for this mine Buechel Stone Corporation (BSC) will fill in the deepest area which currently holds several feet of water. By doing this we will avoid any potential for encroachment into the water table. Beginning from the west side of the area the mining will proceed to the east approximately 50-100'. This will allow us to turn the face of the wall to the east and avoid any fly rock concerns in the future. Moving forward BSC will provide oversight to the blasting process to ensure safety and efficiency. Sedimentation ponds are planned at the two locations shown on Figures 3 and 4. A Notice of Intent (NOI) to discharge stormwater from the site has been filed with the North Carolina Department of Environmental Quality (NCDEQ). Stormwater compliance requirements will be conducted with the help of third party consultants. y . .— -- 1' West end of quarry to be reclaimed ��N Several feet of water to be filled in to avoid holding in the mine New area to start approx. 100' east Year 3: By year 3 BSC will be mining in a northeast direction provided the rock material stays true to the desired colors and quality. As the mine progresses reclamation activities will continue in areas just previously mined to avoid potential stormwater issues with the North Toe River located to the south. At this point we will be approx. 20' down and 150' north east. There will be 1-2 different bench areas for diversity of material. The haul road to the North may have to be rerouted as the quarry moves. We hope to have the demand for 300+ ton per month from this quarry. Year 10: By year 10, provided the rock material is still of acceptable quality BSC will continue to quarry east-northeast toward the edge of the mine permitted area. At that point BSC will consider whether to file a Permit Modification for additional acreage. The haul road will be completely rerouted by now.