HomeMy WebLinkAbout20201021_Water_Balance_narrativeJISUNROCK (10
77
P, 4r
VL
PROSPECT HILL
QUARRY WATER
BALANCE
Mop i
Prospect Hill
Water
o Zero Discharge
Quarry Process
Why?
High Quality Water Shed
NCG02000 Requires
All process water discharge rates (cfs (cubic feet per second) must be
50% below the 7Q 10 of the receiving water body.
Definition of 7Q 10
The 7Q 10 is the lowest 7-day average flow that occurs (on average)
once every 10 years.
The 7Q 10 for all surrounding water bodies is (Determined by
USGS (July 2020)
Thus No Discharge of process water is possible
7r rj
Typical Quarry Dewatering
System (Sunrock Kittrell Quarr
4
r'- tilt
Plant
r-
Plant Water Pond
�ttling
I I
13 Kittrell Quarry
—22 years old
—45-acers
150' maximum pit
depth (sump B)
Average annual
production
+ (-500k-1 million
tons/yr.)
f.: r
Ik
F
SuP.
ns
Plant Make-up Water/Dewatering Pond
Typical Quarry Dewatering
S stem Sunrock Butner Quarry)
0 Butner Quarry,-
i r•
~50 years old
~ 100 Acres'-
250' maximum pit
depth (sump B)
Average annual 1000
production (~ 1-3
� - x
million tons/yr.)
-_ Sump A
--___ _ �..�-.��"-may - _ __. - _ �•� _ � .
ld
mow,
� f• k ` , _ +
•
"7� = Sump B
A _
De -watering Pond`
Prospect Hill Quarry Process
Water Flow Dia
M
ram
It
Quarry Pit Dewatering
Groundwater/Stormwater
Inflow (Pit A)
Concrete Plant
Production
Pump/Pipe
Plant Make-up
Process Waterfromrter
Valve
Pond- AGravityFlowPipe
Mixer Truck washout
FPI.nt
Pump/PipeWeir/filtration
system
to remove solids
Water Pond
lant Make-up Solids recycled back
FP
Pump/Pipe
Pond- B into the production
Excess Water
process
Pump/Pipe
Gravity
Flow
Pump/Pipe
Pipe
Pump/Pipe
Aggregate
Excess
Processing
Settling Basins
Water pH neutralization
Facility
Solids reclaimed back into
system (CO2)
production process, or disposed
in permitted overburden/pond
Gravity
fine disposal areas
Flow
Pipe
Plant Make-up
Plant Make-up
All other process water developed at the facility shall
Pond- B Gravity Spillway
Spillwaybe
Pond-
diverted/pump to above listed process water
Pump/Pipe
facilities and reused in the production process
* Pit B — Dewatering system to be pumped and
contained within Pit A (upon Pit A's Completion)
Prospect Hill Quarry Process
Water Ponds
M
t T$I71p BflSln#17—warwrI KMFM 1
� �welll� ` ■ Plant Water Pond/Plant Make-up
SheetC3.03 Water Pond A
_ - - -
,� Temp Basin v
SheetC3.04 ■ Fed directly from Pit Dewatering
? o Plant Makeup Water Pond -A ■ Interconnected gravity flow
' -2-Acre - 2.574,947 gal Capacity
Plant Water Pond 344,220 Cat Storage Capacity ■ Plant Water Pond Pumps to
-1Acre- Sheet7G Processing Plant and
1,447.000 gat
Capacity Miscellaneous uses (i.e. plant dust
193,378CtA suppression)
storage capacity
Sheet7a ��, Pump lines equipped with
1 ' diverters to allow for discharge
directly back to Pit A as needed.
Il.
24' H E
�. 2f E At '�'B� ■ Plant Process Water Settling Ponds
Series of (8) eight individual
Plant Process ponds
� Water fettling
Ponds Fed via gravity directly from
-3Acres Aggregate Wash Screens
705.488 gal
capacity._ Discharge via gravity flow
9010.08Cutt =- -----� direct) back to Plant Water
�\ G� Storage Capacity Temp 8&sin 91 y
16 shegt7a ;' _ strdetcs.aa ■ Complete Closed loop System
I;r , .
�4 -1
.._. Sediment Trap #4 24 PE
Sheet C3.11 a�ftft
PEA
M
Prospect Hill Quarry Process
Water Ponds
Plard Make-up Water Pond-B
-1"cre- 27,801,126 gal Capacity
-3,718,470 Out Storage Capaclty
See Details - $heat 73
TempBain42
Sheet C3.41
V.
PlarA Make-up Water Pa&C �.
-trAcre - e08.167gal Capa*
-918,140 Cut Storage Capacity
See Details - Sheet 7G
■ Plant Make-up
B/C
It
Water Pond
Fed directly from Pit
Dewatering Pit A
Also fed from excess process
water from concrete plant
systems (truck wash out weir)
via pump
Interconnected gravity Spill
. way to Plant Make-up Water
Pond C
owatareac �r�z'��-
�F
01``
e��JS
Both Ponds equipped with
pumps supplying Concrete and
Asphalt facility's with water for
their process
Pumps also equipped to
discharge back to either Pit A
and or Plant Water Pond/Plant
Make-up Water Pond A as
needed
Complete Closed loop System
Prospect Hill Quarry Process
Water Storage
o Quarry Water Usage
Water Usage
Gallons/Day
Gallons/Month Gallons/Year
% Process Loss Gallons Loss/Day
Gallons
Loss/Month
Gallons
Loss/Year
Aggregates Process facility 2,100,000
54,600,000 655,200,000
20%
420,000
10,920,000
131,040,000
Dust Suppression 9,000
234,000 2,808,000
100%
9,000
234,000
2,808,000
misc. 6,000
156,000 1,872,000
100%
6,000
156,000
1,872,000
Totals 2,115,000
54,990,000 659,880,000
-
435,000
11,310,000
135,720,000
Aggregate Process facility wash
screen
water use
is 3500gpm
Two wash screens proposed only screen used in calculations
Aggregate facility limited to operating 6-days a week 10-hours
per day for calculation purposes only
Typical Aggregate Process Facility —20% water loss
Water lost via evaporation, saturation of finished products, saturation of
generated fines (pond fines or waste materials)
M
Prospect Hill Quarry Process
Water Storage
o Pit Dewater In flows
Is
Water Inputs
Stormwater
ft./day Gallons/day Gallons/Month Gallons/Year
Drainage
Groundwater Inflow Pit A 150'* - - 134,702 4,097,186 49,166,230
Groundwater Inflow Pit A 300'* - - 237,160 7,213,617 86,563,400
Groundwater Inflow Pit B 150'* - - 114,169 3,472,640 41,671,685
Groundwater Inflow Pit B 300'* - - 302,690 9,206,821 110,481,850
Mean Annual Rainfall PIT A** 1,829,083 0.011 145,572 4,427,805 53,133,664
Mean Annual Rainfall PIT B *** 3,613,925 0.011 287,622 8,748,515 104,982,179
Totals 5,443,007 - 1,221,915 37,166,584 445,999,008
o All design calculations based
on maximum fully developed
I pit to a depths of 150' &
I r
300' below grade
13 Average annual precipitation
of 46.60 in/year
Prospect Hill Quarry Process
Water Storage
o Pond Capacity and Evaporation Rates
Water Storage Capacity
Pond
Capacity (gal)
Surface Area
Annual
Gallons
Gallons
Gallons
(sgft)
Evaporation (ft.)
Loss/Day
Loss/Month
Loss/Year
Settling Ponds
705,488
15,718
2.5
805
24,496
293,953
Plant Water Pond
1,447,000
31,862
2.5
1,632
49,655
595,858
Plant Make -Up Water Pond -A
2,574,947
43,324
2.5
2,220
67,517
810,209
Plant Make -Up Water Pond-B
27,801,1 26
406,355
2.5
20,820
633,281
7,599,366
Plant Make -Up Water Pond-C
6,868,167
185,945
2.5
9,527
289,784
3,477,404
Total
39,396,728
-
-
35,005
1,064,733
12,776,790
o Average Evaporation for
North Carolina
is 3' per year
Source USGS
o Note
Evaporation Rates can be
increased via other industrial
practices
Evaporators (Average
increase of 25% to 60%)
M
Prospect Hill Quarry Process
Water Storage
It
Storage Remaining
Total Process Total Process Total Process Total Process Total Process Total Process Excess Water Excess Water Excess Water Total Storage Capacity Capacity
(gal/day) (gal/Mo) (gal/yr) Loss (gal/day) Loss (gal/Mo) Loss (gal/yr) (gal/day) (gal/Mo) (gal/yr) Capacity (gal) Remaining Balance for
(gal/year) evaporation
Pit A @ 150'
-154,726
-2,785,009-33,420,106 39,396,728 72,816,834 85,593,624
2,115,000 54,990,000 659,880,000 435,000 11,310,000 135,720,000
Pit A @ 300'
-52,268
331,422 3,977,064 39,396,728 35,419,664 48,196,454
Pit B @ 150'
-33,209
911,155 10,933,864 39,396,728 28,462,864 41,239,654
2,115,000 54,990,000 659,880,000 435,000 11,310,000 135,720,000
Pit B @ 300'
155,312
6,645,336 79,744,029 39,396,728 (40,347,301) (27,570,511)
o Pit A
a
Additional
Notes
■ Pit A — operating loss for water through 1 50' pit depth no
additional water storage required
■
Pit B is to be opened at or near the completion of Pit A
■ Pit A — —3.9 million gallons excess water annually at 300' pit
■
Both working pits as demonstrated by our existing facilities to
depth to be stored in onsite pond system for future use or allowed
have multiple working levels, and an Internal working sump
to be evaporated
system providing additional storage capacity and operational
flexibility
■ Pit A has —30 to 60 year life span to reach calculated capacities
at 300' pit depth
■
Pit A - 1,555,355,057 gallon capacity when it reaches
equilibrium post dewatering at a 300 foot depth for the pit
13 Pit B
phasing shown on the mine map. Pit A will reach equilibrium in
■ Pit B - —1 1 million gallons excess water annual at 1 50' pit depth to
—13 years post dewatering (-25' below the natural ground
be stored in onsite pond system for future use or allowed to be
surface) based on the Piedmont Geologic hydrogeological study
evaporated
infiltration rates and precipitation estimate
■ Pit B - —80 million gallons excess water annually at 300' pit depth
■
Remaining Pit A storage capacity post de -watering and
to be stored in combination of onsite pond system and/or Pit A
equilibrium is—324,333,295 gallons to its surface elevation
■ Pit B has —40-80 year life span to reach calculated capacities
■
Groundwater hydraulic conductivity/transmissivity of Pit A to
allow excess annual Pit B water to be absorbed through
infiltration to groundwater within 1.5 years