HomeMy WebLinkAbout20240425_DWR Return PDF of this form to DEMLR CO by email. cc DEMLR RO, DWR SPU. Send a copy to the permittee.
DIVISION OF WATER RESOURCES
MINING PERMIT APPLICATION REVIEW FORM
SECTIONTHIS TO BE OUT BY DEIVILR
DEMLR PERMIT: 54-73 Project Action New Modification Transfer Release
Applicant Name: Ernie Everett Site Prep X
Applicant's Email: bevwill@suddenlinkmail.com County:
Project Name: Delaney Pit YES NO Date Commencing
Have land disturbing activities started?? L X
Latitude: 35.3002 Longitude: -77.4794
Please return comments to (at DEMLR CO): Adam Parr adam.parr@deq.nc.gov
Comments due by: = 04/29/2024
SECTION • TO BE FILLED OUT BY DWR
YES NO
Is this mine an active permit in BIMS? El X
Is the RO concerned that the operation, as proposed, would violate standards of water quality? F I X
Comments:
Does this mine (or previous owner) have DWR back fees to pay? X
(If Yes, amount):
Watershed/Stream Name & Classification: I Drainage connects to the Neuse River, correlating section is C;NSW
DWR Compliance Status of Mine: New (Complaint)
401 Wetland Cert. required? Ll 1 0
401 Wetland Cert. existing? I 0
(If Yes, Permit#):
Does DWR RO have enough information to determine if a 401 certification is required? H-11
Central Coastal Plain Capacity Use Area (CCPCUA). Required? I X
Central Coastal Plain Capacity Use Area (CCPCUA). Existing? I I 0
(If Yes, Permit#):
Does DWR RO have enough information to determine if a CCPCUA is required? X
Is an O & M Plan needed? Ll X
Are wetlands disturbed at this site? X
Does DWR RO suspect or know of nearby wetlands to the site? X
Is a wetland delineation required prior to DWR issuing the permit? X
JD
Consultant
Onsite
Offsite
Stream Determination Needed? X
Stream Determination Completed? I 0
Does DWR RO need a statement that no wetlands/streams are disturbed for this project
from applicant?
Rev November 2021 r0
Return PDF of this form to DEMLR CO by email. cc DEMLR RO, DWR SPU. Send a copy to the permittee.
Buffer Determination Needed? X
Buffer Determination Completed? X
Recycle system permit existing? LI X
(If Yes, Permit#):
New Recycle System permit required?
Enough information to determine? X
Non-discharge permit existing?
(If Yes, Permit#):
Will wastewaters discharge to HQW waters with a 7Q10=0? LI I X
7Q10 Flow:
Unknown Permittee must determine
Does DWR require DEMLR to hold the permit (e.g. so DWR can review it further or ❑ I 0
because DWR requires more information)?
Has Violation
O&M Requirements
HQW/7Q10 Concerns
IT-
Pay back fees or renew DWR permit LI
Other
Please describe
the reason to
hold the permit:
RO contact: Hold Until:
Mine must wait to dewater until an O&M plan is approved? ❑ I 0
( -
CentralOffice Date Regional Office I Date
DWR RO Surface Water Brooks Sherman 04/22/2024
RO Aquifer Protection Section
Rev November 2021 r0