HomeMy WebLinkAbout05 2021 DWR Comments Return PDF of this form to DEMLR CO by email cc DEMLR RO,DWR SPU. Send a copy to the permittee.
DIVISION OF WATER RESOURCES
MINING PERMIT APPLICATION REVIEW FORM
THIS SECTION TO BE FILLED OUT
DEMLR PERMIT: 71-12
Applicant Name: r. Parnell Shingleton I LlX
Applicant's Email: bsmith@paramounte-eng.com County: Pender
Project Name: Shingleton Farms Mine
Have land disturbing activities started?? X
Latitude: 134.4100 Longitude: 77.7234
Please return comments to (at DEMLR CO): I Jenna Spencer jenne.spencer®ncdenr,gov
Comments due by: 05/20/2021
Is this mine an active permit in BIMS?
Is the RO concerned that the operation, as proposed,would violate standards of water quality?
Comments: DWR is concerned that the application states that fuel tanks,solvents, or other chemical reagents will be stored on site
however it does not describe the material or how it will be contained there is a spill.JD compete. O&M not needed
Does this mine (or previous owner) have DWR back fees to pay? I Li I I
(If Yes, amount):
Watershed/Stream Name &Clas IP Stream Index,8-7C-.30-,-,Class CSw.cape Fear RlverBsln:Poterhal UT to GW"y Creek Stream Index 18-7C49.1 Class ClSw
DWR Compliance Status of Mine: Compliant
401 Wetland Cert. required? F7
401 Wetland Cert. existing? Li I V(
(If Yes, Permit#):
Does DWR RO have enough information to determine if a 401 certification is required?
Is an O & M Plan needed? v(
Are wetlands disturbed at this site? I I I V/
Does DWR RO suspect or know of nearby wetlands to the site?
Is a wetland delineation required prior to DWR issuing the permit? EmnyGreerVSACEcompleted Fv/
SAW-2018-01325 JD
Consultant
Onsite
Offsite
Stream Determination Needed?
Stream Determination Completed?
Does DWR RO need a statement that no wetlands/streams are disturbed for this project ❑
from applicant?
Buffer Determination Needed? t/
Buffer Determination Completed?
Recycle system permit existing?
(If Yes, Permit#):
New Recycle System permit required?
Enough information to determine?
Rev. December 2020-2020r1
Return PDF of this form to DEMLR CO by email. cc DEMLR RO,DWR SPU. Send a copy to the permittee.
Non-discharge permit existing? 171
(If Yes, Permit#): NCG020963
Will wastewaters discharge to HQW waters with a 7Q10=0? ✓
7Q10 Flow:
Unknown Permittee must determine
Does DWR require DEMLR to hold the permit (e.g. so DWR can review it further or ❑
because DWR requires more information)?
- Has Violation
O&M Requirements
HQW/7Q10 Concerns
Pay back fees or renew DWR permit
Other
Please describe the reason to hold the permit:
RO contact:___F THold Until:
Mine must wait to dewater until an O&M plan is approved? I L ✓
Reviewed
DWR RO Surface Water Megan Faulkner&Halley Snider 05/14/2021
RO Aquifer Protection Section
Rev. December 2020-2020rl