HomeMy WebLinkAboutCorrespondence - OIB Terminal Groin - Construction Observation Report #019 02/01/2022From: Brad Rosov To: Mickey Suaa; Coats. Heather; "Currey, Gregory E CIV USARMY CELRP (USA)'; Dunn. Maria T. Cc: Adam Priest Subject: [External] Ocean Isle Beach Terminal Groin - Construction Observation Report #019 - 02/1/2022 Date: Wednesday, February 2, 2022 10:33:28 AM Attachments: imaae001.Dna Terminal Groin Construction Observation Report #019 2022-02-01.pdf Paces from Tensar Triton Material Submittal - Ocean Isle Proiect Revised 10 5.Ddf Coastal Design & Construction - OIB Terminal Groin Construction Sequence Plan View.pdf CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to Report Spam. Good morning, Please find the attached OIB Terminal Groin Construction Observation Reports from Tuesday February 1st. I've also attached two PDFs that illustrate the stone placement and marine mattress progress. Please let me know if you have any questions or comments regarding the report. Thank you, Brad Rosov Senior Marine Biologist/Project Manager Main: 910-399-1905 Mobile: 910-352-1555 brosov(@coastalprotectioneng.com u Coastal Protection Engineering 4038 Masonboro Loop Road Wilmington, NC 28409 2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT CONSTRUCTION OBSERVATION REPORT Date: February 1, 2022 Observation Report No.: 019 Observer: Brad Rosov Commencement Date: November 16, 2021 Contract Date: 078 Arrival/Departure Times: 11:40— 14:25 Weather Conditions: Clear Wave Height & Direction: 1-2 Feet, ESE Wind Speed & Direction: 10-15 MPH, NE Marine Mattress Installed BTWN: Sta. 10+00 and Sta. 10+20 Armor Stone Installed BTWN: Sta. 10+00 and Sta. 10+20 Sheet Pile Installed BTWN: N/A Completed Armor Stone: Today: 700 Tons (Size A) To Date: 10,250 Tons (Size A) Completed Armor Stone: Today: 0 Tons (Size B) To Date: 7,105 Tons (Size B) Completed Marine Mattress: Today: 2,300 To Date: 49,225 Sq. Ft. Completed Sheet Pile: Today: N/A To Date: N/A OBSERVATIONS Approach to Site Yes/No/NA 1. Is the contractor using the approved construction accesses and vehicle routes? Yes Notes: N/A 2. Are construction warning signs in place? Yes Notes: N/A 3. Are construction and staging areas fenced off to prevent public access? Yes Notes: N/A Resorts/Plans/Specifications 4. Are the construction plans and specifications located at the project site? Yes Notes: N/A 5. Are the permits located and notices displayed at the project site? Yes Notes: N/A 6. Has the contractor provided the Daily Reports for the previous day? Yes If incomplete, list deficiencies of contractor's Daily Report: N/A Project Site 7. Are construction operations being conducted today? Yes Notes: See Detailed Observation #1. 8. Is the marine mattress foundation being constructed today? No Notes: N/A 9. Is armor stone being placed today? Yes Notes: N/A 10. Is the steel sheet pile wall being constructed today? No Notes: N/A 11. Is the accretion fillet being constructed today? No Notes: N/A COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC. I PAGE 1 2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT CONSTRUCTION OBSERVATION REPORT Date: February 1, 2022 Observation Report No.: 019 12. Is the contractor using approved staging storage areas (marked, neat & orderly)? Yes Notes: N/A 13. Is the public being kept out of the construction area? Yes Notes: N/A 14. Is the acceptance survey for a completed section being conducted today? No Location: N/A 15. Was any environmental monitoring (turbidity, turtle, bird, etc.) conducted today? No Notes: N/A Measurements and Samalin 16. Was the constructed structure verified to meet the plans and specifications? Yes Measurement: Visual comparison of the UAS orthomosaic with the structure footprint. 17. Was the constructed sheet pile verified to meet the plans and specifications? N/A Measurement: N/A 18. Were any photographs taken? Yes 19. Was the drone flown today? Yes Detailed Observations: 1. Marine mattresses were observed being placed today between Sta. 10+00 and Sta. 10+20. 2. Armor stones (Size A) were observed being delivered to the project site via flatbed tractor trailer from the Rockingham Vulcan quarry. All stones appeared to be within the size range for the Size A stone (See Photo #2). 3. Construction signs were observed in place and fencing was observed around the 4th Street and Shallotte Blvd staging and laydown areas. 4. Stone fragments were observed in a pile adjacent to the stockpile of acceptable armor stones (See Photo #3). 5. One armor stone was observed outside of the footprint of the terminal groin on the east side of the structure at —Sta. 5+50. (See Photo #4). 6. A fragment of an armor stone was observed outside of the footprint of the terminal groin on the west side of the structure a —6+00. (See Photo #5). 7. Depressions in the sand adjacent to the west side of the structure at —Sta. 4+00 were observed. These depressions were caused by excavating material to form a ramp to the structure for the offroad trucks. (See Photo #6). Items Discussed with Contractor's Superintendent, Surveyor, Regulatory Agencies, ... etc.: 1. Richard Mattingly (CDC) anticipated that 20 marine mattresses would be placed today. He also stated that the crew would depart the project site today and return on Monday with the exception of one crew member who will stay to receive armor stone. Cnn P■�ru,�n E■u■uun COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC. I PAGE 2 2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT CONSTRUCTION OBSERVATION REPORT Date: February 1, 2022 Were any issues identified today which may result in a field adjustment request for interpretation, or noncompliance? If so, describe: 1. No issues were discussed today. Equipment List: • (1) Frontend loader, • (3) off road dump trucks, • (2) off road flatbed trucks for hauling mattresses, • (4) excavators, • (1) bulldozer • 4WD ATV COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC. Observation Report No.: 019 contract modificatio PAGE 3 2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT CONSTRUCTION OBSERVATION REPORT Date: February 1, 2022 Observation Report No.: 019 Phntnc Photo 1. Ocean conditions at approximately 12:30 pm. Photo 2. Size A armor stone being unloaded from flatbed truck. COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC. I PAGE 4 2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT CONSTRUCTION OBSERVATION REPORT Date: February 1, 2022 Observation Report No.: 019 Photo 4. Armor stone positioned outside of the footprint of the terminal groin at -Sta. 5+50. COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC. I PAGE 5 2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT CONSTRUCTION OBSERVATION REPORT Date: February 1, 2022 Observation Report No.: 019 t 3. 1� _"'ecsMh R S ' NO Photo 5. Stone fragments located outside of the footprint of the terminal groin at -Sta. 5+50. Rif„Ui COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC. PAGE 6 hu■uu.n 2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT CONSTRUCTION OBSERVATION REPORT Date: February 1, 2022 Observation Report No.: 019 Photo 6. Depressions in the sand following the excavation of material used to construct a ramp to the structure. Photo 7. Drone rigged with line and a bottle used for sampling ocean water. COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC. I PAGE 7 2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT CONSTRUCTION OBSERVATION REPORT Date: February 1, 2022 Observation Report No.: 019 Photo 8. Marine mattress being placed near Sta. 10+10. Photo 9. Marine mattresses being delivered via offroad truck to the terminal groin. COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC. I PAGE 8 2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT CONSTRUCTION OBSERVATION REPORT Date: February 1, 2022 Observation Report No.: 019 Photo 10. Size A armor stone stockpile. Photo 11. Aerial view of the terminal groin structure looking west. COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC. I PAGE 9 300' 130' TERMINAL GROIN PROFILE 750' TRANSITION FROM STONE SIZE 'A' TO STONE SIZE 'B' AT STATION 8+00 i 10 TOR OF CAP TERMINAL GROIN 10 EXISTING GRADE 5 +4.9' NAVD88 MARCH 2O21 5 +4.5 NAVD88. . MHW EL. +1.79' NAVD88 1r W---------- --- -- ' ' \ p MLW EL. -2.94 NAVD88 5 EL. _ -3.0' NAVD88 `.\ -10 1' MARINE 10 J MATTRESS w -15 TRANSITION STRUCTURE -15 SLOPE 1V:2H TO 1V:3H BETWEEN STA 9+00 AND STA. 9+50 -20 -20 MINIMUM TIP ELEVATION EL. -23.0' NAVD88 0+00 0+50 1+00 1+50 2+00 2+50 3+00 3+50 4+00 4+50 5+00 5+50 6+00 6+50 7+00 7+50 8+00 8+50 9+00 9+50 10+00 10+50 11+00 11+50 DISTANCE ALONG PROFILE (FEET) SECTION A -A' Z= � a W W Z Z C9 zd W z M Z. N 20 LL U ~ = V L o F ., Z o F ooZ N It a °00u �Q 0','- V mZz Z 0 EZz �?y W LEGEND: 0 SIZE A STONE = STONE SIZE A W = 5.5 TO 8.9 TONS WITH 50% GREATER THAN 7.0 TONS, 165 PCF MINIMUM \�o 6 Vi CgRo 0 SIZE B STONE = STONE SIZE B W = 3.1 TO 5.1 TONS WITH . oFESS�o.ti,L u W 50% GREATER THAN 4.0 TONS, 165 PCF MINIMUM _ SEAL �: _ Ua ° z MARINE MATTRESS _ 04 88 = • 52 _ a w ° o _ m�„ z ,( ��Q\ ` �G!NEEC x, J W J O 410 Z za J� it'/! W ce o Lu NOTES: o-;t%12.1 Ln 1. ELEVATIONS SHOWN ARE IN FEET REFERENCED TO NORTH AMERICAN VERTICAL DATUM OF 1988 (NAVD88). 2. BATHYMETRIC SURVEY PERFORMED MARCH 2O21, BY McKIM & CREED AND MAY NOT BE REPRESENTATIVE OF CURRENT CONDITIONS. DRAWING NO. 0 5 10 0 50 100 x5-1 VERTICAL GRAPHIC SCALE IN FT HORIZONTAL GRAPHIC SCALE IN FT SHEET 7 OF 13 1) A Terminal Groin Marine Mattress and Stone Placement Progress Map Mattress Key 20'x5' 275 25'x5' 237 10'x5' 4 Total 516 REVISIONS NO. DATE DESCRIPTION BY NO. DATE DESCRIPTION Image is not to scale. COQ-TQL QN D WAp TERWAY SYSTEMS This image is not intended for construction purposes, it is only an example of how the product looks and should not be used for any other purposes than visual aid. * All measurements are in Imprial Units, and -xWXH format. * All sizes shown are nominal. .I n 15' C 20' IE F CLIENT Coastal Design & Construction, Inc PROJECT NAME Ocean Isle Beach Shoreline Protection Project Terminal Groin SHEET TITLE Mattress Layout 6364 Almondsville Rd Gloucester, VA PROJECT LOCATION NAME DATE PROJECT NO. 000000 CONTRACTING JLS Contracting Services, LLC 1205 Hayes Industrial Drive Brunswick County, NC DRAWN BY JMR 09/13/2021 SCALE AS SHOWN STATE OR FEDERAL AID PROJECT No. SERVICES, LLC Mariana, Georgia 30062I678-264-8170 www.jlscontracnng.com 00000000000000 SHEET 2 OF 1 o n