HomeMy WebLinkAboutTerminal Groin Construction Observation Report #043 04/01/20222021-2022 OCEAN ISLE BEACH —TERMINAL GROIN PROJECT
CONSTRUCTION OBSERVATION REPORT
Date: April 1, 2022 Observation Report No.: 043
Observers: Adam Priest Commencement Date: November 16, 2021
Contract Date: 137
Arrival/Departure Times: 12:45— 15:45
Weather Conditions: Sunny
Wave Height & Direction: 2 Feet, S
Wind Speed & Direction: 10-20 MPH, SW
Marine Mattress Installed BTWN: N/A
Armor Stone Installed BTWN: N/A
Sheet Pile Installed BTWN: 2+00 to 3+00 (concrete cap)
Completed Armor Stone: Today: 0 Tons (Size A) To Date: 12,978 Tons (Size A)
Completed Armor Stone: Today: 0 Tons (Size B) To Date: 7,405 Tons (Size B)
Completed Marine Mattress: Today: N/A Sq. Ft. To Date: 57,325 Sq. Ft.
Completed Sheet Pile: Today: 0 To Date: 300 Ft.
OBSERVATIONS
Approach to Site Yes/No/NA
1. Is the contractor using the approved construction accesses and vehicle routes? Yes
Notes: N/A
2. Are construction warning signs in place? Yes
Notes: N/A
3. Are construction and staging areas fenced off to prevent public access? Yes
Notes: N/A
Resorts/Plans/Specifications
4. Are the construction plans and specifications located at the project site? Yes
Notes: N/A
5. Are the permits located and notices displayed at the project site? Yes
Notes: N/A
6. Has the contractor provided the Daily Reports for the previous day? Yes
If incomplete, list deficiencies of contractor's Daily Report: N/A
Protect Site
7. Are construction operations being conducted today?
Yes
Notes: See Detailed Observation #1, #3, and #4
8. Is the marine mattress foundation being constructed today?
No
Notes: N/A
9. Is armor stone being placed today?
No
Notes: N/A
10. Is the steel sheet pile wall being constructed today?
Yes
Notes: See Detailed Observations #1, #3, and #4
11. Is the accretion fillet being constructed today?
No
Notes: N/A
Pnusup
COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC.
I PAGE 1
2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT
CONSTRUCTION OBSERVATION REPORT
Date: April 1, 2022 Observation Report No.: 043
12. Is the contractor using approved staging storage areas (marked, neat & orderly)? Yes
Notes: N/A
13. Is the public being kept out of the construction area? No
Notes: N/A
14. Is the acceptance survey for a completed section being conducted today? No
Location: N/A
15. Was any environmental monitoring (turbidity, turtle, bird, etc.) conducted today? No
Describe environmental monitoring: N/A
Measurements and SamDlin
16. Was the constructed structure verified to meet the plans and specifications? Yes
Measurement: Visual comparison of the UAS orthomosaic with structure footprint.
17. Was the constructed sheet pile verified to meet the plans and specifications? Yes
Measurement: A minimum cover distance of 3 inches was measured between the steel reinforcing and the
inside edge of the concrete form, the top elevation was checked to be within 0.02 ft. of the design elevation,
and the reinforcement bars were measured to be 4 inches from the expansion joints.
18. Were any photographs taken? Yes
19. Was the drone flown today? Yes
Detailed Observations:
1. Mclean was observed stripping the wooden forms from the underside of the shore anchorage section's concrete
cap between Sta. 1+00 and 2+00 (See Photo #2).
2. Stone fragments and misc. debris observed within the excavated area in proximity to Sta. 0+00 to 2+00 of the
sheet pile wall (See Photo #3).
3. Observations of the concrete cap formwork and steel reinforcement showed that a minimum of 3 inches of cover
was being maintained between the steel and form work between Sta. 1+00 and 2+00. Plastic chairs were
observed being used to support the steel rebar. Double strut coil ties were observed in place at every other sheet
pile handling hole location (See Photo #4).
4. McLean's crew was observed pouring concrete between Sta. 2+00 and 3+00 (See Photos #5 and #6).
5. Materials Testing Technicians from ECS Limited and Carolina Ready Mix were observed on -site and testing the
concrete slump and air content. The technicians also made 5 concrete cylinders (7-day, 14-day, and three 28-day
cylinders) that will be used for compressive strength testing.
6. CDC and McLean lined a depression adjacent to the concrete cap with a plastic liner to be used as a washout
location for the concrete trucks.
7. The top elevation was checked observed to be within 0.02 ft. of the top of cap design elevation.
8. Armor stones (Size B) were observed being delivered to the project site via flatbed tractor trailer from the
Rockingham Vulcan quarry. All stones appeared to be within the size range for the Size B stone (See Photo #7).
Cnn
P■�ru,�n
E■u■uun
COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC. I PAGE 2
2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT
CONSTRUCTION OBSERVATION REPORT
Date: April 1, 2022 Observation Report No.: 043
Armor stones were observed being transferred from the flatbed tractor trailer to an offroad truck. The offroad
truck was observed delivering the stones to the area adjacent to Sta. 3+00 where they were stockpiled (See Photo
#8)
10. Several non -spec. stones were observed along the rubblemound structure primarily within Sta. 4+00 to Sta.
7+00.
11. The high tide the storm surge from the previous day brought ocean water to the base of the dunes and/or
sandbags along the beach fill area between Sta. 1+00 and 30+00 (See Photos #9 and #10).
12. Construction signs were observed in place and fencing was observed around the 4th Street and Shallotte Blvd
staging and laydown areas.
13. No work was observed at the Shallotte Blvd staging area. Signs and barricades were observed in place.
Items Discussed with Contractor's Superintendent, Surveyor, Regulatory Agencies, ... etc.:
1. Mike Hoggard (McLean) asked Adam Priest (CPE) if it would be possible to remove the concrete forms late
Saturday or early Sunday (prior to 72 hours as indicated in the Contract Specifications). Adam indicated that
removal of formwork prior to 72 hours is acceptable if the exposed sections of the concrete are sprayed with
curing compound in accordance with the manufacturer's recommendations.
Were any issues identified today which may result in a field adjustment report, contract modification,
request for interpretation, or noncompliance? If so, describe:
1. No issues were discussed today.
Equipment List:
(1) frontend loader, (2) off road dump trucks, (3) excavators, (1) D6 bulldozer, (1) 75-ton crane w/ vibratory hammer
Cnn
P■�ru,�n
E■u■uun
COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC. I PAGE 3
2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT
CONSTRUCTION OBSERVATION REPORT
Date: April 1, 2022 Observation Report No.: 043
Photo 1. Ocean conditions at 12:45 pm.
Photo 2. Excavator removing the wooden forms from the underside of the concrete cap at -Sta. 0+90.
Plf„Ul COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC. PAGE 4
hu■uu.n
2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT
CONSTRUCTION OBSERVATION REPORT
Date: April 1, 2022 Observation Report No.: 043
Photo 3. Stone fragments and misc. debris found within the excavated area around the concrete cap at Sta. 0+00
to 2+00.
a
Photo 4. On -site observer inspecting forms prior to the concrete pour at Sta. 2+00 to 3+00.
COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC.
PAGE 5
2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT
CONSTRUCTION OBSERVATION REPORT
Date: April 1, 2022 Observation Report No.: 043
Photo 5. Concrete being poured within the forms of the concrete cap near Sta. 2+00.
Photo 6. Concrete cap being finished after the pour at Sta. -2+50.
Plf„Ul COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC. PAGE 6
hu■uu.n
2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT
CONSTRUCTION OBSERVATION REPORT
Date: April 1, 2022
Cnn
P■�ru,�n
E■u■uun
Observation Report No.: 043
Photo 7. Armor stones being unloaded from flatbed truck.
Photo 8. Armor stones being unloaded and stockpiled in proximity to Sta. 3+00.
COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC.
rmuc i
2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT
CONSTRUCTION OBSERVATION REPORT
Date: April 1, 2022 Observation Report No.: 043
Photo 9. View of the wet sand where the high tide had run up following the coastal storm the previous day,
looking south from Shallotte Blvd.
- -
VAL
:w_
Photo 10. View of the terminal groin and beach fill area facing west. Note wet sand following the high tide run-
up.
COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC. I PAGE 8