HomeMy WebLinkAboutTerminal Groin Construction Observation Report #039 03/22/20222021-2022 OCEAN ISLE BEACH —TERMINAL GROIN PROJECT
CONSTRUCTION OBSERVATION REPORT
Date: March 22, 2022 Observation Report No.: 039
Observers: Adam Priest Commencement Date: November 16, 2021
Contract Date: 127
Arrival/Departure Times: 12:00— 15:30
Weather Conditions:
Wave Height & Direction
Wind Speed & Direction:
Marine Mattress Installed BTWN:
Armor Stone Installed BTWN:
Sheet Pile Installed BTWN:
Completed Armor Stone:
Completed Armor Stone:
Completed Marine Mattress:
Completed Sheet Pile:
1 Feet, S
5-15 MPH, S
Sta. 6+40 to 6+00
N/A
Today: 100 Tons (Size A)
Today: N/A Tons (Size B)
Today: N/A Sq. Ft.
Today: 0
To Date: 12,750 Tons (Size A)
To Date: 7,105 Tons (Size B)
To Date: 57,325 Sq. Ft.
To Date: 300 Ft.
OBSERVATIONS
Approach to Site Yes/No/NA
1. Is the contractor using the approved construction accesses and vehicle routes? Yes
Notes: N/A
2. Are construction warning signs in place? Yes
Notes: N/A
3. Are construction and staging areas fenced off to prevent public access? Yes
Notes: N/A
Resorts/Plans/Specifications
4. Are the construction plans and specifications located at the project site? Yes
Notes: N/A
5. Are the permits located and notices displayed at the project site? Yes
Notes: N/A
6. Has the contractor provided the Daily Reports for the previous day? Yes
If incomplete, list deficiencies of contractor's Daily Report: N/A
Protect Site
7. Are construction operations being conducted today? Yes
Notes: See Detailed Observation #1
8. Is the marine mattress foundation being constructed today? No
Notes: N/A
9. Is armor stone being placed today? Yes
Notes: See Detailed Observation #1
10. Is the steel sheet pile wall being constructed today? Yes
Notes: See Detailed Observations #3 and #4
11. Is the accretion fillet being constructed today? No
Notes: N/A
Pnusup
COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC.
I PAGE 1
2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT
CONSTRUCTION OBSERVATION REPORT
Date: March 22, 2022 Observation Report No.: 039
12. Is the contractor using approved staging storage areas (marked, neat & orderly)? Yes
Notes: N/A
13. Is the public being kept out of the construction area? No
Notes: See Detailed Observation #8
14. Is the acceptance survey for a completed section being conducted today? No
Location: N/A
15. Was any environmental monitoring (turbidity, turtle, bird, etc.) conducted today? No
Describe environmental monitoring: N/A
Measurements and SamDlin
16. Was the constructed structure verified to meet the plans and specifications? Yes
Measurement: Visual comparison of the UAS orthomosaic with structure footprint
17. Was the constructed sheet pile verified to meet the plans and specifications? No
Measurement: N/A
18. Were any photographs taken? Yes
19. Was the drone flown today? Yes
Detailed Observations:
1. CDC was observed arranging armor stone (Size B) to meet the project design template. The excavator was working
between Sta. 6+40 and Sta. 6+00 (See Photo 8).
2. A trench was observed on the western side of the structure between Sta. 5+80 and Sta. 6+90. CDC excavated the
trench to expose the armor stone along the toe of the structure (See Photo #3).
3. McLean's crew was observed constructing the form for the concrete cap along the landward 100 ft. of the installed
sheet pile wall (Sta. 0+00 to Sta. 1+00) (See Photos #3 and #4).
4. McLean's crew was observed working with CDC to remove the temporary ramp over the installed sheet pile near
Sta. 2+50 and made final adjustments to the final elevation of the seaward 100 ft. of installed sheet pile.
5. CDC was observed excavating sand from the stockpiled material and loading it into off -road trucks that
transported the sand to sections of sandbags the Town had identified to be covered with sand. CDC was observed
placing the sand on sections of sandbags at the end of Lumberton St. and Durham St. (See Photos #5 and #6).
6. Stone fragments were observed along the waterline near Sta. 2+50 on the east side of the structure.
7. No escarpments were observed along the accretion fillet shoreline between Sta. 1+00 and 10+00.
8. Several beach goers were observed fishing from the end of the terminal groin structure. The on -site observer
informed them of the safety risks and asked them to stay off the structure.
Cnn
P■�ru,�n
E■u■uun
COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC. I PAGE 2
2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT
CONSTRUCTION OBSERVATION REPORT
Date: March 22, 2022 Observation Report No.: 039
Items Discussed with Contractor's Superintendent, Surveyor, Regulatory Agencies, ... etc.:
1. Adam Priest (CPE) spoke with Mike (McLean) about the concrete cap form construction. Mike indicated that the
form for the first 100 ft. should be completed by Thursday (3/24) afternoon and that he anticipated pouring
concrete at 10 am Friday (3/25).
2. Adam Priest (CPE) spoke with Richard Mattingly (CDC) about the stone fragments observed near Sta. 2+50 on the
east side of the structure. Richard indicated that CDC has been picking them up periodically during lower tides
and that the crew would be continuing this process until all of the stone fragments are removed.
A Bi-weekly meeting was held at the OIB Town Hall to discuss the status of the terminal groin construction. The
meeting was attended by Daisy Ivey (OIB), Debbie Smith (OIB), Adam Priest (CPE), and Richard Mattingly (CDC)
and Jim Gunn (CDC), Richard Gunn (CDC) and Brad Rosov (CPE) attended via Zoom. Daisy inquired about the time
frame for completion of the rubblemound structure, Richard Mattingly responded that there was roughly 330 ft.
more to complete and he anticipated it would take several more weeks to complete. Adam asked if the Town
had received any volume quantities for the accretion fillet from the USACE. Daisy said they have not received
anything, but she would reach out and request the volume data. Daisy asked Jim Gunn if he would provide a cost
estimate to spread the remainder of the stockpiled material left over after the sandbags were covered and the
gap filled in up to the terminal groin. Jim indicated that he would provide an estimate tomorrow (3/23). Jim
asked about getting permission from the regulatory agencies to demob several pieces of equipment from the
east end sand spit. Brad said that he would reach out to the appropriate regulatory agencies and get back to
him. Brad asked if the Town had begun planning to install sand fence and plant vegetation at the covered sandbag
locations. Debbie mentioned that they were in talks with a contractor to plant the vegetation and install hay
bales.
Were any issues identified today which may result in a field adjustment report, contract modification,
request for interpretation, or noncompliance? If so, describe:
1. No issues were discussed today.
Equipment List:
(1) frontend loader, (2) off road dump trucks, (4) excavators, (1) D6 bulldozer, (1) 75-ton crane w/ vibratory hammer
Cnn
P■�ru,�n
E■u■uun
COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC. I PAGE 3
2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT
CONSTRUCTION OBSERVATION REPORT
Date: March 22, 2022
Photos
Observation Report No.: 039
Photo 1. Ocean conditions at 11:30 am.
Photo 2. View of the terminal groin structure, looking southeast near Sta. 6+00.
Rif„Ui COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC.
hu■uu.n
PAGE 4
2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT
CONSTRUCTION OBSERVATION REPORT
Date: March 22, 2022 Observation Report No.: 039
Cnn
P■�ru,�n
E■u■uun
Photo 3. McLean's crew installing the bottom of the form for the sheet pile wall concrete cap.
Photo 4. View of the concrete cap form installation near Sta. 0+00 looking south.
COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC.
PAGE 5
2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT
CONSTRUCTION OBSERVATION REPORT
Date: March 22, 2022
Observation Report No.: 039
Photo 5. CDC excavator loading sand into an off -road dump truck to be transported and placed over Town
owned sandbags.
Photo 6. CDC crew spreading sand around the base of a dune crossover adjacent a section of the Town owned
sandbags that was covered with sand.
COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC.
PAGE 6
2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT
CONSTRUCTION OBSERVATION REPORT
Date: March 22, 2022 Observation Report No.: 039
Photo 7. CDC excavator arranging stones to meet the project design template near Sta. 6+20.
Photo 8. View of the rubblemound structure near Sta. 6+20.
COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC. I PAGE 7
2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT
CONSTRUCTION OBSERVATION REPORT
Date: March 22, 2022 Observation Report No.: 039
0
�x &
I�
Photo 9. View of the structure looking south near Sta. 7+00.
Photo 10. Aerially view of the USACE CSRM beach nourishment project looking east near Goldsboro St.
-190
Rif„Ui COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC. PAGE 8
hu■uu.n
2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT
CONSTRUCTION OBSERVATION REPORT
Date: March 22, 2022
Observation Report No.: 039
,',,. yP �--may, ..�•- - - .,.... ,._.,.. _, _
r '1
p
Photo 11. View of beach fill and terminal groin facing east.
Photo 12. View of beach fill and terminal groin facing southwest.
Rif„Ui COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC.
hu■uu.n
PAGE 9