HomeMy WebLinkAboutTerminal Groin Construction Observation Report #011 12/28/20212021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT
CONSTRUCTION OBSERVATION REPORT
Date: December 28, 2021 Observation Report No.: 011
Observer: Brad Rosov Commencement Date: November 16, 2021
Contract Date: 043
Arrival/Departure Times: 08:45 — 12:30
Weather Conditions: Sunny/Foggy
Wave Height & Direction: 2 Feet, S
Wind Speed & Direction: 10-15 MPH, S
Marine Mattress Installed BTWN:
Total Sta. 2+85 to Sta. 7+40
Armor Stone Installed BTWN:
Total Sta. 2+85 to Sta. 7+40
Sheet Pile Installed BTWN:
N/A
Completed Armor Stone:
Today: 540 Tons To Date: 5,072 Tons
Completed Marine Mattress:
Today: 1,400 Sq. Ft. To Date: 24,700 Sq. Ft.
Completed Sheet Pile:
Today: N/A Ft. To Date: N/A Ft.
OBSERVATIONS
Approach to Site Yes/No/NA
1. Is the contractor using the approved construction accesses and vehicle routes? Yes
Notes: N/A
2. Are construction warning signs in place? Yes
Notes: N/A
3. Are construction and staging areas fenced off to prevent public access? Yes
Notes: N/A
Resorts/Plans/Specifications
4. Are the construction plans and specifications located at the project site? Yes
Notes: N/A
5. Are the permits located and notices displayed at the project site? Yes
Notes: N/A
6. Has the contractor provided the Daily Reports for the previous day? Yes
If incomplete, list deficiencies of contractor's Daily Report: N/A
Project Site
7. Are construction operations being conducted today? Yes
Notes: See Detailed Observation #1
8. Is the marine mattress foundation being constructed today? Yes
Notes: N/A
9. Is armor stone being placed today? Yes
Notes: N/A
10. Is the steel sheet pile wall being constructed today? No
Notes: N/A
11. Is the accretion fillet being constructed today? No
Notes: N/A
12. Is the contractor using approved staging storage areas (marked, neat & orderly)? Yes
Notes: N/A
COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC.
I PAGE 1
2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT
CONSTRUCTION OBSERVATION REPORT
Date: December 28, 2021 Observation Report No.: 011
13. Is the public being kept out of the construction area?
Notes: N/A
Yes
14. Is the acceptance survey for a completed section being conducted today? No
Location: N/A
15. Was any environmental monitoring (turbidity, turtle, bird, etc.) conducted today? No
Describe environmental monitoring: N/A
Measurements and Samalin
16. Was the constructed structure verified to meet the plans and specifications? No
Measurement: N/A
17. Was the constructed sheet pile verified to meet the plans and specifications? No
Measurement: N/A
18. Were any photographs taken?
19. Was the drone flown today?
Detailed Observations:
Yes
Yes
1. Excavation, marine mattress installation, and armor stone (Size B) installation operations were being conducted
today on the terminal groin between Stations 7+20 and 7+40. (See Photo #2 and #6).
2. Armor stone (Size A) was observed being delivered and offloaded from trucks during the site visit (See Photo #8).
3. The On -site Observer noted a large fragment of a stone along the outer portion of the groin's west side in proximity
to Station 5+00 (See Photo #5). Jim Gunn (CDC) was made aware.
4. Construction signs were observed in place and fencing was observed around the 4th Street and Shallotte Blvd
staging and laydown areas.
5. No work was observed at the Shallotte Blvd staging area. Signs and barricades were observed in place.
6. The On -site Observer noted a portion dislodged section of a marine mattress along the east side of the groin in
proximity to Station 5+00. The section of marine mattress was discarded (See Photo #7).
7. A scarp was observed immediately to the NE of the groin (See Photo #2).
Items Discussed with Contractor's Superintendent, Surveyor, Regulatory Agencies, ... etc.:
1. The property owner of 469 E. V Street told Brad Rosov (CPE) that cracks have been observed inside his home.
He attributed the cracks to the activity associated with the construction of the terminal groin. Brad Rosov
conveyed that information to Jim Gunn (CDC). Jim Gunn stated that the vibration sensors have not detected any
vibrations above 50% of the allowable threshold.
2. Richard Mattingly (CDC) told Brad Rosov that it was anticipated that 18 mattresses would be installed today
followed by the placement of armor stones (Size B).
Brad Rosov (CPE) told Jim Gunn (CDC) that several dislodged sections of the marine mattresses were observed
alongside the east portion of the groin. Jim Gunn explained that it is not unusual for a portion of the mattress to
break off during construction and it will not result in deficiencies in structural integrity.
Cnn
P■�ru,�n
E■u■uun
COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC. I PAGE 2
2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT
CONSTRUCTION OBSERVATION REPORT
Date: December 28, 2021 Observation Report No.: 011
Were any issues identified today which may result in a field adjustment report, contract modificatio
request for interpretation, or noncompliance? If so, describe:
1. No issues were discussed today.
Equipment List:
• Skid steer loader,
• Forklift for mattress filling,
• Frontend loader,
• (2) off road dump trucks,
• (2) off road flatbed trucks for hauling mattresses,
• Link Belt 460 excavator for loading of mattresses from staging area,
• (3) excavators,
• (1) bulldozer
• 4WD ATV
Cnn
P■�ru,�n
E■u■uun
COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC. I PAGE 3
2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT
CONSTRUCTION OBSERVATION REPORT
Date: December 28, 2021
Photo 1. Ocean conditions at approximately 9:00 am.
Observation Report No.: 011
Photo 2. Small scarp that has formed to the east of the groin.
Am
Rif„Ui COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC. PAGE 4
hu■uu.n
2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT
CONSTRUCTION OBSERVATION REPORT
Date: December 28, 2021
Observation Report No.: 011
Photo 3. View of the structure looking south near Sta. 2+85.
11 �L=
� r
r,
Photo 4. View the easternmost house and sandbag revetment located on E. 3rd Street.
RifrUl COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC. PAGE 5
hu■uu.n
2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT
CONSTRUCTION OBSERVATION REPORT
Date: December 28, 2021 Observation Report No.: 011
Cnn
P■�ru,�n
E■u■uun
1s/ ;`' 1
;
Photo 5. Stone fragment located along the western portion of the groin in proximity to Station 5+00.
Photo 6. Crew unloading marine mattresses at the end of the structure (approximately Station 7+30).
COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC.
PAGE 6
2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT
CONSTRUCTION OBSERVATION REPORT
Date: December 28, 2021 Observation Report No.: 011
r. /
Photo 7. Dislodged section of marine mattress originally found along the eastern portion of the structure in
proximity to Station 5+00.
Photo 8. View of eastern portion of the structure (near Station 3+00) and heavy equipment unloading Size A
armor stone.
Cnn
v■«<,„ COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC. PAGE 7