HomeMy WebLinkAboutTerminal Groin Construction Observation Report #010 12/21/20212021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT CONSTRUCTION OBSERVATION REPORT Date: December 21, 2021 Observation Report No.: 010 Observer: Adam Priest Commencement Date: November 16, 2021 Contract Date: 036 Arrival/Departure Times: 13:45 - 15:30 Weather Conditions: Overcast and rainy Wave Height & Direction: 2-3 Feet, S Wind Speed & Direction: 15-20 MPH, NNE Marine Mattress Installed BTWN: Total Sta. 2+85 to Sta. 7+05 Armor Stone Installed BTWN: Total Sta. 2+85 to Sta. 7+05 Sheet Pile Installed BTWN: N/A Completed Armor Stone: Today: 0 Tons To Date: 4,132 Tons Completed Marine Mattress: Today: 0 Sq. Ft. To Date: 21,250 Sq. Ft. Completed Sheet Pile: Today: N/A Ft. To Date: N/A Ft. OBSERVATIONS Approach to Site Yes/No/NA 1. Is the contractor using the approved construction accesses and vehicle routes? Yes Notes: N/A 2. Are construction warning signs in place? Yes Notes: N/A 3. Are construction and staging areas fenced off to prevent public access? Yes Notes: N/A Resorts/Plans/Specifications 4. Are the construction plans and specifications located at the project site? Yes Notes: N/A 5. Are the permits located and notices displayed at the project site? Yes Notes: N/A 6. Has the contractor provided the Daily Reports for the previous day? Yes If incomplete, list deficiencies of contractor's Daily Report: N/A Project Site 7. Are construction operations being conducted today? No Notes: See Detailed Observation #1 8. Is the marine mattress foundation being constructed today? No Notes: N/A 9. Is armor stone being placed today? No Notes: N/A 10. Is the steel sheet pile wall being constructed today? No Notes: N/A 11. Is the accretion fillet being constructed today? No Notes: N/A 12. Is the contractor using approved staging storage areas (marked, neat & orderly)? Yes Notes: N/A COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC. I PAGE 1 2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT CONSTRUCTION OBSERVATION REPORT Date: December 21, 2021 Observation Report No.: 0010 13. Is the public being kept out of the construction area? Notes: N/A Yes 14. Is the acceptance survey for a completed section being conducted today? No Location: N/A 15. Was any environmental monitoring (turbidity, turtle, bird, etc.) conducted today? No Describe environmental monitoring: N/A Measurements and SamDlin 16. Was the constructed structure verified to meet the plans and specifications? No Measurement: N/A 17. Was the constructed sheet pile verified to meet the plans and specifications? No Measurement: N/A 18. Were any photographs taken? 19. Was the drone flown today? Detailed Observations: Yes No 1. No construction on the terminal groin was observed today (12/21). CDC indicated that no work will be done on the terminal groin this week but that stone delivery to the site would continue until the quarry shuts down for the holidays on Dec. 23rd. CDC indicated that flatbed trucks would continue to deliver Size B armor stone until the Dec. 23rd when the quarry closes down. CDC indicated that construction on the terminal groin would resume on Monday Dec. 27t" 2. A CDC operator was observed on site to unload armor stone being delivered. No armor stone was observed being delivered during the site visit. 3. The On -site Observer noted two (2) rubber mats at the seaward end of the east side of the structure had been moved off of the structure by wave action and only a corner of each of the mattresses were still touching the structure. It appeared as though the waves had moved the stones that were holding them in place (See Photos #7 and #8). 4. Construction signs were observed in place and fencing was observed around the 4th Street and Shallotte Blvd staging and laydown areas. 5. No work was observed at the Shallotte Blvd staging area. Signs and barricades were observed in place. Items Discussed with Contractor's Superintendent, Surveyor, Regulatory Alzencies, ... etc.: A Bi-weekly meeting was held at the 01B Town Hall to discuss the status of the terminal groin construction. The meeting was attended by Debbie Smith (016), Justin Whiteside (016), Jim Gunn (CDC) via phone, Adam Priest (CPE), and Brad Rosov (CPE) via phone. Discussions during the meeting informed the Town that Size A armor stone would begin being delivered next week, starting Jan. 27t" and that CDC is expected that Phase 1 of the construction should be close to finishing by mid -February. The meeting also discussed that the sheet pile wall installation may begin by mid -February. Jim Gun mentioned that the sheet pile sections are in the process of being coated which is expected to take several weeks. Justin Whiteside asked if there had been any updates from the vibration monitoring equipment. Adam Priest stated that he had not heard any updates regarding any vibration results. Marine Mattress construction would be ending mid -December but the Shallotte Blvd staging Cnn P■�ru,�n E■u■uun COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC. I PAGE 2 2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT CONSTRUCTION OBSERVATION REPORT Date: December 21, 2021 Observation Report No.: 0010 area would still be used for storing the constructed marine mattresses. The meeting also discussed the USACE Federal project timing which is anticipated to start near the end of February; however, no date has been confirmed. 2. Adam Priest (CPE) emailed Richard Mattingly (CDC), Richard Gunn (CDC), and Jim Gunn (CDC) a description and photos of the marine mattresses that were observed to have slid off of the east side of the structure. In a phone call with Jim Gunn, he indicated that the crew would attempt to get a chain on the marine mattresses to secure them and that on Monday (12/27) the rubber mats would be retrieved and placed back on the structure. Were any issues identified today which may result in a field adjustment report, contract modification, request for interpretation, or noncompliance? If so, describe: 1. No issues were discussed today. Equipment List: • Skid steer loader, • Forklift for mattress filling, • Frontend loader, • (2) off road dump trucks, • (2) off road flatbed trucks for hauling mattresses, • Link Belt 460 excavator for loading of mattresses from staging area, • (3) excavators, • (1) bulldozer • 4WD ATV Cnn P■�ru,�n E■u■uun COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC. I PAGE 3 2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT CONSTRUCTION OBSERVATION REPORT Date: December 21, 2021 Photos Photo 1. Ocean conditions at approximately 2:55 pm. Ij r' — i �k Observation Report No.: 0010 Photo 2. No terminal groin construction operations being conducted today. Rif„Ui COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC. hu■uu.n PAGE 4 2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT CONSTRUCTION OBSERVATION REPORT Date: December 21, 2021 Observation Report No.: 0010 Photo 3. View of the structure looking south near Sta. S+00. Stones placed on top of rubber mats to hold them in place. Photo 4. View of the structure looking north near Sta. S+00. Stones placed on top of rubber mats to hold them in place. COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC. I PAGE 5 2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT CONSTRUCTION OBSERVATION REPORT Date: December 21, 2021 Observation Report No.: 0010 Photo 5. View of the sediment accretion on the west side of the structure. Photo taken at low tide. Photo 6. View of the structure looking north near Sta. 6+75. Stones placed on top of rubber mats to hold them in place. Rif„Ui COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC. PAGE 6 hu■uu.n 2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT CONSTRUCTION OBSERVATION REPORT Date: December 21, 2021 Observation Report No.: 0010 Photo 7. View of a rubber mat that has slid off the east side of the structure near Sta. 7+05. Wave action during higher tide moved the stone holding it in place. Photo 8. View of a second rubber mat that has slid off the east side of the structure near Sta. 6+75. Wave action during higher tide moved the stone holding it in place. Cnn P■�ru,�n E■u■uun COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC. PAGE 7 300' 130' TERMINAL GROIN PROFILE 750' TRANSITION FROM STONE SIZE 'A' TO STONE SIZE 'B' AT STATION 8+00 i 10 TOR OF CAP TERMINAL GROIN 10 EXISTING GRADE 5 +4.9' NAVD88 MARCH 2O21 5 +4.5 NAVD88. . MHW EL. +1.79' NAVD88 1r W---------- --- -- ' ' \ p MLW EL. -2.94 NAVD88 5 EL. _ -3.0' NAVD88 `.\ -10 1' MARINE 10 J MATTRESS w -15 TRANSITION STRUCTURE -15 SLOPE 1V:2H TO 1V:3H BETWEEN STA 9+00 AND STA. 9+50 -20 -20 MINIMUM TIP ELEVATION EL. -23.0' NAVD88 0+00 0+50 1+00 1+50 2+00 2+50 3+00 3+50 4+00 4+50 5+00 5+50 6+00 6+50 7+00 7+50 8+00 8+50 9+00 9+50 10+00 10+50 11+00 11+50 DISTANCE ALONG PROFILE (FEET) SECTION A -A' Z= � a W W Z Z C9 zd W z M Z. N 20 LL U ~ = V L o F ., Z o F ooZ N It a °00u �Q 0','- V mZz Z 0 EZz �?y W LEGEND: 0 SIZE A STONE = STONE SIZE A W = 5.5 TO 8.9 TONS WITH 50% GREATER THAN 7.0 TONS, 165 PCF MINIMUM \�o 6 Vi CgRo 0 SIZE B STONE = STONE SIZE B W = 3.1 TO 5.1 TONS WITH . oFESS�o.ti,L u W 50% GREATER THAN 4.0 TONS, 165 PCF MINIMUM _ SEAL �: _ Ua ° z MARINE MATTRESS _ 04 88 = • 52 _ a w ° o _ m�„ z ,( ��Q\ ` �G!NEEC x, J W J O 410 Z za J� it'/! W ce o Lu NOTES: o-;t%12.1 Ln 1. ELEVATIONS SHOWN ARE IN FEET REFERENCED TO NORTH AMERICAN VERTICAL DATUM OF 1988 (NAVD88). 2. BATHYMETRIC SURVEY PERFORMED MARCH 2O21, BY McKIM & CREED AND MAY NOT BE REPRESENTATIVE OF CURRENT CONDITIONS. DRAWING NO. 0 5 10 0 50 100 x5-1 VERTICAL GRAPHIC SCALE IN FT HORIZONTAL GRAPHIC SCALE IN FT SHEET 7 OF 13 1) A Terminal Groin Marine Mattress and Stone Placement Progress Map Mattress Key 20'x5' 275 25'x5' 237 10'x5' 4 Total 516 REVISIONS NO. DATE DESCRIPTION BY NO. DATE DESCRIPTION Image is not to scale. COQ-TQL QN D WAp TERWAY SYSTEMS This image is not intended for construction purposes, it is only an example of how the product looks and should not be used for any other purposes than visual aid. * All measurements are in Imprial Units, and -xWXH format. * All sizes shown are nominal. .I n 15' C 20' IE F CLIENT Coastal Design & Construction, Inc PROJECT NAME Ocean Isle Beach Shoreline Protection Project Terminal Groin SHEET TITLE Mattress Layout 6364 Almondsville Rd Gloucester, VA PROJECT LOCATION NAME DATE PROJECT NO. 000000 CONTRACTING JLS Contracting Services, LLC 1205 Hayes Industrial Drive Brunswick County, NC DRAWN BY JMR 09/13/2021 SCALE AS SHOWN STATE OR FEDERAL AID PROJECT No. SERVICES, LLC Mariana, Georgia 30062I678-264-8170 www.jlscontracnng.com 00000000000000 SHEET 2 OF 1 o n