HomeMy WebLinkAboutTerminal Groin Construction Observation Report #009 12/17/20212021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT
CONSTRUCTION OBSERVATION REPORT
Date: December 17, 2021 Observation Report No.: 009
Observer: Sam Lohman Commencement Date: November 16, 2021
Contract Day: 032
Arrival/Departure Times: 10:15 — 14:00
Weather Conditions:
Wave Height & Direction
Wind Speed & Direction:
Marine Mattress Installed BTWN:
Armor Stone Installed BTWN:
Sheet Pile Installed BTWN:
Partly cloudy and warm
1 Foot, NE
5-10 mph NE
Sta. 6+75 to Sta 7+05
N/A
Completed Armor Stone: Today: 325 Tons To Date: 4,132 Tons
Completed Marine Mattress: Today: 0 Sq. Ft. To Date: 21,250 Sq. Ft.
Completed Sheet Pile: Today: N/A Ft. To Date: N/A Ft.
OBSERVATIONS
Approach to Site Yes/No/NA
1. Is the contractor using the approved construction accesses and vehicle routes? Yes
Notes: N/A
2. Are construction warning signs in place? Yes
Notes: N/A
3. Are construction and staging areas fenced off to prevent public access? Yes
Notes: N/A
Resorts/Plans/Specifications
4. Are the construction plans and specifications located at the project site? Yes
Notes: N/A
5. Are the permits located and notices displayed at the project site? Yes
Notes: N/A
6. Has the contractor provided the Daily Reports for the previous day? Yes
If incomplete, list deficiencies of contractor's Daily Report: N/A
Project Site
7. Are construction operations being conducted today? Yes
Notes: N/A
8. Is the marine mattress foundation being constructed today? Yes
Notes: See Detailed Observation #1 and #2.
9. Is armor stone being placed today? Yes
Notes: N/A
10. Is the steel sheet pile wall being constructed today? No
Notes: N/A
11. Is the accretion fillet being constructed today? No
Notes: N/A
12. Is the contractor using approved staging storage areas (marked, neat & orderly)? Yes
Notes: N/A
COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC.
I PAGE 1
2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT
CONSTRUCTION OBSERVATION REPORT
Date: December 17, 2021 Observation Report No.: 009
13. Is the public being kept out of the construction area?
Notes: N/A
Yes
14. Is the acceptance survey for a completed section being conducted today? No
Location: N/A
15. Was any environmental monitoring (turbidity, turtle, bird, etc.) conducted today? No
Describe environmental monitoring: N/A
Measurements and SamDlin
16. Was the constructed structure verified to meet the plans and specifications? Yes
Measurement: Visual comparison of the UAS orthomosaic with the structure footprint.
17. Was the constructed sheet pile verified to meet the plans and specifications? N/A
Measurement: N/A
18. Were any photographs taken?
19. Was the drone flown today?
Detailed Observations:
Yes
Yes
1. Armor stone (Size B) installation operations were being conducted today on the terminal groin. No marine
mattresses were installed today. CDC was observed placing stone on top of stone that was placed yesterday
(12/16) between Sta. 6+75 and Sta. 7+05 (See Photo #2).
2. No marine mattress filling operations were observed today at the staging area located at the north end of Shallotte
Blvd (See Photo #4). CDC stated in their daily report (12/17) that marine mattress filling operations were
completed for the project earlier today.
3. Armor stones (Size B) were observed being delivered to the project site via flatbed tractor trailer from the
Rockingham Vulcan quarry (See Photo #12). All stones appeared to be within the size range for the Size B stone.
4. Construction signs were observed in place and fencing was observed around the 4th Street and Shallotte Blvd
staging and laydown areas.
5. Small and large fragments or chunks of armor stone were observed on top of the structure around Sta 6+75 that
appeared to be less than 3.1-ton lower limit of the specification range for Size B armor stone. (See Photos #7 and
#8) (See Items Discussed #1).
6. Small rocks and wood chunks were seen at the west side of the intersection of 4th street and Shallotte Blvd. (See
Photo #6).
7. Markings from marine mattress operations were seen on the asphalt in the Shallotte Blvd staging area (See Photo
#10).
8. Stockpiles of marine mattresses were observed in the Shallotte Blvd staging area. In the very back of the staging
area a large stockpile of mattresses was observed. The stockpile consisted of approximately 31 rows with each
row contain approximately 6 mattresses (See Photo #3).
9. The onsite observer inspected the intersection of Columbia Street and 4th Street. Most of the intersection was
covered in dirt; the asphalt that was visible did not appear to be damaged. The onsite observer also walked down
Columbia Street which was partially covered in dirt and did not appear to be damaged (See Photo #15).
COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC. I PAGE 2
2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT
CONSTRUCTION OBSERVATION REPORT
Date: December 17, 2021 Observation Report No.: 009
10. Dump trucks were observed backing up on the structure around Sta. 5+00 to dump stones near excavator (See
Photo #14).
Items Discussed with Contractor's Superintendent, Surveyor, Regulatory Agencies, ... etc.:
1. An email was sent by Adam Priest (CPE) to Richard Mattingly (CDC), Richard Gunn (CDC), and Jim Gunn (CDC) on
12/17 regarding the smaller stones that were placed on the structure near Sta. 6+75. To the On -site Observer these
stones appeared to be smaller than 3 tons. Adam Priest (CPE) explained that small stone fragments that are broken
due to placement and inadvertently fall into the structure are a part of the construction process; however, stones
that do not meet the specifications should not be placed within the footprint of the structure. In response to the
email, CDC stated in their daily report (12/17) that the smaller stones around 6+75 were used to ramp up the
elevation for the rubber mats and that those stones would be removed during Phase Two of construction.
2. Sam Lohman (CPE) talked Seth (CDC) and excavator operator Steve (CDC) about construction operations today.
Steve (CDC) stated that during excavation sand was filling in too fast to continue excavating (See Photo #11). Steve
(CDC) stated that the only construction operations that would take place today would be placing armor stones on
top of armor stones placed yesterday (12/16) until the correct grade was met between Sta 6+75 and Sta. 7+05.
Were any issues identified today which may result in a field adjustment report, contract modification,
request for interpretation, or noncompliance? If so, describe:
1. No issues were discussed today.
Equipment List:
• Skid steer loader,
• Forklift for mattress filling,
• Frontend loader,
• (2) off road dump trucks,
• (2) off road flatbed trucks for hauling mattresses,
• Link Belt 460 excavator for loading of mattresses from staging area,
• (3) excavators,
• (1) bulldozer
• 4WD ATV
Cnn
P■�ru,�n
E■u■uun
COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC. I PAGE 3
2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT
CONSTRUCTION OBSERVATION REPORT
Date: December 17, 2021
Observation Report No.: 009
3
17
16
jP
F.
JL
_ - '
Photo 1. Ocean conditions at approximately 10:15 am.
Photo 2. CDC excavator placing stone at the seaward end of the structure, near Sta. 7+05.
COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC. I PAGE 4
2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT
CONSTRUCTION OBSERVATION REPORT
Date: December 17, 2021 Observation Report No.: 009
J
5 C
Photo 3. Stockpile of marine mattresses at the back of the Shallotte Blvd staging area.
Photo 4. Shallotte Blvd staging area.
Rif„Ui COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC. PAGE 5
hu■uu.n
2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT
CONSTRUCTION OBSERVATION REPORT
Date: December 17, 2021
Observation Report No.: 009
t
Photo 5. Armor stone stockpile at approximately 10:30 am.
Photo 6. Small pieces of armor stone and wood seen at the west side of the intersection of Shallotte Blvd and 4tn
street where flatbed trucks unstrap the armor stone.
COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC.
PAGE 6
2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT
CONSTRUCTION OBSERVATION REPORT
Date: December 17, 2021 Observation Report No.: 009
Photo 7. Small armor stone fragments at the end of the structure near Sta. 6+75.
Photo 8. Some armor stones appeared to be smaller than 3 tons.
COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC. I PAGE 7
2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT
CONSTRUCTION OBSERVATION REPORT
Date: December 17, 2021 Observation Report No.: 009
Photo 9. View of the structure and rubber mats looking north.
Photo 10. Marks on the asphalt at the Shallotte Blvd staging area.
Rif„Ui COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC. PAGE 8
hu■uu.n
2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT
CONSTRUCTION OBSERVATION REPORT
Date: December 17, 2021
Observation Report No.: 009
Photo 11. View of excavator excavating material.
0
Photo 12. Flatbed truck delivering armor stone to the site.
Cnn
v■«<,„ COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC.
E■u■uun
PAGE 9
2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT
CONSTRUCTION OBSERVATION REPORT
Date: December 17, 2021
Photo 13. View of terminal groin looking west.
Observation Report No.: 009
{
Photo 14. View of dump truck traveling on the rubber mats down the structure to deliver armor stone.
Rif„Ui COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC.
hu■uu.n
I PAGE 10
2021-2022 OCEAN ISLE BEACH -TERMINAL GROIN PROJECT
CONSTRUCTION OBSERVATION REPORT
Date: December 17, 2021 Observation Report No.: 009
F
Photo 15. View of Columbia Street.
err__;
al'06 �44 r,
Photo 16. View of the intersection of Shallotte Blvd and 41h Street.
Rif„Ui COASTAL PROTECTION ENGINEERING OF NORTH CAROLINA, INC. I PAGE 11
hu■uu.n
300'
130'
TERMINAL GROIN PROFILE
750'
TRANSITION FROM STONE
SIZE 'A' TO STONE SIZE 'B'
AT STATION 8+00
i
10 TOR OF CAP TERMINAL GROIN 10
EXISTING GRADE
5 +4.9' NAVD88 MARCH 2O21 5
+4.5 NAVD88. .
MHW EL. +1.79' NAVD88 1r
W---------- --- --
' ' \
p MLW EL. -2.94 NAVD88
5
EL. _ -3.0' NAVD88 `.\
-10 1' MARINE 10
J MATTRESS
w -15 TRANSITION STRUCTURE -15
SLOPE 1V:2H TO 1V:3H
BETWEEN STA 9+00 AND STA. 9+50
-20 -20
MINIMUM TIP ELEVATION EL. -23.0' NAVD88
0+00 0+50 1+00 1+50 2+00 2+50 3+00 3+50 4+00 4+50 5+00 5+50 6+00 6+50 7+00 7+50 8+00 8+50 9+00 9+50 10+00 10+50 11+00 11+50
DISTANCE ALONG PROFILE (FEET)
SECTION A -A'
Z=
� a
W
W
Z Z
C9
zd
W z M
Z. N
20
LL
U
~ = V
L o F
., Z o
F ooZ
N It a °00u
�Q 0','-
V mZz
Z
0
EZz
�?y W
LEGEND:
0
SIZE A STONE = STONE SIZE A W = 5.5 TO 8.9 TONS WITH
50% GREATER THAN 7.0 TONS, 165 PCF MINIMUM
\�o 6 Vi CgRo
0
SIZE B STONE = STONE SIZE B W = 3.1 TO 5.1 TONS WITH
. oFESS�o.ti,L
u W
50% GREATER THAN 4.0 TONS, 165 PCF MINIMUM
_ SEAL �: _
Ua °
z
MARINE MATTRESS
_ 04 88 =
•
52 _
a
w ° o _
m�„ z
,(
��Q\ `
�G!NEEC x,
J W J O
410 Z
za J�
it'/!
W ce
o Lu
NOTES:
o-;t%12.1
Ln
1. ELEVATIONS SHOWN ARE IN FEET REFERENCED TO NORTH AMERICAN
VERTICAL DATUM OF 1988 (NAVD88).
2. BATHYMETRIC SURVEY PERFORMED MARCH 2O21, BY McKIM & CREED
AND MAY NOT BE REPRESENTATIVE OF CURRENT CONDITIONS.
DRAWING NO.
0 5 10 0 50 100
x5-1
VERTICAL GRAPHIC SCALE IN FT HORIZONTAL GRAPHIC SCALE IN FT
SHEET 7 OF 13
1)
A
Terminal Groin Marine Mattress and Stone Placement
Progress Map
Mattress Key
20'x5' 275
25'x5' 237
10'x5' 4
Total 516
REVISIONS
NO. DATE DESCRIPTION BY NO. DATE DESCRIPTION
Image is not to scale.
COQ-TQL QN D WAp TERWAY SYSTEMS This image is not intended for construction purposes, it is only an example of how
the product looks and should not be used for any other purposes than visual aid.
* All measurements are in Imprial Units, and -xWXH format.
* All sizes shown are nominal.
.I n
15'
C
20'
IE
F
CLIENT
Coastal Design & Construction, Inc
PROJECT NAME
Ocean Isle Beach Shoreline Protection Project Terminal Groin
SHEET TITLE
Mattress Layout
6364 Almondsville Rd
Gloucester, VA
PROJECT LOCATION
NAME
DATE
PROJECT NO. 000000
CONTRACTING
JLS Contracting Services, LLC
1205 Hayes Industrial Drive
Brunswick County, NC
DRAWN BY
JMR
09/13/2021
SCALE AS SHOWN
STATE OR FEDERAL AID PROJECT No.
SERVICES, LLC
Mariana, Georgia 30062I678-264-8170
www.jlscontracnng.com
00000000000000
SHEET 2 OF 1
o
n