HomeMy WebLinkAboutQ1 2024 Meeting NotesOregon Inlet 2024 Q1 Meeting
KW understand will need another meeting for other permits, but want to start discussion
JH miss Katie dredged 52, xxxcy Oct 399,OOOcy off ocean bar- Pea Island
& 14,362 cy inside
Nov 19,085 ocean bar- PI 3247cy- inside 45,xxxcy inside
Dec 19,114cy off bar > inside & 667 cy- inside from bar & 25,721 cy inside -inside
= 86,273cy inside ocean bar- inside 10,718 cy and bar>PI 38,600
KW waiting on ACE as far as EA for authorization for alternate route- will likely result in channel
realignment
Waiting on some feedback from the USACE about straightening out channel
TH ask that they send proposed coordinates
JH would be old box- this has slight bend
KW calc 253,OOOcy of volume available in inshore disposal
Trying to get a better gauge of infilling and sustainability
Me- *let me know of any changes*
■ -other channels=/permits up to north of Manteo, into Wanchese
OHC Range 2
Intent is to use scour hole disposal as last resort only — under normal operations, would
take to nearshore disposal area
Received my request to provide additional info for scour hole disposal- understand DCM
needs to coordinate and may require a mod- so will provide info
GB detail when areas may be used under what circumstances
And @JP- anything else they'll need?
JP do have some conditions regarding surveying- and will run by County- but waiting for
final comments on 408
KW non -fed channels- have SAV report will send out to agencies by the end of this week
No shellfish beds found in dredge or disposal corridors
Walter Slough into OIFC- areas where closest to SAV- do understand will be some
additional coordination —and within 100' close to basin
All of channels are 100' @-14' MLLW -corridor and not fixed so following best water
—269,OOOcy within template (dredged 135,OOOcy last quarter, so more than will likely
dredge, but want to give notice)
Condition 5- SAV shellfish surveys conducted- and discussed Cond 10- coordination for
scour holes — will also wait on federal permit
Cultural resources survey was conducted and will be submitted to DNCR-
GB also id/label where not meeting buffers
JH also identify/qualify whether dense or patchy
KW should be in report will be sending out
GB also discuss any avoidance and minimization measures
KW okay- all of actions would be working as a hopper
@JP- any additional thoughts?
JP no- will also take CAMA permit to try to make sure consistent
KW and their understanding NPS plan to issue a SUP for non-federal channels- is that
correct?
JH P10 and P19- curve is for deep water?
KW yes- but may be able to straighten out
JH would be better operationally
KW also expiring at end of year- so want to go ahead and talk about renewal
Timeframe?
GB expires when?
KW 12/31/24
GB 5 year is standard, but may be able to extend further out
Typically don't start looking at renewals until 3 months prior
Still discussing policy and will know by end of year
Can look at it
KW action items- update plans for disposal areas- with cross sections/volume capacity
Will wait until ACE permit to see if need anything else
Will label SAV areas and provide qualitative info on areas
And look at updating channel orientation in WS-
Looking to schedule next meeting at Monday 3/25
Me -
Need more than 1.5 working days to review plans- we generally require plans to be submitted 2 weeks
prior to work.
So not prepared to go over all the conditions for the other permits and think we need to hold another
meeting once the federal permit is issued- but as for the Oregon Inlet and Alternate Route- I think it's
okay to proceed- I'll just remind you that the depths shown are the absolute depths for Oregon Inlet
ocean bar and OHC Range 1 and no additional overdredge depth is permitted beyond the depths shown
on the plans.
I will also say as far as the other channels, that it doesn't appear that the dredging meets the SAV buffer,
so we will need to consult with DMF and I'm not going to put Jimmy on the spot today as I'm sure he
also needs additional time to review the plan provided at the end of the day on Friday. I think if you're
planning on disposing of material in the scour holes- or what you're now calling Oregon Inlet west- I
think we probably need more detailed plans for that disposal. I'd like to see cross section drawings of the
disposal area with estimated fill shown and a table included on the plans showing dredge volumes and
disposal area capacity volume/proposed fill volume.