Loading...
HomeMy WebLinkAboutNCDOT 257 Maintenance & Repair 5/15/2023 ()\5 Brittingham, Cathy From: Lane, Stephen Sent: Monday, May 15, 2023 10:00 AM To: Doliber, Brian C Cc: Tom Steffens; Ward, Garcy; Brittingham, Cathy Subject: RE:Cherry Branch Ferry Channel Navigation Aid Cluster Replace Good morning Brian, DCM has reviewed the NCDOT Ferry Division's proposal to replace one three-pile cluster in the Cherry Branch ferry channel that provides support for a green light navigational aid (#9) as described in your request email dated May 9, 2023. The request letter indicates that the pile cluster was damaged during a ferry collision with the cluster. The NCDOT Ferry Division letter also states the following information: "The existing 3 piles are wood and will be replaced with wooden piles of the same width and length. The location of the pile cluster will not change. A vibratory hammer, along with a clamshell bucket, will be utilized to remove and install all piles. This work should take approximately 5 days and would take place between May 27 and June 10." DCM has established the proposed work to be maintenance/repair of the existing pilings.Therefore this project, as described,will not require a CAMA permit from the N.C. Division of Coastal Management. Please be reminded that all repair/maintenance work must occur as described and within the existing footprint.This email serves as authorization from DCM to proceed with the proposed work. All conditions and stipulations of the active permit remain in force unless altered herein. Please consult with any other local, state or federal agencies that may require a permit or authorization before project initiation. If any aspect of this authorization request should change, please contact me before proceeding. Please contact me with any questions or if I may be of any further assistance with this project. Sincerely, Stephen Lane Coastal Management Representative From: Doliber, Brian C<bcdoliber@ncdot.gov> Sent:Tuesday, May 09, 2023 4:11 PM To: Lane, Stephen<stephen.lane@ncdenr.gov> Cc:Tom Steffens<thomas.a.steffens@usace.army.mil>; Ward, Garcy<garcy.ward@ncdenr.gov> Subject:Cherry Branch Ferry Channel Navigation Aid Cluster Replace Good afternoon Stephen, Please see the attached Request for Authorization and supporting map for replacing a three-pile cluster that supports a navigation aid in the Cherry Branch ferry channel. We are proposing replacement of the one cluster in kind at the same location.All work would be performed by the NCDOT Ferry Division Marine Maintenance Unit and would be completed between May 27-June 10, 2023. The Ferry Division would adhere to all of the conditions in GC 4239 and the NW 3. 1 , If you need any additional information just let me know. Thank you, Brian Doliber Environmental Program Supervisor/Facility Maintenance Coordinator Ferry Division 252 232 8025 mobile 252 621 6251 office bcdoliber(a�ncdot.gov 159 Lucinda Lane Powells Point, NC 27966 r t 1 if Email correspondence to and from this sender is subject to the N.C.Public Records Law and may be disclosed to third parties. 2 STiTF, .. 4 . ) STATE OF NORTH CAROLINA DEPARTMENT OF TRANSPORTATION ROY COOPER J.ERIC BOYETTE GOVERNOR SECRETARY May 09,2023 Stephen Lane Coastal Management—Transportation Projects NCDEQ 400 Commerce Avenue Morehead City,NC 28557 Mr.Lane, The North Carolina Department of Transportation(NCDOT)Ferry Division is requesting authorization to replace one three-pile cluster in the Cherry Branch ferry channel that provides support for a green light navigation aid(#9).The USCG maintains the light and would replace it following the installation of the new pile cluster.A ferry ran into the existing pile cluster and the damage sustained was significant enough to require full replacement.The existing 3 piles are wood and will be replaced with wooden piles of the same width and length. The location of the pile cluster will not change.A vibratory hammer,along with a clamshell bucket,will be utilized to remove and install all piles.This work would take approximately 5 days and would take place between Maty 27-June 10. Per the conditions of CAMA Major Permit 257 we are notifying you with the below information. A. Original permit-CAMA Major Permit 257 B. No dimensional changes are proposed C. NA D. NA If you have any questions or need any additional information,please contact me. Sincerely, Brian Doliber Environmental Program Supervisor Ferry Division 252 232 8025 mobile 252 621 6251 office bcdoliber(a,ncdot.gov 159 Lucinda Lane Powells Point,NC 27966 Mailing Address: TFI FPJONE:(252)621-6251 NC DEPARTMENT OF TRANSPORTATION NCDOT FERRY DIVISION CusroMER SERVICE: 1-877-368-4968 159 LUCINDA LANE POWELIS POINT,NC 27966 WEBSITE:NCDOT.GOV 3-Pile Cluster for Navigation Aid#9 ' e .; ..... - ---- ; /.....1" .../ ..1" ...' — ../ - .. -.. , , .-----• . .... ..-' ..P''.1 * ..- - 4 State Ferry Channel --. , • / . .L-..... ... „....- * .."Ir'..'"..... , . -...I .....• . la . . i •7°'-7...- c.. . :. ." .... .-..... .....- ..00 ' •' -.. .. - ' • . _ ..: . • - - j --.. ..........? ...s-.-.-......-........-'"'- •"••••• .... . r _ _ -. ._... _ ,1.-. . , . . ... .,.. yi - I l.-. .- ,,' - * . ' •'.. .' Cherry Branch Ferry Terminal • . - -- _ 't/ . . ,0 - --- ---• 4', .• . It -.. ...........------- .. _ -... ` '4, _.....-• .." ' r"-• 41#0„,%%1 '-tt ,i_ ,1 . . .CC:,