HomeMy WebLinkAboutNCDOT 70-20 Moratorium Relief Request Smith Creek (2) Brittingham, Cathy
From: Sprinkle, Hannah H
Sent: Friday, February 4, 2022 12:30 PM
To: Brittingham, Cathy; Farrell, Sean C;Westphal,Anneliese
Cc: Brad Shaver(brad.e.shaver@usace.army.mil); Harding, Kimberlee k;Wilson, Travis W.;
fritz.rohde; Lane, Stephen
Subject: RE: B-4590 New Hanover County Bridge 29 Moratorium Relief Request
DWR not object to removing piles during the approved extension.
From: Brittingham, Cathy<cathy.brittingham@ncdenr.gov>
Sent: Friday, February 4, 2022 12:23 PM
To: Farrell, Sean C<scfarrell@ncdot.gov>; Westphal,Anneliese<aestphal@ncdot.gov>
Cc: Brad Shaver(brad.e.shaver@usace.army.mil) <Brad.E.Shaver@usace.army.mil>; Sprinkle, Hannah H
<hannah.sprinkle@ncdenr.gov>; Harding, Kimberlee k<Kimberlee.Harding@ncdenr.gov>; Wilson,Travis W.
<travis.wilson@ncwildlife.org>;fritz.rohde<fritz.rohde@noaa.gov>; Lane, Stephen<stephen.lane@ncdenr.gov>
Subject: RE: B-4590 New Hanover County Bridge 29 Moratorium Relief Request
Hello,
Thank you for providing an update on the project. Based upon comments received from the N.C. Division of
Marine Fisheries and the N.C. Wildlife Resources Commission, DCM agrees with the request to add the
removal of piles associated with the existing fender system to the in-water work that is approved for an
additional 12 days past the February 1 St start date that is in the CAMA Permit 70-20.
Please note that this e-mail response does not eliminate the need to obtain any additional permits, approvals or
authorizations that may be required. This includes approval, if required, from the U.S. Army Corps of
Engineers and/or the N.C. Division of Water Resources (DWR).
Please let me or Stephen Lane know if you have any questions or concerns.
Sincerely,
Cathy Brittingham
Cathy Brittingham,Transportation Project Coordinator
N.C. Division of Coastal Management
(919)707-9149 phone
cathy.brittingham(a,ncdenr.gov
Mailing Address:
c/o DWR Transportation Permitting Unit
1617 Mail Service Center
Raleigh,NC 27699-1617
Physical Address:
512 North Salisbury Street
Archdale Building
12'Floor, Room 1204C
1
Brittingham, Cathy
From: Shaver, Brad E CIV USARMY CESAW (USA) <Brad.E.Shaver@usace.army.mil>
Sent: Friday, February 4, 2022 1:02 PM
To: fritz.rohde; Farrell, Sean C
Cc: Brittingham, Cathy;Westphal, Anneliese; Sprinkle, Hannah H; Harding, Kimberlee k;
Wilson, Travis W.; Lane, Stephen
Subject: [External] RE: [Non-DoD Source] Re: B-4590 New Hanover County Bridge 29
Moratorium Relief Request
CAUTION: External email. Do not click links or open attachments unless you verify.Send all suspicious email as an attachment to
Report Spam.
Sean,
The Corps has no objection to your current proposal.
Brad
From: Fritz Rohde- NOAA Federal <fritz.rohde@noaa.gov>
Sent: Friday, February 4, 2022 12:54 PM
To: Farrell, Sean C<scfarrell@ncdot.gov>
Cc: Brittingham, Cathy<cathy.brittingham@ncdenr.gov>; Westphal, Anneliese<awestphal@ncdot.gov>; Shaver, Brad E
CIV USARMY CESAW(USA)<Brad.E.Shaver@usace.army.mil>; Sprinkle, Hannah H <hannah.sprinkle@ncdenr.gov>;
Harding, Kimberlee k<Kimberlee.Harding@ncdenr.gov>; Wilson,Travis W.<travis.wilson@ncwildlife.org>; Lane,
Stephen<stephen.lane@ncdenr.gov>
Subject: [Non-DoD Source] Re: B-4590 New Hanover County Bridge 29 Moratorium Relief Request
I just spoke with Brad Shave about this and NMFS has no objection to this request.
Fritz Rohde
NMFS
Beaufort, NC
On Thu, Feb 3, 2022 at 12:26 PM Farrell, Sean C<scfarrell@ncdot.gov>wrote:
All,
The contractor has been able to install the 3 drill casings for one of the bents and will be moving their template today
and likely start driving the other 3 casings tomorrow.Since this seems to be going faster than anticipated the
contractor is asking if they can use any remaining time before 2/13 to remove piles associated with the existing fender
system.There also may be opportunities for the contractor to do this intermittently (i.e., waiting for the template to be
surveyed in) while still keeping the main focus on getting the casings installed. Since this activity was not outlined in our
relief request I wanted to clarify and see if there would be any objection to pile removal during our extended in-water
work period.
i
Brittingham, Cathy
From: Wilson, Travis W.
Sent: Thursday, February 3, 2022 2:49 PM
To: Farrell, Sean C; Brittingham, Cathy;Westphal,Anneliese
Cc: Brad Shaver(brad.e.shaver@usace.army.mil); Sprinkle, Hannah H; Harding, Kimberlee k;
fritz.rohde; Lane, Stephen
Subject: RE: B-4590 New Hanover County Bridge 29 Moratorium Relief Request
WRC does not object to also removing piles during the approved extension.
Travis W.Wilson
Eastern DOT Habitat Conservation Coordinator
Habitat Conservation Program
NC Wildlife Resources Commission
1718 Hwy 56 West
Creedmoor, NC 27522
Phone: 919-707-0370
Fax: 919-528-2524
Travis.Wilson(cr�ncwildlife.org
From: Farrell, Sean C<scfarrell@ncdot.gov>
Sent:Thursday, February 3, 2022 12:26 PM
To: Brittingham, Cathy<cathy.brittingham@ncdenr.gov>; Westphal, Anneliese<awestphal@ncdot.gov>
Cc: Brad Shaver(brad.e.shaver@usace.army.mil) <Brad.E.Shaver@usace.army.mil>; Sprinkle, Hannah H
<hannah.sprinkle@ncdenr.gov>; Harding, Kimberlee k<Kimberlee.Harding@ncdenr.gov>; Wilson,Travis W.
<travis.wilson@ncwildlife.org>;fritz.rohde<fritz.rohde@noaa.gov>; Lane, Stephen <stephen.lane@ncdenr.gov>
Subject: RE: B-4590 New Hanover County Bridge 29 Moratorium Relief Request
All,
The contractor has been able to install the 3 drill casings for one of the bents and will be moving their template today
and likely start driving the other 3 casings tomorrow.Since this seems to be going faster than anticipated the contractor
is asking if they can use any remaining time before 2/13 to remove piles associated with the existing fender system.
There also may be opportunities for the contractor to do this intermittently(i.e.,waiting for the template to be surveyed
in) while still keeping the main focus on getting the casings installed. Since this activity was not outlined in our relief
request I wanted to clarify and see if there would be any objection to pile removal during our extended in-water work
period.
Thanks,
Sean Farrell
Division Environmental Officer
Division 3
NCDOT- Division of Highways
910-341-2033 office
1
Brittingham, Cathy
From: Harding, Kimberlee k
Sent: Thursday, February 3, 2022 3:20 PM
To: Farrell, Sean C; Brittingham, Cathy;Westphal, Anneliese
Cc: Brad Shaver (brad.e.shaver@usace.army.mil); Sprinkle, Hannah H; Wilson, Travis W.;
fritz.rohde; Lane, Stephen
Subject: RE: B-4590 New Hanover County Bridge 29 Moratorium Relief Request
The NCDMF does not have any objections to pile removal during our extended in-water work period till 2/13/22.
Kimberlee Harding
From: Farrell, Sean C<scfarrell@ncdot.gov>
Sent:Thursday, February 3, 2022 12:26 PM
To: Brittingham, Cathy<cathy.brittingham@ncdenr.gov>; Westphal, Anneliese<awestphal@ncdot.gov>
Cc: Brad Shaver(brad.e.shaver@usace.army.mil)<Brad.E.Shaver@usace.army.mil>; Sprinkle, Hannah H
<hannah.sprinkle@ncdenr.gov>; Harding, Kimberlee k<Kimberlee.Harding@ncdenr.gov>; Wilson,Travis W.
<travis.wilson@ncwildlife.org>;fritz.rohde<fritz.rohde@noaa.gov>; Lane, Stephen<stephen.lane@ncdenr.gov>
Subject: RE: B-4590 New Hanover County Bridge 29 Moratorium Relief Request
All,
The contractor has been able to install the 3 drill casings for one of the bents and will be moving their template today
and likely start driving the other 3 casings tomorrow.Since this seems to be going faster than anticipated the contractor
is asking if they can use any remaining time before 2/13 to remove piles associated with the existing fender system.
There also may be opportunities for the contractor to do this intermittently(i.e., waiting for the template to be surveyed
in) while still keeping the main focus on getting the casings installed. Since this activity was not outlined in our relief
request I wanted to clarify and see if there would be any objection to pile removal during our extended in-water work
period.
Thanks,
Sean Farrell
Division Environmental Officer
Division 3
NCDOT- Division of Highways
910-341-2033 office
910-599-1184 mobile
scfarrell@ncdot.gov
5501 Barbados Blvd
Castle Hayne, NC 28429
r T 1 'ii.
1
7o-aD
Brittingham, Cathy
From: Farrell, Sean C
Sent: Thursday, February 3, 2022 12:26 PM
To: Brittingham, Cathy; Westphal, Anneliese
Cc: Brad Shaver (brad.e.shaver@usace.army.mil); Sprinkle, Hannah H; Harding, Kimberlee k;
Wilson, Travis W.;fritz.rohde; Lane, Stephen
Subject: RE: B-4590 New Hanover County Bridge 29 Moratorium Relief Request
Attachments: IMG 8052.JPG
All,
The contractor has been able to install the 3 drill casings for one of the bents and will be moving their template today
and likely start driving the other 3 casings tomorrow.Since this seems to be going faster than anticipated the contractor
is asking if they can use any remaining time before 2/13 to remove piles associated with the existing fender system.
There also may be opportunities for the contractor to do this intermittently(i.e.,waiting for the template to be surveyed
in) while still keeping the main focus on getting the casings installed. Since this activity was not outlined in our relief
request I wanted to clarify and see if there would be any objection to pile removal during our extended in-water work
period.
Thanks,
Sean Farrell
Division Environmental Officer
Division 3
NCDOT- Division of Highways
910-341-2033 office
910-599-1184 mobile
scfarreII@ncdot.gov
5501 Barbados Blvd
Castle Hayne, NC 28429
r T it1
ifA p
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.
From: Brittingham, Cathy<cathy.brittingham@ncdenr.gov>
Sent: Monday,January 31, 2022 9:53 AM
To: Westphal,Anneliese <awestphal@ncdot.gov>; Farrell, Sean C<scfarrell@ncdot.gov>
Cc: Brad Shaver(brad.e.shaver@usace.army.mil) <Brad.E.Shaver@usace.army.mil>; Sprinkle, Hannah H
<hannah.sprinkle@ncdenr.gov>; Harding, Kimberlee k<Kimberlee.Harding@ncdenr.gov>; Wilson,Travis W.
I.
<travis.wilson@ncwildlife.org>;fritz.rohde<fritz.rohde@noaa.gov>; Lane, Stephen <stephen.lane@ncdenr.gov>
Subject: B-4590 New Hanover County Bridge 29 Moratorium Relief Request
Hello,
DCM has reviewed the information submitted by the N.C. Department of Transportation (NCDOT) in the
attached cover letter dated January 28, 2022, including the attached contractor letter and schedule requesting
moratorium relief for the subject bridge.
Based upon comments received in response to this request from the N.C. Division of Marine Fisheries, the N.C.
Wildlife Resources Commission and the National Marine Fisheries Service, DCM has determined that the
NCDOT request to continue in-water work for an additional 12 days past the February Pt start date that is in the
CAMA Permit 70-20 is approved, and does not require additional authorization from DCM beyond this e-
mail. Work must be completed as described, and if any aspect of the project should change,NCDOT must
contact DCM to determine if additional authorization is necessary.
Please note that this e-mail response does not eliminate the need to obtain any additional permits, approvals or
authorizations that may be required. This includes approval, if required, from the U.S. Army Corps of
Engineers and/or the N.C. Division of Water Resources (DWR).
Please let me know if you have any questions or concerns.
Sincerely,
Cathy Brittingham
Cathy Brittingham,Transportation Project Coordinator
N.C. Division of Coastal Management
(919)707-9149 phone
cathy.brittingham@ncdenr.gov
Mailing Address:
c/o DWR Transportation Permitting Unit
1617 Mail Service Center
Raleigh,NC 27699-1617
Physical Address:
512 North Salisbury Street
Archdale Building
12th Floor, Room 1204C
Raleigh,NC 27604
Please visit https://deq.nc.aov/about/divisions/coastal-management/for more information about the N.C.Division of Coastal Management.
E-mail correspondence to and from this address may be subject to the North Carolina Public Records Law and may be disclosed to
third parties.
Email correspondence to and from this sender is subject to the N.C.Public Records Law and may be disclosed to third parties.