HomeMy WebLinkAbout2.26.22 - Oak Island QC ReportDate: 2/26/22 DAILY CONTRACTOR QUALITY CONTROL REPORT Report #: 13 GLDD# 072804 - Oak Island Renourishment Project 2021 / 2022 WEATHER CONDITIONS: Events: Cloudy Visibility: 10 TEMPERATURE (F): Min: 44 Max: 63 WIND SPEED (mph): Max: 15, Gusts to 0 Direction: NNE " WAVE HEIGHT ft.: Jay Bird Shoals: 1-3' CONTRACTOR AND AREA OF RESPONSIBILITY: Great Lakes Dredge & Dock Company, L.L.C.: Dredging and Beach fill SUBCONTRACTOR AND AREA OF RESPONSIBILITY: Subcontractor Name: TI Coastal - third party surveyor and sediment analysis. Coastwise Consulting - ESO and Trawling 1. Progress Summary: - GLDD continues to provide AD/BD Survey Planning for the following 72 hours - The material of these loads was placed between stations 576+00 and 572+00, flipped pipe west and placed material between 608+00 to 610+00 2. Safety: Pre -Shift Meeting The schedule of activities for the day was discussed which included replacing drag head wires on the dredge. Safety discussed performing housekeeping on vessels and barges to minimize tripping hazards. The crews completed Stretch and Flex exercises before starting their shift. SSHO Observation All GLDD personnel and worked with proper PPE being worn in compliance with GLDD policies and contract specifications. Observed corrective actions for deficiencies on the Lady Theo. The vessel did a good job of correcting items. In addition, vessel was was in good order and housekeeping was very good. DREDGE PADRE This Day 11 Cumulative Sand Analysis Dredge Revenue Hours 24.00 22.75 1.25 Results of Daily Sediment Inspection: Dredge Work Hours Dredge Delay Hours Est. Pay Volume CY 11,569 66,080 The sample was a mix of light, olive, and greenish gray course - grained sand with some shell fragments. Est. Dig Volume CY 15,046 85,735 Midnight Station 576+00 DREDGE DODGE This Day Cumulative Dredge Revenue Hours 24.00 21.85 2.15 Results of Daily Visual Turbidity Inspection: Dredge Work Hours Dredge Delay Hours Test conducted and within the 15A NCAC 02b.0220 criteria. Est. Pay Volume CY 5,511 44,674 Est. Dig Volume (CY) 7,167 59,284 Results of nearshore Turbidity Inspection: Midnight Station 576+00 STA. 564+50 23 NTU De th 1' Pay Volume Remaining CY 645,246 2. Explanation of Primary Downtime: Delays include: PADRE:- Flush Line and Dye Test DODGE:- Repair Broken Gimbol Wire, Fill Site pipe move/ Dye Test, Fill Site GPS signle issue GL# 072804 - Oak Island Re -nourishment Project 2020 / 2021 3. Site Equipment (Indicate items of construction equipment other than hand tools at job site) Area Description Area Description 'Dredge and Staging Area AB 114 Beach Fill GL 664 Front-end Loader Dred a and Staciing Area MB 1700 Beach Fill D7 Dozer Dredge and Staging Area Lady Theo Beach Fill D7 Dozer Dredge and Staging Area Miami River Beach Fill D7 Dozer Dredge and Staging Area Ohio River Beach Fill D6 Dozer Dredge and Staging Area Beach Fill Kabota Buaav Dredge and Staging Area Beach Fill Dred a and Staqinq Area Beach Fill Dredge and Staging Area Beach Fill Dredge and Staging Area Beach Fill Dredge and Staging Area Beach Fill Dredge and Staging Area Beach Fill SUBCONTRACTOR EQUIP Beach Fill 4. Crew: (Includes subcontractors) Labor Classifications Number of Employees Labor Classifications Number of Employees GLDD Key Personnel Beachfill Op erations Project Manager 1 General Fill Foreman 1 Site Manager 2 Equipment Operators 5 Site Administrator 1 Welders 1 SSHO 1 Shoreman 3 Pro'ect Engineer 0 0 Assistant Pro'ect Engineer 1 Subtotal 10 Site Engineer 5 Subcontractor TI Coastal Quality Control 1 Superintendent 1 Production Engineer 0 Laboror 2 Admin Assistant 0 Subtotal 3 Dredge Operations Subcontractor Coastwise- PSO Dredges PADRE ISLAND Captain 1 Superintendent 0 Chief Engineer 2 Monitors 4 Lever men 2 Subcontractor Coastwise Consulting Trawler Lady Paige Deck Captain 2 Observer - Lisa Rodriguez 1 Engineer 6 Captains 1 Oiler 1 Subtotal 6 Mate 2 TOTAL PERSONNEL 41 Deck Hand 6 Welder 1 Fuel Used allons Subtotal 35 Dodge Island 3841 DODGE ISLAND Padre Island 4340 Captain 1 Chief Engineer 2 Lever men 2 Deck Captain 2 Engineer 6 Oiler 1 Mate 2 Deck Hand 6 Welder 1 Subtotal 23 5. Quality Control Remarks: List any discussions with the Owner. Cover issues that give rise to delays, any conflicts in plans, and specifications or instructions. ESO / PSO aborad the Dredge Dodge Island (no detections) Trawler reported no relocations for this day Whale spotted in path of travel aborad dredge Padre Island, Report and sighting reported to NOAA. See attached report Upon Sighting Vessels inacted speed restiction in accordance with Specification and SARBO appendix 6. Deficiencies Documented by Client: List any discussions given by the Owner regarding construction deficiencies, testing required, etc., with action to be taken. N/A 7. Prepared by: John Killian, Contractor Quality Control Mike Hun erford, Project Manager Signature �& / Signature Daily / Progress / Task Photos a 576+00 AS 22 576+00 AS 23 581+00 AS 23 COASTWISE CONSULTING Relocation Trawl Daily Report US ArmyneCorps of Engiers Project Name: Trawler Name: Trawling for Dr Date (mm/dd/yyyy): @ I C�� l ,�! � Tow Numbers: �� - �) i t Total Tows: y V Project Captures: _�— ii—i tiff—===�� By Species: Cc — Lk — Start Time First Tow (24 hrs): _213 �f a5� End Vane Last Tow (24 hrs Biologist/ Captains : L Ohs Area, Channel or Borrow Area designation Ops Area Lat/Long (Shoreward): N 33 ° W� ° Ops Area Lat/Long (Seaward): N ° W �. Ll y3 �LQ Cm — Dc — A CH/ BA - — n's CH/BA- T155 Beaufort Sea State: 0 1 7 3 4 5 6 7 Air Temperature: I` I-57 C F Wind Direction: NNE , ij Wind Speed: Wave Height: II O-a Water Temperature (1 fathom): V °C/° Bottom Type: _ &" ENDANGERED SPECIES CAPTURED, Total for the Day: Species: Species: Species: General Release L tion Lat/Long: Tow it: Tow #: Tow #: N W Bycatch and Other Comments (including dredge presence/absence from the ioh sits. End Time: End Time: Trawl Effort Capture # Cc_.o_ Lk_ Cm4 Dc_ M4 Ao 3 AbA Total 3 Total Project Capture # Cc4 Lk_ Cm_ DcA Ei, Ao_a AbZ Total 3 Scanned with CamScanner FI '% . A ''A . 6 %'dr 11L Pff AFEM - -% R me " a -a dr— n M a 0 % M -qqhl. K ff IF 9 1 "1 r __ K 1% 1 A f COASTWISE CONSULTING - ODESS -DAILY REPORT I DATE: 62 / 2G / Z Project Name: - Dredge Name:_?,L_ZR USACE District: Dredge Firm: US Army Cords of Engineer. Contract Maintenance New Work / Beac h Load :. _ 27 Areasworked stations borrow area, Start "Y'imc First Laid: //,3a End Time Last Load. 22.2,2 (e) Ji ozI -bs) Project Takes by Species: CcAo Location, LatlLong: N �j � �° 2 � W0 3?OC� • � 3� Beaufort Sea State: 0 1 iIII TEMP*r11"b1('F z 3 � s s Wind Direction and Speed WATER TEMP*. Surface 3. 0 ° F Condition of deflector: W Column (mid -depth) 7 8 9 10 11 12 'C F Bottom 100da ------ w--..m " C /n F Condition of screening: 0 WERE THERE ENDANGERED OR PRQTEC"CED SPECIES INCIDENTS? 'V<<tiich species? (complete Incident farm)1'k YES SCREEN TYPE �' #' Inflow er Rincy: None % % 7% ;, Overflow screening: None % % 7 % 4-' Other screening-, Done % % 75% I'A -woft I -..- � -CL (—Ik 'F _LL' A & Ar-, NO r NO 0/0�. 1 UD °ro Estimate number screened on this day: Shark (any species) Horseshoe crab Time Species BRIDGE WATCH SUMMARY Sightins/ft Animals 1,ocation/Comments Observers / Watch Hours re me Name: COASTWISE CONSULTING — ODESS LARC'T N111:1LL OBSERNATION 111"ORNI Dredge F1FM 1j 31101 1 r US Array Corp of Engineers 1 _ _ [-0ad 4 M 16 Times Sian End � UM P, Pjk/� I focallon(I t/1oncr) k0A1 tR, SCcl ,tit Wind Direction_ Speed -. 'Loud Cover H2O ut-fA Tenn p Aj �-iN Stall i liii Ti�� Vessel l ci-Itio rs (l-1tr,l0z10 _ � --4i�0 dZ - 7-Yu!�) Mt�€�ii c: ri r t i �rii a� � Esti m,-it eel L i sla ncL� i)ecl s observed ed bi Vessel's )1JF- %-0 t . F= i 11 s or fl i p1- s ob sei-ved _ Sn.-L lb ehavi ors ob s v d `,- ull,fici iicy inteR-als (ume and distance) ^j 9 En itihn �, Time. a4c, �7ess l location Oat/lono) � �_ � � � 0(a , CkC� - Com ni e rats N\ as w-haI e' s b ehavi i- effected b y vessel " h0�� filr -Iiid i II w I1at dI r-CC R Io11 (IT, (l � IlaI e(s) III \.c d u I-1 n L, ob sei-vati on? who k�---a s u on Fi ed 'I) 1 t-�A�A W-Aj-V� ( \��P — Z-13,,) -�Alk k 1�� G C%�:Ilj -k �"qws ("7 Irz COASTWISE CONSULTING - ODESS Fol DAILY REPORT US Army corps of Engineers ® DATE: O ? / 2le/ 27 Project Name: Oak Island Renourishment Project USACE District: Wilmington Dredge Name: Dodge Island Dredge Firm: GLDD Contract # SAW-2018-02230 Maintenance X / New Work / Beach Load #s: 02 '� - o 25 Areas worked (stations, borrow area, etc): Zone 2G Start Time First Load: d 101 End Time Last Load: N 3 le Project Takes by Species: Cc-0Lk4CmkDc_)Lf_Ao_X _Other / Location, Lat/Long: N 33 ° b 2 . U5!8 x W-15 ° 03 . A Beaufort Sea State: 0 1 2 03 4 5 6 7 8 1I9 10 11 12 AIR TEMP: • 3 ° C / ° F Wind Direction and Speed WATER TEMP: Surface-0 .10 ° C /° F Column (mid -depth) — ° C /° F Bottom — ° C P F Condition of deflector: C pod Condition of screening: and WERE THERE ENDANGERED OR PROTECTED SPECIES INCIDENTS? YES NO ® Which species? (complete Incident form) 1 vl PI SCREEN TYPE 4x4 Inflow screening: None 25% 50% 75% 4x4 Overflow screening: None 25% 50% 75% Volo — Other screening: None 25% 50% 75% of material, biological specimens, unusual circumstances, etc): �60LC . Sard Nu.fA Estimate number screened on this day: Shark (any species) Horseshoe crab Time BRIDGE WATCH SUMMARY Species # SiehtinQs/# Animals / Location/Comments Observers / Watch Great Lakes Dredge & Dock Company ]ro Created by Delay Tracker 3000a Datebase: SQL 4 Daily Mate's Log for: February 26 2022, Saturday Project Number: 072804 Project Name: Oak Island Renourishment Project Project Location: Oak Island, NC Project Description: Oak Is Beach, NC 2021 Delays Vessel Type: Hopper Dredge Vessel Name: Dodge Island Database Modification Date: February 27 2022 0:34:50 ID Load Start Finish Duration LZmin Category Subcategory Delay Type Description 13,792,529 23:30 Off Dredge Fill Site Fill Site 13,792,528 25 18:43 18:48 0.08 5 Off Dredge Fill Site Fill Site 13,792,527 24 13:41 14:14 0.56 34 Survey Calibration Survey 5;� 13,792,526 23 00:00 01:00 1.01 61 Gimbal Hoist Wires Gimbal Hoist Delay Count: 4 Total Delay (h.hh): 1.65 Work Time (h.hh): 22.35 Time Efficiency: 93.1% -mechanical oM - one arm Daily Note No record. DYE TEST WIRE BROKE. HAVE TO RETRIEVE GIMBAL Created on 2/27/2022 0:34 Page 1 of 9 Great Lakes Dredge & Dock Company Created by Delay Tracker 3000a Datebase: SQL 41Aff Daily Mate's Log for: February 26 2022, Saturday Project Number: 072804 Project Name: Oak Island Renourishment Project Project Location: Oak Island, NC Project Description: Oak Is Beach, NC 2021 Delays Vessel Type: Hopper Dredge Vessel Name: Padre Island Database Modification Date: February 27 2022 1:57:56 ID Load Start Finish Duration Category Subcategory Delay Type Description h.hh min 25,517,141 31 17:22 17:40 0.30 18 Off Dredge Fill Site Flush Line Fill Site 25,517,140 30 12:59 13:04 0.09 5 Off Dredge Fill Site Flush Line Fill Site 25,517,139 30 11:06 11:53 0.79 47 Survey Calibration Survey 25,517,138 28 02:57 03:02 0.08 5 Off Dredge Fill Site Flush Line Fill Site Delay Count: 4 Total Delay (h.hh): 1.26 Work Time (h.hh): 22.74 Time Efficiency: 94.8% -mechanical oM - one arm Daily Note No record. dye test Created on 2/27/2022 1:58 Page 1 of 9 0 70Nr:: L. /. 9B Ir sw�70NP: ` — Depth Range Color from to -10 14 14.1 16 16.1 18 18.1 20 20.1 22 22.1 24 24.1 26 26.1 28 28.1 30 30.1 32 32.1 34 LEGEND GRAPHIC SCALE m-mmm-m---m ----W�---- Tht' dxvment rontaliti confldenYtal and proprletary Inf'--t— of Creat Lakrs Dr cdge 6 Duck Compeay. /f you have,—d this document fi e irzuned,-Jy drerd or destroy It mth- ropy! g or distributing further. A U N:y ZONE 2B Depth Range Color from to -10 14 14.1 16 16.1 18 18.1 20 20.1 22 22.1 24 24.1 26 26.1 28 28.1 30 30.1 32 32.1 34 ZONE 1B ZONE 1 C q GREAT LAKES DREDGE AND DOCK COMPANY ± zfzz PORK ROAD OAK BROOK IL 60523 CIVIL ENGINEERING /SURVEYING DIVISION Phone.(630)574-3000 Fax (630)574-15/5 PROJECT: 72804 Oak Island Beach RenoUrishment PROJECT METADATA LEGEND GRAPTTTC SC:a T'r PAGE OF 1 PA-S (IN FEET) TITLE : 220226 PI Jay Bird Shoals BA Depth Loads 28-33 „„asee.a. rye DISPOSAL DATE 300 0 150 300 800 1200 i >a� = soo: t< ��er..,oa„o �Ta.„eo a. em sine This documentrontellns confidential and pruprietar,iri Halloo oi'Greal LaArs Dredge&Dock Company. /f you have rerei thin document in ertor, immediately discard or destroy it without ropying or dtstrlbuting f-hef- rune. GAU. NM.mem m (GLDD)wtieaa oak ieia„d�Predecdon d. isiaeeba Dredge Tackiegtneoa oak lsba d Pi Dredge Tackieg.dw