HomeMy WebLinkAboutCAPE HATTERAS 2006 GROIN REHAB, PROBABLE COST 04102006OPINION OF PROBABLE COST
DATE PREPARED
10-Apr-06
SHEET OF
1 1
ACTIVITY AND LOCATION
Cape Hatteras
CONSTRUCTION CONTRACT NO.
IDENTIFICATION NUMBER
ESTIMATED BY
Moffatt & Nichol
CATEGORY CODE NUMBER
PROJECT TITLE
Existing Groin 1 PCSP
STATUS OF DESIGN
Conceptual Design
JOB ORDER NUMBER
5811
ITEM DESCRIPTION
ENGINEERING ESTIMATE
TOTAL COST
SUMMARY:
MOBILIZATION AND DEMOBILIZATION
OPINION OF PROBABLE COST
TOTAL
$50,000.00
$172,500.00
$222,500.00
OPINION OF PROBABLE COST
DATE PREPARED
10-Apr-06
SHEET OF
1 1
ACTIVITY AND LOCATION
Cape Hatteras
CONSTRUCTION CONTRACT NO
IDENTIFICATION NUMBER
ESTIMATED BY
Moffatt & Nichol
CATEGORY CODE NUMBER
PROJECT TITLE
Groin 1 - 18 inch thick precast concrete sheet pile
STATUS OF DESIGN
Conceptual Design
JOB ORDER NUMBER
5811
ITEM DESCRIPTION
QUANTITY
MATERIALCOST
LABOR COST
ENGINEERING ESTIMATE
NUMBER UNIT
UNIT COST TOTAL
UNIT COST TOTAL
UNIT COST I TOTAL
CONSTRUCTION 11 inch PCSP :
Precast Concrete Sheet pile
Wale, connections
Insurance and Taxes
Sales Tax
Overhead and Profit (Materials)
Overhead and Profit (Labor)
Bonds
Total Estimated Contractor Cost
Contingency
TOTAL ESTIMATED COST
146 LF $470.00 $68,620
146 LF $20.00 $2,920
Sub -Total $71,540
32.00%
6.00%
10.00%
22.00%
0.75%
20%
$4,292
Sub -Total $75,832
$7,583
$83,416
$232.00 $33,872 $702.00
$102,492
$20.00 $2,920 $40.00
$5,840
$36,792
$108,332
$11,773
$11,773
$4,292
$48,565
$124,398
$7,583
$10,684
$10,684
$1,070
$59,250
$143,735
$28,747
SAY: $772,500
OPINION OF PROBABLE COST
DATE PREPARED
10-Apr-06
SHEET OF
1 1
ACTIVITY AND LOCATION
Cape Hatteras
CONSTRUCTION CONTRACT NO.
IDENTIFICATION NUMBER
ESTIMATED BY
CATEGORY CODE NUMBER
PROJECT TITLE
Moffatt & Nichol
Rehabiliation Groin 1 PCSP
STATUS OF DESIGN
JOB ORDER NUMBER
Conceptual Design
5811
ITEM DESCRIPTION
ENGINEERIN G ESTIMATE
OTAL COST
SUMMARY:
MOBILIZATION AND DEMOBILIZATION ASSUME TWICE
OPINION OF PROBABLE COST
TOTAL
$100,000.00
$396,200.00
$496,200.00
OPINION OF PROBABLE COST
DATE PREPARED
10-Apr-06
SHEET OF
1 1
ACTIVITY AND LOCATION
Cape Hatteras
CONSTRUCTION CONTRACT NO
IDENTIFICATION NUMBER
ESTIMATED BY
Moffatt & Nichol
CATEGORY CODE NUMBER
PROJECT TITLE
Groin 1 - 18 inch thick precast concrete sheet pile
STATUS OF DESIGN
Conceptual Design
JOB ORDER NUMBER
5811
ITEM DESCRIPTION
QUANTITY
MATERIAL COST
LABOR COST
ENGINEERING ESTIMATE
NUMBER UNIT
UNIT COST I TOTAL
UNIT COST TOTAL
UNIT COST TOTAL
CONSTRUCTION 18 inch PCSP :
Precast Concrete Sheet pile
Wale, connections
Insurance and Taxes
Sales Tax
Overhead and Profit (Materials)
Overhead and Profit (Labor)
Bonds
Total Estimated Contractor Cost
Contingency
TOTAL ESTIMATED COST
384 LF $567.60 $217,958
384 LF $20.00 $7,680
Sub -Total $225,638
32.00%
6.00%
10.00%
22.00%
0.75%
20%
$13, 538
Sub -Total $239,177
$23,918
$263,094
$84.50 $32,448 $652.10 $250,406
$20.00 $7,680 $40.00 $15,360
$40,128 $265,766
$12,841 $12,841
$13,538
$52,969 $292,146
$23,918
$11,653 $11,653
$2,458
$64,622 $330,174
$66,035
SAY: $396,200
OPINION OF PROBABLE COST
DATEPREPARED
1 O-Apr-06
SHEET OF
1 1
ACTIVITY AND LOCATION
Cape Hatteras
CONSTRUCTION CONTRACT NO.
IDENTIFICATION NUMBER
ESTIMATED BY
Moffatt & Nichol
CATEGORY CODE NUMBER
PROJECT TITLE
Groin 1 New Steel Sheet Pile Constructruction
STATUS OF DESIGN
Conceptual Design .
JOB ORDER NUMBER
5611
ITEM DESCRIPTION
ENGINEERING ESTIMATE
TOTAL COST
SUMMARY:
MOBILIZATION AND DEMOBILIZATION ASSUME TWICE
OPINION OF PROBABLE COST
TOTAL
$1 00,000.00
$394,600.00
$494,600.00
OPINION OF PROBABLE COST
DATE PREPARED
10-Apr-06
OF
SHEET 1 1
ACTIVITY AND LOCATION
Cape Hatteras
CONSTRUCTION CONTRACT NO.
IDENTIFICATION NUMBER
ESTIMATED BY
Moffatt & Nichol
CATEGORY CODE NUMBER
PROJECT TITLE
Groin 1 New Steel Sheet Pile Construction
STATUS OF DESIGN
Conceptual Design
JOB ORDER NUMBER
5811
ITEM DESCRIPTION
QUANTITY
MATERIAL COST
LABOR COST
ENGINEERING ESTIMATE
NUMBER UNIT
UNITCOST TOTAL
UNIT COST TOTAL
UNITCOST TOTAL
CONSTRUCTION PZ-27 :
PZ 27 Steel Sheet Piles
Wale, connections
Insurance and Taxes
Sales Tax
Overhead and Profit (Materials)
Overhead and Profit (Labor)
Bonds
Total Estimated Contractor Cost
Contingency
TOTAL ESTIMATED COST
108 Ton $2,259.17 $243,991
6 Ton $295.00 $1,770
Sub -Total $245,761
32.00%
6.00%
10.00%
22.00%
0.75%
20%
$14,746
Sub -Total $260,506
$26, 051
$286,557
$228.80 $24,710
$0.00 $0
$24,710
$7,907
$32,618
$7,176
$39,794
$2,487.97 $268,701
$295.00 $1,770
$270,471
$7,907
$14,746
$293,124
$26,051
$7,176
$2,448
$328,798
$65,760
SAY: $394,600
OPINION OF PROBABLE COST
DATE PREPARED
SHEET OF
1
10-Apr-06
1
ACTIVITY AND LOCATION
CONSTRUCTION CONTRACT NO.
IDENTIFICATION NUMBER
Cape Hatteras
ESTIMATED BY
CATEGORY CODE NUMBER
PROJECT TITLE
Moffatt & Nichol
Existing Groin 2 PCSP
STATUS OF DESIGN
JOB ORDER NUMBER
Conceptual Design
5811
ITEM DESCRIPTION
ENGINEERING ESTIMATE
TOTAL COST
SUMMARY:
MOBILIZATION AND DEMOBILIZATION
OPINION OF PROBABLE COST
TOTAL
$50,000.00
$290,600.00
$340,600.00
OPINION OF PROBABLE COST
DATE PREPARED
SHEET OF
10-Apr-06
1 1
ACTIVITY AND LOCATION
CONSTRUCTION CONTRACT NO.
IDENTIFICATION NUMBER
Cape Hatteras
ESTIMATED BY
Moffatt & Nichol
CATEGORY CODE NUMBER
PROJECT TITLE
Groin 2 - 11 inch thick precast concrete sheet pile
STATUS OF DESIGN
JOB ORDER NUMBER
Conceptual Desi n
5811
QUANTITY
MATERIAL COST
LABOR COST
ENGINEERING ESTIMATE
ITEM DESCRIPTION
NUMBER UNIT
UNIT COST TOTAL
UNIT COST TOTAL
UNIT COST TOTAL
CONSTRUCTION 11 inch PCSP
Precast Concrete Sheet pile
Wale, connections
Insurance and Taxes
Sales Tax
Overhead and Profit (Materials)
Overhead and Profit (Labor)
Bonds
Total Estimated Contractor Cost
Contingency
TOTAL ESTIMATED COST
246 LF $470.00 $115,620
246 LF $20.00 $4,920
Sub -Total $120,540
32.00%
6.00%
10.00%
22.00%
0.75%
20%
$7,232
Sub -Total $127,772
$12,777
$140,550
$232.00 $57,072
$20.00 $4,920
$61, 992
$19,837
$81,829
$18, 002
$99,832
$702.00 $172,692
$40.00 $9,840
$182,532
$19,837
$7,232
$209,602
$12,777
$18,002
$1,803
$242,184
$48,437
SAY: $290,600
OPINION OF PROBABLE COST
DATE PREPARED
10-Apr-06
SHEET OF
1 1
ACTIVITY AND LOCATION
Cape Hatteras
CONSTRUCTION CONTRACT NO.
IDENTIFICATION NUMBER
ESTIMATED BY
Moffatt & Nichol
CATEGORY CODE NUMBER
PROJECT TITLE
Rehabiliation Groin 2 - PCSP
STATUS OF DESIGN
Conceptual Design
JOB ORDER NUMBER
5811
ITEM DESCRIPTION
ENGINEERING ESTIMATE
TOTAL COST
SUMMARY:
MOBILIZATION AND DEMOBILIZATION ASSUME TWICE
OPINION OF PROBABLE COST
TOTAL
$100,000.00
$293,000.00
$393,000.00
OPINION OF PROBABLE COST
DATE PREPARED
SHEET OF
10-Apr-06
1
L
ACTIVITY AND LOCATION
CONSTRUCTION CONTRACT NO.
IDENTIFICATION NUMBER
Cape Hatteras
ESTIMATED BY
Moffatt & Nichol
CATEGORY CODE NUMBER
PROJECT TITLE
Groin 2 - 18 inch thick precast concrete sheet pile
STATUS OF DESIGN
JOB ORDER NUMBER
Conceptual Design
5811
QUANTITY
MATERIAL COST
LABOR COST
ENGINEERING ESTIMATE
ITEM DESCRIPTION
NUMBER JUNIT
I UNIT COST I TOTAL
UNIT COST TOTAL
UNIT COST TOTAL
CONSTRUCTION 18 inch PCSP :
Precast Concrete Sheet pile
Wale, connections
Insurance and Taxes
Sales Tax
Overhead and Profit (Materials)
Overhead and Profit (Labor)
Bonds
Total Estimated Contractor Cost
Contingency
TOTAL ESTIMATED COST
284 LF $567.60 $161,198
284 LF $20.00 $5,680
Sub -Total $166,878
32.00%
6.00%
10.00%
22.00%
0.75%
20%
$10,013
Sub -Total $176,891
$17,689
$194,580
$84.50 $23,998 $652.10 $185,196
$20.00 $5,680 $40.00 $11,360
$29,678 $196,556
$9,497 $9,497
$10,013
$39,175 $216, 066
$17,689
$8,618 $8,618
$1,818
$47,793 $244,191
$48,838
SAY: $293,000
OPINION OF PROBABLE COST
DATE PREPARED
10-Apr-06
SHEET OF
1 1
ACTIVITY AND LOCATION
Cape Hatteras
CONSTRUCTION CONTRACT NO.
IDENTIFICATION NUMBER
ESTIMATED BY
Moffatt & Nichol
CATEGORY CODE NUMBER
PROJECT TITLE
Groin 2 New Construction SSP
STATUS OF DESIGN
Conceptual Design
JOB ORDER NUMBER
5811
ITEM DESCRIPTION
ENGINEERING ESTIMATE
TOTAL COST
SUMMARY:
MOBILIZATION AND DEMOBILIZATION ASSUME TWICE
OPINION OF PROBABLE COST
TOTAL
$100,000.00
$291,900.00
$391,900.00
OPINION OF PROBABLE COST
DATE PREPARED
10-Apr-06
SHEET OF
1 1
ACTIVITY AND LOCATION
Cape Hatteras
CONSTRUCTION CONTRACT NO.
IDENTIFICATION NUMBER
ESTIMATED BY
Moffatt & Nichol
CATEGORY CODE NUMBER
PROJECT TITLE
Groin 2 New Construction SSP
STATUS OF DESIGN
Conceptual Design
JOB ORDER NUMBER
5811
17 7QUANTITY
ITEM DESCRIPTION
MATERIALCOST
LABOR COST
ENGINEERING ESTIMATE
NUMBER UNIT
UNIT COST TOTAL
UNIT COST TOTAL
UNITCOST TOTAL
CONSTRUCTION PZ-27 :
PZ 27 Steel Sheet Piles
Wale, connections
Insurance and Taxes
Sales Tax
Overhead and Profit (Materials)
Overhead and Profit (Labor)
Bonds
Total Estimated Contractor Cost
Contingency
TOTAL ESTIMATED COST
80 Ton $2,259.17 $180,734 $228.80
4 Ton $295.00 $1,062 $0.00
Sub -Total $181,796
32.00%
6.00%
10.00%
22.00%
0.75%
20%
$10,908
Sub -Total $192,704
$19,270
$211,974
$18,304 $2,487.97
$0 $295.00
$18,304
$5,857
$24,161
$5,315
$29,477
$199,038
$1,062
$200,100
$5,857
$10,908
$216,865
$19,270
$5,315
$1,811
$243,262
$48,652
SAY: $291,900
OPINION OF PROBABLE COST
DATE PREPARED
10-Apr-06
SHEET OF
1 1
ACTIVITY AND LOCATION
Cape Hatteras
CONSTRUCTION CONTRACT NO.
IDENTIFICATION NUMBER
ESTIMATED BY
Moffatt & Nichol
CATEGORY CODE NUMBER
PROJECT TITLE
Exisitng Groin 3 SSP
STATUS OF DESIGN
Conceptual Design
JOB ORDER NUMBER
5811
ITEM DESCRIPTION
ENGINEERING ESTIMATE
TOTAL COST
SUMMARY:
MOBILIZATION AND DEMOBILIZATION
OPINION OF PROBABLE COST
TOTAL
$50,000.00
$1,085,500.00
$1,135,500.00
OPINION OF PROBABLE COST
DATE PREPARED
SHEET OF
10-Apr-06
1 1
ACTIVITY AND LOCATION
CONSTRUCTION CONTRACT NO.
IDENTIFICATION NUMBER
Cape Hatteras
ESTIMATED BY
CATEGORY CODE NUMBER
PROJECT TITLE
Moffatt & Nichol
Groin 3 EXISTING PZ-27
STATUS OF DESIGN
JOB ORDER NUMBER
Conceptual Design
5811
OUANTITV
MATERIAL COST
LABOR COST
ENGINEERING ESTIMATE
ITEM DESCRIPTION
NUMBER UNIT
UNIT COST TOTALI
UNIT COST TOTAL
UNIT COST TOTAL
CONSTRUCTION PZ-27 :
PZ 27 Steel Sheet Piles
Wale, connections
Insurance and Taxes
Sales Tax
Overhead and Profit (Materials)
Overhead and Profit (Labor)
Bonds
Total Estimated Contractor Cost
Contingency
TOTAL ESTIMATED COST
150 Ton $2,259.17
6 Ton $295.00
Sub -Total
32.00%
6.00%
10.00%
22.00%
0.75%
20%
$338,876
$1,770
$340, 646
$20,439
Sub -Total $361,085
$36,108
$397,193
$228.80 $34,320 $2,487.97
$373,196
$0.00 $0 $295.00
$1,770
$34,320
$374,966
$10,982
$10,982
$20,439
$45,302
$406,387
$36,108
$9,967
$9,967
$3,393
$55,269
$455,855
$91,171
SAY: $547,000
OPINION OF PROBABLE COST
DATE PREPARED
10-Apr-06
SHEET OF
1 1
ACTIVITY AND LOCATION
Cape Hatteras
CONSTRUCTION CONTRACT NO
IDENTIFICATION NUMBER
ESTIMATED BY
Moffatt & Nichol
CATEGORY CODE NUMBER
PROJECT TITLE
Groin 3 EXISTING PZ-40
STATUS OF DESIGN
Conceptual Design
JOB ORDER NUMBER
5811
ITEM DESCRIPTION
QUANTITY
MATERIAL COST
LABOR COST
ENGINEERING ESTIMATE
NUMBER JUNIT
I UNITCOST I TOTAL
UNITCOST TOTAL
UNITCOST TOTAL
CONSTRUCTION PZ-40 :
PZ 40 Steel Sheet Piles
Wale, connections
Insurance and Taxes
Sales Tax
Overhead and Profit (Materials)
Overhead and Profit (Labor)
Bonds
Total Estimated Contractor Cost
Contingency
TOTAL ESTIMATED COST
148 Ton $2,259.17 $334,358 $228.80
3 Ton $295.00 $885 $0.00
Sub -Total $335,243
32.00%
6.00%
10.00%
22.00%
0.75%
20%
$20,115
Sub -Total $355,357
$35,536
$390,893
$33,862 $2,487.97 $368,220
$0 $295.00 $885
$33,862 $369,105
$10,836 $10,836
$20,115
$44,698 $400,055
$9,834
$54,532
$35,536
$9,834
$3,341
$448,765
$89,753
SAY: $538,500
OPINION OF PROBABLE COST
DATE PREPARED
10-Apr-06
SHEET OF
1 1
ACTIVITY AND LOCATION
Cape Hatteras
CONSTRUCTION CONTRACT NO.
IDENTIFICATION NUMBER
ESTIMATED BY
Moffatt & Nichol
CATEGORY CODE NUMBER
PROJECT TITLE
Groin 3 New Construction SSP
STATUS OF DESIGN
Conceptual Design
JOB ORDER NUMBER
5811
ITEM DESCRIPTION
ENGINEERING ESTIMATE
TOTAL COST
SUMMARY:
MOBILIZATION AND DEMOBILIZATION ASSUME TWICE
OPINION OF PROBABLE COST
TOTAL
$100,000.00
$1,280,700.00
$1,380,700.00
OPINION OF PROBABLE COST
SHEET OF
�PREPAOR6ED
1 1
ACTIVITY AND LOCATION
CONSTRUCTION CONTRACT NO.
IDENTIFICATION NUMBER
Cape Hatteras
ESTIMATED BY
Moffatt & Nichol
CATEGORY CODE NUMBER
PROJECT TITLE
Groin 3 - New Construction SSP
STATUS OF DESIGN
JOB ORDER NUMBER
Conceptual Design
5811
QUANTITY
MATERIAL COST
LABOR COST
I ENGINEERING ESTIMATE
ITEM DESCRIPTION
NUMBER UNIT
UNIT COST TOTAL
UNIT COST TOTAL
UNIT COST TOTAL
CONSTRUCTION PZ-40 :
PZ 40 Steel Sheet Piles
Wale, connections
Insurance and Taxes
Sales Tax
Overhead and Profit (Materials)
Overhead and Profit (Labor)
Bonds
Total Estimated Contractor Cost
Contingency
TOTAL ESTIMATED COST
352 Ton $2,259.17
7 Ton $295.00
32.00%
6.00%
10.00%
22.00%
0.75%
20%
Sub -Total
$795,228
$2,065
$797,293
$47,838
Sub -Total $845,130
$84,513
$929,643
$228.80 $80,538
$0.00 $0
$80,538
$25,772
$106,310
$23,388
$129,698
$2,487.97 $875,765
$295.00 $2,065
$877,830
$25,772
$47,833
$951,440
$84,513
$23,388
$7,945
$1,067,286
$213,457
SAY: $1,280,700