From: James Stephenson <jstephenson@beacon-street.com>
Sent: Wednesday, February 9, 2022 11:30 AM
To: Grandy, Ashley; Dunn, Maria T.; Harrison, James A
Cc: tobin@rsnet.org; Spivey, Kelly; Bodnar, Gregg
Subject: Re: [External] Moss East
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to
Report Spam.
Ashley et al,
We acknowledge the relief in the moratorium and will work within these guidelines.
Thank you for processing this request.
Sincerely,
James Stephenson
BEACON STREET
0. 919.785.1445
JAMES STEPHENSON M. 919.219.8238
Development Manager jstephenson@beacon-street.com
Beacon-Street.com
From: Grandy, Ashley <ashley.grandy@ncdenr.gov>
Date: Wednesday, February 9, 2022 at 9:38 AM
To: Dunn, Maria T. <maria.dunn@ncwildlife.org>, Harrison, James A <James.Harrison@ncdenr.gov>
Cc: tobin@rsnet.org <tobin@rsnet.org>, James Stephenson <jstep henson@beacon-street.com>, Spivey, Kelly
<kelly.spivey@ncdenr.gov>, Bodnar, Gregg <gregg.bodnar@ncdenr.gov>
Subject: RE: [External] Moss East
Jimmy and Maria,
Thank you for the quick response. We will notify Mr. lames Stephenson that Moss East has been granted moratorium
relief through Feb 28, 2022.
Ashley
Bodnar, Gregg
From: Harrison, James A
Sent: Wednesday, February 9, 2022 9:18 AM
To: Grandy, Ashley, Dunn, Maria T.
Cc: tobin@rsnet.org; James Stephenson; Spivey, Kelly; Bodnar, Gregg
Subject: Re: [External] Moss East
Good morning Ashley,
DMF has reviewed the moratorium relief request submitted in regards to the Moss East permit (CAMA Major
Permit # 115-21). The permit included a 15 February through 30 September moratorium on all in -water work.
Inclusion of this permit condition is intended to minimize impacts to resources of interest to the Division of
Marine Fisheries and Wildlife Resources Commission, including a variety of fish species. Due to the need for
different constnuction materials than what was expected, delays in construction have occurred.
DMF is amenable to granting moratorium relief through 28 February. Based on the information submitted with
the request, DMF believes that this is sufficient time to complete construction of the bulkhead portion of the
project, including removal of any water -based construction equipment.
Thank you for providing DMF with the opportunity to provide feedback.
Jimmy
Jimmy Harrison
Ha6itat and Enhancement Section
NC Division of Marine riskeries
j a mes.6a rriso nC@ n cd e n r.gov
252-948-3835 (Office)
757-272-3230 (Mo6ile)
Email correspondence to and from this address is subject to the
North Carolina Public Records Lmr and may he disclosed to third parties.
From: Grandy, Ashley <ashley.grandy@ncdenr.gov>
Sent: Friday, February 4, 2022 11:06 AM
To: Dunn, Maria T. <maria.dunn@ncwildlife.org>; Harrison, James A <James.Harrison@ncdenr.gov>
Cc: tobin@rsnet.org <tobin@rsnet.org>; James Stephenson <jstephenson@beacon-street.com>; Spivey, Kelly
<kelly.spivey@ncdenr.gov>; Bodnar, Gregg <gregg.bodnar@ncdenr.gov>
Subject: RE: [External] Moss East
Jimmy & Maria,
From: Dunn, Maria T.
Sent: Wednesday, February 9, 2022 9:08 AM
To: Grandy, Ashley <ashley.grandy@ncdenr.gov>; Harrison, James A <James.Harrison @ncdenr.gov>
Cc: tobin@rsnet.org; James Stephenson <jstephenson@beacon-street.com>; Spivey, Kelly <kelly.spivey@ncdenr.gov>;
Bodnar, Gregg <gregg.bodnar@ncdenr.gov>
Subject: RE: [External) Moss East
Good morning Ashely,
NCWRC has reviewed the request to continue work on bulkhead installation for the Moss East project. The majority of
the work has been completed outside of the moratorium, but due to the need of different marine materials, a delay has
occurred.
The NCWRC requested the February 15 — September 30 in -water work moratorium as a permit condition to protect
primary nursery area (PNA) resources, including Atlantic sturgeon. We believe minimizing certain disturbances during
this period is a very important fishery management tool. However, due to the description of work provided, the
proposed schedule, and reported activity in the river, an allowance to work through February 28 would not cause
significant impacts. This two -week extension should provide adequate time if the project progresses as proposed.
Extended time into March would be problematic.
Thank you for the opportunity to provide comment on this request. Please continue to inform NCWRC of the project's
progression or complications if they arise.
Maria
Maria T. Dunn
Coastal Coordinator
NC Wildlife Resources Commission
943 Washington Sq. Mall
Washington, NC 27889
office: 252-948-3916
www.ncwildlife.org
Email correspondence to and from this sender is subject to the N.C. Public Records Law and may be disclosed to third parties.
From: Grandy, Ashley <ashley.grandv6Dncdenr.Rov>
Sent: Friday, February 4, 2022 11:07 AM
To: Dunn, Maria T. <maria.dunn@ncwildlife.org>; Harrison, lames A <James.Harrison@ncdenr.gov>
Cc: tobin@rsnet.org; James Stephenson <isteohenson@beacon-street.com>; Spivey, Kelly <kellv.spivev@ncdenr.gov>;
Bodnar, Gregg <gregg.bodnar@ncdenr.gov>
Subject: RE: [External) Moss East
Jimmy & Maria,
Mr. James Stephenson Development Manager at Moss East has requested a 2-week relief from the moratorium placed
on CAMA Major Permit 115-21 for all in water work from February 15`b —September 301 of every year. They have
currently have set 940' of their permitted 1,140' of permitted bulkhead to date. They had a problem this week that will
delay the completion date of the project. They found their vinyl bulkhead sheets to be an inadequate length and have
had to order additional materials to complete the project correctly. The contractor on site said the delivery date for the
additional materials is 11-February-2022 and he would be able to complete all in water work for the bulkhead project
within the requested two -week relief window which would be March 1, 2022. Please let me know if you have any
additional questions or concerns involving this request.
Ashley Grandy
Field Representative, Division of Coastal Management
North Carolina Department of Environmental Quality
252 946-6481 office
252 948 3854 direct office
a s h l ev.g ra n d y (dn cd e n r.g ov
943 Washington Square Mall
Washington, North Carolina 27889
^Nothing Compares. �.
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.
From: James Stephenson fmailto:istephenson@beacon-street.com]
Sent: Thursday, February 3, 2022 4:05 PM
To: Spivey, Kelly <kellv.spivev@ncdenr.gov>; Grandy, Ashley <ashlev.grandv@ncdenr.gov>
Cc: tobin@rsnet.org
Subject: [External] Moss East
rnal email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to
Report Spam. ,
Kelly -
I hope you are doing well. I just spoke with our Marine Contractor, TJ's Marine -Toby Tetterton. We are on the last 200
feet of bulkhead at Moss East and have hit a snag. In the last section, 16' sheets are proving to be inadequate in
length. Until now the 16' sheets have worked well. Mr. Tetterton is trying to get 20' vinyl sheets to finish up and achieve
the required resistance when driving the sheets. The delivery date of the vinyl sheet pile is scheduled for next Friday 2/11.
We would like to ask for 2 week relief in the moratorium to be able to complete the job and get out of the water. Does
your office handle this request or do I need to direct the question to someone else? Thank you for your direction with this.
Sincerely,
James Stephenson
BEACON