STATE OF NORTH CAROLINA
Department of Environmental Quality
and
Coastal Resources Commission
V e r m t
for
X Major Development in an Area of Environmental Concern
pursuant to NCGS I I3A-118
Excavation and/or filling pursuant to NCGS 113-229
Permit Number
34-22
Issued'to Bluewater Point, LLC, c/o Todd Isenhour, 3411 Healy Drive, Suite A, Winston-Salem, NC 27103
Authorizing development in Brunswick County at adi. to the AIWW, at 5710 57th Place West,
in Oak Island as requested in the permittee's application dated 9/29/21 (MP-1 & MP-4) , incl.
work plan drawings (3) Sheets 1-2 of 2, dated 9/29/21, and physical survey dated "received in MHC 12/2/21".
This permit, issued on March 23, 2022 , is subject to compliance with the application (where
consistent with the permit), all applicable regulations, special conditions and notes set forth below. Any violation
of these terms may be subject to fines, imprisonment or civil action; or may cause the permit to be null and void.
Upland Development — Parking Areas
Unless specifically altered herein, this permit authorizes the grading and other land disturbing
activities associated with the development of the above referenced property, including improvements
to the two proposed parking areas and dumpster pad, all as expressly and specifically set forth in the
attached permit application and workplan drawings.
(See attached sheets for Additional Conditions)
This permit action maybe appealed by the permittee or other
qualified persons within twenty (20) days of the issuing date.
This permit .must be accessible on -site to Department
personnel when the project is inspected for compliance.
Any maintenance work or project modification not covered
hereunder requires further Division approval.
All work must cease when the permit expires on
December 31, 2025
In issuing this permit, the State of North Carolina agrees that
your project is consistent with the North Carolina Coastal
Management Program.
Signed by the authority of the Secretary of DEQ and the Chair
of the Coastal Resources Commission.
Braxton C. Davis, Director
Division of Coastal Management
This permit and its conditions are hereby accepted.
Signature of Permittee
Bluewater Point, LLC
ADDITIONAL CONDITIONS
Marina
Permit No. 34-22
Page 2 of 3
2) This permit authorizes only the docks, piers, gazebos, pump out facility, and other structures and uses
located in or over the water that are expressly and specifically set forth in the permit application. No
other structure, whether floating or stationary, shall become a permanent part of this marina without
permit modification. No non -water dependent uses of structures shall be conducted on, in or over Public
Trust waters without permit modification.
3) This permit authorizes a maximum of 50 formalized boat slips.
4) No portion of the authorized docking facility, including tie piles, shall extend more than one quarter of
the width of the water body. Measurements to determine width of the water body shall be made from the
normal high-water line or the waterward edge of any coastal wetland vegetation which borders the water
body, whichever is more restrictive.
5) Any portion of the permitted access pier and docking facilities built over wetlands shall not exceed six
feet in width and shall be elevated a minimum of three feet above the wetland substrate as measured
from the bottom of the decking.
6) The authorized covered gazebos shall not be enclosed. Any material used on the sides shall not obstruct
view and shall be permeable to air and water. Screen or wire on the sides along with benches are
permitted. Lattice is specifically excluded from being used under this authorization.
7) The roof of the covered gazebos shall not be designed for second story,use.
8) The permittee shall install and maintain at his expense any signal lights or signals prescribed by the U.S.
Coast Guard, through regulation or otherwise, on the authorized facilities. At minimum, permanent
reflectors shall be attached to the structure in order to make it more visible during hours of darkness or
inclement weather.
9) The piers and associated structures shall have a minimum setback distance of 15 feet between any parts
of the structure and the adjacent property owner's area of riparian access.
0) No attempt shall be made by the permittee to prevent the full and free use by the public of all navigable
waters at or adjacent to the authorized work.
1.1) The authorized structure and associated activity shall not cause an unacceptable interference with
navigation and shall not exceed the dimensions shown on the attached permit drawings.
12) Prior to the occupancy of any new slips authorized under this permit, a marine pump out sewage
disposal facility shall be installed in an easily accessible location and maintained in operable condition
for the life of the marina.
13) Prior to the occupancy of any slips authorized by this permit, the permittee shall meet on -site with a
representative of the Division to ensure that the required pump out facility is in place and operable.
Bluewater Point, LLC Permit No. 34-22
Page 3 of 3
ADDITIONAL CONDITIONS
14) The marina shall display a sign showing the location of the on -site pump out facility, including other
appropriate waste disposal information, at the entrance and exit from the main pier(s).
Sedimentation and Erosion Control
15) In order to protect water quality, runoff from construction shall not visibly increase the amount of
suspended sediments in adjacent waters.
16) Appropriate sedimentation and erosion control devices, measures or structures shall be implemented to
ensure that eroded materials do not enter adjacent wetlands, watercourses or properties.
General
17) This permit shall not be assigned, transferred, sold, or otherwise disposed of to a third party without the
written approval of the Division of Coastal Management.
18) All construction debris associated with the removal or construction of the permitted docking facilities
shall be contained within the authorized project area and disposed of in an approved upland location.
19) The permittee and/or his or her contractor shall meet with a representative of the Division prior to
project initiation.
NOTE: This permit does not eliminate the need to obtain any additional state, federal or local permits,
approvals or authorizations that may be required, including but not limited to any authorizations
required from the U.S. Army Corps of Engineers.
NOTE: The N.C. Division of Water Resources authorized the proposed project by way of Water Quality
Certification 4620 and assigned the project DWR Project No. 19970009v2.
NOTE: Future development of the permittee's property may require a modification of this permit.
Contact a representative of the Division at (910) 796-7215 prior to the commencement of any
such activity for this determination. The permittee is further advised that many non -water
dependent activities are not authorized within 30 feet of the mean high-water level.
NOTE: An application processing fee of $400 was received by DCM for this project.