Cost Estimate and Phasing Plan
'
for the
Washington Water Front and Stewart Parkway
'
Redevelopment Plan
This cost estimate and phasing plan is based on the Washington Water Front
Master Plan prepared under the direction of the Washington Water Front
'
Commission, the report prepared by the Washington Development Advisory
Commission and the Mid -East Commission entitled, "Heritage and Promise:
Washington Returns to the River", and through personal direction by the
'
Washington City Manager and the City Planner.
Costs are based on figures derived from standard industry construction
'
estimation guides and costs recently observed for similar kinds of work in the
State of North Carolina.
Although it has been suggested that some items of work may be completed by
City employees, civic organizations, and private concerns, the figures provided
reflect costs, overhead, and profit associated with a private contractor obtained
'
through competitive bidding.
Costs are provided in 1989 dollars and do not include a consideration for
inflation or increases in the cost of certain items of work overtime. Other costs
not included are figures for mobilization/de-mobilization associated with
multiple phasing plans or costs for future surveying, engineering, and design
'
fees.
Several assumptions have directed the Phasing Plan. The first is that the
associated cost would necessitate a ten year build out period. Secondly, the
'
first phase should be tied to and immediately follow anticipated repair and
stabilization of the eastern end of the water front bulkhead and include
'
whatever amount of work in the west -end that could presently be afforded with
the existing State funding monies. Finally, phasing would be based primarily
on contiguous work units and secondarily on similarities of work type.
'
Cost Estimate Summary
PhaseI................................................................................$ 176,000.00
'
Phase II .......................................................... ..................... $ 66,453.00
PhaseIII..............................................................................$ 68,963.00
Phase IV (two years..........................................................$ 110,737.00
'
Phase V..............................................................................$ 85,536.00
PhaseVI ............. :............................................................... $ 72,200.00
PhaseVII............................................................................$ 82,000.00
'
Phase Vlll (two years) ......................................................$ 154,420.00
TOTAL REDEVELOPMENT COSTS .............................$ 816,309.00
'
TOTAL COSTS W/ 6% CONTINGENCY ......................$ 870,000.00
DRAFT
installation of concrete walks
construction of a wooden trellis/arbor
mounding and grading
planting of trees, shrubs and lawns
flower bed preparation -
purchase and installation of selected lights and benches
selective demolition and removal of existing structures and elements.
Detailed Cost Estimate
Phase 1
' Work in Phase I includes construction activities in the east -end and west -end
areas of the water front. Such work in intended to commence after completion
of work related to bulkhead repair/stabilization. The extent of the work in the
east -end includes:
' West -end work includes:
• installation of concrete walks
• installation of a brick plaza
• construction of a wooden deck over existing planter
• construction of a brick -facade retaining wall
• mounding and grading
• planting of trees, shrubs and lawn
• purchase and installation of lights and benches
• selected demolition and removal of existing structures and elements.
DRAFT
' PHASE I CONSTRUCTION COST ESTIMATE
WASHINGTON WATERFRONT REDEVELOPMENT
April 7, 1989
Unit
' Item Unit Qty. Cost ($) Cost ($) Total ($)
PHASE
'
East End:
_
Demolition
Brick planter removal:
demolish, load, haul for
storage/disposal
CF
285
3.00
855.00
Flag pole ring walls
'
demolish and dispose
CF
90
3.00
270.00
Remove 3 planter rings
CF
60
3.00
180.00
'
74 LF of 10 walk
CF
250
3.00
750.00
Total Demolition
2,055.00
Grading, Earthwork, Site Prep.
'Grade
planter fill, remove excess
to east end mounding
CY
75
15.00
1,125.00
for walks, other paved
'Excavate
areas, mound/grade
CY
200
15.00
3,000.00
place, prepare soil in
'Haul,
mounded areas, former walk
CY
100
15.00
1,500.00
Total Grading, Earthwork, Site
Prep.
5,625.00
Concrete Paving
PSI, 4 thick, 6x6 - #10-10
'3000
mesh, no base, exp. jts. a0 30,
broom finish
SF
18000
3.00
54,000.00
'
Total Paving
54,000.00
Planting
25
200.00
5,000.00
Lawn: seed, mulch, fertilize
MSF
'
Flower bed; prep. only
SF
1200
1.00
1,200.00
Trees: mixed spp., 2 1/2",
'
B&B, fert., staked, guyed
EA
40
350.00
14,000.00
Vines
EA
40
15.00
600.00
'
Total Plant Material
20,800.00 -
'
Special Structures
Trellis/Arbor
SF
1200
18.00
21,600.00
'
Site Furnishings
Benches
EA
8
900.00
7,200.00
'
14,000.00
Lights: Washington Style
EA
8
1,750.00
'
TOTAL EAST END COST
125,280.00
West End Plaza:
'
Demolition
'
Remove 12' of stair cheek wall
SF
60
3.00
180.00
Total Demolition Cost
180.00
'
Grading, Earthwork, Site
Prep.
sod, topsoil, haul,
'Remove
place in mound area for areas
,
to be paved
CY
50
15.00
750.00
'Remove
excess fill behind
stair cheek wall
CY
30
15.00
450.00
'
Mound and grade
CY
80
15.00
1,200.00
Total Grading, Earthwork,
Site Prep.
2,400.00
'
Paving
DRAFT
'
SF
150
3.00
450.00
Concrete walk
Brick paving: 2 1/4" thick on
sand bed, unmortored
SF
2500
3.50
8,750.00
'
Total Paving
9,200.00
Wall: Reinf. block w/brick
face ay. 24" high
LF
50
75.00
3,750.00
Planting
Lawn
MSF
3
200.00
600.00
'
Shrubs
EA
25
15.00
375.00
Trees
EA
5
350.00
1,750.00
Total Planting
2,725.00
Special Structures
Wood deck over old planter,
handicap access, future bldg.,
dock access, w/tree wheels
SF
2400
10.00
24,000.00
Total Special Structures
24,000.00
Site Furnishings
Benches
EA
5
900.00
4,500.00
'
Lights
EA
4
1,750.00
7,000.00
'
Total Furnishings
11,500.00
Total West End Cost
53,755.00
'
1
TOTAL PHASE I COST
176,430,.00
' Detailed Cost Estimate
Phase. II
' Phase II work includes:
' • demolition and new construction associated with the alteration of the
Gladden, Main Street, Stewart intersection
• installation of a brick plaza at the civic center
• installation of concrete walks from the civic center to the Main Street
' crossing and to the west -end plaza
• installation of brick cross -walks
• alterations in and around the area of the Stewart Plaque -mast monument
' • mounding and grading
• planting of trees, shrubs and lawn
• installation of an angle -parking area
' NOTE: Work in the mini -park at the south-east corner of the intersection is not
included in this cost estimate since such work is to be completed with private
' funds.
u
7
0
11
'
DRAFT
'
PHASE II CONSTRUCTION
COST
ESTIMATE
WASHINGTON WATERFRONT REDEVELOPMENT
'
April 7, 1989
Unit
'
Item
Unit
Qty.
Cost ($)
Cost ($) Total ($)
GLADDEN/MAIN/STEWART INTERSECTION AREA
'
Excavate and haul 6" topsoil
CY
26
15.00
390.00
Brick plaza - Civic Center
SF
1400
3.50
4900.00
'
Concrete walks
SF
4850
3.00
14550.00
Excavate and haul 4" topsoil
CY
60
15.00
900.00
'
Pvt. demolition
SY
2700
1.75
4725.00
'
Curb removal
LF
270
2.75
750.00
Debris removal
----
-----
------
2000.00
1
Sidewalk Demolition
SY
70
1.75
123.00
New Curb: Straight
LF
310
3.91
1212.00
'
Radius
LF
50
5.10
255.00
'
Crosswalks, concrete slab
SF
1290
3.00
3870.00
Brick paving
SF
1290
5.40
6970.010
'
Lawn
MSF
6
200.00
1200.00
Trees
EA
9
350
3150.00
Patch roadway and recoat
with 1"
SY
450
5.95
2618.00
'
Paint parking lines (6")
LF
120
0.19
23.00
1
ISTEWART
MONUMENT
Brick planter
I
CF 100 3.00 300.00
Pavement removal
SY 280 1.75 490.00
' Ring wall removal
CIF 72 3.00. 216.00
Curb: Straight LF 45 3.91 176.00
Radius LF 120 5.10 612.00
Topsoil/backfill
CY
30
15.00
450.00
Concrete paving.
SF
1400
3.00
4200.00
' Lights
EA
5
1750.00
8750.00
Benches
EA
4
900.00
3600.00
'
Paint parking lines (6")
LF
120
0.19
23.00
' TOTAL PHASE II COST
66,453.00
t
,
1
' DRAFf
' Detailed Cost Estimate
Phase III
' Phase III work entails modifications to the Harding Square and alterations to the Water Street, Stewar
Bonner intersection. Major work items are:
• narrowing and realignment of the parkway
• installation of brick cross -walks at the end of Market Street and at the Water Street/Stewart interse
'• brick paving of selected walks in Harding Square
• concrete paving of the Water Street/Stewart corner area
• planting of trees and lawn
' • installation of lights and benches.
n
I
0
'
PHASE III CONSTRUCTION
COST ESTIMATE
WASHINGTON WATERFRONT REDEVELOPMENT
April 7, 1989
Unit
Item
Unit
Qty.
Cost ($)
Cost ($) Total ($)
HARDING SQUARE
AND
WATER/BONNER/STEWART
INTERSECTION AREA
'
2.50
750.00
Concrete walk demolition
CY
30
'
Debris disposal
----
----
----
1000.00
Brick paving, sand bed,
'
no mortar
SF
2000
3.50
7000.00
Remove fountain control,
'
fill with topsoil
----
----
----
250.00
Benches
EA
8
900.00
7200.00
'
Trees
EA
9
350.00
3150.00
Lights
EA
3
1750.00
5250.00
'
Concrete slab
SF
600
1.75
1050.00
'
Brick paving/mortared
SF
600
5.40
3240.00
Pavement demolition
SY
500
1.75
875.00
3000.00
Debris haul
----
----
----
'
Topsoil haul and place
CY
250
15.00
3750.00 ,
Curb: Straight
LF
100
3.91
3910.00
'
Radius
LF
680
5.10
3468.00
Concrete slab for brick
SF
800
3.00
2400.00
'
Brick - Crosswalks
SF
800
5.40
4320.00
'
Trees
EA
22
350.00
7700.00
Lights
EA
11
1750.00
8250.00
1
Concrete walks SF 800 3.00 2400.00
TOTAL HARDING SQUARE AND
IWATER/BONNER/STEWART INTERSECTION COST 68,963.00
p
lQRAFr
1 Detailed Cost Estimate
Phase V
IPhase VE is the alterations to the parking areas north of Stewart Parkway. Major elements are:
• reorientation of parking in the central area
• brick paving of selected walks
• the creation of new green spaces
'• planting of trees and lawns
• installation of lights
• re -painting of parking stalls at 9' widths.
n
11
PHASE V CONSTRUCTION
COST
ESTIMATE
WASHINGTON WATERFRONT REDEVELOPMENT
April 7, ' 1989
Unit
' Item
Unit
Qty.
Cost ($)
Cost ($) Total ($)
PARKING AREAS
' Pavement removal
SY
2200
1.75
3850.00
Curb: Straight
LF
900
3.91
3519.00
' Radius
LF
320
5.10
1632.00
Trees thur. concrete
EA
25
500.00
12500.00
' Topsoil and grade
LY
278
15.00
4170.00
Lawn
MSF
3
200.00
600.00
500
3.00
1500.00
Concrete walk
SF
' Brick on asphalt
SF
1500
4.50
6750.00
Trees
EA
29
350.00
10150.00
Asphalt patch and repair
SY
500
5.95
2975.00
' Shrubs
EA
150
25.00
3750.00
Line painting
LF
6000
0.19
1140.00
' Debris removal
----
----
----
3000.00
Concession/information center
SF
600
50.00
30000.00
TOTAL PHASE V COST
85,536.00
1
DRAFT
' Detailed Cost Estimate
Phase VI
IPhase VI is the construction of two wooden pavilions, associated paving, walls, lighting, and benches
DRAFT
' PHASE VI CONSTRUCTION COST ESTIMATE
WASHINGTON WATERFRONT REDEVELOPMENT
' April 7, 1989
U nit
' Item Unit Qty. Cost ($) Cost ($) Total ($)
'
PAVILIONS
Pavilions/wood
SF
1800
25.00
45000.00
'
_
Lights
EA
4
1750.00
7000.00
'
Benches
EA
4
900.00
3600.00
Bollards
EA
4
300.00
1200.00
Concrete paving
SF
3000
3.00
9000.00
Retaining walls/brick facade
on block
LF
170
55.00
9400.00
'
TOTAL PHASE VI COST
75,200.00
1
1
1 DRAFF
Detailed Cost Estimate
Phase VII
Phase VII construction includes two twelve -slip boat docks and installation of associated wooden
dolphin pilings.
1
I
n
0
1 DRAFr
1 PHASE VII CONSTRUCTION COST ESTIMATE
WASHINGTON WATERFRONT REDEVELOPMENT
April 7, 1989
Unit
1 Item Unit Qty. Cost ($) Cost ($) Total ($)
1 MARINE CONSTRUCTION
Boat docks SF 2560 25.00 64000.00
1 Docking pilings EA 30 600.00 18000.00
1 TOTAL PHASE VII COST 82,000.00
i
C
DRAFT
' Detailed Cost Estimate
Phase IV
IPhase IV work is the major narrowing of the center section of Stewart Parkway. Work included is:
'• a new concrete walk along the south side of Stewart
• additional perpendicular walks to the river walk
• six brick cross -walks
• grading and importation of topsoil material
' • planting of trees, shrubs and lawn
• installation of lights and benches.
CAI
0
0
1 DRAFr
' PHASES IVA & IVB CONSTRUCTION COST ESTIMATE
WASHINGTON WATERFRONT REDEVELOPMENT
1 April 7, 1989
Unit
' Item Unit Qty. Cost ($) Cost ($) Total ($)
CENTER ROAD
NARROWING
(2 years)
1
Pavement removal
SY
4200
1.75
7350.00
Wall - planter removal
CF
275
3.00
825.00
'
Topsoil/backfill
CY
500
15.00
7500.00
Lawn
MSF
25
200.00
5000.00
1
Concrete walk
SF
10000
3.00
30000.00
Curb: Straight
LF
1000
3.91
3910.00
'
Radius
LF
200
5.10
1020.00
1
Benches
EA
7
900.00
5600.00
Lights
EA
4
1750.00
7000.00
Flower bed preparation
SF
2690
1.00
2690.00
1
Repair ends of retained planter
LF
80
100.00
800.00
Concrete slab
SF
146
3.00
438.00
Cut and excavate
CY
36
16.00
576.00
Brick
SF
1320
540.00
7128.00
Patching roadway
SY
3000
5.95
17850.00
1
Trees
EA
23
350.00
8050.00
Debris Disposal
----
----
----
5000.00
1
110,737.00
TOTAL PHASE IV
1
DRAFT
' Detailed Cost Estimate
Phase Vill
' Phase Vlll is the final work including the construction of the step-terraces/amphitheater and the brick
paving of Union and Harris Alleys. It is anticipated that concrete work would be done in one year, foil,
by brick work in both areas.
III
F�
' DRAFT
' PHASES V111-A & VIII-B CONSTRUCTION COST ESTIMATE
WASHINGTON WATERFRONT REDEVELOPMENT
April 7, 1989
Unit
' Item Unit Qty. Cost ($) Cost ($) Total ($)
'
CENTER STAIR/AMPHITHEATER/
PAVE HARRIS, UNION
ALLEYS
'
C.I.P. concrete steps/terraces
CY
300
250.00
75000.00
'
Brick paving
SF
5000
3.50
17500.00
Bollards
EA
6
300.00
1800.00
'
Lights - 4-way
EA
5
2500.00
12500.00
Difficult concrete demolition
SF
450
3.50
1350.00
Haul debris
----
----
----
2000.00
'
Grading and haulage
SV
500
15.00
7500.00
Union and Harris
Brick on asphalt
SF
6800
5.40
36720.00
'
TOTAL PHASES VIII-A &
VIII-B COST
154,370.00