HomeMy WebLinkAboutAQ_F_1300067_20181018_PRMT_Permit c STq 7F
ROY COOPER ���Ym.,s¢�Governor
MICHAEL S.REGAN 1 -
Secretary .-
a�QUAM
MICHAEL A.ABRACZINSKAS NORTH CAROLINA
Director Environmental Quality
October 18, 2018
Mr. Richard Roper
VP Finance
Vulcan Construction Materials, LLC - Gold Hill Quarry
4401 N. Patterson Ave.
Winston-Salem,NC 27105
Subject: Air Permit No. 10592R00
Vulcan Construction Materials, LLC - Gold Hill Quarry
Gold Hill, Cabarrus County,North Carolina
Permit Class: Small
Facility ID# 1300067
Dear Mr. Roper:
In accordance with your completed application received September 25, 2018, we are
forwarding herewith Permit No. 10592R00 to Vulcan Construction Materials, LLC- Gold Hill
Quarry, Gold Hill, Cabarrus County,North Carolina for the construction and operation of air
emissions sources or air cleaning devices and appurtenances. Additionally, any emissions activities
determined from your air permit application as meeting the exemption requirements contained in
15A NCAC 2Q .0102 have been listed for information purposes as an"ATTACHMENT" to the
enclosed air permit. Please note the records retention requirements are contained in General`
Condition 2 of the General Conditions and Limitations.
If any parts,requirements, or limitations contained in this permit are unacceptable to you,
you have the right to request a formal adjudicatory hearing within 30 days following receipt of this
permit, identifying the specific issues to be contested. Such a request will stay the effectiveness of
the entire permit. This hearing request must be in the form of a written petition, conforming to G.S.
150E-23 of the North Carolina General Statutes, and filed with the Office of Administrative
Hearings, 6714 Mail Service Center, Raleigh,NC 27699-6714. The form for requesting a formal
adjudicatory hearing may be obtained upon request from the Office of Administrative Hearings.
Unless a request for a hearing is made pursuant to G.S. 15013-23,this air permit shall be final and
binding.
You may request modification of your air permit through informal means pursuant to G.S.
15013-22. This request must be submitted in writing to the Director and must identify the specific
provisions or issues for which the modification is sought. Please note that the permit will become
final and binding regardless of a request for informal modification unless a request for a hearing is
also made under G.S. 15013-23.
Z A North Carolina Department of Environmental Quality I Division of Air Quality
E� Mooresville Regional Office 1 610 East Center Avenue,Suite 301 1 Mooresville,NC 28115
NORTH CAnOUNA �
704.663.1699 T 1 704.663.7579 F
Richard Roper
October 18, 2018
Page 2 -
Unless exempted by a condition of this permit or the regulations, construction of new
air pollution sources or air cleaning devices, or modifications to the sources or air cleaning
devices described in this permit must be covered under a permit issued by the Division of Air
Quality prior to construction. Failure to do so is a violation of G.S. 143-215.108 and may
subject the Permittee to civil or criminal penalties as described in G.S. 143-215.114A and 143-
215.114B.
This permit shall be effective from October 18; 2018 until September 30, 2026, is
nontransferable to future owners and operators, and shall be subject to the conditions and limitations
as specified therein.
Changes have been made to the permit stipulations. The Permittee is responsible for
carefully reading the entire permit and evaluating the requirements of each permit
stipulation. The Permittee shall comply with all terms, conditions,requirements,limitations
and restrictions set forth in this permit. Noncompliance with any permit condition is grounds
for enforcement action, for permit termination, revocation and reissuance, or modification, or
for denial of a permit renewal application. Should you have any questions concerning this matter,
please contact Carlotta Adams at 704-235-2228.
Sincerely,
r.
Bruce J. Ingle,Regional Supervisor
Division of Air Quality, NC DEQ
CA
Enclosures
c: Mooresville Regional Office
https://neconnect.sharepoint.com/sites/deq/daq_mro/Counties/CABARRUS/00067/R00_PERMIT.docx
Revised 8-16-2018
AM Equipment List for Vulcan Construction Materials-Gold Hill Quarry
E ui E ui meut_ _MFG- _NSPS . - ---- - --
ID No. Description Date Status Testing Date Test Submitted Comments
es o Yes/LFL
CRUSHERS
CRl C 125B Jaw(700 tph) 1996 YesAXL NA NA This is the only primary crusher at Gold Hill.
CR2 5 1/2'Std(750 tph) 2017 Yes/LFL N/A-LFL NA-LPL A crusher ieconsttuctred in 2017
CR3 HP 400(640 tph) 1997 Yes Apr-98 May-98
SCREENS
F1 60"X 24'Grizzly 1971 No NA -
Sl 6'x 16'-3 Deck 1994 Yes Aug-95 Oct-95 —
S2 8'x 20'-3 Deck 1988 Yes/LFL NA --
S4 8'x 20'-3 Deck 2007 Yes/LFL NA-Wet NA-Wet Wet Process
S5. 6'x 16'-3 Deck 2007 Yes/LFL NA-Wet NA-Wet Wet Process
SAND SCREW
.SS-1 44"X33'Double Sand Screw 1993 No NA-Wet NA-Wet Wet proces
CONVEYORS
C-1 48"Belt Width 1994 Yes Aug-95 Oct-95
C-2 48"Belt Width 1994 Yes Aug-95 Oct-95
C-3 42"Belt Width 1994 Yes Aug-95 Oct-95 --
C-4 36"Belt Width 1994 Yes Aug-95 Oct-95 -
C-5 36"Belt Width 2002 LFL NA ---
C-6 42"Belt Width 1995 Yes Aug-95 Oct-95 --
C-7 36"Belt Width 1995 Yes Aug-95 Oct-95 --
C-8 36"Belt Width 1995 Yes Aug-95 Oct-95 ---
C-9 30"Belt Width 1994 Yes Aug-95 Oct-95 —
C-10 30"Belt Width " 1994 Yes Aug-95 Oct-95
C-11 36 B Width 1995 Yes Aug-95 Oct-95 ---
C-12 36"Beltelt Widt' 1995 Yes Aug-95 Oct-95 -
C-16 36"Belt Width 1994 Yes Aug-95 Oct-95 Capacity increase to 700 TPH
C-17 36"Belt Width 1995 Yes Aug-95 Oct-95 ---
C-18 30"Belt Width 1994 Yes NA-Wet NA-Wet Wet Process
C-19 30"Belt Width Pre-2001 Yes NA-Wet NA-Wet Wet Process. Manufacture date between 1994-2001.
C-20 30"Belt Width 1994 Yes NA Wet Process
C-21 30"Belt Width 1995 Yes Aug-95 Oct-95
C-22 30"Belt Width 1995 Yes Aug-95 Oct-95 Minor extention,capacity increase to 500 tph
C-23 36"Belt Width 1997 Yes Sep-98 Sep-98 ---
SC-1 30"Belt Width 1995 Yes Aug-95 Oct-95 Realign then remove when new Stalite bins are build
SC-2 36"Belt Width 2001 Yes Apr-05 'Apr-OS
SC-3 30"Belt Width Pre-2008 Yes 7/13/2016 719/2116
SC-8 42"Belt.Width 1989 Yes Pending Pending
BINS
SB-1 75 To. 1994 Yes Aug-95 Oct-95 --
SB-2 75 Tn 1994 Yes Aug-95 Oct-95 --
OR TABLE EQUIPMENT
Portable Crashing Unit I
Powerscipen Premteitrak 600'Jaw
Crush'ee
T-CR1 ( apacity , es,.
17 -atePPT-Cl 47 Belt\Vidth .2017 _ Yes. Nov,17 Nov=17.
PT C2 30.Belt Width 2017 , Yes N/AAfookpile' N/A Stockpile'
lof2
Revised 8-16-2018
CRl C125B Jaw(700 h) 1996 YOSI FL NA NA This is the onl rimary crusher at Gold Hill.
Portable Crushing Unit 2
---Y —Powersc[een 1300=, exTYack— -
r
MT CRl (385 tph rated capgt try) 2017 Yes I4ov 17
1viT C1, 31'Belt Wid017 1!s Nov,17, Nod 1:? ,.
MT C2, 39 Bj jf Widih ." 20.17 Yes,Nov 17 Nd�=`17,
ortable.Crushing Unit
PowerSgtee#TrrakpacXor 320SR
TP CR 1 (35.0':;tph rated capacity) 2019 es Feb 18 Feb)$ .
Tp SX, 5'x Ii 2 D.gck: 2017 Yes Feb 18 Feb.18
TP C1 39"Belt Width 2,0,17. Yes Feb 18 Feb 3i1_.,,
TP:C2, 2b!'Belt Width 2¢1T `'Xes !A S[ocltpl, rr/A ti( ,le
TP C3. 20"Belt Width,' 2017 Yes Feb,I8 Peb'X$
TP C4 20"Belt Wi"dth : 407, Yes Feb 18 Fcb1:8',
TP CS 20"Belt Width:,' •'2017 ,•.,�'es Feb 18 � Feb..l;;:,.
TP C6 55,Belt Width , . 2017. Yes Feb 18 Peb 18: .
Portable Crushing Unit 4
Powerscteen Preriuertr 300
dn
PT300 C .. (3013:,tph rated capaetty) 2A15; fY,6p. Pending ., „ Pegdllg .
PT300 CtY 31"Bett W Btlt,..-. XS X.11 - .. .,s. Pandmg {.ri Pyulltpq
PT300. k,,2`2 '�BeltWidth_ 2Of,5 I`es Pending Pertdtig, .
Portable Screening Unit
PoWetScteen Warn& 00
2100 C l 5:1"Belt Width 20.17. TCes Nou 17 No 17
2100 C2 55"felt Wi}h„ , 2017 Yes Nov 17 NoY
2100 C3„ 3t1 Belt Width6)7, Nov 17 f Nztr!:17'. .
Z100'C4 , ;3;5" felt Width 3Q1_. Yes t Nov 17 Noir17:
ortable Screening Unit IA
Powrtgozeen Warrior 2 00 f
Y.
2100 S1A 5 R 16 2 Deft 017 fps Ang 17, µ clog J
T00 C1A, = r
S 1"Be1E Wi(111t :kugsl�,
2100 C2A' 51',Be1tW,ilth, „2Q1;7. Ye Aug l l,. A
2100 C3A %i 35"Belt'Width , ,, 20,17, Yes 1Vov 17`,' Nod 11
21QO C4A' � :.,35'!Belt Wlilth ti ;. ����� :::xe� _.� 1!�11A:sroe>��t�v. Nix s�.•'y '.
2100 CS „r. ;55'$elt Width;. 2 " MA
Portable Screening Unit 2
,; Powe;scfeeu Chietto�t 1700 ,�
1700 C2 `s` 42'!Belt,Wdtli' 2017 .. "SFe1{ r•. ,. deli,l8.et,, Febnl'6:,..
1700 20I,. Yqs Feb 1$ Fe15`18,, .
POP- r.. 29°r. .:: NGA`StockPlit /k�
u w. a, Fell 18 roo C1.. ,,2$ Be1t ywiJth .. Q1 .. ... z ..
.ortable Conveyors
Ci65 C1,; A2'Belt Wid 2017 �r¢s s „r Nov 17 No , rr
CT65,C2 :1}2n$el(wt3lst t.. . 047_
11F521 C11.'.'; 42"Belt Wii1,,,r„ ,0,17, •Yes. NoY 17<Ti, :; NoV,17e
i
TC424 Q'A' 40'Belt W.idth„ , 2012, Yes Nov 17 Nov,17
40'BeltVifiBth,. .., 01`.7r. Xe5 ;� IAStockPL(a.,LN/A53p 'l
Notes: 1. Shaded area indicates update.
2 of 2 i
i
t
---------------------
241 12794
2 4I 36'HW C-23
60'X24'GRIZZLY f 200 TPH
11237 (Fl) RB-18063 i
14132 1
DUMP POINT 0125 ERG ?' 14103 3 6 X 16 3D
C
F �� CCRll 9�.j. q29 ,1ptl 34 2' \`S]J RIP RAP
14102 p9 .CQ pp0 �w 1 150 TPH
P91P).�Zpp 1 1 14306�6
1200 TPH 9p� �� (F5) CLEAN
's - p?'A'1h 75 TONS I 8(S21 3D STONE
f
Sg_1 I
8000TONS LIVE STORAGE I -' 14107 'I s'
C-yl 14121 3 MF FEEDERS(F2-F4) I FEEDER �G� e
PUSH POINT 3p'13W' r-- I 3�9 12060
STD
TUNNEL W/FEEDER<F13) J40'!=ADIgL 3 ] 14108
6Zv,c S 1000 7pH 38 0 TPH4 1 - , (CR 2) 350 W'fPHB ---��0'TFH)
ABC 14116 1 I q 75 TONS
--- - -------------- SB-
1 U109 n FEEDER
I 30'HW C-9 4l CFBJ
C-16 175'R
14122 36'BW ADIAL I 200 TPH
I �`
' 700 TPH 1
4110
17660 1 1 C-30 125'RADIAL
SC-2,36'BW .I I 30'HW HP 400
500 TPH 1 SCREENINGS 200 TPH (CR 3)
_- STALITE __----- 14958
12868 L.NV CF9-F12 ) ----------------1 -
STALITE S 350 TPH I 14111
.BINS 36'BW,C-I1
PUSH POINT 14112 900 TPH
14123 36'BW C-12
04 S 35b3TPH 25 S 900 TPH
EXIST.CONV.
369 17 AH%C14.1 17
350 TPH
0BB9
3]SC-3,30W
EXIST.CONV. � a UNCLOUDED
FUTURE GYRADI3C
3D VASH DR
CSSJ DRT SCREEN cxwc xT
STALITE 19372 CS4)
BINS 19371
125'RADIAL 3O'BW FLUME FLUME ALL TONS SHOWN ARE MAXIMUM
N0.5 300 TPH Q
S P WET SUPPRESSION POINT
DOUBLE HACKUP/OVERFLOW CHUTE
13802 44 X 33'SCREW
C-1H 130'RADIAL I
14119 6 T 0 Q FLOP GATE
N0.67 00 TPH
C-20125'RADIAL m O FINGER GATE
30'BW 78 M
200 TPH WASHED SCRS.
14120
+ +uwo 1 ¢-uwcs xmm rwD Rcnuar NORTH CAROLINA GOLD HILL
Materials Company
as e s 2838-000—FLWAGG-0001 aD
GRIZZLY 42"x12'8" FEEDER
IJ�U` 350 TPH
--- POWER SCREEN UNIT#1
TRAKPACTOR 320SR
i
1 TP-CR-I
50TPH 9'BW
Tp -- I200TPH _p
50TPN 2g e ; 1 3501?
WWW TP-S1
r, N POWER SCREEN UNIT#2
�SrpN 35ptP ,fop G� az SSp aH CHIE, ON 1700 �j6S
i- -
r�C4 •, ____________ '
TP_OS 20 __
� ______SrP _______N W appjPN
'sorpy
1q PC\ 2
PH
� 40ew � <FVtURE�
15pSpH
i
i
i
D TDIERANr BNlF55 ROTm nDW DR/pf FOR PDpiARIE WPACIOR Plal(f �NORTH.CAROLINAPORTABLE:uu'i®
' A�/i wumx M�+mrt
DaTse RUMMaterials Company NCP;P-107—FLWAGG-0001 �A
i
i
GRIZZLY 46'x14' FEEDER -
POEM so}1
PT—CR1
47"x32"JAW VJI SC �UNR 12 MOW
AW RRIOR.2100
R - 9YD A 2 DECK 5x16'9501PH S� MT—CR7
----- 2100—S1 V��� 1300
------ § AUTOMAX
CRUSHER
A q8„
BASE 'PORTABLE BASE
PLANT
D TOLE��s-Y Eg NoTm PoIIf�BfE BASE/RELYCIE PUNT nnwaucr "`NORTH CAROLINA PORTABLE
uuIlon
A� u anww mmm� �smu s¢ a
.Materials Com an
WE """°s uwsrox B =� P v NCPP-000-FLWAGG-0002 FB
a0
2100—S1A LOADING o O Oa e
772 TPH HOPPER
5'X16 2D 51" BW
2100-CIA
40'BWx78' 35" BW
51" B
2100—C3A 2100—C2A
TC424—ClA
2100—C4A 35" BW
2100—05A 55" BW
I
I
I
I
POWERSCREEN WARRIOR 2100
PORTABLE SCREENING PLANT
o roue -uxuss xorEo PoRT,,E PUNT i NORTH CAROLINA PORTABLE
Vulcan
-,♦ m `����� 7'-m-mte Lt SISLI t OFt
oere xwaax - or "Materiais Company NCPP 000-FLWAGG-0004
i
I
GRIZZLY 3e'x12' FEEDER
vO O PT3OO-Fl -
300 TPH POWER SCREEN
PREMIERTRAK 300
III
PT3OO-CR1
39"x23.5"JAW
8d
175�
I
R TaLEwxc s-un1E Q
PORUBIE LW CRUSIRXG flANf —NORTH CAROLINA PORTABLE
c Uukan
R J 0111kR. ...
p _ FR-wie a sen a
Materials Company NCPP-000—FLWAGG-0005 GATE REVISION BY °u01C
NORTH CAROLINA ENVIRONMENTAL MANAGEMENT COMMISSION
DEPARTMENT OF ENVIRONMENTAL QUALITY
--DIVISION-OF AIR QUALITY-
AIR PERMIT NO. 10592R00
Issue Date: October 18,2018 Effective Date: October 18,2018
Expiration Date: September 30, 2026 Replaces Permit: (new)
To construct and operate air emission source(s) and/or air cleaning device(s), and for the
discharge of the associated air contaminants into the atmosphere in accordance with the provisions
of Article 21B of Chapter 143;General Statutes of North Carolina (NCGS) as amended, and other
applicable Laws,Rules and Regulations,
Vulcan Construction Materials,LLC - Gold Hill Quarry
16745 Old Beatty Ford Road
Gold Hill, Cabarrus County,North Carolina
Permit Class: Small
Facility ID# 1300067
(the Permittee) is hereby authorized to construct and operate the air emissions sources and/or air
cleaning devices and appurtenances described below:
Emission Emission Source Control Control System
Source ID Description System ID Description
_
Non-metallic mineral processing plant utilizing water suppression with no other control -
devices,including:
ES-Convey(NSPS) cone in o operations N/A N/A
_ _ _
ES-Crush(NSPS) crushing operations N/A NIA
ES-Screen(NSPS) Iscreening operations N/A N/A
in accordance with the completed application 1300067.18C received September.25,2018 including
any plans, specifications,previous applications, and other supporting data, all of which are filed
with the Department of Environmental Quality, Division of Air Quality(DAQ) and are incorporated
as part of this permit.
This permit is subject to the following specified conditions and limitations including any
TESTING, REPORTING, OR MONITORING REQUIREMENTS:
A. SPECIFIC CONDITIONS AND LIMITATIONS
1. Any air emission sources or control devices authorized to construct and operate above must
be operated and maintained in accordance with the provisions contained herein.The
Permittee shall comply with applicable Environmental Management Commission
Permit No. 10592R00
Page 2 -
Regulations, including Title 15A North Carolina Administrative Code (NCAC), Subchapter
2D .0202, 2D .0510, 2D .0521, 2D .0524 (40 CFR 60, Subpart 000), 2D .0535,2D .0540,
2D ..060-5 and-2D-1806. ---- __.._- _-
2. PERMIT RENEWAL AND EMISSION INVENTORY REQUIREMENT -The Permittee,
at least 90 days prior to the expiration date of this permit,shall request permit renewal by
letter in accordance with 15A NCAC 2Q .0304(d) and (f). Pursuant to 15A NCAC 2Q
.0203(i), no permit application fee is required for renewal of an existing air permit(without
a modification request). The renewal request(with AA application form) should be
submitted to the Regional Supervisor, DAQ. Also, at least 90 days prior to the expiration
date of this permit,the Permittee shall submit the air pollution emission inventory report
(with Certification Sheet) in accordance with 15A NCAC 2D .0202,pursuant.to N.C.
General Statute 143 215.65. The report shall be submitted to the Regional Supervisor, DAQ
and shall document air pollutants emitted for the 2025 calendar year.
3. PARTICULATE CONTROL REQUIREMENT - As required by 15A NCAC 2D .0510
"Particulates from Sand, Gravel, or Crushed Stone Operations," the following requirements
apply:
a. The Permittee of a sand, gravel,recycled asphalt pavement(RAP), or crushed stone
operation shall not cause, allow, or permit any material to be produced,handled,
transported, or stockpiled without taking measures to reduce to a minimum any
particulate matter from becoming airborne to prevent exceeding the ambient air
quality standards beyond the property line for particulate matter, both PMIo and total
suspended particulates.
b. Fugitive dust emissions from sand, gravel, RAP,or crushed stone operations shall be
controlled by 15A NCAC 2D .0540 "Particulates from Fugitive Dust Emission
Sources."
c. The Permittee of any sand, gravel,RAP, or crushed stone operation shall control
process-generated emissions:
i. From crushers with wet suppression(excluding RAP crushers); and
ii. From conveyors, screens, and transfer points
such that the applicable opacity standards in 15A NCAC 2D .0521 Control of Visible
Emissions," or 15A NCAC 2D .0524 "New Source Performance standards" are not
exceeded.
4. VISIBLE EMISSIONS CONTROL REQUIREMENT-As required by 15A NCAC 2D
.0521 "Control of Visible Emissions," visible emissions from the emission sources,
manufactured after July 1, 1971, shall not be more than 20 percent opacity when averaged
over a six-minute period, except that six-minute periods averaging not more than 87 percent
opacity may occur not more than once in any hour nor more than four times in any 24-hour
period.However, sources which must comply with a visible emissions standard in 15A
NCAC 2D .0524 "New Source Performance Standards"or .I 110 "National Emission
Standards for Hazardous Air Pollutants" shall meet that standard instead of the 2D .0521
visible emissions standard.
Permit No. 10592R00
Page 3
5. VISIBLE EMISSIONS CONTROL REQUIREMENT-As required by 15A NCAC 2D
.0521 "Control of Visible Emissions," visible emissions from the emission sources,
manufactured as of July 1, 1971, shall not be more than 40 percent opacity when averaged
over a six-minute period, except that six-minute periods averaging not more than 90 percent
opacity may occur not more than once in any hour nor more than four times in any 24-hour
period. However, sources which.must comply with a visible emissions standard in 15A
NCAC 2D .0524 "New Source Performance Standards" or .1110 "National Emission
Standards for Hazardous Air Pollutants" shall meet that standard instead of the 2D .0521
visible emissions standard.
6. 15A NCAC 2D .0524 "NEW SOURCE PERFORMANCE STANDARDS" -For the
nonmetallic mineral processing equipment(wet material processing operations, as defined in
60.671, are not subject to this Subpart) including the emission sources,the Permittee shall
comply with all applicable provisions, including the notification,testing,reporting,
recordkeeping, and monitoring requirements contained in Environmental Management
Commission Standard 15A NCAC 2D .0524 "New Source Performance Standards" (NSPS)
as promulgated in 40 CFR 60, Subpart 000, including Subpart A "General Provisions."
a. NSPS Reporting Requirements - In addition to any other notification requirements to
the Environmental Protection Agency(EPA),the Permittee is required to NOTIFY
the Regional Supervisor, DAQ, in WRITING, of the following:
i. The actual date of initial start-up of an affected facility,postmarked within 15
days after such date;
b. NSPS Emissions Limitations - As required by 15A NCAC 2D .0524 [40 CFR
60.672],the following permit limits shall not be exceeded:
i. For affected facilities that commenced construction,modification, or
reconstruction after August 31, 1983 but before April 22,2008 (wet material
processing operations, as defined in 60.671, and Like-For-Like-Replacement,
as allowed in 60.670(d), are not subject to this Subpart): -
Affected Facility Pollutant Emission
--......._. _._.... - _..._...................... __......Y...___....., _.._.._ . .__.. . .
Limit
Crushers Visible
Emissions 15%opacity
._.... _ _ _-._..- _, __._ _._......
Fugitive emissions from conveyor belts, Visible 10% opacity
screening operations, and other affected facilities Emissions
ii. For affected facilities that commenced construction,modification, or
reconstruction on or after April 22, 2008(wet material processing operations,
as defined in 60.671, and Like-For-Like-Replacement, as allowed in
60.670(d), are not subject to this Subpart):
Permit No. 10592R00
Page 4
- - - -------- __.
j Affected Facility Pollutant
Emission
Limit
Visible 120/0 opacity
Crushers lEm.iss-ionsi!
Fugitive emissions from conveyor belts, Visible j °
screening operations, and other affected facilities Emissions! 7/o opacity
c. NSPS Monitoring Requirements -As required by 15A NCAC 2D .0524 [40 CFR
60.674],the following monitoring shall be conducted:
i. For any affected facility that commenced construction, modification, or
reconstruction on or after April 22,2008 that uses wet suppression to control
emissions (Like-For-Like-Replacement, as allowed in 60.670(d), is not
subject to this Subpart),the Permittee shall:
A. Perform monthly periodic inspections to check that water is flowing
to discharge spray nozzles in the wet suppression systems.
B. Initiate corrective action within 24 hours and complete corrective
action as expediently as practical if the Permittee finds that water is
not flowing properly during an inspection of the water spray nozzles.
d. NSPS Recordkeeping Requirements -As required by 15A NCAC 2D .0524 [40 CFR
60.675],the following recordkeeping requirements shall be conducted:
i. Each inspection of the water spray nozzles,including the date of each
inspection and any corrective actions taken, shall be recorded in a logbook (in
written or electronic form).
ii. Each quarterly Method 22, including the date, results of the observation, and
any corrective actions taken, shall be recorded in a logbook (in written or
electronic form).
iii. The logbooks (in written'or electronic form) shall be maintained on-site and
made available to DAQ personnel'upon request.
e. NSPS Performance Testing-As required by 15A NCAC 2D .0524,the following
performance tests shall be conducted:
Permit No. 10592R00
Page 5
Affected Facility Pollutant Test
_.. ..... .......... ....... _._.__,_ _...... ..,....Method ,
Visible
Crushers Method 9 j
Emissions
Fugitive emissions from conveyor belts, screening Visible
p
o erations and other affected facilities Emissions [Method 9
_ __ ...
i. All performance tests shall be conducted in accordance with EPA Reference
Methods, contained in 40 CFR 60,Appendix A;
ii. The EPA Administrator retains the exclusive right to approve equivalent and
alternative test methods, continuous monitoring procedures, and reporting
requirements;
iii. Within 60 days after achieving the maximum production rate at which the
affected facility(s) will be operated,but not later than 180 days after the
initial start-up of the affected facility(s),the Permittee shall conduct the
required performance test(s) and submit two copies of a.written report of the
test(s)to the Regional Supervisor, DAQ;
iv. The Permittee shall be responsible for ensuring,within the limits of
practicality,that the equipment or process being tested is operated at or near
its maximum normal production rate or at a lesser rate if specified by the
Director or his delegate;
V. All associated testing costs are the responsibility of the Permittee;
vi. The Permittee shall arrange for air emission testing protocols to be provided
to the DAQ prior to testing. Testing protocols are not required to be pre-
approved by the DAQ prior to testing. The DAQ shall review testing -
protocols for pre-approial prior to testing if requested by the Permittee at
least 45 days before conducting the test; and
vii. To afford the Regional Supervisor, DAQ,the opportunity to have an observer
present,the Permittee shall PROVIDE the Regional Office, in WRITING, at
least 7 days notice of any required performance test(s)that involve only
Method 9. All other tests require a 30 day notice.
viii. When determining compliance with the visible emissions limit from fugitive
emissions from crushers, conveyor belts, screening operations, and other
affected facilities (as described in 60.672(b) or 60.672(e)(1)),the duration of
the Method 9 test must be 30 minutes (five 6-minute averages). Compliance
with the fugitive visible emissions limits must be based on the average of the
five 6-minute averages.
ix. For any affected facility that commenced construction, modification, or
reconstruction on or after April 22, 2008 that does not use wet suppression to
Permit No. 10592R00
Page 6
control emissions,the Permittee shall repeat the performance tests within five
(5) years of the previous test.
A. If an affected facility relies on water carryover from upstream wet
suppression to control fugitive emissions, then that affected facility is
exempt from the 5-year repeat testing requirement provided that the
Permittee conducts periodic inspections of the upstream wet
suppression that is responsible for controlling fugitive emissions from
the affected facility and designates which upstream wet suppression
systems will be periodically inspected at the time of the initial
performance test.
f. Like-For-Like-Replacement- As provided in 40 CFR 60.670(d), when an existing
facility is replaced by a piece of equipment of equal or smaller size, as defined in 40
CFR 60.671,having the same function as the existing facility, and there is no
increase in the amount of emissions,the new facility is exempt from the provisions
of 40 CFR 60.672, 60.674, and 60.675 except as provided for in 60.670(d)(3). The
Permittee shall comply with the reporting requirements of 40 CFR 60.676(a).
Equipment covered under 40 CFR 60.670 shall comply the requirements of 15A
NCAC 2D .0521.
7. NOTIFICATION REQUIREMENT -As required by 15A NCAC 2D .0535,the Permittee of
a source of excess emissions that last for more than four hours and that results from a
malfunction, a breakdown of process or control equipment or any other abnormal
conditions, shall:
a. Notify the Director or his designee of any such occurrence by 9:00 a.m. Eastern time
of the Division's next business day of becoming aware of the occurrence and
describe:
i. the name and location of the facility,
ii. the nature and cause of the malfunction or breakdown,
iii. the time when the malfunction or breakdown is first observed,
iv. the expected duration, and
V. an estimated rate of emissions.
b. Notify the Director or his designee immediately when the corrective measures have
been accomplished.
This reporting requirement does not allow the operation of the facility in excess of
Environmental Management Commission Regulations.
8. FUGITIVE DUST CONTROL REQUIREMENT -As required by 15A NCAC 2D .0540
"Particulates from Fugitive Dust Emission Sources," the Permittee shall not cause or allow
fugitive dust emissions to cause or contribute to substantive complaints or excess visible
emissions beyond the property boundary. If substantive complaints are received or excessive
Permit No. 10592R00
Page 7
fugitive dust emissions from the facility are observed beyond the property boundaries for six
minutes in any one hour(using Reference Method 22 in 40 CFR,Appendix A),the owner or
operator may be required to submit a fugitive dust plan as described in 2D .0540(f).
"Fugitive dust emissions" means particulate matter that does not pass through a process
stack,or vent and that is generated within plant property boundaries from activities such as:
unloading and loading areas,process areas stockpiles, stockpile working,plant parking lots,
and plant roads (including access roads and haul roads).
9. QUARRY EQUIPMENT REPORTING - As required by 15A NCAC 2D .0605, the
Permittee shall maintain on-site an equipment list and a plant (or flow) diagram of all
equipment covered under this permit.
a. The equipment list shall include the following information for each piece of
equipment:
i. A description of equipment including applicability of New Source
Performance Standards, and:
A. Width of belt conveyors,
B. Dimensions and configuration(e.g., triple deck)of screens, and
C. Rated capacity (tons or tons/hr) of all nonmetallic mineral processing
equipment.
ii. A unique ID number.
iii. . The date the equipment was manufactured.
iv. The dates any required performance testing was conducted and submitted to
the Regional Supervisor, DAQ. ---
b. The equipment list and plant(or flow) diagram shall bear the date when the current
list and diagrams were revised.
c. The Permittee shall provide documentation to the Regional Supervisor, DAQ, for
any required performance testing within seven days of a written request.
d. Notwithstanding General Conditions and Limitations titled 'Equipment Relocation"
and "Reporting Requirement," the Permittee may install new and relocate existing
nonmetallic mineral processing equipment. The Permittee shall provide written
notification to the Regional Supervisor, DAQ, including a revised equipment list and
plant(or flow) diagram, each time nonmetallic mineral processing equipment is
installed or relocated at a facility. This notification shall be submitted at least 15 days
before the equipment is installed or relocated at the facility unless otherwise
approved by the Director. Nonmetallic mineral processing equipment includes all
crushers, screens, conveyors and loadout bins.
10. CONTROL AND PROHIBITION OF ODOROUS EMISSIONS -As required by 15A
NCAC 2D .1806 "Control and Prohibition of Odorous Emissions" the Permittee shall not
Permit No. 10592R00
Page 8
operate the facility without implementing management practices or installing and operating
odor control equipment sufficient to prevent odorous emissions from the facility from
causing-or-contributing-to-objectionable-odors beyond-the-facility-'s boundar-y ---- ----
B. GENERAL CONDITIONS AND LIMITATIONS
1. In accordance with G.S. 143-215.108(c)(1), TWO COPIES OF ALL DOCUMENTS,
REPORTS, TEST DATA,MONITORING DATA,NOTIFICATIONS, REQUESTS FOR
RENEWAL, AND ANY OTHER INFORMATION REQUIRED BY THIS PERMIT shall
be submitted to the:
Regional Supervisor
North Carolina Division of Air Quality
Mooresville Regional Office
610 East Center Avenue, Suite 301
Mooresville,NC 28115
704-663-1699
For identification purposes, each submittal should include the facility name as listed on the
permit,the facility identification number, and the permit number.
2. RECORDS RETENTION REQUIREMENT - In accordance with 15A NCAC 2D .0605,
any records required by the conditions of this permit shall be kept on site and made available
to DAQ personnel for inspection upon request. These records shall be maintained in a form
suitable and readily available for expeditious inspection and review. These records must be
kept on site for a minimum of 2 years, unless another time period is otherwise specified.
3. ANNUAL FEE PAYMENT- Pursuant to 15A NCAC 2Q .0203(a),the Permittee shall pay
the annual permit fee within 30 days of being billed by the DAQ. Failure to pay the fee in a
timely manner will cause the DAQ to initiate action to revoke the permit.
4. EQUIPMENT RELOCATION- In accordance with 15A NCAC 2Q .0301, a new air permit
shall be obtained by the Permittee prior to establishing, building, erecting, using, or
operating the emission sources or air cleaning equipment at a site or location not specified in
this permit.
5. REPORTING REQUIREMENT- In accordance with 15A NCAC 2Q .0309, any of the
following that would result in previously unpermitted,new,or increased emissions must be
reported to the Regional Supervisor,DAQ:
a. changes in the information submitted in the application regarding facility emissions;
b. changes that modify equipment or processes of existing permitted facilities; or
c. changes in the quantity or quality of materials processed.
If appropriate,modifications to the permit may then be made by the DAQ to reflect any
necessary changes in the permit conditions. In no case are any new or increased emissions
allowed that will cause a violation of the emission limitations specified herein.
Permit No. 10592R00
Page 9
6. In accordance with 15A NCAC 2Q .0309, this permit is subject to revocation or
modification by the DAQ upon a determination that information contained in the application
or presented in the support thereof is incorrect, conditions under which this permit was
granted have changed, or violations of conditions contained in this permit have occurred. In
accordance with G.S. 143-215.108(c)(1), the facility shall be properly operated and
maintained at all times in a manner that will effect an overall reduction in air pollution.
Unless otherwise specified by this permit, no emission source may be operated without the
concurrent operation of its associated air cleaning device(s) and appurtenances.
7. In accordance with G.S. 143-215.108(c)(1),this permit is nontransferable by the Permittee.
Future owners and operators must obtain a new air permit from the DAQ.
8. In accordance with G.S. 143-215.108(c)(1),this issuance of this permit in no way absolves
the Permittee of liability for any potential civil penalties which may be assessed for
violations of State law which have occurred prior to the effective date of this permit.
9. In accordance with G.S. 143-215.108(c)(1),this permit does not relieve the Permittee of the
responsibility of complying with all applicable requirements of any Federal, State,or Local
water quality or land quality control authority.
10. In accordance with 15A NCAC 2D .0605, reports on the operation and maintenance of the .
facility shall be submitted by the Permittee to the Regional Supervisor,DAQ at such
intervals and in such form and detail as may be required by the DAQ. Information required
in such reports may include, but is not limited to,process weight rates, firing rates, hours of
operation, and preventive maintenance schedules.
11. A violation of any term or condition of this permit shall subject the Permittee to enforcement
pursuant to G.S. 143-215.114A, 143-215.11413, and 143-215.114C, including assessment of
civil and/or criminal penalties.
12. Pursuant to North Carolina General Statute 143-215.3(a)(2),no person shall refuse entry or
access to any authorized representative of the DAQ who requests entry or access for
purposes of inspection, and who presents appropriate credentials,nor shall'any person
obstruct,hamper, or interfere with any such representative while in the process of carrying
out his official duties. Refusal of entry or access may constitute grounds for permit
revocation and assessment of civil penalties.
13. In accordance with G.S. 143-215.108(c)(1), this permit does not relieve the Permittee of the
responsibility of complying with any applicable Federal, State,or Local requirements
governing the handling, disposal, or incineration of hazardous, solid,or medical wastes,
including the Resource Conservation and Recovery Act(RCRA) administered by the
Division of Waste Management.
14. PERMIT RETENTION REQUIREMENT- In accordance with 15A NCAC 2Q .0110,the
Permittee shall retain a current copy of the air permit at the site. The Permittee must make
available to personnel of the DAQ, upon request, the current copy of the air permit for the
site.
15. CLEAN AIR ACT SECTION 112(r)REQUIREMENTS -Pursuant to 15A NCAC 2D .2100
"Risk Management Program," if the Permittee is required to develop and register a risk
Permit No. 10592R00
Page 10 —_
management plan pursuant to Section 112(r) of the Federal Clean Air Act,then the
Permittee is required to register this plan with the USEPA in accordance with 40 CFR Part
68. ------
16. PREVENTION OF ACCIDENTAL RELEASES - GENERAL DUTY - Pursuant to Title I
Part A Section 112(r)(1) of the Clean Air Act"Hazardous Air Pollutants -Prevention of
Accidental Releases -Purpose and General Duty," although a risk management plan may not
be required, if the Permittee produces, processes, handles, or stores any amount of a listed
hazardous substance,the Permittee has a general duty to take such steps as are necessary to
prevent the accidental release of such substance and to minimize the consequences of any
release. This condition is federally-enforceable only.
17. GENERAL EMISSIONS TESTING AND REPORTING REQUIREMENTS - If emissions
testing is required by this permit, or the DAQ, or if the Permittee submits emissions testing
to the DAQ in support of a permit application or to demonstrate compliance,the Permittee
shall perform such testing in accordance with 15A NCAC 2D .2600 and follow all DAQ
procedures including protocol approval, regional notification, report submittal, and test
results approval. Additionally, in accordance with 15A NCAC 2D .0605,the permittee shall
follow the procedures for obtaining any required audit sample and reporting those results.
Permit issued this the 18t`of October,2018.
NORTH CAROLINA ENVIRONMENTAL MANAGEMENT COMMISSION
Bruce J. ngle
Regional Supervisor
By Authority of the Environmental Management Commission
Air Permit No. 10592R00
-ATTACHMENT to Permit No. 10592R00, October 18,2018
Insignificant Exempt Activities
Exemption Source of Source of Title V
Source
Regulation —.—T-APs:?-----PolIutauts?
IES-2 -propane-fired pressure washer
(0.33 million BTU per hour maximum heat 12Q .0 1 02(h)(1)(B) No Yes
4
input)
---
------------------------IES-3 - diesel fuel storage tank(20,000 2Q .0102 (g)(4) Yes Yes
gallons capacity)
.. ........
.
capacity) Yes
IES-4- antifreeze storage tank(500 gallons 2Q 0 102 (g)(4) No
IES-5 -waste oil storage tank(1000
gallons capacity) 2Q .0102 (g)(4) Yes Yes
IES-6 - propane storage tank(250 gallons
2Q .0102 (g)(4) No Yes
capacity)
IES-7 -parts washer 2Q .0102 (h)(3) No Yes
1. Because an activity is exempted from being required to have a permit or permit modification
does not mean that the.activity is exempted from an applicable requirement or that the owner
or operator of the source is exempted from demonstrating compliance with any applicable
requirement.
2. When applicable, emissions from stationary source activities identified above shall be
included in determining compliance with the,permit requirements for toxic air pollutants
under 15A NCAC 2D .1100 "Control of Toxic Air Pollutants" or 2Q .0711 "Emission Rates
Requiring a Permit."
3. Sample permit conditions showing the regulatory requirements for exempt sources subject to
NESHAP,NSPS, and NCAC rules may be found here:
h gps://deq.nc.gov/about/divisions/air-quality/air-quality:pennits/specific-pennit-conditions-
regulatory-guide