HomeMy WebLinkAboutAQ_F_0000066_20200507_CMPL_CAV-Rpt (4) 000DD66 - CAd
NORTH CAROLINA DIVISION OF Asheville Regional Office
AIR QUALITY Vulcan Construction Materials,LLC-Toe River
Quarry
Inspection Report NC Facility ID 0000066
Date: 05/12/2020 County/FIPS: Yancey/199
Facility Data Permit Data
Vulcan Construction Materials,LLC -Toe River Quarry Permit n/a
752 Highway 80 South Issued n/a
Burnsville,NC 28714 Expires n/a
Lat: 35d 53.5940m Long: 82d 12.8740m Class/Status Permit Exempt
SIC: 1411 /Dimension Stone Permit Status Inactive
NAICS: 212311 /Dimension Stone Mining and Quarrying Current Permit Application(s)None
Contact Data Program Applicability
Facility Contact Authorized Contact Technical Contact SIP
Jamie Freeman Jonathan Mann Tony Johnson
Plant Supervisor Vice President,HR Environmental Engineer
(828)260-5905 (704)549-1540 (704)547-7076
Compliance Data
Comments:
Inspection Date 05/07/2020
Inspector's Name Angela Hopper
Inspector's Signature: ..'� 7 Operating Status Operating
Compliance Code Compliance-inspection
Action Code PCE
Date of Signature: 114,�Od 0 On-Site Inspection Result Compliance
Total Actual emissions.in TONSIYEAR:
TSP S02 NOX VOC CO PM10 *HAP
2015 --- --- --- ---
2010 --- --- --- --- ---
*Highest HAP Emitted(inpounds)
Five Year Violation History:None
Date Letter Tyae Rule Violated Violation Resolution Date
r
ack Tests since last FCE:None
Test Results Test Method(s) Source(s)Tested
DIRECTIONS: Take 19123 north out of Asheville. Just north of Mars Hill, veer right onto Hwy 19 east.
Go through Burnsville and turn right onto Hwy 80 south in Micaville. The facility is on the right.
Partial Compliance Evaluation Narrative:
On May 7, 2020,I contacted Mr. Tony Johnson and Mr.Travis Barnes vis email to conduct a Partial
Compliance Evaluation. Mr.Barnes promptly replied to my email. He told me that the company has no
plans to operate at this site in the new future. No changes have been made at the site. All the process
equipment has been removed from the site. The last time this facility was observed in operation by DAQ
staff was May 1, 1997. The last Compliance Assurance Visit was made by me,Angela Hopper,on April
29, 2019.
Permit Exemption:
This office received a request from Vulcan Construction Materials,LLC on April 21, 2017, which
requested rescission of Air Permit No. 06055RI I covering the Toe River Quarry site. The request was
determined to be complete and accepted for processing on the date received. Vulcan stated in the letter
received on April 21,2017,that there are no plans to resume operation. However,because this letter
speculates that if the facility resumes operation, it would be exempt under the revised 15A NCAC 2Q
.0102. On April 27, 2017,Vulcan Construction Materials, LLC-Toe Rive Quarry became exempt for air
permitting.
Facility Contacts:
I went over the IBEAM FacFinder report with Mr. Barnes. Mr.Jamie Freeman is now the area Plant
Supervisor and the Facility Contact. No other changes or updates are needed at this time.
Emission Sources:
This facility was previously permitted for the operation of a native granite quarry and processing plant.
There is no longer any process equipment on site.
Reporting and Record Keeping Requirements:
The facility has no reporting or record keeping requirements.
Five-Year Compliance History
There have been no documented violations or compliance issues in the last five years.
Stack Test Review:
The facility has no stack test requirements.
112r Review:
Vulcan Construction Materials, LLC-Toe River Quarry is not subject to 112r.
Recommendations:
None
Conclusion:
Vulcan Construction Materials,LLC-Toe River Quarry is in compliance by shutdown.